Nann Htike Win Construction Co.
,Ltd
(100'-0" x 30'-0" ) 4-Units 4-Storeyed RCC Staff Housing
Drain and Apron
Summary
Sr. No. Descriptions Amount (Kyat)
1 Material Charges 821,220.00
2 Labour Charges 890,920.00
Total 1,712,140.00
Nann Htike Win Construction Co.,Ltd
(100'-0" x 30'-0" ) 4-Units 4-Storeyed RCC Staff Housing
Drain and Apron
Detail of Measurements
Sr. Measurement Deduc-
Particular Qty. Contents Total of Each
No. L (ft) B (ft) H (ft) tion
1 Earthwork excavation.
Drain 1 294'- 4" 2'- 1.5" 1'- 6" 938.19 Cft
Apron 1 294'- 4" 3'- 0" 0'- 6" 441.50 Cft
1379.69 Cft
2 Sand filling.
Drain 1 294'- 4" 2'- 1.5" 0'- 3" 156.36 Cft
Apron 1 294'- 4" 3'- 0" 0'- 3" 220.75 Cft
377.11 Cft
3 ([Link]) Cement concrete work.
Drain 1 294'- 4" 2'- 1.5" 0'- 3" 156.36 Cft
Apron 1 294'- 4" 3'- 0" 0'- 3" 220.75 Cft
377.11 Cft
4 Brick work with (1:3) cement mortar.
Interior Drain Wall 1 294'- 4" 0'- 4.5" 0'- 9" 12.50 Cft
Exterior Drain Wall 1 294'- 4" 0'- 9" 1'- 0" 36.50 Cft
49.00 Cft
5 1½" Thick ([Link]) cement concrete flooring.
Apron 1 294'- 4" 3'- 0" 883.00 Sft
883.00 Sft
6 ¾" Thick plastering in (1:3) cement mortar.
Interior Drain Wall Vertic 1 294'- 4" 1'- 0" 294.33 Sft
Exterior Drain Wall Verti 1 294'- 4" 1'- 0" 294.33 Sft
Exterior Drain Wall Outsi 1 294'- 4" 0'- 3" 73.58 Sft
Exterior Drain Wall Top 1 294'- 4" 0'- 9" 220.75 Sft
882.99 Sft
Page 2 of 8
Nann Htike Win Construction Co.,Ltd
(100'-0" x 30'-0" ) 4-Units 4-Storeyed RCC Staff Housing
Drain and Apron
Builder's Estimate
Amount (Ks)
Sr. No. Particular Unit Quantity Rate Per
Materials Labour
1 Earthwork excavation.
Cft 1379.69
Labour
Worker No 20.70 8,000 No 165,600.00
2 Sand filling.
Cft 377.11
Material
Sand Sud 4.71 14,000 Sud 65,940.00
Labour
Worker No 4.00 8,000 No 32,000.00
3 ([Link]) Lean concret work for foundation
Cft 377.11
Material
Cement Bag 48.49 6,000 Bag 290,940.00
River Shingle Sud 3.62 26,000 Sud 94,120.00
Sand Sud 1.81 14,000 Sud 25,340.00
Fuel Gal 7.54 3,500 Gal 26,390.00
Labour
Mason No 4.00 10,000 No 40,000.00
Worker No 23.00 8,000 No 184,000.00
Machine driver No 2.00 10,000 No 20,000.00
4 Brick work with (1:3) cement mortar for retaining wall.
Cft 49.00
Material
Cement Bag 3.41 6,000 Bag 20,460.00
Page 3 of 8
Nann Htike Win Construction Co.,Ltd
(100'-0" x 30'-0" ) 4-Units 4-Storeyed RCC Staff Housing
Drain and Apron
Builder's Estimate
Amount (Ks)
Sr. No. Particular Unit Quantity Rate Per
Materials Labour
Brick No 662.00 95 No 62,890.00
Sand Sud 0.13 14,000 Sud 1,820.00
Labour
Mason No 1.96 10,000 No 19,600.00
Worker No 2.94 8,000 No 23,520.00
5 1½" Thick ([Link]) cement concrete flooring.
Sft 883.00
Material
Cement Bag 20.42 6,000 Bag 122,520.00
River Shingle Sud 1.02 26,000 Sud 26,520.00
Sand Sud 0.51 14,000 Sud 7,140.00
Labour
Mason No 6.62 10,000 No 66,200.00
Worker No 13.25 8,000 No 106,000.00
6 ¾" Thick plastering in (1:3) cement mortar
Sft 882.99
Material
Cement Bag 11.83 6,000 Bag 70,980.00
Sand Sud 0.44 14,000 Sud 6,160.00
Labour
Mason No 9.00 10,000 No 90,000.00
Worker No 18.00 8,000 No 144,000.00
Total of Material Charges 821,220.00
Total of Labour Charges 890,920.00
Total of Material and Labour Charges 1,712,140
Page 4 of 8
Nann Htike Win Construction Co.,Ltd
(100'-0" x 30'-0" ) 4-Units 4-Storeyed RCC Staff Housing
Drain and Apron
Builder's Estimate
Amount (Ks)
Sr. No. Particular Unit Quantity Rate Per
Materials Labour
Page 5 of 8
Nann Htike Win Construction Co.,Ltd
(100'-0" x 30'-0" ) 4-Units 4-Storeyed RCC Staff Housing
Drain and Apron
Abstract of Cost
Sr. No. Particular Unit Quantity Rate Per
1 Earthwork excavation. Cft 1379.69 120.03 Cft
2 Sand filling. Cft 377.11 259.71 Cft
3 ([Link]) Lean concret work for foundation Cft 377.11 1,805.28 Cft
4 Brick work with (1:3) cement mortar for retaining wall. Cft 49.00 2,618.16 Cft
5 1½" Thick ([Link]) cement concrete flooring. Sft 883.00 371.89 Sft
6 ¾" Thick plastering in (1:3) cement mortar Sft 882.99 352.37 Sft
Total Cost
Page 6 of 8
Amount (Ks)
165,600.00
97,940.00
680,790.00
128,290.00
328,380.00
311,140.00
1,712,140.00
Page 7 of 8
Nann Htike Win Construction Co.,Ltd
(100'-0" x 30'-0" ) 4-Units 4-Storeyed RCC Staff Housing
Drain and Apron
Bill of Quantity
Sr. No. Particular Unit Quantity Rate Per Amount (Ks)
Materials
1 Brick No 662.00 95 No 62,890.00
2 Cement Bag 84.15 6,000 Bag 504,900.00
3 Fuel Gal 7.54 3,500 Gal 26,390.00
4 River Shingle Sud 4.64 26,000 Sud 120,640.00
5 Sand Sud 7.60 14,000 Sud 106,400.00
Total of Material Cost 821,220.00
Labour
1 Mason No. 21.58 10,000 No. 215,800.00
2 Machine driver No. 2.00 10,000 No. 20,000.00
3 Worker No. 81.89 8,000 No. 655,120.00
Total of Labour Cost 890,920.00
Total Material+Labour Cost 1,712,140.00
Page 8 of 8