PROJECT: K028-FAYYHEALTH-POLYCLINIC
RISK ASSESSMENT FOR SLAB CORING WORK
NO of
ASSESSMENT,
PROJECT/CONTRACT ACTIVITY ASSESSMENT REVIEWED
BY: BY: REVISION &
DATE
PROJECT: K028-FAYYHEALTH-POLYCLINIC
CLIENT: MR SALEM SAIF MOHAMED SEED AL MAZROUEI SLAB CORING SE PM CH/RA/01
WORK
CONSULTANT: AL BAHRI ENGINEERING CONSULTANACY REV: 00
MAIN CONTRACTOR: CHERWELL INTERIOR DECORATION 09/06/2022
LLC.
PREPARED BY: APPROVED BY: APPROVED BY:
ABIOLA FREDERICK ADENIYI PROJECT MANAGER AL BAHRI ENGINEERING
HSE OFFICER CONSULTANACY
CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 SLAB CORING RISK ASSESSMENT
PROJECT: K028-FAYYHEALTH-POLYCLINIC
RISK ASSESSMENT FOR SLAB CORING WORK
POTENTIAL HAZARDS/CONDITIONS TO BE CONSIDERED
Deep Excavations Work on over water Falls from height X Fire risk High winds
Demolition Confined space Falls from level ground Noise/Dust/Vibration X Adverse
Plant/Machinery X Working Platforms X Slips/Tripping X Fumes Environmental risk
Lifting Operations X Manual Handling X Fuel Storage Traffic X Training Required
Buried/Overhead Service COSHH Storage/Lay Down Area Ground Conditions Health surveillance
NO ACTIVITY HAZARD IDENTIFIED AT RISK L S R CONTROL MEAUSRES L S R ACTION BY:
DESCRIPTION (PEOPLE/PROPERTY)
1. Manual handling of Muscle pain, Back Pain, Moditif Technicians. 2 3 4 TBT to be conducted by work supervisor to 1 2 2 P.E, S.O and
concrete coring Back injury all workers before work start. Foreman
machine Properties Ensure Manual handling training is in place.
Use manual handling techniques in lifting
heavy equipment e.g., 2 people must carry
this coring machine to divide the total weight
of this machine thus making it lighter and
easier to carry.
Barricade the work zone for maximum radius
Place relevant safety signs.
Full PPE to be comply, Hard hat, safety
shoes, safety glasses and cut resistant gloves
and dust mask.
2 Concrete coring Muscle pain Operator, Workers, and 2 3 6 Only trained and authorized person must 1 2 2 P.E, S.O &
machine operator Property damage operate this machine. Foreman
Visually inspect the wires and cables for any
defects or ties to avoid short circuit.
Technicians must keep the electrical cord
CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 SLAB CORING RISK ASSESSMENT
PROJECT: K028-FAYYHEALTH-POLYCLINIC
RISK ASSESSMENT FOR SLAB CORING WORK
away from moist surface to prevent its
accidental contact with water which can
caused electrocution.
3 Concrete coring Electrocution Operator, workers, and 3 3 9 Visually inspect the wires and cables for any 1 2 2 P.E, S.O &
machine operation property damage defects or ties to avoid short circuit. Foreman
Technicians must keep the electrical cord
away from moist surface to prevent its
accidental contact with water which can
caused electrocution.
Proper PPE should be provided for all
workforces.
ELCB is compulsory for electrical usage
Power supply points to be identified & get
approval from DWTC management before
using.
4 Concrete/Slab Dust / Spill of drilling Moditif Workforce, Trip 2 3 6 Barricade the work areas & maintain good 1 2 2 P.E, S.O &
Coring. fluid & slip housekeeping Foreman
Wear appropriate PPE according to the job
Environmental Affect descriptions like, helmets dust mask, gloves,
and goggles.
Ensure that there is a proper protection on
the area to prevent water spillage on the
floor.
Place polyethylene material on the wall or in
the floor prior to coring operation, drip try to
be available
5 Concrete Coring Coring noise, Workers, Public. 2 3 6 Continuous use of machinery must be 1 2 2 P.E, S.O &
Machine Operation Environmental affect minimized. Foreman
Wear appropriate PPEs like wear muffs or
ear plugs
6 Working at height on Personnel/ Objects fall Workers, Public & 3 3 9 Ensure scaffold platform is erected and 1 2 2 P.E, S.O &
scaffold platform from height/property property damage. inspected by the authorized personnel. Foreman
All tools must be secured.
Only trained personnel to work on scaffold
platform.
CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 SLAB CORING RISK ASSESSMENT
PROJECT: K028-FAYYHEALTH-POLYCLINIC
RISK ASSESSMENT FOR SLAB CORING WORK
Workplace supervisor is responsible for
ensuring the safe access from ground to work
area
Continuous monitoring by the supervisor.
Restrict other parts entry into workplace
without PPE like helmet, safety harness,
goggles & safety shoes.
7 Working near Damage to live Utilities, Moditif Workers, Public 2 3 6 Maintain good housekeeping 1 2 2 P.E, S.O &
utilities and Property damage. Ensure all personnel are aware the risk Foreman
Slip, Trip, & Fall involved in workplace.
Injuries. Close monitoring by the supervisor
Ensure access and egress are free from
obstruction.
Conduct TBT to ensure all employees are
aware of the hazards in the workplace and
emergency procedure
Wear appropriate PPE like helmet, goggles,
and safety shoes.
CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 SLAB CORING RISK ASSESSMENT
PROJECT: K028-FAYYHEALTH-POLYCLINIC
RISK ASSESSMENT FOR SLAB CORING WORK
LIKELIHOOD RISKIN RATING The above risk assessment has been briefed as fully understood
RISK 3 2 1 SEVERITY
RATING Name Sign
3 Major/injury/pollution/Damage
S Name Sign
2 Minor/Pollution/Damage/Loss
E Name Sign
1 Injury/Low Damage/Loss
V 3 9 6 3 Name Sign
LIKELIHOOD
E
3 Likely Name Sign
R 2 6 4 2
2 Possible Name Sign
I
1 Never/Very Unlikely Name Sign
T 1 3 2 1
Name of person given risk assessment briefing
Name Date:
Signature Time
CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 SLAB CORING RISK ASSESSMENT