EOI Submission Extension for Solar Projects
EOI Submission Extension for Solar Projects
Amendment No-VIII
Extension of due date of submission of
Expression of Interest (EOI) for Empanelment of Agencies for Design, Supply, Installation, testing & commissioning including
warranty, Comprehensive Operation & maintenance of Grid connected Rooftop Solar Plant of various capacities under the Phase-II
of Grid Connection Rooftop Solar Scheme of MNRE/Surya Gujarat Scheme in the State of Gujarat during the year (2021-22) for
Residentital Consumers in Rural Area.
AND
Corrigendum in the Terms condition and specification of the EOI Schedule dates are amended as under:-
Date: 03/06/2022
1 Last Date & time of online (e-tender) submission of offer (This is mandatory)
Up to 16.00 hours
2 Last Date & Time of Physical submission of documents by RPAD or SPEED POST Date:07/06/2022
only. up to 16.00 hours
Date:08/06/2022
3 Date of opening of “Techno-commercial bids” in on – line mode.
at 11.00 hours
Date: 15/ 06/2022
4 Tentative Date of opening of Price bid in online mode / e-tender (if possible)
at 11.00 hours
Note: (1) All bidders are informed that Price bid format is revised & uploaded through corrigendum-VII. Hence all bidders who have
fill up their price in earlier price bid format; they are requested to submit their price in new revised Price bid format.
(2) Bids are accepted / considered from those bidders who have submitted their bid duly signed and stamped of all uploaded
corrigendum with original SBD and Tender Notice.
1
Corrigendum in the Terms condition and specification of the EOI are as under:-
EoI
EoI
Sr. Existing
Page Existing terms Amended Terms
no. Clause
No.
No.,
This para is replaced as under:
1. Page Clause:- All the above benchmark costs are exclusive of total system cost
i. All the above benchmark costs are inclusive of total system cost
no. 27 Note: i including Photo-Voltaic solar modules, inverters, balance of systems including Photo-Voltaic solar modules, inverters, balance of systems
of SBD including cables, Switches/Circuit Breakers /Connectors/ Junction
Boxes, mounting structure, earthing, Lightening arrester, local including cables, Switches/Circuit Breakers /Connectors/ Junction
Docume Boxes, mounting structure, earthing, Lightening arrester, local
nt connectivity cost, cost of civil works, foundations etc. and its
installation, commissioning, transportation, insurance, comprehensive connectivity cost, cost of civil works, foundations etc. and its
maintenance charges for five years, other applicable fees and taxes if installation, commissioning, transportation, insurance, comprehensive
any (excluding GST) etc. maintenance charges for five years, other applicable fees and taxes if
any (excluding GST) etc.
2
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
Item Wise Earnest Money Deposit amount in Rs. This para is replaced as under:
2. Page No.1 Sr. no. 4 of Bid bond/EMD
Of tender Tender Bid Bond/EMD amount in For General Category bidders - Rs. 3.00 lakhs (Three lakhs Only)
Part of Bid with capacity Range (in kW)
notice notice Rs.
For Open Category - Rs. 1.50 lakhs (One Lakh fifty thousand Only)
Part-A (1 kW) 3.75 Lac
Part-B (1.01 to 2) 11.0 Lac
And Part-C (2.01 to 3) 35.0 Lac The Bidder shall furnish Interest free Bid Bond in the form of Bank Guarantee (BG)/ Demand
Part-D (3.01 to 4) 50.0 Lac Draft drawn in favor of MGVCL, payable at Vadodara. The validity of Bid Bond/EMD shall be
for a period of one year from the Bid Deadline. The Bid Bond/EMD of unsuccessful bidders
Part-E (4.01 to 5) 15.0 Lac
And shall be returned within 30 days from the date of issue of List of Empanelled Vendors. Bid
Page no. Part-F (5.01 to 6) 15.0 Lac bond(s) of Empanelled Vendor shall be released after the receipt of PBG in the format
40 of Part-G (6.01 to 10) 12.0 Lac prescribed by MGVCL and after the receipt of confirmation of their PBG’s from their
SBD Clause no. Part-H (10.01 to 25) 3.00 Lac respective banker.
docume 10.6 of SBD Part-I (25.01 to 50) 2.50 Lac
Document Bidders registered under Small Scale Industries of Gujarat State and holding subsequent
nt Part-J (50.01 to 100) 2.50 Lac registration with CSPO/NSIC/DGS&D registration certificate will be eligible for exemption
Part-K (100.01 to 500) 2.50 Lac from payment of EMD on submission of duly notarized copies of their Udyam Registration
TOTAL 152.25 Lac Certificate only out of SSI/MSME Part –II/Udhyog Adhar /Udyam Registration certificate
shall remain valid from 1st April 2022 OR from the date as amended in future by the with
time to time Notification issued from Ministry of Micro, Small & Medium Enterprises
Bid BOND/EMD
(MSME), Govt. of India, provided that the quoted value of the tender is within the monetary
The Bidder shall furnish Interest free Bid Bond in the form of Bank Guarantee limit for the said unit set by NSIC/State Director of Industries. Bidders seeking exemption
(BG)/ Demand Draft drawn in favour of “MGVCL”, payable at Vadodara. The should enclose a photocopy of valid registration certificate giving details such as validity,
validity of Bid Bond/EMD shall be for a period of one year from the Bid stores and monetary limits in EMD Cover failing which they run the risk of their tenders, as
Deadline. Bid bond /EMD shall be submitted separately for each part. The Bid ineligible.
Bond/EMD of unsuccessful bidders shall be returned within 30 days from the
Also, a Valid UDYAM REGISTRATION CERTIFICATE/ Udyog Aadhar Memorandum, the
date of issue of List of Empanelled Vendors. Bid bond(s) of Empanelled Vendor Certificate should indicate related group of item/s as per Section D, Division 35, Group 351
shall be released after the receipt of PBG in the format prescribed by MGVCL having NiC 5- digit code of 35105 (Electric power generation using solar energy).
and after the receipt of confirmation of their PBG’s from their respective
No relaxation shall be given to the bidder of outside Gujarat State even though having
banker. The formula applicable to calculate the Bid Bond amount under
above certificate. No relaxation given to the Gujarat Based bidders having only one
different parts will be: The Bid Bond amount for PART A, B,C … K is as under.
registration number from Government of Gujarat but no subsequent registration with NSIC
(This is as per clause no. of 4.9.6 of Purchase Policy of GUVNL) registration certificates for the item under tender.
3
EoI
Sr. EoI Page
no. No.
existing Existing terms Amended Terms
Clause
No., The tenders submitted without Earnest Money Deposit by the bidders which are not eligible
FOR TOTAL 300 MW CAPACITY for any exemption, will be rejected without entering in to further correspondence in this
regard and no reference will also made. Tender submitted without EMD shall be rejected
Total Amoun out rightly.
TOTAL
Sr. Capacity Aggregat Rate t of
PROJECT Quoted value of the offered quantity is calculated as under.
No Part range(KW e in Rs/ EMD in
COST in
. ) Capacity KWP Rs in Total Offer Quantity in KW * 0.4 (Rs in lakh/KW)
RS in Crs.
(KW) Lakhs
= __________ Lakh
1 Part-A 1 3801 46923 17.835 3.75
If the Quoted value is higher than monetary limits than the Bidder shall have pay the
Part-B 1.01 to 2 11586 43140 49.982 11.00 EMD. Bidder must submit the Annexure Z-2 for the same with EMD Cover.
2
3 Part-C 2.01 to 3 59939 42020 251.864 35.00
4
Sr. EoI Page EoI Existing
no. No.
Existing terms Amended Terms
Clause No.,
5
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
This para is replaced as under :
4. Page No.5 Schedule Maximum/Minimum Capacity.
Maximum/Minimum Capacity;
Of tender A of
For General Category bidder (Rural)
notice Tender Sr. Part Capacity Total 30% of 70% of 10% Min Max Min [Link]
No. range(KW) Aggregate Aggregate Aggregat Minimum Capacity Capacity Capacity (for which the
notice Total 70% of Aggregate
(for which Bidder can
Capacity Capacity for e reserved (for (for which Sr. Capacity Aggregate Capacity for
Part the Bidder submit its Bid)
No. range(KW) Capacity General category
(MW) Open Capacity Qty. for which the the Bidder can MW
(MW) Bidders(MW)
submit its
category for L1 (MW) Bidder can submit Bid) MW
And And Bidders General can its Bid) MW 1 Part-A 1 3.801 2.661
category submit its 2 Part-B 1.01 to 2 11.586 8.110
(MW) Bidders( Bid) MW 3 Part-C 2.01 to 3 59.939 41.957
4 Part-D 3.01 to 4 131.218 91.853
MW)
5 Part-E 4.01 to 5 38.523 26.966
6 Part-F 5.01 to 6 33.008 23.106 0.5 MW
1 Part-A 1 3.801 1.140 2.661 0.380 0.011 0.025 1.3 MW
page no. 7 Clause no.
7 Part-G 6.01 to 10 17.489 12.242
8 Part-H 10.01 to 25 1.919 1.343
and 30 of 2.2 of SBD 2 Part-B 1.01 to 2 11.586 3.476 8.110 1.159 0.031 0.069 9 Part-I 25.01 to 50 0.624 0.437
0.893 0.625
SBD Document 3 Part-C 2.01 to 3 59.939 17.982 41.957 5.994 0.125 0.279
10 Part-J 50.01 to 100
11 Part-K 100.01 to 500 1.000 0.700
document 300 210 0.5 MW 1.3 MW
4 Part-D 3.01 to 4 131.218 39.365 91.853 13.122 0.262 0.585
For Open Category (Rural)
5 Part-E 4.01 to 5 38.523 11.557 26.966 3.852 0.080 0.179
Min
6 Part-F 5.01 to 6 33.008 9.902 23.106 3.301 0.069 0.153 Capacity
30% of
Total (for
Sr. Aggregate
7 Part-G 6.01 to 10 17.489 5.247 12.242 1.749 0.036 0.081 Capacity Aggregate which the
No Part Capacity for
range(KW) Capacity Bidder
. Open category
8 Part-H 10.01 to 25 1.919 0.576 1.343 0.192 0.009 0.010 (MW) can
Bidders(MW)
submit its
9 Part-I 25.01 to 50 0.624 0.187 0.437 0.062 0.025 0.050 Bid) MW
1 Part-A 1 3.801 1.140
10 Part-J 50.01 to 100 0.893 0.268 0.625 0.089 0.050 0.100 2 Part-B 1.01 to 2 11.586 3.476
3 Part-C 2.01 to 3 59.939 17.982
11 Part-K 100.01 to 1.000 0.300 0.700 0.100 0.100 0.500 4 Part-D 3.01 to 4 131.218 39.365
500 5 Part-E 4.01 to 5 38.523 11.557 0.030
300 90 210 30 0.798 2.031 6 Part-F 5.01 to 6 33.008 9.902 MW
7 Part-G 6.01 to 10 17.489 5.247 (30 KW)
8 Part-H 10.01 to 25 1.919 0.576
9 Part-I 25.01 to 50 0.624 0.187
10 Part-J 50.01 to 100 0.893 0.268
11 Part-K 100.01 to 500 1.000 0.300
300 90 0.030
6
Sr.
EoI Page EoI Existing
no
No.
Existing terms Amended Terms
. Clause No.,
7
EoI
EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
8
EoI
EoI Existin
Sr.
no.
Page g Existing terms Amended Terms
No.
Clause
No., This para is replaced as under:
7. Page Clause However, MNRE vide Office
Min 5 % allocation to L1 bidder
no. 30 no. 2.2 Memorandum No. 318/331/2017-
th
of SBD of SBD Grid Connected Rooftop Dated 19 The quantity to be executed by the group of L1 bidders under various 11 no of capacities/slabs shall be at least 5 % of the total
docum Docume February 2021 has kept a provision of allocated capacity under the tender i.e. 15 MW. The L1 bidder in respective slab/capacity range shall require to execute at
ent nt minimum 10% of the total allocated least 0.5 % of tender quantity i.e. 1.5 MW, comprising of all slabs, so as to meet overall at least 5 % quantity by group of L1
capacity under the tender to L1 bidders. However, 10% quota will be reserved of tender quantity for L1 bidder’s i.e 30 MW. Also L1 bidders are allowed to
bidder and in the case L1 vendor execute more capacity than 30 MW without any restriction. (subject to condition under PBG clause)
does not execute the allocated “0.5 % of total allocated capacity in each part is allocated to L-1 bidder and in case L1 vendor does not execute the allocated
capacity, as a penalty his/her bank capacity, as a penalty his/her bank guarantee will be enchased and he/she shall be blacklisted for 5 years from all Government
guarantee will be encashed and tender
he/she shall be blacklisted for 5 years 30% of
70% of
Aggregate
from all Government tenders. Total Aggregate 0.5 % Minimum
Capacity
Aggregate Capacity for allocation
Sr. No. Part Capacity range(KW) for General
Capacity Open reserved Qty.
category
(MW) category for L1 (MW)
Bidders(M
Bidders(MW)
W)
1 Part-A 1 3.801 1.140 2.661
2 Part-B 1.01 to 2 11.586 3.476 8.110
3 Part-C 2.01 to 3 59.939 17.982 41.957
4 Part-D 3.01 to 4 131.218 39.365 91.853
5 Part-E 4.01 to 5 38.523 11.557 26.966
6 Part-F 5.01 to 6 33.008 9.902 23.106
1.5 MW
7 Part-G 6.01 to 10 17.489 5.247 12.242
8 Part-H 10.01 to 25 1.919 0.576 1.343
9 Part-I 25.01 to 50 0.624 0.187 0.437
10 Part-J 50.01 to 100 0.893 0.268 0.625
11 Part-K 100.01 to 500 1.000 0.300 0.700
300 90 210
If any bidder who is L1 in one or more slab/s and does not agree to match the L1 rate in other all slabs must have
to execute multiple of 0.5 % (i.e 1.5 MW/ slab) for which the bidder is L1 in the slab. E.g. The bidder is L1 in any 3
slabs, the bidder shall require to execute 4.5 MW comprising of capacity for which the bidder is L1.
9
Sr. EoI Page EoI Existing
no. No.
Existing terms Amended Terms
Clause No.,
10
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
This para is replaced as under:
General Condition:-
9. Page No. Sr. no. 5
General Condition: To meet the General Conditions of Eligibility Criteria, Bidders must have one of
9 of of Tender
the following credentials:
tender notice To meet the General Conditions of Eligibility Criteria, Bidders must
Bidder should have one of the following:
notice have one of the following credentials:
Bidder should have one of the following: The Bidder should be either a body incorporated in India under the Companies
Act, 1956 or 2013 including any amendment thereto.
The Bidder should be either a body incorporated in India under the Or
And
And Companies Act, 1956 or 2013 including any amendment thereto. The Bidders should be a Limited Liability Partnership firm.
Or
Or The Bidders should be a Proprietor firm
The Bidders should be a Limited Liability Partnership firm. Or
Clause no. The Bidders should be a Partnership firm
Page No.35, Or
5.5.1of
of SBD
SBD The Bidders should be a Proprietor firm.
Document
Document The Bidder should have valid PAN & GST registration certificate for General Bidder,
The Bidder should have valid PAN & GST registration certificate for
however for MSMEs, State GST Registration is mandatory.
General Bidder, however for MSMEs, State GST Registration is
mandatory.
The Bidder should have an Engineer (B.E./[Link] Electrical or The Bidder should have an Engineer (B.E./[Link] Electrical or Diploma in Electrical)
Diploma in Electrical) as proprietor/director/Employee of the Bidder. as proprietor/director/Employee of the Bidder. Brief Bio-Data of the Key personnel
Brief Bio-Data of the Key personnel is to be given by bidder in is to be given by bidder in online/offline mode. (Annexure –Z).
online/offline mode. (Annexure -
11
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
12
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
13
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
Bidders shall furnish documentary evidence as per the Format-7 (online as
well as offline), duly certified by Authorized Signatory and the Statutory FOR STATE REGISTERED MSME:
Auditor / Practicing Chattered Accountant of the Bidding Company in
The Bidders who are local MSME and registered under the MSME
support of their financial capability.
Development Act, 2006 in State of Gujarat as per Section D, Division 35, Group
FOR STATE REGISTERED MSME: 351 having NIC 5-digit code of 35105 (Electric power generation using solar
energy) are exempted from the financial eligibility requirements. The Bidder
The Bidders who are local MSME and registered under the MSME
being a local MSME must submit a valid copy of UDYAM REGISTRATION
Development Act, 2006 in Gujarat as per Section D, Division 35, Group
CERTIFICATE Only out of SSI/MSMEPart-II/Udhyog Aadhar/Udyam Registration
351 having NIC 5-digit code of 35105 (Electric power generation using solar
Certificate shall remain valid from 01st April 2022 OR from the date as
energy) are exempted from the financial eligibility requirements. The
amended in future by the with time to time Notification issued from Ministry
Bidder being a local MSME must submit a valid copy of the certificate of
of Micro, Small & Medium Enterprises (MSME) , Govt of India.
registration issued by an appropriate authority. This is applicable only for
the State registered MSMEs.
However, the Local MSME who does not possess the requisite technical
Or experience shall not allowed in process of discovery of rate in general
category, however such bidder shall be allowed in open category.
Vendors registered with DIPP under Renewable Energy sector are eligible
to participate in the Tender Part A to G only in line with Office Order of
Department for Industrial Policy & Promotions issued vide no. 12 Vendors registered with DIPP under Renewable Energy sector are eligible to
(11)/2017-SI dated 22.06.2017, which says that Central Ministries/ participate in the tender in open category only and EMD will be applicable.
Departments may relax condition of prior turn over & prior experience in
Public procurement subject to meeting of quality & technical specifications
by Start-ups.
14
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
This para is replaced as under:
12 Page Sr. no. 6 Performance Bank Guarantee: (I & C)
Performance Bank Guarantee (I&C)
No.10 of Tender The bidder has to submit the PBG in the following manner:
Of tender notice For Urban Area tender
1. Performance Bank Guarantee for Installation and The formula is revised as
notice
Commissioning (I&C): The bidder shall furnish the performance PBG amount = INR (Highest rate discovered) per KW out of 11 Slab) X 3% X Allocated
bank guarantee for installation and commissioning based on the Capacity in KWp
And And
allocated capacity.
3% PBG for installation and Commissioning, in part as follows.
PBG amount = INR [(cost discovered)] Lakhs X 3% X Allocated (URBAN)
page Capacity in MWp.
no. 41 Clause no. The L1 bidders shall require to submit 3% PBG corresponding to the first allocated capacity
10.7 of The PBG shall be submitted within 30 days from the date of issue of 1.3 MW. There after based on the performance, further 300 KW quota will be allocated
of SBD
SBD of LOI/LOA/Work Order, whichever is issues first, and be valid on completion of 95 % registration of applications, 75% payment of Firm quotation and 50
docume
Document for 24 months. Bidders should submit Single PBG based on the % installation of allocated capacity. Instead of taking new PBG for next 300 KW, originally
nt PBG submitted for initial quota will be reused.
allocated capacity in each category. The Performance Bank
Guarantee shall be released after completion of the
If the bidder is L1 in more than 2 slab than the initial PBG may be caped to Rs. 50 lakhs.
empanelment period with the compliance of entire obligations
in the contract. The bidders other than L1 shall require to submit 3% PBG corresponding to the first
allocated capacity of 0.5 MW. There after based on the performance, further 150 KW quota
Further, any delay in submission of PBG for I& C period beyond will be allocated on completion of 95 % registration of applications, 75% payment of Firm
60 days, MGVCL at its sole discretion may cancel the allocated quotation and 50 % installation of allocated capacity. Instead of taking new PBG for next
capacity and forfeit 100% of Bid bond. Such Vendors (who have 150 KW, originally PBG submitted for initial quota will be reused.
not submitted PBG) shall be debarred from participating in
MGVCL is future tenders for a period as decided by Competent For open category,
Authority. Part PBG shall not be accepted. Those bidders of Open Category who are technically qualified shall be empanelled subject
to agree with discovered price for each of all ranges and quota shall be allocated equally
among them and PBG will be paid accordingly. There after based on the performance,
further 30% quota of originally allocated quota will be allocated on completion of 95 %
registration of applications, 75% payment of Firm quotation and 50 % installation of
allocated capacity. Instead of taking new PBG for next quota, originally PBG submitted for
initial quota will be reused.
15
EoI
EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
For the bidders other than L1, the maximum quota allocation will be limited up to 1.3
MW or offered quantity whichever is lower. However, based on the performance and
progress, quota allocation shall be reviewed time to time and all rights of quota
allocate will be reserved with MGVCL/GUVNL.
The PBG shall be submitted within 30 days from the date of issue of LOI/LOA/Work
Order, whichever is issues first, and be valid up to 18.1.2024. The Performance Bank
Guarantee shall be released after completion of the empanelment period with the
compliance of entire obligations in the contract
Further, any delay in submission of PBG for I& C period beyond 60 days, MGVCL at its
sole discretion may cancel the allocated capacity and forfeit 100% of Bid bond. Such
Vendors (who have not submitted PBG) shall be debarred from participating in
DISCOMs of Gujarat State for future tenders for a period as decided by Competent
Authority.
“If the Empaneled Vendor is not able to complete the installation & commission of
allotted capacity within time to the satisfaction of DISCOMs /GUVNL, PBG (for I&C
period) amount on pro-rata basis by the empaneled vendor shall be 100% encashed.”
16
EoI
EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
And PBG amount = INR [Insert the Amount (cost discovered)] Lakhs X 3% X PBG amount = INR [Rate discovered)] Per KWp X 3% X Installed Capacity in KWp.
And
Installed Capacity in MWp.
The Empanelled Agency shall require to pay the Performance Guarantee of an
The Empanelled Agency shall require to pay the Performance amount equivalent to 3% of the value of the total System Cost which shall be
page Guarantee of an amount equivalent to 3% of the value of the total recovered from the payment of subsidy claim by respective DISCOMs.
no. 42 Clause no.
System Cost which shall be recovered from the payment of subsidy The amount deducted towards performance guarantee shall be release against
of SBD 10.7.2 of
claim by respective DISCOMs. the PBG shall be submitted of the equivalent amount valid within 30 days from
docume SBD
the end of the empanelment period and be valid for 05 year + 3 months. The
nt Documen The amount deducted towards performance guarantee shall be Performance Bank Guarantee shall be released after completion of the O&M
t release against the PBG shall be submitted of the equivalent amount period with the compliance of entire obligations in the contract.
valid within 30 days from the end of the empanelment period and be In case, Agency does not want to submit the performance bank guarantee (PBG),
valid for 05 year + 3 months. Bidders should submit Single PBG based the amount deducted towards performance bank guarantee shall remain with
on the installed capacity. The Performance Bank Guarantee shall be DISCOMs for the period of 5 year interest free from the date of the
released after completion of the O&M period with the compliance of commissioning of the last system installed.
entire obligations in the contract The Performance Bank Guarantee shall be denominated in Indian Rupees and
In case, Agency does not want to submit the performance bank shall be in the following forms: Bank guarantee from the List of banks as given in
guarantee (PBG), the amount deducted towards performance bank Annexure-B.
guarantee shall remain with DISCOMs for the period of 5 year interest If empaneled vendors are fail to comply with the O&M Guidelines as per clause
no.16 of RFP documents it may lead to encashment of performance bank
free from the date of the commissioning of the last system installed.
guarantee and subsequently debarring blacklisting from the future state/central
The Performance Bank Guarantee shall be denominated in Indian Government tender.
Rupees and shall be from the List of banks as given in Annexure-B.
17
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
This para is replaced as under:
14 Page [Link].9 of EVALUATION OF PRICE BID
EVALUATION OF PRICE BID
No. 13 tender
Price Bid (s) of the Qualified Bidders shall be opened online in presence of the
of notice
Price Bid (s) of the Qualified Bidders shall be opened online in presence representatives of such Qualified Bidders, who wish to be present, on a date as
tender
of the representatives of such Qualified Bidders, who wish to be may be intimated by MGVCL to the Bidders through [Link] website or
notice
present, on a date as may be intimated by MGVCL to the Bidders Email. The evaluation of Price Bid shall be carried out based on the information
through [Link] website or Email. The evaluation of Price Bid furnished in Financial Bid (Price Bid). The Price Bid submitted by the Bidders shall
shall be carried out based on the information furnished in Financial Bid be scrutinized to ensure conformity with the RFP. Any Bid not meeting any of the
And And
(Price Bid). The Price Bid submitted by the Bidders shall be scrutinized requirements of this RFP may cause the Bid to be considered “Non-responsive” at
to ensure conformity with the RFP. Any Bid not meeting any of the the sole decision of the MGVCL.
requirements of this RFP may cause the Bid to be considered “Non- Price Rate in Rs. per KWp are to be quoted by the bidders for the following System
Page no. Clause No.
responsive” at the sole decision of the MGVCL. Capacities and Ranges :
61 of 2.2
SBD
1.00 KW, 1.01 to 2.00 KW, 2.01 to 3.00 KW, 3.01 to 4.00 KW, 4.01 to 5.00 KW,
Docume
5.01KW to 6.00 KW, 6.01 KW to 10KW, 10.01 KW to 25KW, 25.01 KW to 50 KW,
nt
50.01 to 100 KW and 100.01 to 500 KW.
All EOV offers will be evaluated on Price Rate in Rs. per KWp basis for each of the
SPV System Capacities & Ranges INCLUSIVE of total system cost as per clause no.3
“Components/Package of Grid Connected Rooftop Solar PV System” of section I of
MNRE SBD for determining L1 rate in each of the SPV Capacities & ranges.
The applicable fees shall be borne by the Consumer and charges for CONNECTIVITY
CHARGE, Bidirectional Net-METER, METER TESTING CHARGE, SMC BOX, etc which
shall be paid Separately to the concerned DISCOM by the Consumer.
18
EoI
Sr. EoI Page
no. No.
Existing Existing terms Amended Terms
Clause
No., 2.3 SUCCESSFUL BIDDER(S) SELECTION
15 Page No.13 Sr. no. a) Price ranking will be done considering weighted sum of all quoted rates by the bidder for all 11 nos. of individual capacities and
Of tender 10 of ranges of Solar PV Systems by multiplying the quoted rates with the ‘Factor for Evaluation’ as mentioned in the on line price bid
2.3 SUCCESSFUL BIDDER(S)
notice Tender b) The example calculating weighted sum of all individual capacities of solar PV systems is under:
SELECTION Bidder-A
notice
i. i Bids qualifying in Clause 5.5 Sr. Solar Rooftop PV System Rate in Rs. Per KWp DC to be COST FOR
Capacity/Capacity range in KW quoted by bidder (excluding EVALUATION
of Section-I shall only be GST) Factor for
And And evaluated in this stage. Evaluation
[A] [B] [C] [D] [E = C x D]
ii. Ii. Project Cost quoted in all 1 Bidder-A 1.00 KW Rs. 43,000 / Kilo Watt(DC) 0.56% Rs. 240.80
page no. Clause Price Bids of Qualified 2 Bidder-A 1.01KW to 2.00 KW Rs. 39,501 / Kilo Watt(DC) 2.25% Rs. 888.77
60 of no. 2.3 3 Bidder-A 2.01KW to 3.00 KW Rs. 39,120 / Kilo Watt(DC) 14.83% Rs. 5,801.50
Bidders shall be ranked from 4 Bidder-A 3.01KW to 4.00 KW Rs. 38,200 / Kilo Watt(DC) 41.60% Rs. 15,891.20
SBD of SBD the lowest to the highest for 5 Bidder-A 4.01KW to 5.00 KW Rs. 38,300 / Kilo Watt(DC) 15.24% Rs. 5,836.92
documen Docume 6 Bidder-A 5.01KW to 6.00 KW Rs. 37,800 / Kilo Watt(DC) 14.17% Rs. 5,356.26
PART-A, PART-B, PART-C & 7 Bidder-A Above 6 KW(DC) and up to 10 KW(DC) Rs. 37,900 / Kilo Watt(DC) 8.74% Rs. 3,312.46
t nt PART-D…PART K separately. 8 Bidder-A Above 10 KW(DC) and up to 25 KW(DC) Rs. 34,750 / Kilo Watt(DC) 1.79% Rs. 622.03
9 Bidder-A Above 25 KW(DC) and up to 50 KW(DC) Rs. 30,000 / Kilo Watt(DC) 0.56% Rs. 168.00
iii. Iii. Allocation of Capacity and 10 Bidder-A Above 50 KW(DC) and up to 100 KW(DC) Rs. 29,000 / Kilo Watt(DC) 0.12% Rs. 34.80
Empanelment of Vendors 11 Bidder-A Above 100 KW(DC) Rs. 28,000 / Kilo Watt(DC) 0.14% Rs. 39.20
38,191.93
for CAPEX Part-A, Part-B,
Bidder -B
Part-C ……PART K. Factor for
Sr. Solar Rooftop PV System Rate in Rs. Per KWp DC to be COST FOR
Capacity/Capacity range in KW quoted by bidder (excluding Evaluation EVALUATION in
[A] [B] [C] [D] [E = C x D]
2.3.1 PART-A, PART-B, PART- 1 Bidder-B 1.00 KW Rs. 43,250 / Kilo Watt(DC) 0.56% Rs. 242.20
C……UP to PART K: Based on 2 Bidder-B 1.01KW to 2.00 KW Rs. 39,480 / Kilo Watt(DC) 2.25% Rs. 888.30
3 Bidder-B 2.01KW to 3.00 KW Rs. 38,560 / Kilo Watt(DC) 14.83% Rs. 5,718.45
the price bid quoted by the 4 Bidder-B 3.01KW to 4.00 KW Rs. 37,643 / Kilo Watt(DC) 41.60% Rs. 15,659.49
bidders, MGVCL shall 5 Bidder-B 4.01KW to 5.00 KW Rs. 37,643 / Kilo Watt(DC) 15.24% Rs. 5,736.79
arrange the bids in the 6 Bidder-B 5.01KW to 6.00 KW Rs. 37,643 / Kilo Watt(DC) 14.17% Rs. 5,334.01
7 Bidder-B Above 6 KW(DC) and up to 10 KW(DC) Rs. 37,643 / Kilo Watt(DC) 8.74% Rs. 3,290.00
ascending order i.e. L1, L2,
8 Bidder-B Above 10 KW(DC) and up to 25 KW(DC) Rs. 35,102 / Kilo Watt(DC) 1.79% Rs. 628.33
L3, _ _ _ (L1 being the lowest 9 Bidder-B Above 25 KW(DC) and up to 50 KW(DC) Rs. 31,000 / Kilo Watt(DC) 0.56% Rs. 173.60
quote). 10 Bidder-B Above 50 KW(DC) and up to 100 KW(DC) Rs. 30,150 / Kilo Watt(DC) 0.12% Rs. 36.18
11 Bidder-B Above 100 KW(DC) Rs. 29,520 / Kilo Watt(DC) 0.14% Rs. 41.33
37,748.67
19
EoI
Sr. EoI
Existin
no Page Existing terms Amended Terms
. No. g
Clause
No., Lowest bidder will be declared as
the L1 against each Part/Category. c) In above example of Bidder A & Bidder-B, the Bidder A will be considered as L1 for the capacities at sr. no. (1 & 8 to 11 ) and
The L1 bidder’s quoted capacity the bidder B will be considered as L1 for the capacities at sr. no. (2 to 7 ) to work out weighted sum for the ranking purpose.
shall be allocated to the L1 d) The weighted sum of the price discovered for each of the SPV Capacities and ranges as mentioned under above shall be
calculated. An example (just for calculation ) showing weighted sum of the price discovered by different bidders is shown as
successful bidder subject to the
under:-
condition that it should not be less Sr. Bidder Solar Rooftop PV System Rate in Rs. Per KWp DC to be COST FOR
Name Capacity/Capacity range in KW quoted by bidder (excluding EVALUATION in
than 10% of aggregated capacity
GST) Factor for Rs.
for respective part/category. On Evaluation
[A] [B] [C] [D] [E = C x D]
acceptance, capacity will be
1 Bidder-A 1.00 KW Rs. 43,000 / Kilo Watt(DC) 0.56% Rs. 240.80
allocated to the L1 bidder. In case 2 Bidder-B 1.01KW to 2.00 KW Rs. 39,480 / Kilo Watt(DC) 2.25% Rs. 888.30
3 Bidder-B 2.01KW to 3.00 KW Rs. 38,560 / Kilo Watt(DC) 14.83% Rs. 5,718.45
L-1 bidder did not accept the 4 Bidder-B 3.01KW to 4.00 KW Rs. 37,643 / Kilo Watt(DC) 41.60% Rs. 15,659.49
maximum bid capacity or10% of L1 5 Bidder-B 4.01KW to 5.00 KW Rs. 37,643 / Kilo Watt(DC) 15.24% Rs. 5,736.79
6 Bidder-B 5.01KW to 6.00 KW Rs. 37,643 / Kilo Watt(DC) 14.17% Rs. 5,334.01
aggregated capacity for the 7 Bidder-B Above 6 KW(DC) and up to 10 KW(DC) Rs. 37,643 / Kilo Watt(DC) 8.74% Rs. 3,290.00
8 Bidder-A Above 10 KW(DC) and up to 25 KW(DC) Rs. 34,750 / Kilo Watt(DC) 1.79% Rs. 622.03
respective part/category, then 9 Bidder-A Above 25 KW(DC) and up to 50 KW(DC) Rs. 30,000 / Kilo Watt(DC) 0.56% Rs. 168.00
Submitted Bank Guarantee will be 10 Bidder-A Above 50 KW(DC) and up to 100 KW(DC) Rs. 29,000 / Kilo Watt(DC) 0.12% Rs. 34.80
11 Bidder-A Above 100 KW(DC) Rs. 28,000 / Kilo Watt(DC) 0.14% Rs. 39.20
encashed, and L-1 bidder shall be 37,731.87
blacklisted from all the e) Those Agencies of General Category, whose weighted sum of quoted rates with effect of evaluation factor having rates higher
Government Tenders for 5 Years. up to 25% than the weighted sum of L1 rates under all capacities and ranges shall only be considered for the empanelment in
all ranges subject to matching of the price with all the L1 rates in each capacities and ranges for empanelment.
Further, if total no. of empanelled agencies are found to be less than 5 in the acceptable band as mentioned above, in that
case those Agencies of General Category, whose weighted sum of quoted rates with effect of evaluation factor having rates
beyond 25% and up to 30% than the weighted sum of L1 rate under all capacities and ranges may also be included in the
empanelment in all ranges subject to matching of the price with all the L1 rates in each capacities and ranges for
empanelment under the General Category.
Agencies beyond 25% or 30% higher rates than L1 rates, as the case may be, as mentioned above, such agencies may be
empanelled under Open Category subject to matching of L1 price as mentioned above, if required and decided by
MGVCL/GUVNL.
All the empanelled bidders shall provide the services to the consumers at L1 rate which they have agreed.
20
EoI
Sr. EoI
Existing
no Page Existing terms Amended Terms
. No. Clause
No.,
[Link] bids will be arranged in ascending (f) In any case, the Empanelment shall not be made if any agency does not fulfil the requirement of all criteria and
order Starting from L1, L2, L3………. The does not agree to match their price with discovered price of all SPV capacities and all ranges. Lowest bidder will
Approved Lowest Rate against each be declared as the L1 against each Part/Category. The L1 bidder’s quoted capacity shall be allocated to the L1
part/category will be the project cost successful bidder subject to the condition that it should not be less than 0.5 % of aggregated capacity of tender.
and bidder will be allocated their quoted On acceptance, capacity will be allocated to the L1 bidder. In case L-1 bidder did not accept the maximum bid
capacity as on the cover letter. The capacity or 0.5 % of L1 aggregated capacity of tender, then Submitted Bank Guarantee will be encashed, and L-1
remaining bidders, i.e. L2, L3, L4……., will bidder shall be blacklisted from all the Government Tenders for 5 Years.
be given 14 Days’ time to submit the
letter of acceptance of L1 Rate. The The bids will be arranged in ascending order Starting from L1, L2, L3………. The Approved Lowest Rate against
bidders, who provide their consent to each part/category will be the project cost and bidder will be allocated their quoted capacity as on the cover
work on L1 Rate, will be allocated their letter. The remaining bidders, i.e. L2, L3, L4……., will be given 7 Days’ time to submit the letter of acceptance of
quoted capacity in the order of merit, till L1 Rate. The bidders, who provide their consent to work on L1 Rate, will be allocated their quoted capacity in the
the entire capacity is exhausted. If order of merit, till the entire capacity is exhausted. If quantity/capacity is left unallocated in any category,
quantity/capacity is left unallocated in DISCOM reserves the right to reallocate the left-over capacity to the bidders’ subject to their consent and at the
any category, DISCOM reserves the right sole discretion of MGVCL/GUVNL
to reallocate the left-over capacity to
the bidders’ subject to their consent and Those bidders of Open Category who are technically qualified shall be empanelled subject to agree with
at the sole discretion of [Insert the name discovered price for each of all ranges and quota shall be allocated equally among them subject to maximum 5%
of Implementing Agency] of the capacity reserved for Open Category.
iii. The selection process shall stand The quota if any, left after allocation to the bidders in General/open Category will be transferred to the vice
completed once the Tender Capacity has versa. In case of non-performance, the quota reserved for L1 bidders will be transferred to General/open
been achieved through the summation Category bidders by reviewing the performance time to time.
of the capacity offered by the Successful
Enhancement of quota will be as per modality mentioned in PBG (I&C) clause.
Bidders.
Quantity: Tender capacity 700 MW may be increased up to 100% depending up on requirement and as may be
decided time to time.
21
EoI
Sr.
EoI Page Existing
no
No.
Existing terms Amended Terms
. Clause
No.,
This para is replaced as under:
16 Page No.15 Sr. no.
CFA DISBURSEMENT & PAYMENT CLAUSES: The net amount of project cost (i.e. project cost - CFA) shall be paid by the concerned roof
Of tender 11 of top owner to any of the empanelled vendors as per the following methodology:
notice Tender The net amount of project cost (i.e. project cost - CFA) 20% payment in advance after signing of agreement.
notice shall be paid by the concerned roof top owner to any 20% payment after installation of structure
and of the empanelled vendors as per the following 20% payment after installation of SPV modules and inverters at site
And page
methodology: 20% payment after completing plant installation including net-metering and submission
no. 63 of
of written inspection request to the implementing agency
SBD Clause 20% payment in advance after signing of agreement.
Final 20% payment after commissioning of the plant and injection of power to the grid.
document no. 5.1 20% payment after installation of structure
20% payment after installation of SPV modules and This is advisory type of payment stages for the non-subsidy part of system’s cost to be paid
of SBD
by the Applicant to the concerned Empanelled Vendor. Empanelled Vendor himself shall
Docume inverters at site
require to collect payment from applicant instead of collecting through Sub-vendor.
nt 20% payment after completing plant installation
Empanelled Vendor shall give valid money receipt to the consumers as a proof of payment
(including net-metering) and submission of written
and same is required to be uploaded on portal within three days of payment transacted. If
inspection request to the implementing agency the Agency is found indulged in fraudulent practice, the agency shall be stop-dealt and legal
Final 20% payment after commissioning of the plant actions be initiated against the agency.
and injection of power to the grid. It shall be noted that beneficiary/customer shall be solely responsible for financial
transaction with the vendor for the net of CFA (Total cost – Admissible CFA) amount. The
It shall be noted that beneficiary/customer shall be beneficiary/customer are advised to thoroughly check the documents/claims of the vendors
solely responsible for financial transaction with the and shall make only online payments wherever required. GUVNL/MGVCL or MNRE in no
vendor for the net of CFA (Total cost – Admissible CFA) way shall be responsible for disputes arising out of payments of agreements between
amount. The beneficiary/customer are advised to vendor and the beneficiary.
thoroughly check the documents/claims of the vendors
Empanelled vendor shall be liable toward any irresponsible behaviour towards consumers.
and shall make only online payments wherever required.
Making false claim or fraud practice will attract stop deal actions.
[Insert the name of State Implementing Agency or
MNRE] in no way shall be responsible for disputes arising In case of any type of misappropriations, cheating or intention of cheating, frauds,
out of payments of agreements between vendor and the irregularities, malpractice, etc., DISCOM reserves the right to cancel the Empanelment
beneficiary. Agreement without giving reasons thereof and forfeit the security deposit and / or
performance bank guarantee/s and purchase the system under risk & cost of the supplier.
22
EoI
EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
This para is replaced as under:
17 Page Sr. no.
2.12.4 The Bidders should have one no. of Service centre with The Bidders should have one no. of Service centre with necessary spare parts and
No. 18 16.4
necessary spare parts and technicians in their service network or in technicians in the area of Discoms where the installation work done by them. The
of
each DISOCMs. The Service Centre should have adequately trained Service Centre should have adequately trained staff available for repair and
tender
staff available for repair and maintenance of Solar PV System, Inverters maintenance of Solar PV System, Inverters supplied and installed. The service
notice
supplied and installed. The service centre should be open for at least 8 centre should be open for at least 8 hours per day and 6 days a week excluding
hours per day and 6 days a week excluding bank holidays. The bidders bank holidays. The bidders should have a dedicated mobile number which should
&
should have a dedicated mobile number which should be readily be readily available during its office hours and an e-mail ID for correspondence
&
available during its office hours and an e-mail ID for correspondence and shall provide address of service centre in O&M manual. A copy of the same
and shall provide address of service centre in O&M manual. A copy of shall also be provided to the Respective DISCOMs.
Clause
the same shall also be provided to the Respective DISCOMs
Page no no.
48, 49 2.12.4
of SBD
Docum
ent
23
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
24
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
In the event any defect is found or developed in the system within guarantee
period, shall be rectified/replaced by empanelled agencies at his own expense
promptly.
In case the defects are not rectified within 2 (Two) days from the receipt of the
complaint by empanelled agencies than penalty of Rs 100 per day is applicable till
the complaint is resolved.
25
EoI EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
20 Page Clause no
Inverter/PCU This para is replaced as under:
No. 71 2.5
of SBD 2.5 Allowable inverter capacity is equal to Module Capacity (+/- 10% Inverter/PCU
Docum tolerance allowed). 2.5 Allowable inverter capacity is equal to Module capacity (+15/-10% tolerance
ent
allowed).
26
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
76 Clause
D.2.(f)
Of SBD
Docume
nt
27
EoI EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
22 Page Clause no
7.1 Earthing Protection This para is replaced as under:
No. 79 7.1
i. The earthing shall be done in accordance with latest Standards. 7.1 Earthing Protection
of SBD
[Link] array structure of the PV yard, Low Tension (LT) power system, i. The earthing shall be done in accordance with latest Standards.
Docum
earthing grid for switchyard, all electrical equipment, inverter, all ii. Each array structure of the PV yard, Low Tension (LT) power system, earthing
ent
junction boxes, etc. shall be grounded properly as per IS 3043-2018. grid for switchyard, all electrical equipment, inverter, all junction boxes, etc. shall
be grounded properly as per IS 3043-2018.
iii. All metal casing/ shielding of the plant shall be thoroughly
grounded in accordance with CEA Safety Regulation 2010. In addition, iii. All metal casing/ shielding of the plant shall be thoroughly grounded in
the lightning arrester/masts should also be earthed inside the array accordance with CEA Safety Regulation 2010. In addition, the lightning
field. arrester/masts should also be earthed inside the array field.
iv. Earth resistance should be as low as possible and shall never be iv. Earth resistance should be as low as possible and shall never be higher than 5
higher than 5 ohms. ohms.
v. Separate three earth pits shall be provided for individual three v. Separate three earth pits shall be provided for individual three earthing viz.: DC
earthing viz.: DC side earthing, AC side earthing and lightning arrestor side earthing, AC side earthing and lightning arrestor earthing.
earthing.
V vi. The earthing shall be maintenance free type earthing and shall be done
through at least 1.5 meter Electrode.
28
EoI
EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
This para is replaced as under:
23 Page Clause no
No. 119 Annexure- Solar PV Modules/Panels
Solar PV Modules/Panels
of SBD E IEC 61215/ Design Qualification and Type Approval for
Docum IEC 61215/ IS Design Qualification and Type Approval for Crystalline
IS Crystalline Silicon Silicon
ent 14286
14286 Terrestrial Photovoltaic (PV) Modules Terrestrial Photovoltaic (PV) Modules
IEC 61701 Salt Mist Corrosion Testing of Photovoltaic (PV) IEC 61701 Salt Mist Corrosion Testing of Photovoltaic (PV) Modules
Modules
IEC 61853- Photovoltaic (PV) module performance testing and
IEC 61853- Photovoltaic (PV) module performance testing and Part 1/ energy rating: Irradiance and temperature performance
Part 1/ energy rating: Irradiance and temperature measurements, and power rating
IS 16170: Part
IS 16170: performance measurements, and power rating
1
Part 1
IEC 62716 Photovoltaic (PV) Modules – Ammonia (NH3) Corrosion
IEC 62716 Photovoltaic (PV) Modules – Ammonia (NH3) Testing (As per the site condition like dairies, toilets)
Corrosion Testing (As per the site condition like
IEC 61730-1,2 Photovoltaic (PV) Module Safety Qualification – Part 1:
dairies, toilets)
Requirements for Construction, Part 2: Requirements for
IEC 61730- Photovoltaic (PV) Module Safety Qualification – Part Testing
1,2 1: Requirements for Construction, Part 2:
IEC 62804 Photovoltaic (PV) modules - Test methods for the
Requirements for Testing
detection of
IEC 62804 Photovoltaic (PV) modules - Test methods for the
Potential-induced degradation. IEC TS 62804-1: Part 1:
detection of
Crystalline silicon (mandatory for applications where the
Potential-induced degradation. IEC TS 62804-1: Part system voltage is > 600 VDC and advisory for installations
1: Crystalline silicon (mandatory for applications where the system voltage is < 600 VDC)
where the system voltage is > 600 VDC and advisory
for installations where the system voltage is < 600
VDC)
IEC 62759-1 Photovoltaic (PV) modules – Transportation testing,
Part 1:
Transportation and shipping of module package
units
29
EoI
Sr. EoI Page Existing
no. No.
Existing terms Amended Terms
Clause
No.,
30
EoI
EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
2.22.6 Empanelment of Agencies may be reviewed time to time. In case of change in law,
guideline, Regulation, etc., the Company/ DISCOMs reserve the Right to discontinue the
Empanelment with one-month Notice in advance.
DISCOM reserves the right to terminate the empanelment or part thereof at any time giving 01
(One) months’ notice of Termination or the reasons thereof. You will not be entitled for any
compensation / damages / losses, whatsoever, on account of such termination of the
empanelment.
DISCOM will be entitled to deduct directly, from the subsidy to be paid to you, any sum or sums
payable by you and which sum/sums due to you or the DISCOM is required to pay as a principal
employer on account of your default in respect of all liabilities referred to MGVCL/concerned
DISCOM has right to make minor changes / modifications in the Technical & Site condition
matter. In such matter, decision of Additional Chief Engineer of MGVCL/concerned DISCOM shall
be final and binding to you to carry out work accordingly.
31
EoI EoI
Sr. Page Clause Existing Terms Amended Terms
no. No. No.
The Bidder shall be required to rectify the faults in the PV system within 1 week of such failure, after which, one more
inspection shall be carried out to verify the rectification.
This penalty plus GST & Cess as applicable shall be paid by the Agency within 15 days of the Notice, failure of the same,
the PBG shall be encashed.
The reference for the testing of the performance ratio shall be taken as per IS/IEC 61724 (1998): Photovoltaic System
Performance Monitoring - Guidelines for Measurement, Data exchange and Analysis [ETD 28: Solar Photovoltaic Energy
Systems]. The illustration of the calculation of the performance ratio is given as below for the reference.
32
EoI EoI
Sr.
Page Clause Existing Terms Amended Terms
no.
No. No.
Performance Ratio
PR = Performance Ratio (Without correction)
PRCorr = Temperature Corrected Performance Ratio at
PGen (kw) = Generated Power measured by Solar Meter (Instantaneous)
2
Irr (kw/m ) =Solar Irradiance Measured by Pyranometer (Instantaneous)
Kwp =Installed DC capacity of plant at STC
PRCorr =Instantaneous Gen. of Solar Energy (Kw)
µ=Temperature coefficient provided by module manufacturer (Negative sign % / °C).
Tcell= Temperature of Cell/Module at the particular instant
Illustration:-
33
EoI
EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
This para is replaced as under:
26 Page Clause no. SCOPE OF WORK
SCOPE OF WORK
no. 45 1.2 of SBD 1.2 Project Time schedule:- It is very critical to complete the work for the 1.2 Project Time schedule:- It is very critical to complete the work for the
of SBD Documen application registered by the Agency in time bound manner so as to install application registered by the Agency in time bound manner so as to install
docume t the SPV System within 85 days from the date of payment of Firm quotation the SPV System within 85 days from the date of payment of Firm quotation
nt charges including connectivity charges to DISCOM by the applicant. charges including connectivity charges to DISCOM by the applicant.
In the event of failure to install the SPV System, DISCOMs will lead to
In the event of failure to install the SPV System, DISCOMs will lead to
forfeiture of the Security deposit and performance guarantee up to 100%
forfeiture of the Security deposit and performance guarantee up to 100%
and will lead to disqualification of the Bidders for transacting business with
and will lead to disqualification of the Bidders for transacting business with
DISCOMs for at least three years or the time duration as may be decided by
DISCOMs for at least three years or the time duration as may be decided by
the Concern DISCOM/GUVNL.
the Concern DISCOM/GUVNL.
The work for Installation of the SPV System shall be considered as Moreover, in case the empanelled vendor fails to install 10 or more
completed if the SPV System is installed completely in all aspects including registered applications within the prescribe time limit i.e. 85 days, new
the submission of all required documents, self-certification/CEI certificate registration of application will be stopped with immediate effect and
on portal and PPA duly signed. The Agency shall require to intimate for the however, on submission of justified reason for delay, further the registration
work completion date on portal. may be allowed.
The work completion date shall be the date entered by the DE of Sub- The work for Installation of the SPV System shall be considered as completed
Division as the “Intimation Approval” Date on portal on completion of entire if the SPV System is installed completely in all aspects including the
Installation work and submission of the documents as per the following two submission of all required documents, self-certification/CEI certificate on
cases. portal and PPA duly signed. The Agency shall require to intimate for the work
completion date on portal.
The work completion date shall be the date entered by the DE of Sub-
Division as the “Intimation Approval” Date on portal on completion of entire
Installation work and submission of the documents as per the following two
cases.
34
EoI
EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
(1) In case, all the documents are submitted and work is also found (1) In case, all the documents are submitted and work is also found
completed before the Intimation Request raised by the Empanelled Agency completed before the Intimation Request raised by the Empanelled Agency
then DE of the sub-division shall consider the “Intimation Approval” in the then DE of the sub-division shall consider the “Intimation Approval” in the
Surya Gujarat Portal; Surya Gujarat Portal;
(2) In case, any document is not submitted or installation work is not (2) In case, any document is not submitted or installation work is not
completed before the “Intimation Request” raised by the Empanelled completed before the “Intimation Request” raised by the Empanelled Agency
Agency then DE of the sub-division may receipt the intimation request or then DE of the sub-division may receipt the intimation request or shall decide
shall decide the date of work completion when the pending task is the date of work completion when the pending task is completed.
completed.
35
EoI
EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
27 Page Clasue Every bidder should, at the time of submission of bid, give a
This para is replaced as under:
No. 28 no.39 declaration that bidder and/or proprietor/ partner/ director of the
Of Last para firm has not been placed on Stop dealing / Banned for business Every bidder should, at the time of submission of bid, give a
Tender after dealing / blacklisting by GUVNL and it’s any Subsidiary Companies. declaration that bidder and/or proprietor/ partner/ director of the
firm has not been placed on Stop dealing / Banned for business
Notice 39.3.7 dealing / blacklisting by GUVNL and it’s any Subsidiary Companies/
Torrent Power Ltd. Ahmedabad/ Torrent Power Ltd. Surat/Govt.
distribution/transmission/generation/ SECI or MNRE or state
Renewable development agencies across the country or by any other
Govt. PSU / Govt. Company / Govt. Department in India.
36
EoI
Sr
EoI Existin
.
Page g Existing terms Amended Terms
n
No. Clause
o.
No.,
FORMAT: A This format is replaced as under :-
28 Page Format PRICE BID FORMAT: A
no A – (To be submitted online separately) PRICE BID
Performa for submission of rates of different capacity of roof top Solar Power (To be submitted online separately)
85 Price
Projects under RFP No. ____________ by MGVCL. Performa for submission of rates of different capacity of roof top Solar Power
SBD Bid Projects under RFP No. ____________ by MGVCL.
Name of Bidder: - __________________________
Docu Name of Bidder: - __________________________
men
Bid
t Solar Rooftop Rate in Rs. per kWp to be Rate per
Descripti Capacit COST FOR
Sr. No. Scope of Work Capacity range quoted by bidder kWp in
on y in EVALUATION
in KWp (excluding GST) words Solar Rooftop Rate in Rs. per kWp to
KWp Descripti Factor for in Rs.
Sr. No. Scope of Work Capacity range be quoted by bidder
on Evaluation
in KWp (excluding GST)
1 PART-A 1 Rs / Kilowatt
Design, supply,
2 PART-B 1.01 to 2 Rs / Kilowatt
erection, testing [C] [D]
3
[A] [B] [E = C x D]
and commissioning PART-C 2.01 to 3 Rs / Kilowatt Design, supply,
including warranty, PART-D
1
erection, testing
PART-A 1 Rs / KW 0.56% Rs.
4 3.01 to 4 Rs / Kilowatt
Comprehensive 2 and commissioning PART-B 1.01 to 2 Rs / KW 2.25% Rs.
5 PART-E 4.01 to 5 Rs / Kilowatt
operation & 3 including warranty, PART-C 2.01 to 3 Rs / KW 14.83% Rs.
6 maintenance of grid PART-F 5.01 to 6 Rs / Kilowatt Comprehensive
connected rooftop PART-G
4
operation &
PART-D 3.01 to 4 Rs / KW 41.60% Rs.
7 6.01 to 10 Rs / Kilowatt
solar power plant of 5 maintenance of PART-E 4.01 to 5 Rs / KW 15.24% Rs.
8 PART-H 10.01 to 25 Rs / Kilowatt
various capacities 6 grid connected PART-F 5.01 to 6 Rs / KW 14.17% Rs.
9 in the State of PART-I 25.01 to 50 Rs / Kilowatt rooftop solar
GUJARAT under
7
power plant of
PART-G 6.01 to 10 Rs / KW 8.74% Rs.
10 PART-J 50.01 to 100 Rs / Kilowatt
Phase-II Scheme. 8 various capacities PART-H 10.01 to 25 Rs / KW 1.79% Rs.
11 PART-K 100.01 to 500 Rs / Kilowatt
9 in the State of PART-I 25.01 to 50 Rs / KW 0.56% Rs.
GUJARAT under
10
Phase-II Scheme.
PART-J 50.01 to 100 Rs / KW 0.12% Rs.
● Rates quoted will be exclusive of GST.
11 PART-K 100.01 to 500 Rs / KW 0.14% Rs.
● In case there is difference between Figure Rate & Words Rate, then the
Weighted Sum
rates given in words column will be accepted by MGVCL.
● In case of discrepancy in price bid (Excel file) and electronic form, the
Rates quoted will be exclusive of GST.
price mentioned in Excel file will prevail.
In case of discrepancy in price bid (Excel file) and electronic form, the price
mentioned in Excel file will prevail.
37
EoI
Sr
EoI Existin
.
Page g Existing terms Amended Terms
n
No. Clause
o.
No.,
Format -7 This format is replaced as under :-
29 Page FINANCIAL ELIGIBILITY CRITERIA REQUIREMENT Format -7
(AS PER CLAUSE 10.9 of Section-I) Format for Annual Turnover certificate )
no Format (To be submitted on the letterhead of Bidding Company)
99 7– (To be submitted in ‘on-line’ and physical mode by Both ‘General Category’
To,
Only)
SBD [Name and Address of State Implementing Agency]
Docu Sub: Bid for Implementation of Grid connected Roof Top Solar System scheme in
response to the RFP No: …………………………. Category-B bidders are not required to submit this Annexure)
men
t Dear Sir, To be submitted on letter head of practicing Chartered Accountant
We submit our Bid/Bids for the total capacity of ………… kWp in Part-A/ Part-B/ Part C/
Part- D….Part K put together for which details of our Financial Eligibility Criteria TO WHOMSOEVER IT MAY CONCERN
Requirements are as follows.
We have verified the books of accounts and related record of
We certify that the Financially Evaluated Entity (ies) had an Annual Turnover as follows:
The Annual turnover of [Insert the amount] per kW of the capacity offered in its Bid in any M/s._____________________ situated at Address of the factory/firm>
one of the last 3 financial years preceding the bid deadline subjected to the condition that _________________________________________and on verification of the records,
the bidder should at least have completed one financial year. we hereby certify that average Turnover and net worth of this mentioned
OR entity/firm during the last three financial years which are as under:
Net worth (strike out whichever is not applicable) of Rs………Crore computed as per
instructions provided in Clause 5.5.2 of this RFP based on unconsolidated audited annual
Sr. Financial Year Total Net wort
accounts (refer Note-1 below) any of the last 3 Years immediately preceding the Bid
No. Turnover Rs. (Positive/Ne
Deadline.
In lacs gative)
Name of Relationshi Financi Year of Annual Net 1 2018-19
Financiall p with al Incorporation Turnove worth
2 2019-20
y Bidding yea r (Rs. as per
Evaluate Company** r Crore) Clause 3 2020-21
d Entity* 5.5.2 (in Rs. Crore) Total
Average Annual Turn Over of
last three years
* The Financially Evaluated Entity may be the Bidding Company itself.
The column for “Relationship with Bidding Company” is to be filled in only in case Place:
financial capability of Parent Company and/or Affiliate has been used for meeting
Qualification Requirements. Sign and seal of Chartered Accountant with UDIN No.,
38
EoI
EoI
Sr. Existing
no.
Page Existing terms Amended Terms
No. Clause
No.,
Format-2
Page Clasue
30
No. 90 Format -2 General Particulars of the bidder
This Format -2 is modified as per Page No. 41 this Amendment
Of S. Particulars Details
Tender No.
Notice 1. Name of the Company
2. Registered Office Address
3. E-mail ID
4. Web site
Authorized Contact Person(s) with name, designation Address
5. and Mobile Phone No., E- mail address/ Fax No. to whom all
references shall be made
6. Year of Incorporation
Have the bidder/Company ever been debarred By any Govt.
7.
Dept./ Undertaking for undertaking any work
Reference of any document information
8.
attached by the Bidder other than specified in the RFP.
Details of the Ownership structure (Details of persons owning Yes/No
9. 10% or more of the Total Paid up equity of the Bidding Company
in the Format as below
10. Whether company is MSME as on the bidding date Yes/No
Signature:
Name:
39
EoI
EoI
Sr. Existing
Page Existing terms Amended Terms
no. Clause
No.
No.,
Annexure V
31 Page This format is remove from EOI Document
Format for Bid Security Declaration
no Annexure
146 -V
(To be submitted separately for each Project Group)
SBD
(To be stamped on non – judicial stamp paper as per the stamp act of the state
Docu
where the document is made)
ment
Ref: ______________
Declaration No.: (Insert Name of Project Group)
Date: ___________
40
Modified Format -2
GENERAL INFORMATION ABOUT THE BIDDERS and its legal Status
(To be submitted in ‘on-line’ and physical mode by Both ‘General and ‘Open Category’ bidders)
1 Name of the EOI Applicant Bidder
8 PAN no
9 PF NO
20 Has any Govt. Dept. / Undertaking ever debarred the company / firm from
executing any work?
41
21 Address of Registered Office of EOI applicant Factory / Works of mfg. Authorized Representative/ Signatory
Sr. Name of Partners / Directors Address of Office & Contact Address of Residence & Contact Phone / Fax
e- mail ID
No. DIN no. as applicable Phone / Fax No. / Mobile No. No./ Mobile No.
(i)
(ii)
(iii)
(iv)
(v)
It is certified that the information provided above is true to the best of my knowledge and belief. If any information found to be concealed, suppressed or incorrect at
later date, our EOI shall be liable to rejected and our company debarred from executing any business with MGVCL/GUVNL/DICOMs.
42
THIS NEW FORMAT ADDED IN EOI
Format-12
Details of the Experience and declaration of Category of the bidder
(To be submitted in ‘on-line’ and physical mode by Both ‘General’ and ‘Open’ category bidders)
Note: If Experience as mentioned above fulfills the Bidder category shall be ‘General’ otherwise the bidder shall be of
- the open category
Please write down applicable category of bidder below i.e. “General Category” or “Open Category”
I/We hereby confirm that the experience mentioned above by us are actual for Solar Rooftop/ grid connected SPV System installed & Commissioned
by us as a bidder only and considering the EOI Criteria, I/we declare that my/our bidder category is “_________________________”.
(Self-Certified Copies of Work orders, GEDA /GUVNL Registration No, SECI Project No. etc, if any, along with Work completion certificates shall be
attached with
this information. If necessary, separate sheet may be used to submit the information.
(Signature of EOI Applicant bidder)
With seal
43
THIS NEW FORMAT ADDED IN EOI
FORMAT -13
Details of the EPC work Execution Capacity
(To be submitted in ‘on-line’ and physical mode by both ‘General and Open’ bidders)
EPC Project execution capacity of the bidder per month for: Design, Supply, Installation, testing & Commissioning of Grid
connected Rooftop Solar Photovoltaic Systems in Residential premises
Sr. No. Solar Rooftop PV System Capacity/Capacity range Aggregate Capacity of execution of
in KW EPC work per month in KW
1 1 kW
2 1.01 to 2.00 kW
3 2.01 to 3.00kW
4 3.01 to 4.00 kW
5 4.01 to 5.00 kW
6 5.01 to 6.00 kW
7 Above 6 KW and up to 10 KW
8 Above 10 KW and up to 25 KW
9 Above 25 KW and up to 50 KW
11 Above 100 KW
44
THIS NEW FORMAT ADDED IN EOI
FORMAT -14
DEVIATION SHEET
(To be submitted in ‘on-line’ and physical mode by both ‘General and Open Category’ bidders)
Any deviations offered from the terms and conditions of the offer should be clearly specified below in this sheet. If there is no-deviation
Offered, it Should be clearly mentioned on this page.
45
THIS NEW FORMAT ADDED IN EOI
FORMAT -15
UNDERTAKING IN REGARD TO STOP DEAL / BLACK LIST THEREOF
(To be submitted in ‘on-line’ and physical mode by both ‘General and Open Category’ bidders)
Sub: Undertaking in regard to Stop Deal / Black List thereof.
I / We, an authorized signatory of our company (EOI applicant) here by certify that our company (EOI applicant) is
not stopped deal/blacklisted by GUVNL and or their any subsidiary company viz. GSCEL / GETCO / DGVCL / PGVCL
/ UGVCL / MGVCL / Torrent Power Ltd. Ahmedabad/ Torrent Power Ltd. Surat/SECI or MNRE or state Renewable
development agencies across the country or by any other Govt. PSU / Govt. Company / Govt. Department in India.
Authorized Signature
Company’s seal
Date
46
THIS NEW FORMAT ADDED IN EOI
FORMAT -16
Acceptance of Terms and conditions
(To be submitted in ‘on-line’ and physical mode by Both ‘General and Open Category’ bidders)
Name of EOI Applicant:-……………………………………………….
Accepted /
SR
Terms and conditions Not
No
accepted
1 Scope of work, technical specification and General & Commercial
Terms and condition of EOI Document.
2 Penalty condition in case the PV system fails to meet the minimum
instantaneous PR of 70%,
3 Penalty against delay in execution of project
4 PERFORMANCE GUARANTEE TO COVER EXECUTION PERIOD
(SECURITY) TERMS OF EOI DOCUMENT AGREED:
PERFORMANCE GAURANTEE TOCOVER GAURANTEE PERIOD
5 (INCLUDING MAINTENANCE DURING GUARENTEE PERIOD) TERMS
OF EOI DOCUMENT AGREED: (Wherever applicable):
6 VALIDITY OF THE OFFER OF EOI DOCUMENTAGREED
7 SUBSIDY TERMS
8 TERMS AND CONDITION OF EMD, SD AND PBG
9 TERMS OF PRICE DISCOVERY AND AGENCY
SHORTLISTING CRITERIA
TO EXECUTE THE PROJECT AS PER ALL RELVENT
10 STANDERDS/ IS/ CODE/ REGULATIONS/ GUIDELINES
ISSUED/ ENFORCED OR AMENDED/ UPDATED TIME TO
TIME BY APPROPIRATE AUTHORITY.
47
THIS NEW FORMAT ADDED IN EOI
FORMAT - 17
(To be submitted in online mode)
(UNDERTAKING IN REGARD TO QUOTED PRICE)
To be submitted in ‘on-line’ and physical mode)
(All bidders will have to furnish the following undertaking duly filled in, for all the quoted item/s of the EOI along with online
Technical)
We accept and undertake that MGVCL is authorized to place LOA/Purchase Order at lower 'unit ex- works price without GST on
ex-works price' than the 'unit ex-works price without GST on ex-works price' quoted/offered by us in the present EOI of
MGVCL for item/(s) under the EOI with similar specifications as per the above EOI of MGVCL, which is quoted/offered to other
subsidiary company of GUVNL, during the period of past 30 days from last date of submission of this EOI to next 30 days after
the last date of submission of bid of this EOI by MGVCL.
We also understand that LOA /Purchase Order placed by one Subsidiaries of GUVNL on the basis of above undertaking shall not
be considered as 'offered' price for the items under the EOI in subsequent tender/ EOI by other Subsidiaries of GUVNL, lf it is
not within period mentioned above.
------------------------------------------------------------------------------------------------
Check box: To be confirmed by the bidder in ONLINE mode. If not checked, the supplier will not able to submit his bid online
mode. The system shall give pop up message to supplier that in the event of non-checking of above box, he will not able to
submit his bid.
48
THIS NEW FORMATE ADDED IN EOI
FORMAT - 18
Details of the Quantity Offered by the Bidder
(To be submitted in ‘on-line’ and physical mode by Both General and Open Category’ bidders)
Quantity Offered by the Bidder for Design, Supply, Installation, testing & commissioning of Grid connected Rooftop Solar
Photovoltaic Systems in Residential premises
49