DETAILED MASTER SCHEDULE
January (1) February (2) March (3) April (4) May (5) June (6)
27-Dec 2-Jan 9-Jan 16-Jan 23-Jan 30-Jan 6-Feb 13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 1-May 8-May 15-May 22-May 29-May 5-Jun 12-Jun 19-Jun
1 PRE-CONSTRUCTION
Permits & Clearances
2 SUB-STRUCTURE
CIVIL/STRUCTURAL WORKS
Mobilization
Temporary Facitities
Clearing & Grubbing
Layout & Staking
Excavation
Reinf. Fabrication
Reinf. Installation
Concrete Pouring
Falseworks
Backfill
Embankment
3 GROUND FLOOR
CIVIL/STRUCTURAL WORKS
Slab base Preparation
Reinf. Installation
Falseworks installation
Concrete Pouring
ARCHITECTURAL WORKS
Masonry works
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Sunbuffer
January (1) February (2) March (3) April (4) May (5) June (6)
27-Dec 2-Jan 9-Jan 16-Jan 23-Jan 30-Jan 6-Feb 13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 1-May 8-May 15-May 22-May 29-May 5-Jun 12-Jun 19-Jun
ELECTRICAL WORKS
Rough-ins
Fixtures
PLUMBING WORKS
Rough-ins
Fixtures
ECE WORKS
Rough-ins
Fixtures
4 SECOND FLOOR
CIVIL/STRUCTURAL WORKS
Reinf. Fabrication
Reinf. Installation
Falseworks installation
Concrete Pouring
Structural Steel Works
ARCHITECTURAL WORKS
Masonry works
Roofing Works
Ceiling Works
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Alum. Cladding & Spandrel Ceiling
ELECTRICAL WORKS
Rough-ins
Fixtures
PLUMBING WORKS
Rough-ins
Fixtures
ECE WORKS
Rough-ins
Fixtures
ACTIVITIES 27-Dec 2-Jan 9-Jan 16-Jan
1 PRE-CONSTRUCTION
Permits & Clearances
2 SUB-STRUCTURE
CIVIL/STRUCTURAL WORKS
Mobilization
Temporary Facitities
Clearing & Grubbing
Layout & Staking
Excavation
Reinf. Fabrication
Reinf. Installation
Concrete Pouring
Falseworks
Backfill
Embankment
3 GROUND FLOOR
CIVIL/STRUCTURAL WORKS
Slab base Preparation
Reinf. Installation
Falseworks installation
Concrete Pouring
ARCHITECTURAL WORKS
Masonry works
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Sunbuffer
ELECTRICAL WORKS
Rough-ins
Fixtures
PLUMBING WORKS
Rough-ins
Fixtures
ECE WORKS
Rough-ins
Fixtures
4 SECOND FLOOR
CIVIL/STRUCTURAL WORKS
Reinf. Fabrication
Reinf. Installation
Falseworks installation
Concrete Pouring
Structural Steel Works
ARCHITECTURAL WORKS
Masonry works
Roofing Works
Ceiling Works
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Alum. Cladding & Spandrel Ceiling
ELECTRICAL WORKS
Rough-ins
Fixtures
PLUMBING WORKS
Rough-ins
Fixtures
ECE WORKS
Rough-ins
Fixtures
23-Jan 30-Jan 6-Feb
13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr
10-Apr 17-Apr
24-Apr W19 W20 (Month 5) W21 W22 W23 W24 (Month 6)
DETAILED MASTER SCHEDULE
ACTIVITIES W1 W2 W3 W4 (Month 1) W5 W6 W7
1 PRE-CONSTRUCTION
Permits & Clearances
2 SUB-STRUCTURE
CIVIL/STRUCTURAL WORKS
Mobilization
Temporary Facitities
Clearing & Grubbing
Layout & Staking
Excavation Footing
Reinf. Fabrication Footing, Column & Tie Beam
Reinf. Installation Footing & Col. Tie Beam
Concrete Pouring Footing & Column TB TB
Falseworks Column Tie Beam
Backfill
Embankment
3 GROUND FLOOR
CIVIL/STRUCTURAL WORKS
Slab base Preparation
Reinf. Installation Slab
Falseworks installation Column
Concrete Pouring
ARCHITECTURAL WORKS
Masonry works Below Grade Slab CHB Filling (1m ht.)
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Sunbuffer
ELECTRICAL WORKS
Rough-ins
Fixtures
PLUMBING WORKS
Rough-ins
Fixtures
ECE WORKS
Rough-ins
Fixtures
4 SECOND FLOOR
CIVIL/STRUCTURAL WORKS
Reinf. Fabrication Beams Beams Slab
Reinf. Installation Beams & Slab
Falseworks installation Scaffoldings, Shoring & Forms ( Beams & Slab)
Concrete Pouring
Structural Steel Works Trusses Fabrication
ARCHITECTURAL WORKS
Masonry works
Roofing Works
Ceiling Works
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Alum. Cladding & Spandrel Ceiling
ELECTRICAL WORKS
Rough-ins
Fixtures
PLUMBING WORKS
Rough-ins
Fixtures
ECE WORKS
Rough-ins
Fixtures
W8 (Month 2) W9 W10 W11 W12 (Month 3) W13 W14 W15 W16 (Month 4) W17
CHB Filling & Plastering
Door Jambs
Columns & Roof Beam
Beams & Slab Columns Roof Beam
& Forms ( Beams & Slab) Columns Roof Beam
Columns RB
Trusses, Purins & Accessories Installation
CHB Filling (1m ht.) CHB Filling & Plastering
W18 W19 W20 (Month 5) W21 W22 W23 W24 (Month 6)
Doors Windows
M1 M2 M3 M4 M5 M6
PRE-CONSTRUCTION
SUB-STRUCTURE
Civil Works
GROUND FLOOR
Civil Works
Archt. Works
SECOND FLOOR
Civil Works
Archt. Works