0% found this document useful (0 votes)
456 views19 pages

Construction Master Schedule Overview

The document provides a detailed master schedule for a construction project spanning 6 months from January to June. It is divided into 4 main sections - pre-construction, sub-structure, ground floor, and second floor. Each section contains civil/structural, architectural, electrical, plumbing and other works. The schedule outlines the timelines and sequence of key activities like permits, excavation, reinforcement installation, concrete works, masonry works, electrical/plumbing installation etc. for each section to be completed within the planned project duration.

Uploaded by

Oikea Builders
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
456 views19 pages

Construction Master Schedule Overview

The document provides a detailed master schedule for a construction project spanning 6 months from January to June. It is divided into 4 main sections - pre-construction, sub-structure, ground floor, and second floor. Each section contains civil/structural, architectural, electrical, plumbing and other works. The schedule outlines the timelines and sequence of key activities like permits, excavation, reinforcement installation, concrete works, masonry works, electrical/plumbing installation etc. for each section to be completed within the planned project duration.

Uploaded by

Oikea Builders
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

DETAILED MASTER SCHEDULE

January (1) February (2) March (3) April (4) May (5) June (6)
27-Dec 2-Jan 9-Jan 16-Jan 23-Jan 30-Jan 6-Feb 13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 1-May 8-May 15-May 22-May 29-May 5-Jun 12-Jun 19-Jun

1 PRE-CONSTRUCTION
Permits & Clearances

2 SUB-STRUCTURE
CIVIL/STRUCTURAL WORKS
Mobilization
Temporary Facitities
Clearing & Grubbing
Layout & Staking
Excavation
Reinf. Fabrication
Reinf. Installation
Concrete Pouring
Falseworks
Backfill
Embankment

3 GROUND FLOOR
CIVIL/STRUCTURAL WORKS
Slab base Preparation
Reinf. Installation
Falseworks installation
Concrete Pouring

ARCHITECTURAL WORKS
Masonry works
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Sunbuffer
January (1) February (2) March (3) April (4) May (5) June (6)
27-Dec 2-Jan 9-Jan 16-Jan 23-Jan 30-Jan 6-Feb 13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 1-May 8-May 15-May 22-May 29-May 5-Jun 12-Jun 19-Jun
ELECTRICAL WORKS
Rough-ins
Fixtures

PLUMBING WORKS
Rough-ins
Fixtures

ECE WORKS
Rough-ins
Fixtures

4 SECOND FLOOR
CIVIL/STRUCTURAL WORKS
Reinf. Fabrication
Reinf. Installation
Falseworks installation
Concrete Pouring
Structural Steel Works

ARCHITECTURAL WORKS
Masonry works
Roofing Works
Ceiling Works
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Alum. Cladding & Spandrel Ceiling

ELECTRICAL WORKS
Rough-ins
Fixtures

PLUMBING WORKS
Rough-ins
Fixtures

ECE WORKS
Rough-ins
Fixtures
ACTIVITIES 27-Dec 2-Jan 9-Jan 16-Jan

1 PRE-CONSTRUCTION
Permits & Clearances

2 SUB-STRUCTURE
CIVIL/STRUCTURAL WORKS
Mobilization
Temporary Facitities
Clearing & Grubbing
Layout & Staking
Excavation
Reinf. Fabrication
Reinf. Installation
Concrete Pouring
Falseworks
Backfill
Embankment

3 GROUND FLOOR
CIVIL/STRUCTURAL WORKS
Slab base Preparation
Reinf. Installation
Falseworks installation
Concrete Pouring

ARCHITECTURAL WORKS
Masonry works
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Sunbuffer

ELECTRICAL WORKS
Rough-ins
Fixtures

PLUMBING WORKS
Rough-ins
Fixtures

ECE WORKS
Rough-ins
Fixtures

4 SECOND FLOOR
CIVIL/STRUCTURAL WORKS
Reinf. Fabrication
Reinf. Installation
Falseworks installation
Concrete Pouring
Structural Steel Works

ARCHITECTURAL WORKS
Masonry works
Roofing Works
Ceiling Works
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Alum. Cladding & Spandrel Ceiling

ELECTRICAL WORKS
Rough-ins
Fixtures

PLUMBING WORKS
Rough-ins
Fixtures

ECE WORKS
Rough-ins
Fixtures
23-Jan 30-Jan 6-Feb
13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr
10-Apr 17-Apr
24-Apr W19 W20 (Month 5) W21 W22 W23 W24 (Month 6)
DETAILED MASTER SCHEDULE

ACTIVITIES W1 W2 W3 W4 (Month 1) W5 W6 W7

1 PRE-CONSTRUCTION
Permits & Clearances

2 SUB-STRUCTURE
CIVIL/STRUCTURAL WORKS
Mobilization
Temporary Facitities
Clearing & Grubbing
Layout & Staking
Excavation Footing
Reinf. Fabrication Footing, Column & Tie Beam
Reinf. Installation Footing & Col. Tie Beam
Concrete Pouring Footing & Column TB TB
Falseworks Column Tie Beam
Backfill
Embankment

3 GROUND FLOOR
CIVIL/STRUCTURAL WORKS
Slab base Preparation
Reinf. Installation Slab
Falseworks installation Column
Concrete Pouring

ARCHITECTURAL WORKS
Masonry works Below Grade Slab CHB Filling (1m ht.)
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Sunbuffer

ELECTRICAL WORKS
Rough-ins
Fixtures

PLUMBING WORKS
Rough-ins
Fixtures

ECE WORKS
Rough-ins
Fixtures

4 SECOND FLOOR
CIVIL/STRUCTURAL WORKS
Reinf. Fabrication Beams Beams Slab
Reinf. Installation Beams & Slab
Falseworks installation Scaffoldings, Shoring & Forms ( Beams & Slab)
Concrete Pouring
Structural Steel Works Trusses Fabrication

ARCHITECTURAL WORKS
Masonry works
Roofing Works
Ceiling Works
Tile Works
Painting Works
Doors & Windows
Handrails & Guardrails
Alum. Cladding & Spandrel Ceiling

ELECTRICAL WORKS
Rough-ins
Fixtures

PLUMBING WORKS
Rough-ins
Fixtures

ECE WORKS
Rough-ins
Fixtures
W8 (Month 2) W9 W10 W11 W12 (Month 3) W13 W14 W15 W16 (Month 4) W17

CHB Filling & Plastering

Door Jambs

Columns & Roof Beam


Beams & Slab Columns Roof Beam
& Forms ( Beams & Slab) Columns Roof Beam
Columns RB
Trusses, Purins & Accessories Installation

CHB Filling (1m ht.) CHB Filling & Plastering


W18 W19 W20 (Month 5) W21 W22 W23 W24 (Month 6)

Doors Windows
M1 M2 M3 M4 M5 M6

PRE-CONSTRUCTION

SUB-STRUCTURE
Civil Works

GROUND FLOOR
Civil Works
Archt. Works

SECOND FLOOR
Civil Works
Archt. Works

You might also like