Hazard Identification and Risk Assessment Worksheet.
Project Name : Project No : IN13-2910959 Ref No:
ROYAL ENFIELD VV1
Location : Paint Shop /Yard Work Activity Loading ,Unloading & Shifting of materials Page: 1 of 2
INITIAL RISK INITIAL RISK
S.No HAZARDS HARAM / EFFECTS CONTROLS
Severity Probability Risk Severity Probability Risk
Secure load with wedges and fasten by cargo
belt.
Load Only licensed and experienced person will
sliding/falling drive the truck.
1 Property damage & personal injuries H M H L L
off the trailer Obey all traffic signs 5 km/h at site L
Follow one way traffic rule in site..
Sound horn and reduce speed at turnings.
Banks man to escort the loaded trailer to site.
Mobile crane Set up the crane on a firm, ground level.
Property damage & Fatal, Loss of limb,
2 tends to Broken bone for person
H L M Competent & liciensed (HMV) should L L L
overturn operate the vechile .
Back of the
Provide reverse alarm and flag man.
3 trailer hitting Personal injuries & Fatal M L M Look at the back before reversing L L L
Worker
Personal injuries M M M Only certified rigger identified by wearing a L L L
Finger trapped
fluorescent jacket (red) will give signal to
4 between the
the crane operator
load and sling
He will ensure all persons are fully clear of
/conversion/tmp/activity_task_scratch/618319160.doc
DSIN 25.24 Hazard Identification and Risk assessment Dürr India Pvt. Ltd. 2 Page(s)
Hazard Identification and risk assessment worksheet Paint and Assembly Systems
PFS, APT, CTS
Version: C Operations
Issued on: 27.01.2014 S.Sridhar 1
Hazard Identification and Risk Assessment Worksheet.
the load.
INITIAL RISK
S.No INITIAL RISK
HAZARDS HARAM / EFFECTS CONTROLS
Severity Probability Risk Severity Probability Risk
Ensure the lifting gears have valid 3rd party
test certificates
Sling snaps and Check the slings before lift for their
5 load falls on Property damage & Fatal, Loss of limb,
M L M
condition and capacity. L L
L
persons. Broken bone for person Use softeners at sharp edges.
Barricade the area and exclude
unauthorized persons.
Use taglines to guide and control load.
Date
Assessed by M.Hariharan Position Safety Executive Signature
/conversion/tmp/activity_task_scratch/618319160.doc
DSIN 25.24 Hazard Identification and Risk assessment Dürr India Pvt. Ltd. 2 Page(s)
Hazard Identification and risk assessment worksheet Paint and Assembly Systems
PFS, APT, CTS
Version: C Operations
Issued on: 27.01.2014 S.Sridhar 2