ID Task Task Name Start Finish Duration Work
Mode
1 Cement Factory Mon 6/1/15 Mon 12/14/15 141 days 2,928 hrs
2 Envisioning & Design Mon 6/1/15 Thu 7/2/15 24 days 384 hrs
3 Meeting with Business user Mon 6/1/15 Fri 6/19/15 15 days 120 hrs
4 FSD preperation Mon 6/1/15 Fri 6/19/15 15 days 120 hrs
5 Submit FSD for Review Mon 6/22/15 Fri 6/26/15 5 days 80 hrs
6 Update FSD based on feedback Mon 6/29/15 Tue 6/30/15 2 days 32 hrs
7 Resubmit Review Wed 7/1/15 Thu 7/2/15 2 days 32 hrs
8 Finalize & Approve FSD Thu 7/2/15 Thu 7/2/15 0 days 0 hrs
9 Development Fri 7/3/15 Mon 11/16/15 97 days 2,224 hrs
10 Training Module Phase 2 Fri 7/3/15 Thu 8/13/15 30 days 640 hrs
24 Recruitment Wed 8/12/15 Tue 9/8/15 20 days 280 hrs
31 Employee Movement Tue 8/4/15 Fri 9/4/15 24 days 192 hrs
35 Employee History Module Mon 9/7/15 Fri 9/25/15 15 days 120 hrs
40 Enhancing position master module Mon 9/28/15 Mon 10/12/15 11 days 88 hrs
43 miscellaneous modules Fri 9/4/15 Mon 11/16/15 52 days 904 hrs
57 Deployment & UAT Tue 11/17/15 Mon 12/14/15 20 days 320 hrs
58 Deployment on Stagging server Tue 11/17/15 Wed 11/18/15 2 days 32 hrs
59 UAT & Training Thu 11/19/15 Wed 12/9/15 15 days 240 hrs
60 Deployment on production Thu 12/10/15 Mon 12/14/15 3 days 48 hrs
61 Deployment & UAT completed Mon 12/14/15 Mon 12/14/15 0 days 0 hrs
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 1
Predecessors Resource
May 24, '15 Names May 31, '15 Jun 7, '15 Jun 14, '15 Jun 21, '15 Jun 28, '15
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
C1[50%],C2[50%] C1[50%],C2[50%]
3SS C1[50%],C2[50%] C1[50%],C2[50%]
4 C1,C2 C1,C2
5 C1,C2 C1,
6 C1,C2
7 C1,C2
2
43 C1,C2
58 C1,C2
59 C1,C2
60
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 2
Jul 5, '15 Jul 12, '15 Jul 19, '15 Jul 26, '15 Aug 2, '15 Aug 9, '15
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
C1,C2
C1,C2
7/2
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 3
Aug 16, '15 Aug 23, '15 Aug 30, '15 Sep 6, '15 Sep 13, '15 Sep 20, '15
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 4
Sep 27, '15 Oct 4, '15 Oct 11, '15 Oct 18, '15 Oct 25, '15 Nov 1, '15
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 5
Nov 8, '15 Nov 15, '15 Nov 22, '15 Nov 29, '15 Dec 6, '15 Dec 13, '15
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
C1,C2
C1,C2
C1,C2
12/14
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 6