Sample Plan v3

This Gantt chart outlines the tasks, durations, dependencies, and resources for a project to develop a new cement factory system over 141 days from June 1, 2015 to December 14, 2015. It involves envisioning and design, development of various modules like training, recruitment, employee history, and deployment and user acceptance testing. Key milestones include finalizing the functional specifications document, completing development, and deploying the system.

Uploaded by

Shahab Juman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views6 pages

Sample Plan v3

This Gantt chart outlines the tasks, durations, dependencies, and resources for a project to develop a new cement factory system over 141 days from June 1, 2015 to December 14, 2015. It involves envisioning and design, development of various modules like training, recruitment, employee history, and deployment and user acceptance testing. Key milestones include finalizing the functional specifications document, completing development, and deploying the system.

Uploaded by

Shahab Juman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ID Task Task Name Start Finish Duration Work

Mode
1 Cement Factory Mon 6/1/15 Mon 12/14/15 141 days 2,928 hrs
2 Envisioning & Design Mon 6/1/15 Thu 7/2/15 24 days 384 hrs
3 Meeting with Business user Mon 6/1/15 Fri 6/19/15 15 days 120 hrs
4 FSD preperation Mon 6/1/15 Fri 6/19/15 15 days 120 hrs
5 Submit FSD for Review Mon 6/22/15 Fri 6/26/15 5 days 80 hrs
6 Update FSD based on feedback Mon 6/29/15 Tue 6/30/15 2 days 32 hrs
7 Resubmit Review Wed 7/1/15 Thu 7/2/15 2 days 32 hrs
8 Finalize & Approve FSD Thu 7/2/15 Thu 7/2/15 0 days 0 hrs
9 Development Fri 7/3/15 Mon 11/16/15 97 days 2,224 hrs
10 Training Module Phase 2 Fri 7/3/15 Thu 8/13/15 30 days 640 hrs
24 Recruitment Wed 8/12/15 Tue 9/8/15 20 days 280 hrs
31 Employee Movement Tue 8/4/15 Fri 9/4/15 24 days 192 hrs
35 Employee History Module Mon 9/7/15 Fri 9/25/15 15 days 120 hrs
40 Enhancing position master module Mon 9/28/15 Mon 10/12/15 11 days 88 hrs
43 miscellaneous modules Fri 9/4/15 Mon 11/16/15 52 days 904 hrs
57 Deployment & UAT Tue 11/17/15 Mon 12/14/15 20 days 320 hrs
58 Deployment on Stagging server Tue 11/17/15 Wed 11/18/15 2 days 32 hrs
59 UAT & Training Thu 11/19/15 Wed 12/9/15 15 days 240 hrs
60 Deployment on production Thu 12/10/15 Mon 12/14/15 3 days 48 hrs
61 Deployment & UAT completed Mon 12/14/15 Mon 12/14/15 0 days 0 hrs

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
Predecessors Resource
May 24, '15 Names May 31, '15 Jun 7, '15 Jun 14, '15 Jun 21, '15 Jun 28, '15
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

C1[50%],C2[50%] C1[50%],C2[50%]
3SS C1[50%],C2[50%] C1[50%],C2[50%]
4 C1,C2 C1,C2
5 C1,C2 C1,
6 C1,C2
7 C1,C2
2

43 C1,C2
58 C1,C2
59 C1,C2
60

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
Jul 5, '15 Jul 12, '15 Jul 19, '15 Jul 26, '15 Aug 2, '15 Aug 9, '15
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

C1,C2
C1,C2
7/2

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
Aug 16, '15 Aug 23, '15 Aug 30, '15 Sep 6, '15 Sep 13, '15 Sep 20, '15
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
Sep 27, '15 Oct 4, '15 Oct 11, '15 Oct 18, '15 Oct 25, '15 Nov 1, '15
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
Nov 8, '15 Nov 15, '15 Nov 22, '15 Nov 29, '15 Dec 6, '15 Dec 13, '15
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

C1,C2
C1,C2
C1,C2
12/14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cement Factory-2
Summary Manual Summary Rollup Progress
Date: Sun 5/17/15
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6