100% found this document useful (1 vote)
2K views10 pages

3-Bedroom Bungalow Estimate

This document is a cost proposal from SIEFSI Construction for the construction of a 3-bedroom bungalow, detailing the scope of work, material and labor costs, and payment terms. The total estimated cost for the project is Php. 1,806,170.08, which includes various construction phases such as earthworks, civil works, and fit-out works. The proposal also outlines the responsibilities of both the contractor and the owner regarding permits and project implementation.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views10 pages

3-Bedroom Bungalow Estimate

This document is a cost proposal from SIEFSI Construction for the construction of a 3-bedroom bungalow, detailing the scope of work, material and labor costs, and payment terms. The total estimated cost for the project is Php. 1,806,170.08, which includes various construction phases such as earthworks, civil works, and fit-out works. The proposal also outlines the responsibilities of both the contractor and the owner regarding permits and project implementation.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

SIEFSI CONSTRUCTION

DESIGN AND BUILD


Pob. Sur, Sta. Barbara, Pangasinan
Contact # 0908-185-1283

Ref. # : CFC/CAF0531202

Date : May 31, 2021

To : ________________________________

Subject : Cost Proposal for the Construction of 3-Bedroom Bungalow

Dear Sir,

Find herewith our best proposal for the Construction of 3-Bedroom Bungalow (interior) wit:

Scope of works:

A. GENERAL
1. Mobilization/demobilization of materials, instruments, equipment and manpower as necessary
for the completion of the project.
2. Hauling of all needed materials from any source to site.
3. Supply and provision of materials, labor, tools, equipment and supervision necessary to
complete the project.
4. Supply and installation of all materials not shown in the plan nor mentioned in these
specifications but necessary to complete the project.
5. Implement QC/QA program during project implementation.

B. CONSTRUCTION OF 3-BEDROOM BUNGALOW


1. Preparation of complete set of construction drawings and perspective.
2. Processing and acquisition of building permit. The Owner will pay for these permits or
approvals and cooperate in obtaining them.
3. Layout of concrete foundations.
4. Excavation works/backfilling works
5. Fabrication and installation of formworks
6. Fabrication and installation of reinforcing bars
7. Concrete pouring of concrete framing system
8. Construction of masonry including plaster finish
9. Fabrication and erection of structural steel works for the canopy.
10. Painting Works
11. Supply and Install of Doors and windows
12. Supply and install of Hanging Cabinet (kitchen only)
13. Ceiling Works
14. Tile Works
15. Electrical works including service entrance cap ready for tapping to power line supply
16. Plumbing works including all accessories specified on plan and specifications. (Water pump
not included)
17. Construction of Septic tank
SIEFSI CONSTRUCTION
DESIGN AND BUILD
Pob. Sur, Sta. Barbara, Pangasinan
Contact # 0908-185-1283

 Material Cost = Php. 1,206,170.08


 Labor Cost = Php. 600,000.00

GRAND TOTAL = Php. 1,806,170.08

Amount in words: One Million Eight Hundred Six Thousand One Hundred Seventy Pesos & 08/100

Notes:
1. During the actual construction to take on the owner recommendation with respects to the design
2. Contractor’s Price is VAT – Exclusive
3. Payment Terms:
 30% Down Payment upon approval of the Contract.
 70% Progress Billing, claim shall be accompanied by such evidence of the achievement of
such progress.

Regards,

ENGR. CHRISTIAN A. FERNANDEZ


Civil Engineer

Conforme :

_______________________
Owner
COMMERCIAL PROPOSAL

Project title PROPOSED 3-BEDROOM BUNGALOW

Client Estimated by: [Link] Page 1

Checked by: [Link] Date


Contract ref. SUMMARY OF PROPOSAL 31-May-21
Noted by: [Link] Estimated

ITEM WORK AREAS UNIT QTY. RATE(PHP.) AMOUNT(PHP.)

A.0 CONSTRUCTION PHASE:


A.1 EARTHWORKS [Link] 1.00 63,064.21 63,064.21
A.2 CIVIL WORKS [Link] 1.00 689,680.88 689,680.88
A.3 FIT OUT WORKS [Link] 1.00 1,053,425.00 1,053,425.00

TOTAL PROPOSED CONTRACT AMOUNT(PHP.) 1,806,170.08


AMOUNT IN WORDS:
One Million Eight Hundred Six Thousand One Hundred Seventy Pesos & 08/100
DETAILED BREAKDOWN

Project title PROPOSED 3-BEDROOM BUNGALOW


Client Estimated by: [Link] Page 2

Checked by: [Link] Date


Contract ref. 31-May-21
Noted by: [Link] Estimated

ITEM No. SHORT DESCRIPTION UNIT QTY. Material Cost Labor Cost AMOUNT
(1) (2) (3) (4) (5) (6) (4) x [(5)+(6)]
A.1 EARTHWORKS
Demolition Works (Roofing) lot 1.00 10,000.00 10,000.00
Layout and Batterboard lot 1.00 5,000.00 3,000.00 8,000.00
Excavation cu.m 60.00 495.52 29,731.20
Earthfill and Backfill cu.m 28.70 258.65 7,423.26
Gravel Bedding cu.m 14.50 500.00 45.50 7,909.75

PAGE -2 TOTAL CARRIED FORWARD TO SUMMARY 63,064.21


DETAILED BREAKDOWN

Project title PROPOSED 3-BEDROOM BUNGALOW


Client Estimated by: [Link] Page 3

Checked by: [Link] Date


Contract ref. 31-May-21
Noted by: [Link] Estimated

ITEM No. SHORT DESCRIPTION UNIT QTY. Material Cost Labor Cost AMOUNT
(1) (2) (3) (4) (5) (6) (4) x [(5)+(6)]
A.2 CIVIL WORKS
Structural Steel Works
Concreting Works
Column Footing cu.m 3.00 12,000.00 4,000.00 48,000.00
Column cu.m 1.40 12,000.00 4,000.00 22,400.00
Wall Footing cu.m 2.65 12,000.00 4,000.00 42,368.00
Reinforced Concrete Beam cu.m 3.60 12,000.00 4,000.00 57,600.00
Slab on Ground cu.m 3.50 12,000.00 4,000.00 56,000.00
Septic Tank cu.m 1.58 12,000.00 4,000.00 25,280.00
Kitchen Counter cu.m 1.20 12,000.00 4,000.00 19,200.00
Masonry Works
CHB 4" sq.m 236.16 489.39 220.00 167,529.54
Plastering sq.m 472.32 200.00 180.00 179,481.60
Structural Steel Works
Canopy kgs 456.07 65.78 26.31 42,000.40
Poly Carbonate Sheet sqm 34.96 489.65 220.34 24,821.34
Consumables lot 1.00 5,000.00 5,000.00

PAGE -3 TOTAL CARRIED FORWARD TO SUMMARY 689,680.88


DETAILED BREAKDOWN

Project title PROPOSED 3-BEDROOM BUNGALOW


Client Estimated by: [Link] Page 4

Checked by: [Link] Date


Contract ref. 31-May-21
Noted by: [Link] Estimated

ITEM No. SHORT DESCRIPTION UNIT QTY. Material Cost Labor Cost AMOUNT
(1) (2) (3) (4) (5) (6) (4) x [(5)+(6)]
A.3 FIT OUT WORKS
Ceiling and Carpentry Works
Supply and Installation of Ceiling sq.m 110.70 800.00 300.00 121,770.00
Supply and Installation of Hanging Cabinet l.m. 8.76 3,500.00 1,500.00 43,800.00
Doors and Windows
D-1 sets 1.00 8,000.00 1,500.00 9,500.00
D-2 sets 4.00 8,000.00 1,500.00 38,000.00
D-3 sets 1.00 8,000.00 1,500.00 9,500.00
W-1 sets 2.00 9,600.00 1,920.00 23,040.00
W-2 sets 2.00 3,000.00 600.00 7,200.00
W-3 sets 1.00 24,000.00 4,800.00 28,800.00
W-4 sets 2.00 12,000.00 2,400.00 28,800.00
W-5 sets 1.00 9,600.00 1,920.00 11,520.00
W-6 sets 2.00 9,600.00 1,920.00 23,040.00
W-7 sets 1.00 1,920.00 384.00 2,304.00
Door Hardwares lot 1.00 12,000.00 3,000.00 15,000.00
Tile and Stone Works
600mm x 600mm Homogenous Floor Tiles sq.m 145.66 1,100.00 300.00 203,924.00
600mm x 600mm Homogenous Wall Tiles sq.m 33.30 1,100.00 300.00 46,620.00
Painting Works
Exterior Walls sq.m 236.16 180.00 110.00 68,486.40
Interior Walls sq.m 236.16 250.00 110.00 85,017.60
Ceiling sq.m 110.70 180.00 110.00 32,103.00
Painting Works of Roofing lot 1.00 25,000.00 10,000.00 35,000.00
Electrical Works
Electrical Works lot 1.00 110,000.00 40,000.00 150,000.00
Plumbing Works
Plumbing Works lot 1.00 50,000.00 20,000.00 70,000.00

PAGE -4 TOTAL CARRIED FORWARD TO SUMMARY 1,053,425.00


.
`

You might also like