Ecm367 Lecture Notes
Ecm367 Lecture Notes
PRINCIPLES OF
MANAGEMENT
LESSON OUTCOMES (LO)
At the end of this module, students should be able to:
Understand the sequential and continuous function of
construction management.
Explain the principle requirements and processes
involved in sequential function of construction
management.
CONSTRUCTION
In the fields of architecture and civil engineering, construction
is a process that consists of the building or assembling of
infrastructure, which may involve some or any of the activity
as follow:-
Site Position
Site Clearing
CCC
Hand-Over
awang295@[Link]
MANAGEMENT
The art and science of controlling human resources,
equipment, materials, cash flow and schedule to complete a
project within a specified time and approved cost efficiently
and effectively.
Various activities involving the organization at multi-level of
the number of individuals.
The function of getting things done through other people.
awang295@[Link]
CONSTRUCTION
MANAGEMENT
Study and practice of the managerial and technological
aspects in construction industry.
E.g.: construction, construction science, construction
management and construction technology.
May also serve as a consultant, providing both design and
technical construction advice.
awang295@[Link]
FUNCTIONS OF MANAGEMENT
Sequential Function
Occur in sequence
Includes planning, organizing, staffing, directing
and controlling (POSDC)
Output or result of an activity is measured
Necessary corrective action will be proposed
Appears in cycle
MOSTLY OCCUR DURING CONSTRUCTION STAGE
Continuous Function
Problem analysis, decision-making
and communicating
Throughout the management processes
rather than any particular sequence
Manager must have effective communication skill
MOSTLY OCCUR DURING DESIGN STAGE
awang295@[Link]
SEQUENTIAL FUNCTION
MANAGEMENT
1. Planning
2. Organizing
INPUT 3. Staffing OUTPUT
4. Directing
5. Controlling
awang295@[Link]
SEQUENTIAL FUNCTION
MANAGEMENT
INPUT SUCCESSFUL
(Resources) = MANAGEMENT
OUTPUT =
Human, Financial, =
Time, Money and
Technological Efficiently
Quality
and Natural +
Effectively
awang295@[Link]
PLANNING
Who conducts Planning?
Planner or Manager.
One who directs the work of others
and who does his work by getting
other to do theirs.
‘People at the top’.
awang295@[Link]
PLANNING
The formulation of a course of action
(objectives) to guide a project to
completion.
Resources planning management
including time, cost, equipment,
manpower and schedule.
Use Master Work Programme to
breakdown the main activities (Task)
into smaller activities (Sub-Task).
awang295@[Link]
PLANNING
5 Steps Involved In Planning Process.
awang295@[Link]
ORGANIZING
The process of assigning tasks,
allocating resources and arranging
coordinated activities to implement
plans.
Establishing the organizational
structure.
Defining responsibilities of each
department.
Establish relationship between
individual/department to others.
awang295@[Link]
STAFFING
Control selection of individuals who
have the expertise to produce the
work.
People are the most important
resource as they provide the
knowledge to design, coordinate and
construct the project.
Consists of assigning human
resources, work progress evaluation,
promoting and suspending human
resources.
awang295@[Link]
About Planning,
Organizing and Staffing
PLANNING, ORGANIZING and STAFFING are THE MOST
INTER-RELATED processes in performing planning
management.
awang295@[Link]
DIRECTING
Process of directing, issuing
orders/instructions to the human
resource efforts with guidance of work
for project completion.
Important skills required;
communication, motivation, decision
making, problem solving, supervision
and public relation.
Influencing others' behaviour,
leadership and discipline.
Steps include staffing, training,
supervising, delegating and motivating.
awang295@[Link]
DIRECTING
Steps Involved In Directing Process
Staffing: seeing that a qualified person is
selected for each position.
awang295@[Link]
CONTROLLING
Establish a system to measure, report and
forecast outcome/corrective actions in
project scope, budget, schedule.
Requires the continual reporting of
information in a timely manner to have
direct management respond.
Most difficult tasks.
Steps; determine standard and progress,
progress evaluation, establish verification
system, corrective plan.
Ensures that plans are being
implemented properly (influence
schedule, cost, quality, etc.).
awang295@[Link]
CONTROLLING
3 steps process of measuring progress
towards an objective, evaluating what
remains to be done and taking the
necessary corrective action to achieve
or exceed the objectives as follow:-
During design stage, most of the problems that are expected will be
analyzed and communicated thoroughly so that the project is able to run
smoothly. However, continuous function does not necessarily stop there. It
depends on the project progress.
Directing – Project Manager will play the vital role here to ensure everyone
feels motivated to complete the project and accomplish their tasks
throughout the project lifecycle.
awang295@[Link]
SUMMARY
awang295@[Link]
ACKNOWLEDGEMENTS
Additional Notes:
Principles of Management
Management Principles
CONTENT DEVELOPERS
Topic 2
Introduction To The
Construction Industry
Learning Outcomes (LO)
awang295@[Link]
Construction Industry
Scenario
• As one of the largest industry in the world
b. Infrastructure
1. Switzerland 8. France
2. Singapore 9. Austria
awang295@[Link]
awang295@[Link]
Construction Industry Scenario
• Strong influence on the global economy because of diverse trades and
professions (mega projects)
• Construction 7 years
‒ Planning on the Petronas Towers started on 1st January 1992.
‒ Spires of Tower 1 and Tower 2 were completed on 1 March
1996.
‒ Officially opened by the Prime Minister of Malaysia's Tun Dr.
Mahathir bin Mohamad on 1st August 1999.
awang295@[Link]
iii. Dam and hydroelectric Projects
Construction ‒ Bakun Dam, Sarawak, Malaysia.
Industry
➤ Total cost for building the entire dam is
valued at RM5.8 billion.
awang295@[Link]
Scenario in
Malaysia
‒ Government is the biggest key player (owner)
‒ E.g. through:-
➤ Malaysia Plan (Eleventh Malaysia Plan)
➤ Master Plan City or District
awang295@[Link]
Scenario in
Malaysia
awang295@[Link]
Scenario in
Malaysia
In 2015, construction industry employed 1.3 million peoples, whereas in 2016 the contribution of GDP
from construction sector was RM 49.87 billion. (Department of Statistics, Malaysia)
awang295@[Link]
Scenario in
Malaysia
Advantages
Political Stability
Peacefulness
Economic Prosperity
awang295@[Link]
Scenario in
Malaysia
Problems faced
Highly traditional and fragmentation
Slow to embrace new technology
Restrictive/outdated building codes
Labour agreements and craft jurisdictional issues
Liability and legal consideration
Lack of profit motive or other incentive
awang295@[Link]
Scenario in
Malaysia
awang295@[Link]
Owner/Client/Developer
Powers to:
• Defer giving possession of site to the contractor
• Assign the contract
• Appoint clerks of works
• Insure against property damage
• Employ and pay other persons to do work (third
party)
awang295@[Link]
Owner/Client/Developer
Some of the project appoint Project Manager to deal
directly with consultant or contractor to perform task
as follow:-
Act as a leader of the planning team
To coordinate the project with local and federal
authorities
Responsible for calling and recommendation of
tenders
To certify progress payment to consultant and
contractor
To keep a record of work progress and report to
the management other problems encountered.
awang295@[Link]
Owner/Client/Developer
Duties to:
awang295@[Link]
Consultant
awang295@[Link]
Contractor
• Main Contractor that physically translates the
projects by coordinating the works of various
contractor through the construction works.
• Powers to:
‒ Inspect the contract documents
‒ Assign the contract if consent is given
‒ Sub-contract any part of the works if required
‒ Serve a default notice on the owner specifying the
faults alleged
awang295@[Link]
Contractor
Duties to:
awang295@[Link]
Sub-Contractor (SC)
awang295@[Link]
Nominated Sub-Contractor
(NSC)
awang295@[Link]
Nominated Supplier
awang295@[Link]
Financial Institution
awang295@[Link]
Government
Agencies
Local Authorities
awang295@[Link]
Government Government Department
• Sewerage work
➤ SPAN
➤ IWK (different for East Malaysia)
awang295@[Link]
Government Government Department
awang295@[Link]
Government
Agencies
awang295@[Link]
Lawyers
awang295@[Link]
Summary
Malaysia construction industry progressive towards Vision
2020 and National Transformation 2050.
All parties need to communicate and cooperate for better
performance of construction industry.
awang295@[Link]
Acknowledgements
Janidah Eman (UiTMPP)
Nur Muizzah Nawi (UiTMJ)
Muhammad Isha Ismail (UiTMP)
Noor Raifana Ab Rahim (UiTMJ)
Chitkara, K. K. (2014). Construction Project Management. Tata
McGraw-Hill Education.
References
Knutson, K., Schexnayder, C. J., Fiori, C., Mayo, R. E. (2009).
Construction Management Fundamentals (2nd ed.). McGraw-Hill
Additional Notes:
The Work of The Construction Industry
What is the Construction Industry? An Economic Fact Book
Global country ranking by quality of infrastructure (2016)
Content Developers
TOPIC 3
INTRODUCTION TO
PROJECT
MANAGEMENT
LESSON OUTCOMES (LO)
At the end of this module, students should be able to understand and explain:
The definition and concept of project management.
The objective of project management.
The key indicators in defining a successful project.
DEFINITION & CONCEPT
Buchanan & Boddy (1992) p.8 - Take the Lead: Interpersonal Skills
for Project Managers
awang295@[Link]
DEFINITION & CONCEPT
awang295@[Link]
DEFINITION & CONCEPT
PROJECT CHARACTERISTICS
Project is a unique undertaking
Projects have specific objectives (or goals) to achieve
Projects require resources
Projects have budgets
Projects have schedules
Projects require the effort of people and measures of quality will apply
Projects require temporary organization
Projects are not permanent in nature
awang295@[Link]
DEFINITION & CONCEPT
awang295@[Link]
DEFINITION & CONCEPT
(Oxford dictionary)
awang295@[Link]
DEFINITION & CONCEPT
Art encompasses:
Political and interpersonal skills
Making creative decisions
Knowing intuitively when to delegate works
The art of leadership embodies skills that are gain through experience,
sensitivity and a thorough knowledge of the Basic Science of
Management
awang295@[Link]
DEFINITION & CONCEPT
awang295@[Link]
DEFINITION & CONCEPT
awang295@[Link]
DEFINITION & CONCEPT
CONCEPT OF PROJECT
MANAGEMENT (PROCESS INVOLVE)
A Process is:
“A Series of actions bringing about results”.
PLANNING EXECUTING
INITIATING
PROCESSES PROCESSES
PROCESSES
awang295@[Link]
CONTROLLING CLOSING
PROCESSES PROCESSES
DEFINITION & CONCEPT
CONCEPT OF PROJECT
MANAGEMENT (PROCESS INVOLVE)
INITIATING PROCESS (Definition stage)
Considers the necessary processes to assure that the project will be accomplished.
awang295@[Link]
DEFINITION & CONCEPT
CONCEPT OF PROJECT
MANAGEMENT (PROCESS INVOLVE)
PLANNING PROCESS
The planning process aims at planning the work scheme or program to achieve
the project objectives.
Involving defining the scope, formulation of execution strategies, sequencing of
activities and planning of resources required.
Note: all actions above are usually illustrated on the Master Work Programme.
awang295@[Link]
DEFINITION & CONCEPT
CONCEPT OF PROJECT
MANAGEMENT (PROCESS INVOLVE)
EXECUTING and MONITORING PROCESSES
Consists of coordinating people and resources to execute the plan and involves
quality and cost control procedures, information distribution and suppliers selection.
It is at the implementation stage that all the activities and actions take place.
Monitoring processes aim at assuring that the project objectives are achieved
through monitoring and appraisal of its progress, controlling project changes or
variations which may effect costs, quality and risks.
The sooner the problems, delay or changes are identified, the easier it will be for
the project manager to address them, adjust its course and meet the project
goals.
Note: Most of the executing and controlling activities will conducted as per
PQP or SOP provided by contractor with approval from consultants.
awang295@[Link]
DEFINITION & CONCEPT
CONCEPT OF PROJECT
MANAGEMENT (PROCESS INVOLVE)
CLOSING PROCESS
At this stage, it is important to review the project’s performance on time, budget,
team performance, quality related problems and also to complete all the
necessary reports, audits and paper works.
(CCC + HO + LD + DC [as-built & etc.])
It will be beneficial to use this information to learn from the project and utilize
this information to ensure continual improvement in future projects.
awang295@[Link]
OBJECTIVES
The objectives of
construction project
management is to
TIME COST
make sure that the
project completion on
time, within cost, RESOURCES
required quality of
standards and meets
the client’s needs and PERFORMANCE
requirements.
awang295@[Link]
OBJECTIVES
OVERVIEW OF PROJECT
MANAGEMENT (HAROLD KERZNER,
2006)
awang295@[Link]
INDICATORS OF A SUCCESSFUL PROJECT MANAGEMENT
awang295@[Link]
INDICATORS OF A SUCCESSFUL PROJECT MANAGEMENT
Project success are related to project objectives; hence the Key Performance
Indicators to measure the success of a project are:
Costs
Time
Quality
Health and Safety
Environmental Performance
Profit and Commercial Value
Team Participation Satisfaction
User or Client’s Satisfaction
awang295@[Link]
INDICATORS OF A SUCCESSFUL PROJECT MANAGEMENT
1. INADEQUATE RESOURCES
2. UNREALISTIC DEADLINE
3. UNCLEAR GOALS OR DIRECTION
4. TEAM MEMBERS UNCOMMITTED
5. INSUFFICIENT PLANNING
6. COMMUNICATION BREAKDOWN
awang295@[Link]
INDICATORS OF A SUCCESSFUL PROJECT MANAGEMENT
According to Sariwati, Sodri and Ahmanul (2007), the success of a project is still
determined by these factors:
The project scope or work scope: The work must be done within the
prescribed work scope set by the customer and that the deliverables meet the
customers’ requirements or acceptance criteria.
The project cost: The project cost is based on a budget that includes cost
estimates associated with all the various resources that will be used to
accomplish the project. The cost of the project is the amount that the
customer is paying for the project and its deliverables.
awang295@[Link]
INDICATORS OF A SUCCESSFUL PROJECT MANAGEMENT
According to Sariwati, Sodri and Ahmanul (2007), the success of a project is still
determined by these factors: (cont)
The project time schedule: The time schedule specifies when each activity
should start and finish. To achieve the project objectives, it is important to
develop the time schedule plan before the start of the project; and this plan
should include all work tasks, associated costs and time estimates to
complete all the activities till project completion.
Customer satisfaction: The main responsibility of a project manager is to
ensure that the customers are satisfied. A project manager must execute
good planning and communication skills to resolve problems, and to minimize
its impacts on the achievement of the project objectives and assuring
customer’s satisfaction.
awang295@[Link]
INDICATORS OF A SUCCESSFUL PROJECT MANAGEMENT
According to Sariwati, Sodri and Ahmanul (2007), the success of a project is still
determined by these factors: (cont)
Achieve the business objectives and smart goals: To create project goals, it
have to be specific, and measurable in terms of time and costs, achievable
where every team member agrees to these goals and realistic in terms of
costs, resources and time management.
Good management support with high commitment and active team
involvement throughout the phase of the project.
An experienced project manager with good leadership, communication and
human skills.
awang295@[Link]
SUMMARY
PLANNING
INITIATING
PROCESSES
PROCESSES
EXECUTING
PROCESSES
CONTROLLING
PROCESSES
CLOSING
PROCESSES
awang295@[Link]
ACKNOWLEDGEMENTS
Janidah Eman (UiTMPP)
Nur Muizzah Nawi (UiTMJ)
Muhammad Isha Ismail (UiTMP)
Noor Raifana Ab Rahim (UiTMJ)
REFERENCES
Chitkara, K. K. (2014). Construction Project Management. Tata McGraw-Hill
Education.
Additional Notes:
Peterson, S. (2012). Pearson’s Pocket Guide to Construction Management.
Prentice Hall. Chapter 7: Introduction to Construction Management.
Introduction to Project Management
Project Management Handbook (2006)
CONTENT DEVELOPERS
TOPIC 4
CONSTRUCTION
PROJECT
LIFECYCLE
LESSON OUTCOMES (LO)
At the end of this module, students should be able to:
Understand the definition and concept of construction
project lifecycle.
Understand and explain the phases and construction
project lifecycle using RIBA plan of work;
i. Inception Phase / Pre-Construction Phase.
ii. Construction Phase.
iii. Completion Phase / Post-Construction Phase.
Definition & Concept
awang295@[Link]
Definition & Concept
CONSTRUCTION PHASE
COMPLETION PHASE/Post-Construction Phase
Three main phases and construction PLC using RIBA Plan of Work
Associate Drawings (PLC) CONCEPT
Pre-Tender Phase
}
• Conceptual drawings (normally prepared by an architect)
• Preliminary drawings (various amendment)
}
Construction Phase
• Construction drawings (endorsed by architect/engineer) with
CONSTRUCTION
input from shop drawings PHASE
• Shop drawings (prepared by sub-contractor, endorsed by
consultant)
COMPLETION
}
Completion Phase/Post-Construction Phase PHASE
(Post-Construction
• As-Built (after construction completed)
Phase)
awang295@[Link]
Definition & Concept
TWO WAYS OF
LOOKING AT PLC
BY PROJECT
PHASE (ADAMS
AND BRANDT,
1983):
awang295@[Link]
Managerial actions
Tasks accomplish
Definition & Concept
awang295@[Link]
Construction Phase
CONSTRUCTION PHASE:
Detail out of project planning and execution inclusive of
monitoring and controlling the project.
Converting idea from designers’ plans and specifications to the
physical structures or facilities within controlling the time, cost
and quality.
CONSTRUCTION TEAMS:
Including Project Manager Team, Specialist in design level, Main
Contractor, Sub-contractors and Suppliers.
awang295@[Link]
( )
DETAILED OUT IN TOPIC
10 FOR SITE
ORGANIZATION
GENERAL
FLOWCHART OF
awang295@[Link]
CONSTRUCTION
PHASE
Construction Phase
The objectives:
Deposit for loans ‒ The security deposits serves as security against the
materials or plant and machinery delivered to site; which on behalf of the
contractor, the bank had paid to the supplier.
Punishment ‒ In case the contractor does not complete the work in time, use
inferior quality materials or left the work incomplete, the security deposit is
forfeited as a punishment to the contractor and in view of getting
compensation of the damages done by the contractor to the owner.
awang295@[Link]
Construction Phase
War, invasion, act of foreign enemy, civil war, rebellion, mutiny, riot and
civil combination.
Nuclear reaction and radiation.
Willful act or negligence of the insured.
Cessation of works when total or partial.
awang295@[Link]
Construction Phase
awang295@[Link]
Construction Phase
Contract drawing
Drawings embedded in the contract document with stamping imprint with the
words of “CONTRACT DRAWING” for all discipline as per agreed in early
tendering stage by consultants namely as architecture, structural, civil,
surveyor, mechanical and electrical.
Useful as a reference for any misunderstanding during the construction stage.
Construction drawing
Design drawings that have been approved by the responsible parties
(consultants) for construction stage usages.
Attached with the detailing and subjected to revision if any change has been
made by responsible parties.
The drawing is imprint with the stamping words of “CONSTRUCTION
DRAWING”.
awang295@[Link]
Construction Phase
Shop drawing
Consists of drawings, schedules, diagrams, and other related data to illustrate
a material, a product, or a system for some portion of the work not clarified in
the Construction drawing or counter proposed detail design from contractor,
subcontractor, manufacturer, distributor or supplier.
Compulsory to seek design approval from relevant external consultant before
it is able to be used for construction after permission from existing consultant.
awang295@[Link]
Construction Phase
Site Meeting
To coordinate site activities, monitor
awang295@[Link]
Construction Phase
awang295@[Link]
Construction Phase
awang295@[Link]
Completion Phase/Post-Construction Phase
GENERAL
FLOWCHART OF
POST-CONSTRUCTION
PHASE
awang295@[Link]
Completion Phase/Post-Construction Phase
awang295@[Link]
Completion Phase/Post-Construction Phase
FINAL INSPECTION
Before the S.O. is able to issue CPC, there is a final inspection conducted to identify
any defects for completed works.
Include the comments from relevant authorities starting from design stage to the
project completion.
Also include inspection for utilities/infrastructure such as water reticulation,
sewerage and drainage systems.
awang295@[Link]
Completion Phase/Post-Construction Phase
FINAL INSPECTION
Testing and Commissioning conducted within certain periods or times to fulfill the
function and safety. The facilities or services involves are as bellow:
• Plumbing – pressure test, etc.
• Fire Fighting System – Active and Passive
‒ Active include sprinklers, pump and etc.
‒ Passive include fire extinguishers, passage ways and etc.
• Lift System – Motor room, lift system, etc.
• A/C System – chillers, pumps, temperature, air balancing, etc.
• Electrical System – continuity and insulation test, lamps, gen-set.
After final inspection and Testing and Commissioning completed, S.O. will then issue
Schedule of Defects to the main contractor within 14 days to resolve/improve during
Defect Liability Period (DLP).
awang295@[Link]
Completion Phase/Post-Construction Phase
S.O. shall issue CPC to Main Contractor by stating the date of completion based on
agreed DLP and attached together with Schedule of Defects.
The issuance of CPC means the starting of DLP.
With the issuance of CPC, Main Contractor shall prepare the documents below:
‒ As-Built Drawing
‒ Compilation of Quantitative and Qualitative Records.
‒ Warranty roducts
‒ Final Claim
awang295@[Link]
CERTIFICATE OF
Completion Phase/Post-Construction Phase
PRACTICAL
COMPLETION (CPC)
Compilation of Qualitative
As-Built Drawing and Quantitative Records
Including as built drawings for piling, Qualitative records include measurement
sanitary and cold water and etc. It is and observations of works related to the
pictorial record of all the works quality and behavior under test such as
completed, showing the whereabouts and result of compression tests (cube test),
dimensions of all parts as they exist at piling test, soil test and etc.
completion, their operation as described Quantitative records include measuring
in the instruction manual and their of work done with the time and rate
performance under tests. stated, together with all relevant
particulars including piling record, Claim
Warranty Products
Evaluation, Progress/Interim Payment
Warranty products are such as warranty
and etc. Warranty Products
for water proofing, painting, roofing and
etc.
awang295@[Link]
Completion Phase/Post-Construction Phase
Final Claim
The Main Contractor shall submit the Final
CERTIFICATE OF
Claim (include all variations) within 3 months
PRACTICAL affected from issuance of CPC to enable S.O.
COMPLETION (CPC) prepare the Final Account.
(CONT) After issuance of Final Claim, the contractor
shall not claim for any money.
awang295@[Link]
Completion Phase/Post-Construction Phase
HAND OVER
The issuance of CCC approval means the readiness of structure or facilities hand
over to client and ready for public usages.
awang295@[Link]
Completion Phase/Post-Construction Phase
FINAL CERTIFICATE
awang295@[Link]
PROJECT LIFECYCLE:
awang295@[Link]
ACKNOWLEDGEMENTS
Ritz, G. J., Levy, S. M. (2013). Total Construction Project Management (2nd ed.).
McGraw-Hill Education.
Additional notes:
Pellicer, E., Yepes, V., Teixeira, J. C., Moura, H. P., Catalá, J. (2013). Construction
Management. Wiley-Blackwell. Chapter 1: Organising Construction Processes in
Construction Companies, Chapter 15: Project Closeout.
awang295@[Link]
awang295@[Link]
Associate drawings
Pre-tendering
phase
General flowchart of
Pre-Tendering Phase
Needs and Objectives of the Project
DETAIL EXPLANATION IN TOPIC 6
awang295@[Link]
Conceptual Drawings
Based on RFP, the architect shall produce the conceptual drawings for
consultant engineers to work on detail engineering and design.
The building illustration by architect shows the overall views of the
project including elevations, views and cut-sections of the building.
Planning Execution
Planning execution includes tasks as follow:
i. Management and Coordination
ii. Design
iii. Construction
‒ Supervision
‒ Method of Construction
‒ Approval from Authorities
awang295@[Link]
Planning Execution
Management and Coordination
A representative on behalf of Client responsible to coordinate the
activities of those engaged in the design on construction of the project
and also lies between the management.
Preferably an architect or civil engineer.
Employer decide either to delivered the project by Turnkey Contract or
Traditional Contract.
awang295@[Link]
Planning Execution
Design
Execute based on type of Project Delivery System implemented as
follow:
– Use-in house technical team – Turnkey contract
– Employ consultants – Traditional Contract
Two main phases of engineering and design:
– Preliminary
– Detail
awang295@[Link]
Planning Execution
Design: Preliminary Engineering and Design
Emphasize on architectural concepts, evaluation of technological process
alternatives, size and capacity decisions and comparative economic studies.
The steps evolve directly from the concept and feasibility stage, and it is
sometimes difficult to see where one leaves off and the other begins.
In heavy construction, engineers are responsible for the preliminary design,
but they often need substantial input from geologist, hydrologist, and
increasingly from ecologist and other professionals in the natural sciences.
In construction industry, it involves input and output decisions, choices
awang295@[Link]
awang295@[Link]
Planning Execution
Construction: Authorities Approval
Before commencement of any construction, all the design and construction
method adopted must first receive the approval from the local and federal
authorities: i.e. all designs must comply with the building-laws of the following
authorities;
Municipality / City Council.
JPBD (Jabatan Perancangan Bandar raya).
JKR (Jabatan Kerja Raya).
JBA (Jabatan Bekalan Air).
JPS (Jabatan Pengairan dan Saliran).
JAS (Jabatan Alam Sekitar).
JPP (Jabatan Perparitan dan Pembetungan) – IWK.
TNB (Tenaga Nasional Berhad).
Telekom.
Public Health Department.
Fire Fighting Department.
Factory Act for Machinery Department.
awang295@[Link]
Feasibility Study (FS) and Site Investigation (SI)
WILL BE COVERED IN DETAIL IN TOPIC 6 ON SITE SELECTION
FS reveal on objective, business and technical point of view in order to help
Client to make decisions on planning and execution of the project.
SI is a detail investigation based on FS and emphasize more on the
economical and technical factor in order to help Client minimize the cost
within design and safety optimizations .
awang295@[Link]
Preliminary Drawing
Initial plans for projects prepared by the designer or architects and
engineers firm during the early planning or promotional stage of the
building development.
These drawings are NOT intended to be used for construction, but they are
used for exploring design concepts, material selection, preliminary cost
estimates, approval by the customer, and as a basis for the preparation of
finished working drawings.
awang295@[Link]
awang295@[Link]
TENDERING PHASE
General flowchart of
Tendering Phase
awang295@[Link]
Tender Document and Tender Drawings
TENDER DRAWINGS
Design drawing that need to be used for tendering stage and should be
attached with tender document.
Consists of architectural, structural, mechanical and sanitary, and
M&E services drawings.
TABLE TENDER DOCUMENT (TTD)
TTD is a drawing showing all particular details of layout drawing such
as type of material, sizes of structures (foundation, column, beam slab
and trusses), fitting services and etc.
Available in a paper A3 size and imprint with the words “Table Tender
Document”.
awang295@[Link]
Contractor Considerations Bid/Not To Bid
for the tenders
Contractors need to be realistic about their ability to prepare
proposals and the probability of winning the contract.
In order to offer the client with competitive price and service, the
factors as follow shall be recognized:
Extension of Reputation
Capability
Competitiveness/
Competition
Client funds
Factors whether to bid or
not to bid for the project
Risks Proposed
Resources
Mission
awang295@[Link]
Contractor Considerations Bid/Not To Bid
for the tenders
Competitiveness/Competition
To seek out whom are the other contractors bidding for the project.
To find out whether these contractors have a competitive advantage
through earlier projects or assignment or having affiliation with the
customer.
Risks
To identify risks on the project viability and success.
To ascertain the uncertainties and technological barrier.
To ascertain whether research and development need to be carried out
on the feasibility of the project.
Mission
To access whether the project is in line with the company business
mission and core areas.
awang295@[Link]
Contractor Considerations Bid/Not To Bid for the tenders
Extension of Capabilities
To decide whether the proposed project will provide the contractor
with an opportunity to enhance its expertise and capabilities.
Reputation
To decide whether the organization has a good reputation and
relationships with the customer, such as established close rapport and
good successful records on past projects with the customers.
Review past documents on how many times the contractor bid for the
same organizations and was unsuccessful.
Client Funds
To find out about the clients funds and financial credibility for the
project.
Proposed Resources
To ascertain whether the contractor has the right amount and quality
of resources to bid for the project.
awang295@[Link]
Contractor Considerations Bid/Not To Bid
for the tenders
IMPORTANT OF HAVING SITE VISIT
NO CLAIMS CAN BE MADE DUE TO ADVERSE SITE CONDITION THUS
CONTRACTORS MUST CHECK FOR THE FOLLOWING POINTS:
Access to Site
Ground
Condition Availability
of Services
Factors whether to bid or
not to bid for the project
Environment
Local Labor
Accommodation
for Staff Local Suppliers
awang295@[Link]
Contractor Considerations Bid/Not To Bid
for the tenders
IMPORTANT OF HAVING SITE VISIT
awang295@[Link]
Scrutiny the Tenders
After opening the tenders, the tenders should be scrutinized. Tender Report
Things that need to be checked: Structures
List of all tenders received along with detail of the Earnest The 1st report is the tabular statement of
Money (Tender Deposit). tenders which consists of:
It should be checked that the contractors duly signs every • Name of tenderer, class and status
necessary pages in Tender Document. • Tender Sum (before correction of any
The address of the contractor should be clear and complete. arithmetical error)
Verification of the contract conditions should be done. • Construction period (time of completion)
Whether the contract condition is original or alteration has
been done.
Rates are written in words as well as figure or not. Both
should be the same. When different, then the lower should be
considered. The 2nd report, same as 1st report,
The calculation and amount stated by contractor (arithmetic except for:
error) should be carefully checked. • Name of the contractor not listed
• The list of tender will be listed in
*After proper scrutiny: ascending price order
The comparative statement of all the tenders should be • The lowest tender will be at the top,
prepared the highest tender price will be at the
Signed by all persons present at the time of opening tenders bottom of the list
awang295@[Link]
Tender Evaluation Process
Coordinated by tender committee and contract department and lead by a secretary.
Secretary responsible to coordinate all parties on date, time and place of opening
tenders.
A tender committee comprise of the technical committee that looks into the
specifications, construction method, resources and etc., while commercial committee
will looks into the price and costing aspects of the project.
Stages involve in tender evaluation are as shown below:
Financial
Standardization
Standing
EVALUATION TENDER
(Based on
awang295@[Link]
Technical
capability Warranties
Performance
Capacity Experience
Standards
Awarding of Contract
General flowchart for awarding of contract
Awarding Phase
Recommending tenders
awang295@[Link]
Awarding of Contract
Recommending Tenders
Open tender committee will recommend a few (say, 3) short-listed tenders, but only
one contractor will be awarded with the contract except for a mega project. The
important criteria recommendations in selecting contractor are as follow;
Financial
Background
Paid-up
Tender Sum Capital
Factors when considering
contractor for the project
Construction
Equipment Period
Technical Knowledge
& Experience
awang295@[Link]
Awarding of Contract
Recommending Tenders
Tender Sum
Wherever possible the lowest tender sum shall be recommended. BQ in tender allow
checking the cost of each item. Some contractor will quote higher price for the early stage
job i.e: preliminaries, site clearing and foundation. As contractors are being paid as they
constructed will allow them to collect great profit margin up to sub-structure work and then
abandon the project.
Paid-Up Capital
Paid-Up Capital concern with the possibility of bankruptcy. To enable recovery from
bankruptcy is based on the assets and Paid-Up Capital. Depending on the project size,
contractor should have reasonable Paid-Up Capital to decease possibility of bankruptcy.
awang295@[Link]
Awarding of Contract
Recommending Tenders
Construction Period
Wherever possible contractors offer the shortest construction period should be accepted,
but shortest construction period normally does not align with the tender sum and may
avoiding SOP.
Equipment
Contractor possess the equipment shall run the job better than if they were rented. Some
equipment may be hard to rent during peak season.
awang295@[Link]
Awarding of Contract
Recommending Tenders
Other factors:
Contractor’s qualification
Construction method
Contractor’s previous project track record
Contractor’s office and site management skill
Knowledge about surrounding (environment aspects)
Integrity background
Insurance and warranty
Performance (workmanship)
awang295@[Link]
Awarding of Contract
awang295@[Link]
Awarding of Contract
awang295@[Link]
awang295@[Link]
summary
Construction project inception involve several phases
as follow:
Pre-Tender Phase
• Conceptual drawings (normally prepare by an architect)
• Preliminary drawings (various amendment)
Tendering Phase
• Tender Drawings
The key to the process is ensuring that the requirements for the site are
properly defined and that the selected site meets these requirements
within the constraints of the project programme and with minimal risks to
the client.
awang295@[Link]
FEASIBILITY STUDY
Objectives of
the project
Factors governing
Feasibility study
awang295@[Link]
OBJECTIVES OF THE
PROJECT
The client must define the need and
objectives of the project in the project
brief.
Sometimes money/expenses is not the
priority compare to the need of the
project.
Examples: Project of infrastructure for
people (such as school, public hall and
etc.), flood disaster area, landslide disaster
area and etc.
awang295@[Link]
FEASIBILITY STUDY
Land Financial
Valuation Study
Market
Risk Analysis (Economic)
Analysis
awang295@[Link]
BUSINESS POINT OF VIEW
Land Valuation – The owner/client needs to assess the
current value of the proposed land and decide whether to
acquire/buy the land.
Financial Study – Then, the owner/client has to prepare
budget and forecast the cashflow of the project for the
items as follow:
‒ Pre-Development Cost
‒ Infrastructural Cost
‒ Preliminaries
‒ Construction
‒ Sales Revenue
‒ Profitable Return
‒ Cashflow
awang295@[Link]
BUSINESS POINT OF VIEW
Market (Economic) Analysis
The owner/client has to identify potential buyer, carry out
the market analysis and determinewhetherf the percentage
of profit margin is worthwhile to proceed the project or not.
Concerned with the supply and demand situation and also
the country’s economic market situation (discuss further in
class for current situation).
Risk Analysis
Usually carried out together with the market analysis.
Purpose is to make known the liability should the project fail.
At the same time, it encourage the owner/client to work
towards success.
awang295@[Link]
FEASIBILITY STUDY
Site Visit
Preliminary
Preliminary
Layout Plan
Investigation
awang295@[Link]
TECHNICAL POINT OF VIEW
TECHNICAL SITE SUITABILITY FACTORS
awang295@[Link]
TECHNICAL SITE SUITABILITY FACTORS
awang295@[Link]
TECHNICAL SITE SUITABILITY FACTORS
6. Environment
The surrounding may affect the project feasibility. A remote area
is normally not suitable for a housing scheme. On the other hand,
the project will affect the surrounding.
Interfacing with human activities include components like soil,
rock, water and geologic hazard (flooding, erosion, slope failures
and subsidence).
Understanding on these geological components are important so
that the construction activities can be carried out according to the
adopted designs with minimal impacts on the geological
environments.
awang295@[Link]
TECHNICAL SITE SUITABILITY FACTORS
The existing and project drainage scheme for flash flood or flood
mitigation shall be checked. These existing drainage systems record/
as-built are available at JPS, JKR, district office, resident office and
municipal/city council office.
awang295@[Link]
TECHNICAL SITE SUITABILITY FACTORS
8. Topography
Available hard/soft copy of topography map are available at Survey
Department Malaysia. This map provide information on contours
level, elevations, river, facilities and etc.
Site topography map can be used to determine the volume of earth
to be cut and/or filled, the location (storage) of resources, building,
and services; the temporary access and etc.
awang295@[Link]
SITE INVESTIGATION
Site Investigation is a study to examine the suitability of the
site in terms of physical properties, geological and
geotechnical materials properties (soils, rocks and geological
structures) and the environment aspects in order to meet the
standards with the most economical layout for the proposed
site location.
awang295@[Link]
GEOLOGICAL & GEOTECHNICAL
Geotechnical Engineering is the branch of Civil Engineering that
concerned with the engineering behavior of earth materials. It includes
investigation on existing subsurface conditions and materials; assessing
risks posed by site conditions; designing earthworks and structure
foundations; and monitoring site conditions, earthwork and foundation
construction.
Engineering Geology is the ‘application’ of the geologic sciences in
engineering practice for the purpose of assuring that the factors
affecting the location, design, construction, operation and maintenance
of engineering works are recognized and adequately provided.
Engineering Geologists investigate and provide geologic and
geotechnical recommendations, analysis, and design. Engineering
Geologic studies may be performed during the planning, environmental
impact analysis, and construction phases of public and private works
projects, and during post construction and forensic phase of projects.
awang295@[Link]
Factors governing
Site Investigation
Economical Technical
Factor Factor
awang295@[Link]
➤ Development Cost
Compare cost of any similar project in the area
nearby, and study if the project is worthwhile.
➤ Transportation Cost
Economical
Poor transportation may increase the contract sum
Factor
due cost of transportation for materials, labours and
equipments.
awang295@[Link]
➤ Ground Water Level (G.W.L.)
Ground water presence need to be identified, and
the level of corrosiveness must be examined.
Ground water level may be determining the type of
foundation to be used.
awang295@[Link]
➤ Location of Existing Services (water pipe, electrical cable
and etc.)
The existing services underground must be seriously
assessed to avoid disturbance or damaging to
existing underground services such as water pipe,
sewerage pipe, electrical cable, telephone cable and
etc.
Usually any existing services will be mapped on plan
Technical using sophisticated detectors equipment.
Factor
➤ Marine Effect
Structures on the shore, i.e. wharf and jetty, are
subjected to environment marine effect.
The tide of water encourages sea water attacks against
the structural elements (reinforcement); as there are
periodic supply of air, saltwater (from the sea), and
heat (from sun).
As a result, structure may fail during service due to
corrosion problem.
awang295@[Link]
➤ Site Survey
Boundary stone for the site must be determined to ensure
the construction is on the exact location.
If available topography survey is incomplete or not
consistent, additional survey is required before detailed
design stage.
Data survey includes TBM, contour line, elevation, spot
Technical level, existing features on ground and etc. It is useful to
Factor determine the volume of earth to be cut and/or filled, to
assign the location (storage) of resources, building, and
services; the road access and etc.
awang295@[Link]
➤ Environment
Interfacing impacts the ecosystem and surrounding
area to minimize direct and indirect impacts on the
Technical geological environment.
Factor Samples Studies frequently conducted are as follow:
1. Environment Impact Assessment (EIA)
2. Traffic Impact Assessment (TIA)
3. Social Impact Assessment (SIA)
awang295@[Link]
METHOD OF SITE INVESTIGATION
Method of Site Investigation (SI) can be grouped into 2 types, i.e. Surface
and Sub-Surface Method. The need depends on the type of structures to
be constructed and other factors as follow;
Stage of investigation
Condition and topography of the site
Amount of information required
Allocated fund
Accessibility
Availability of materials required for the investigation (e.g. water for
flushing in drilling)
awang295@[Link]
METHOD OF SITE INVESTIGATION
➤ Limitations:
awang295@[Link]
METHOD OF SITE INVESTIGATION
➤ Some of SI methods are:
Desk study of previous records publications Sampling taken either
Trial pits from disturb or
Soil electrical sensitivity probe kit undisturbed samples.
Land survey Generally, reports are
Auger boring divided into 2
Wash boring categories namely
Rotary drilling preliminary and
Constant Rate Penetrate Test detailed investigation
Mackintosh probe test report.
Maintain Load Test
Satellite image and topographic maps
Seismic wave propagation (reflection) and seismic effect (reflection)
awang295@[Link]
SUMMARY
awang295@[Link]
ACKNOWLEDGEMENTS
Additional notes:
The Site Selection Guide
Site Selection Considerations
CONTENT DEVELOPERS
Topic 7
Tendering System
Lesson Outcomes (LO)
awang295@[Link]
Purposes of Tender Notice
awang295@[Link]
Contents in Tender Notice
The name of the customer’s organization and its logo in the Tender
Notice.
The word “Tender Notice or Invitation of Tender”, and its tender number
and references.
Tender qualification or pre‒qualifications:
‒ Eligibility criteria on whom should participate in the tender.
‒ Contractors are registered with bodies such as Pusat Khidmat
Kontraktor (PKK), Ministry of Finance (MoF) and government agencies
such as Public Works Department (PWD) or Jabatan Kerja Raya (JKR),
MARA, Tenaga Nasional or SIRIM.
awang295@[Link]
Contents in Tender Notice
Tender Description is the scope of the project and the outline of the
tasks or scope of work the customer wants the contractor to perform or
deliver.
Tender document fees (Purchased by the Contractor)
Modes of payment (cash, bank draft, banker’s cheque, money order,
bank guarantee)
Date and time details availability of Tender Document
Request for site visit (compulsory before the purchase a Tender
Document).
awang295@[Link]
Contents in Tender Notice
Submission of tenders and address ‒ specify the closing dates and time
for tender and the address to submit the Tender Document.
Clause of indemnity ‒ the Client is not bound to accept the lowest bidder
or quotations nor to assign any reason for the rejection of any tender nor
it will be responsible for any costs incurred by the tenderers.
awang295@[Link]
Earnest Money (Tender Deposit)
Amount that accompanies the tender form while submitting the tender, in
which usually based on the sum of total estimated work (Construction
Cost)
Tender Document without Earnest Money shall not be scrutinized (only
parties who shows that they are really interested will pass the first stage)
Deposit is refunded to unsuccessful tenders.
Three reasons why Earnest money is required are to restrict unnecessary
competition and to act as a punishment and compensation.
awang295@[Link]
Punishment
In case the contractor who is awarded with the project has no intention of
proceeding the work, the Earnest Money shall be forfeited by the
Owner/Client as a punishment to the contractor.
awang295@[Link]
Unnecessary
Competition
awang295@[Link]
Compensation
In case the contractor is awarded with the work refuses to proceed, the
work can be allocated to other contractor.
The Earnest Money shall compensate the owner to a certain extend.
awang295@[Link]
Scheme of Work-Tender
Note:
Most of the Open and Closed Tenders are subjected to tenderers interview.
awang295@[Link]
awang295@[Link]
Tenderer/Company Profile
Tender Form
Working Standard Specification
BQ (Bill of Quantities)
Project Drawings
Schedule of Rates
Letter of Acceptance
awang295@[Link]
TENDERER/COMPANY PROFILE
awang295@[Link]
Tender Form
awang295@[Link]
Working Standard
Specification
Amplifies the information given in the contract
drawings and BQ.
Describes the detail of proposed work to be
executed under contract, nature and quality of
material to be used etc.
It helps to determine scope of work and allows
contractor to decide on the methods.
Standard specification for general scope of work
(ex. soil works, concrete work, pipes, drainage
etc.)
Extra specification for specific work (ex. land
reclamation, dredging)
awang295@[Link]
Bill of Quantities (BQ)
Gives detailed information of required works to
be done and quantity of materials to be used.
Consists of schedule with brief descriptions of
work to be carried out, with quantities entered
for each item.
Contractors only need to quote the unit rate
and required to name the price without
calculating the exact quantity from Drawings and
Specification.
Offers a mean by comparing all previous
tenders submission received.
awang295@[Link]
Bill of Quantities (BQ)
awang295@[Link]
Contract/Engineering
Drawing
Drawings are needed by tenderer to get
overview of type and scope of work to estimate
fees and material cost for progress claim and
plan the work to be done.
They should be prepared sufficiently in detail
to enable tenderers satisfactorily understand the
requirement of the project.
For contract based on drawing and
specification, complete plan is required to be
given to tenderer.
Drawings should be complete, anything that is
not explained should be written in the plan.
Complete drawings incur additional payment
cost for the contractor.
awang295@[Link]
Schedule of Rates
awang295@[Link]
Labour Rates and
Construction
Materials Price
awang295@[Link]
awang295@[Link]
Tender Acceptance Form
awang295@[Link]
‘Ganging-up’ of Contractor/
Cost Syndicate
“Gang-up” - a group of contractors who know that they are the only
tenderers invited to tender for the project.
The idea is to raise the tendered prices above the normal price of that
specific project so that the additional profit will be shared among all
tenderers.
To avoid ganging-up of contractors, the consultant:
‒ Should not disclose the detail of tenderers.
‒ Prepare their own estimation on tender sum/price.
‒ Retender should they feel necessary.
awang295@[Link]
Examples:
Assume that 5 contractors united for a Closed Tender and agreed among
themselves that contractor B should be awarded the project, which is estimated
to be RM 10 million inclusive of profit. They will quote the following pricing:
awang295@[Link]
Types of Tender/
Tendering Method
i. Open Tender
ii. Closed Tender
iii. Negotiated Tender
awang295@[Link]
Open Tender
awang295@[Link]
Advantages of Open
Tender
Lesser possibility of contractors ‘ganging-up’ to
quote higher tender sum/price for the project.
Give a chance to new and inexperienced
contractors to bid for the project.
Tender shall be very competitive, thus it is
possible to get the lowest tender sum/price.
awang295@[Link]
Disadvantages of Open
Tender
awang295@[Link]
Closed Tender
awang295@[Link]
Advantages of Closed
Tender
Normally up to 10 tenderers (contractors) are
invited; then the exact number of Tender
Document copies will be prepared. Hence, no
wastage of extra copy.
As the contractors performance were based on
their previous record, financial, experienced and
equipment's, thus a good quality of works shall
be produced (expected).
Suitable for a special project which require
efficiencies, experiences and skilled contractor.
Lower possibility of project delay as tender
valuations consume lesser time compared to
Open Tender.
awang295@[Link]
Disadvantages of
Closed Tender
Officers inviting tenderer can be accused of
being biased.
Tender price may be higher than it should be, as
other qualified tenderers (contractors) are not
invited to participate in the tender.
Possibility of contractors “ganging-up/cost
syndicate” to quote for higher tender price.
No opportunities to the new and inexperienced
contractor to get involved in the job.
awang295@[Link]
Negotiated Tender
awang295@[Link]
Negotiated Tender
It is most applicable for:
Project to be carried out urgently where
Tender/Contract/Construction Drawings are
still in the process.
A highly special circumstance, such as
contractors who:
‒ Has performed successfully for the owner on
previous occasion.
‒ Is specialized in the types of work to be
undertaken (e.g. dam construction).
‒ Has special knowledge and experience of the
site (e.g. contractors for the restricted armed
force area and have carried out the job
satisfactorily).
awang295@[Link]
Advantages of
Negotiated Tender
Only 1 Tender Document is produced, thus no
wastage.
As the contractor’s performance is based on the
previous record, financial, experienced and
equipment's, there is no possibility of delaying
the project.
Only 1 contractor is invited; which is simplifying
the procedure.
Normally a good quality of works is expected.
Suitable for a special project which require
efficiencies, experiences and skilled contractor.
awang295@[Link]
Disadvantages of
Negotiated Tender
awang295@[Link]
Summary
TENDERING METHOD depends on suitability of
the project desired.
Open Tender
Close Tender
Negotiate Tender
awang295@[Link]
Acknowledgements
Janidah Eman (UiTMPP)
Nur Muizzah Nawi (UiTMJ)
Muhammad Isha Ismail (UiTMP)
Noor Raifana Ab Rahim (UiTMJ)
References
Garisan Panduan Penilaian Tender (Edisi Januari 2008). (2008). Bahagian
Perolehan Kerajaan Kementerian Kewangan Malaysia.
Murdoch, J., Hughes, W. (2008). Construction Contracts Law and Management (4th
ed.). Taylor & Francis.
Ritz, G. J., Levy, S. M. (2013). Total Construction Project Management (2nd ed.).
McGraw-Hill Education.
Additional notes:
Pellicer, E., Yepes, V., Teixeira, J. C., Moura, H. P., Catalá, J. (2013). Construction
Management. Wiley-Blackwell. Chapter 2: Contract Documents.
Project Delivery System refers to a method used in implementing the project and
the parties involved such as Owner/Client and professional members (architect,
engineers and QS) in construction project. It is the overall processes by which a
project is designed, constructed, and/or maintained.
Procurement is the action of obtaining or procuring something and buying goods
such as materials and equipment. It is the process of finding, agreeing terms and
acquiring services or works from an external source, often via a tendering or
competitive bidding process to ensure the buyer receives goods, services or
works at the best possible price, when aspects such as quality, quantity, time, and
location are compared.
awang295@[Link]
PUBLIC PROCUREMENT STRATEGIES
Procurement of Public
Assets and Services
Method Method
Traditional, also knows as Design- Funding arrangement through
Bid-Build concession agreement between
Design-Build/Turnkey the public sector and the private
Management based. i.e. either sector:
Management Contracting or ‒ Privatization
Construction Management ‒ Private Finance Initiative (PFI)
(Khairuddin, 2008) ‒ Private Finance Initiative (PFI): Concept and Method of Procurement for
Construction Projects (with Specific Reference to Malaysia)
CONVENTIONAL PROCUREMENT
awang295@[Link]
TRADITIONAL CONTRACT
awang295@[Link]
TRADITIONAL CONTRACT
awang295@[Link]
TRADITIONAL CONTRACT
SEQUENTIAL FUNCTION
awang295@[Link]
TRADITIONAL CONTRACT
COMPETITIVE TENDER
The open bidding procedure, in which the lowest bidder is the ‘winner’ gives
the owner the lowest price available in the marketplace and presumably the
greatest, economic efficiency.
awang295@[Link]
TRADITIONAL CONTRACT
The construction professional does not enter process until the design is
completed, meaning that the design is not usually reviewed for constructability
before it is finished due to problems as follow;
‒ More responsibility to coordinate and check on the project by Client (PM).
‒ Additional work for investigation required, when there is design and
supervision problem occur.
‒ Risks in claims against owner in design faults.
The traditional approach is difficult to reduce the time required to do both
design and construction.
awang295@[Link]
TRADITIONAL CONTRACT
awang295@[Link]
TURNKEY CONTRACT
awang295@[Link]
TURNKEY CONTRACT
Characteristics of Turnkey Contract
awang295@[Link]
TURNKEY CONTRACT
Advantages of Turnkey Contract
SAVE TIME
The Owner is less heavily involved and sits outside the direct day-to-day
communication between designer and constructor.
DESIGN LIABILITY BY MC
This keeps owner staffing to a minimum and puts the full responsibility for
good communication, problem solving, and project delivery on design/ build
team. THEREFORE:
‒ Design and supervision problems, it is contractor responsibility.
‒ No claims against Owner for design faults.
awang295@[Link]
TURNKEY CONTRACT
Advantages of Turnkey Contract
awang295@[Link]
TURNKEY CONTRACT
Disadvantages of Turnkey Contract
SUB-STANDARD WORK
Sub-standard work (lower quality) are rarely occur due to factors as follow;
‒ Owner control lesser on the design and specification of the project.
‒ Designer works for the same company as the builder.
‒ Lack of checks and balances, which MC doing in-house design.
awang295@[Link]
COMPARISON
MERITS
awang295@[Link]
DEMERITS
PUBLIC-PRIVATE PARTNERSHIP
What is PPP?
awang295@[Link]
PUBLIC-PRIVATE PARTNERSHIP
A Focus efficient
performance- allocation of risk, whole
based life service approach,
PPP
procurement private sector
model which innovation and
optimize management skill.
value for
money.
awang295@[Link]
awang295@[Link]
PUBLIC-PRIVATE PARTNERSHIP
PPP Approach
awang295@[Link]
PPP, PRIVATIZATION AND PFI
Corporatization
Management contracts
Method
BLT
Service Sold
BOT
Financially Free Standing
BOOT
Joint-Venture
BOO
DBFO
(Khairuddin, 2008) ‒ Private Finance Initiative (PFI): Concept and Method of Procurement for
Construction Projects (with Specific Reference to Malaysia)
PRIVATIZATION
What is Privatization?
Privatization means allowing profit-making corporations to take over the duties that
have been performed by public agencies. This means the government will contract out
work to private companies that previously was performed by public employees.
Issue: Faced with tight budgets, many sees privatization as a quick fix. But in the long
run, privatization often ends up costing taxpayers more, while putting private profit
ahead of the public interest.
awang295@[Link]
PRIVATE FINANCE INITIATIVE (PFI)
What is PFI?
awang295@[Link]
PFI & PRIVATIZATION
awang295@[Link]
PFI & PRIVATIZATION
awang295@[Link]
PRIVATE FINANCE INITIATIVE (PFI)
awang295@[Link]
PRIVATE FINANCE INITIATIVE (PFI)
Advantages of PFI
awang295@[Link]
PRIVATE FINANCE INITIATIVE (PFI)
Disadvantages of PFI
High costs are usually incorporated when tendering for PFI projects.
Agreements are brought through complex negotiations where the
attitude of government, supportive or otherwise, may either ease or
complicate the problems.
The cost of finance is considerably high, given that government is able to
make loan less than that of private firms.
There could be disparity problems between the private and public sector
in terms of differing modes of operations, decision making and
accountability.
awang295@[Link]
PFI IN MALAYSIA
UTILITY
It should be suitable for the
purposes for which it is used.
awang295@[Link]
BASIC PRINCIPLES OF CONSTRUCTION CONTRACT
Contract
awang295@[Link]
DEFINITION AND CONCEPT
Definition
awang295@[Link]
DEFINITION AND CONCEPT
Definition (cont.)
awang295@[Link]
DEFINITION AND CONCEPT
Concept
awang295@[Link]
CONCEPT OF CONTRACT
awang295@[Link]
CONCEPT OF CONTRACT
awang295@[Link]
CONCEPT OF CONTRACT
awang295@[Link]
CONCEPT OF CONTRACT
Example:
awang295@[Link]
CONCEPT OF CONTRACT
awang295@[Link]
CONCEPT OF CONTRACT
1. Principle (Consideration)
awang295@[Link]
CONCEPT OF CONTRACT
1. Principle (Consideration)
Example:
1. If A signs a contract to buy a car from B for RM50,000, A's consideration
is the RM50,000, and B's consideration is the car.
2. Additionally, if A signs a contract with B such that A will paint B's house
for RM700, A's consideration is the service of painting B's house, and B's
consideration is RM700 paid to A.
awang295@[Link]
CONCEPT OF CONTRACT
awang295@[Link]
CONCEPT OF CONTRACT
3. Invalid/Illegal Contract
awang295@[Link]
CONCEPT OF CONTRACT
awang295@[Link]
CONTRACT DOCUMENT AND APPLICATION IN CONSTRUCTION PROJECTS
In Malaysia context, these following documents are legally bind and form
as part of the Contract:
1. Article of Agreement
2. Contract Form
3. Conditions of Contract
4. Letter of Acceptance
5. Contract Drawings
6. Bill of Quantities
7. Working Standard Specification
8. Bank Guarantee/Performance Bond
9. Insurance Guarantee
awang295@[Link]
CONTRACT DOCUMENT AND APPLICATION IN CONSTRUCTION PROJECTS
1. Article of Agreement
awang295@[Link]
CONTRACT DOCUMENT AND APPLICATION IN CONSTRUCTION PROJECTS
2. Contract Form
awang295@[Link]
CONTRACT DOCUMENT AND APPLICATION IN CONSTRUCTION PROJECTS
3. Conditions of Contract
awang295@[Link]
CONTRACT DOCUMENT AND APPLICATION IN CONSTRUCTION PROJECTS
4. Letter of Acceptance
awang295@[Link]
CONTRACT DOCUMENT AND APPLICATION IN CONSTRUCTION PROJECTS
5. Contract Drawings
awang295@[Link]
CONTRACT DOCUMENT AND APPLICATION IN CONSTRUCTION PROJECTS
6. Bill of Quantities
The Bill of Quantities must be filled up with their quantity figures and
price. The bill should be priced so as to represent a reasonable amount
in the contract document as agreed.
The price stated is inclusive of provision, delivery, unloading, storage,
packing, carriage and cartage, hoisting all labour setting, fitting and fixed
position, use of plant, supervision, establishment charges, profit, labour
and everything else that is necessary for the due completion of the job.
awang295@[Link]
CONTRACT DOCUMENT AND APPLICATION IN CONSTRUCTION PROJECTS
awang295@[Link]
CONTRACT DOCUMENT AND APPLICATION IN CONSTRUCTION PROJECTS
‒ Method Specification
Method Specification states or explains precisely equipment and
procedure to be used in performing the construction.
Since everything is stated, if any damage occur the liability for
damages will be liable on the Owner/Engineer's side.
‒ Performance Specification
Performance Specification or Result Specification only specify the
result to be achieved.
Since the method is not specified, all the cost for any damages or
failure will be liable to the Contractor.
awang295@[Link]
CONTRACT DOCUMENT AND APPLICATION IN CONSTRUCTION PROJECTS
awang295@[Link]
CONTRACT DOCUMENT AND APPLICATION IN CONSTRUCTION PROJECTS
9. Insurance Guarantee
awang295@[Link]
TYPES OF CONSTRUCTION CONTRACTS
awang295@[Link]
TYPES OF CONSTRUCTION CONTRACTS
awang295@[Link]
TYPES OF CONSTRUCTION CONTRACTS (PRICE BASED SYSTEM)
awang295@[Link]
TYPES OF CONSTRUCTION CONTRACTS (PRICE BASED SYSTEM)
awang295@[Link]
TYPES OF CONSTRUCTION CONTRACT (PRICE BASED SYSTEM)
Bridge
Painting
Guardrail
Landscaping
Lighting
Sidewalks
Signing
Signalization
awang295@[Link]
TYPES OF CONSTRUCTION CONTRACTS (PRICE BASED SYSTEM)
Advantages:
Suitable for projects where later changes are not expected, and a simple
and quick form of payment is preferred.
Payments are made in stages, as identified in agreement form. For
example 10% of the contract price shall be paid upon the completion of
foundation stage.
No physical measurements need to be taken, general visualization is
sufficient.
awang295@[Link]
TYPES OF CONSTRUCTION CONTRACTS (PRICE BASED SYSTEM)
Disadvantages:
If there is any change in the plans and or drawings, the value of the
change should be negotiated with the Contractor. This may cause delay
and sometimes disputes.
Lesser control of cashflow from point of view of the Owner. Sometimes
Owner has to pay more or sometimes less than the value of the actual
work completed.
There is no provision of payment for materials at site.
awang295@[Link]
TYPES OF CONSTRUCTION CONTRACTS (PRICE BASED SYSTEM)
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (PRICE BASED SYSTEM)
For either type of schedule, it may or may not state the approximate
quantities to be executed for each item of work.
The ‘contract price’ is thus determined by summing up the amounts
obtained, multiplying the respective quoted rates and actual quantity of
each item of work to be executed.
Provision for valuation on a day-work basis or otherwise is usually made
in this form of contract, in cases where the quoted rates are not
applicable.
A schedule listing the works with the rates will be provided for the
valuation of variations purpose.
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (PRICE BASED SYSTEM)
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (PRICE BASED SYSTEM)
Advantages:
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (PRICE BASED SYSTEM)
Disadvantages:
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (PRICE BASED SYSTEM)
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (PRICE BASED SYSTEM)
Advantages:
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (PRICE BASED SYSTEM)
Advantages:
Owner knows exactly what he pays for. BQ shows the breakdown of every
item of works and how the total price is summed up.
Lesser risk to Owner and Contractor. They pay exactly according to rates
quoted in the bill.
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (PRICE BASED SYSTEM)
Disadvantages:
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (PRICE BASED SYSTEM)
LS Contract BQ Contract
SR Contract BQ Contract
There is no implied guarantee given that all or All of the work scheduled will be
any of the work scheduled will be carried out. carried out and verified.
More items are scheduled for temporary works Lesser items are scheduled for
than usually appear in BQ, because the amount temporary work as items need
of temporary works that the contractor has to to be quantified.
undertake is uncertain.
awang295@[Link]
SR Contract LS Contract
Contractor will reimburse and they will be paid based on the actual Prime
Cost spent for the work plus a certain fee to cover his overheads and
profits.
There is no finite sum tendered by the Contractor nor is the one
established at the time of contracting.
The actual contract sum will only be determined on completion of the
works and the ascertainment of the final account figure.
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
The Contractor in this form of contract will charge an agreed fee in terms
of a percentage (%) of the cost of the actual work executed.
The percentage normally varies from 5% to 20%.
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
Advantages
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
Disadvantages
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
Advantages
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
Disadvantages
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
This is also known as Cost Plus Sliding Scale of Fee Contract, since the
fee paid to the Contractor is based on some form of a sliding scale.
It is designed in such a way that the Contractor may have a definite
financial incentive to effect economy in the cost of work (to the
Owner).
As the cost of the project increases, the percentage becomes lesser.
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
Advantages
In this case the contractor shall not try to increase the actual cost.
The actual cost is lower and lower so both the owner and the
contractor will be benefited.
Disadvantages
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
Advantages
awang295@[Link]
TYPES OF CONSTRUCTION ON CONTRACTS (COST BASED SYSTEM)
Disadvantages
awang295@[Link]
SUMMARY
Project Delivery System will decides on how the project will be carried out.
Usually the application of different types of contract in construction industry
will very much depends on the types of project desired to be carried out
since there are various options in contracting.
The selection on method of contracting also depends on varied situations,
suitability and the capacity of business entities involved in the project.
awang295@[Link]
ACKNOWLEDGEMENTS
Janidah Eman (UiTMPP)
Nur Muizzah Nawi (UiTMJ)
Muhammad Isha Ismail (UiTMP)
Noor Raifana Ab Rahim (UiTMJ)
REFERENCES
Hendrickson, C. (1998). Project Management for Contract. Pittsburg:
Prentice Hall.
Additional notes:
Pellicer, E., Yepes, V., Teixeira, J. C., Moura, H. P., Catalá, J. (2013).
Construction Management. Wiley-Blackwell. Chapter 3: Procurement
Approaches, Chapter 13: Progress Payment.
Contract Strategy
ORGANIZATION STRUCTURE
Organizational are continually restructured to meet the demands imposed by
the environment.
Restructuring can change the role of individuals in the formal and the
informal organization.
Whatever organizational form is finally selected, formal channels must be
developed so that each individual has a clear description of the authority,
responsibility, and accountability necessary for the work to proceed.
awang295@[Link]
Introduction
awang295@[Link]
Introduction
awang295@[Link]
Contractor's Site Organization
awang295@[Link]
Contractor's Site Organization
awang295@[Link]
Contractor's Site Organization
SAMPLE OF CONTRACTOR’S SITE ORGANIZATION
CHART (TRADITIONAL CONTRACT)
awang295@[Link]
Contractor's Site Organization
SAMPLE OF CONTRACTOR’S SITE ORGANIZATION
CHART (D&B CONTRACT)
awang295@[Link]
Contractor's Site Organization
The numbers of person employed depends not only on the size but
also on the complexity of the job and it’s physical extend.
The five key personnel for Contractor's site organization are:
‒ Site Agent - who is in charge
‒ Site Engineer
‒ Office Manager
‒ General Foreman
‒ Plant Engineer
awang295@[Link]
Contractor's Site Organization
SITE AGENT
Responsible for directing and controlling the whole of the construction
work on site.
Have wide powers to enable him to employ workers, hire/purchase
machinery and equipment, purchase materials, and employ
subcontractors.
Site Agent must have a knowledge in civil engineering field of
construction.
He must be diplomatic enough to control workers and deal with the
Consultant representatives such as Resident Engineer (RE).
awang295@[Link]
Contractor's Site Organization
SITE AGENT
Able to command men and be a good organizer and administrator.
He needs to has business sense, because his job is not only to get
the works built properly to the satisfaction of the engineer but also to
make a profit for the Contractor.
He is therefore tough, practical, experienced, fair-minded and
energetic.
Site Agent will give the great majority of his instructions verbally.
awang295@[Link]
Contractor's Site Organization
SITE AGENT
He needs to keep the job moving. He has to solve problems on sites
and make correct decision quickly because he cannot afford to let
resources stand idle.
He is responsible for claiming and collection of progress payments.
But he also has to bear in mind the capacities of the people who work
for him.
Once the Site Agent has made up his mind, it is the Office Manager
and sub-agent’s job to see that necessary instructions get through to
the right persons without delay.
awang295@[Link]
Contractor's Site Organization
SITE AGENT
Site Agent without high integrity may:
awang295@[Link]
Contractor's Site Organization
SITE ENGINEER
Site Engineer main responsibility is to see that the works are
constructed to the right specification.
Advising the Site Agent on all design and engineering matters.
Their duties may be varied, which included levelling of construction
work, planning temporary access road, power supply, etc.
Carry out minor design such as temporary structures, diversion works,
etc.
Measurement of monthly work done for the purpose of claiming
progress payment.
awang295@[Link]
Contractor's Site Organization
SITE ENGINEER
Each Site Engineer has a section of work to look after. They prepare
weekly and monthly progress report with the quality record.
On small sites, the Site Engineer may virtually act as sub-agents as
well, the two job merging into one when the job is not large enough to
justify having both sub-agent and engineer.
awang295@[Link]
Contractor's Site Organization
SITE SUPERVISOR
Responsible to their superior, Site Engineer.
Ensure proper method of construction being carried out.
Check the work done is accordingly to drawings and specifications.
Ensure the work progress following the schedule.
awang295@[Link]
Contractor's Site Organization
OFFICE MANAGER
The Office Manager must be efficient, because upon him rests the
responsibility for seeing that materials flow onto the site as required
and that all invoices and accounts are properly dealt with.
There may be thousands or more accounts to deal with per month.
Unless there is a separate Site Cashier, the Office Manager will also
have to handle the workmen’s pay.
Large amounts of cash may pass under his control, and he must be a
man of integrity, sharply sensitive to any mishandling of the cash. His
work of this nature will naturally be subjected to auditing checks
carried out from time to time by accountants from the head office of
the Contractor.
awang295@[Link]
Contractor's Site Organization
GENERAL FOREMEN
The General Foreman is the agent’s right hand man for the execution
of the work in the field.
His explicit duty is to keep the work moving ahead daily as the agent
has originally planned.
On a large contract, much of his daily work is concerned with issuing
detailed instructions to the foreman and coordinating their works.
He has to be a man of wide practical knowledge and long experience,
so that he can, if need be, demonstrate personally how things should
be done correctly.
awang295@[Link]
Contractor's Site Organization
GENERAL FOREMEN
He should stand a lot of his time outside, visiting all parts of works
under his control at least once a day.
He needs to keep sub-agent advised of his wants for materials and
equipment, the Plant Engineer about machine needs, and he
constantly calls upon the engineering staff to set out the details.
General Foreman have much authority on site and any junior engineer
who fails to get on with a foreman of standing may find days on site
will be numbered by the patience that foreman is willing to exercise.
awang295@[Link]
Contractor's Site Organization
GENERAL FOREMEN
The agent must support a foreman who is keeping the job going at the
right speed and in the right manner, irrespective a minor error of
decision.
General Foreman may sometimes have strange prejudices (biased)
and inexplicable (unable to be explained) attitudes, but are often
astonishingly capable men.
Frequently it is the General Foreman who contributes most to
changing the job from a set of plans into areal structure. The foreman
must also be able to read the engineer’s drawing for them to interpret
and apply in their daily work.
awang295@[Link]
Contractor's Site Organization
GENERAL FOREMEN
awang295@[Link]
Contractor's Site Organization
PLANT ENGINEER
The position of Plant Engineer is normally separately designated from
the General Foreman, even on small jobs; although, depending on his
status, he is either called Plant Engineer/Manager or Plant Foreman.
Maintain and service the plants or equipment.
He will be kept advised of long-term planning by the agent, and of
day-to-day planning by the General Foreman or sub-agent.
Under his control come the fitters and welders (cut, fit, assemble,
weld), and it will be often his job to maintain power suppliers to site
-i.e. to run site generators.
awang295@[Link]
Contractor's Site Organization
PLANT ENGINEER
awang295@[Link]
Consultant's Site Organization
awang295@[Link]
Consultant's Site Organization
Generally, his main duty is to see that the Contractor carries out his
obligations under condition as follow;
1. Document Contract
2. Construction Drawings
3. Authorities Requirement
awang295@[Link]
Consultant's Site Organization
awang295@[Link]
Consultant's Site Organization
awang295@[Link]
Consultant's Site Organization
awang295@[Link]
Consultant's Site Organization
awang295@[Link]
Consultant's Site Organization
awang295@[Link]
Consultant's Site Organization
awang295@[Link]
Consultant's Site Organization
awang295@[Link]
Consultant's Site Organization
awang295@[Link]
SUMMARY
awang295@[Link]
ACKNOWLEDGEMENTS
Additional notes:
Pellicer, E., Yepes, V., Teixeira, J. C., Moura, H. P., Catalá, J. (2013). Construction
Management. Wiley-Blackwell. Chapter 5: Site Setup and Construction Processes.
Managing Consultants and Contractors (2014)
Site Organization and Management (2015)
CONTENT DEVELOPERS
TOPIC 10
CONDITIONS OF
CONTRACT PWD FORM
203A
LESSON OUTCOMES (LO)
At the end of this module, students should be able to:
awang295@[Link]
PWD FORM 203A
awang295@[Link]
PWD FORM 203A
awang295@[Link]
PWD FORM 203A
awang295@[Link]
PWD FORM 203A
awang295@[Link]
PWD FORM 203A
awang295@[Link]
PWD FORM 203A
awang295@[Link]
PWD FORM 203A
awang295@[Link]
PWD FORM 203A
awang295@[Link]
Introduction
Contract Document
Variations
Performance Bond
awang295@[Link]
Possession of Site
Completion of Works
awang295@[Link]
P.W.D. FORM OF CONTRACT 203 (2010)
awang295@[Link]
P.W.D. FORM OF CONTRACT 203 (2010)
awang295@[Link]
P.W.D. FORM OF CONTRACT 203 (2010)
It should be noted that although the PWD Forms of Contract are used
extensively on nearly all government projects, there are some
exceptions such as projects which receives funding from the World Bank
or Asian Development Bank which adopt variants of the FIDIC Forms of
Contract.
awang295@[Link]
THE ROLE OF OWNER AND
CONTRACTOR ACCORDING TO PWD
FORM 203A
awang295@[Link]
DUTIES
a) Not to divulge (disclose) Contractors’ rates and prices. [Clause 71.1]
b) Be the custodian of the contract documents. [Clause 8.1(a)]
c) Contractor will be paid for work caused by S.O. negligence. (i.e. S.O. will
bear the cost of making good of any work due to S.O.I. (open up or re-
execute) if found to be S.O. negligence). [Clause 5.0]
d) Pay contractor for any or additional works not mentioned the contract
documents, i.e. V.O. [Clause 25.1]
e) Give possession of site to the Contractor on or before the date of
possession. [Clause 38.2]
f) Pay the contractor amount certified within period of honouring payment
certificates. [Clause 28.6]
g) Pay the Contractor amount awarded by the Arbitrator. [Clause 54.1]
awang295@[Link]
POWERS
awang295@[Link]
POWERS
h) Instruct Contractor to make good any defects of work. [Clause 5.1(g),
Clause 48.1(a)]
i) Employ and pay other Contractor to do the work. [Clause 5.3]
j) Agree with the Contractor to adjust contract sum. [Clause 29.0]
k) Defer giving possession of site to the Contractor. [Clause 38.4]
l) Deduct liquidated damages to the Contractor. [Clause 42.1(d)]
m) Suspend the Contractor’s work. [Clause 50.1(a)]
n) Reinstate the Contractor’s employment. [Clause 50.1(d)]
awang295@[Link]
THE ROLE OF CONTRACTOR
According to PWD 203A Conditions of Contract, the Contractor has the
following implied duties and powers.
Duties:
a) Primary obligation is to execute and complete works in accordance with
contract document (until the issuance of Certificate of Practical
Completion), i.e. use contract document for the purpose of the work.
[Clause 10.0(a)]
b) Forthwith carry out written instruction issued by S.O. (Architect/
Engineer). [Clause 5.2]
c) Make specific written application to the S.O. (Architect/Engineer) for any
instruction or drawing. [Clause 5.2, Clause 8.1(c)]
awang295@[Link]
THE ROLE OF CONTRACTOR
Duties (cont'd):
d) Bear cost of opening up and testing and consequential costs of making
good. [Clause 6.2]
e) Set out the works accurately and amend at his own cost any errors.
[Clause 19.2]
f) Keep a competent person in charge of the works at all reasonable
times [Clause 10.1(d), Clause 23.6(a)]
g) Indemnify the Owner against personal injury or death of any person
and property damage. [Clause 14.0]
h) Begin the works when given possession of the site. [Clause 38.1]
i) Regularly and diligently proceed with works and complete by date of
completion. [Clause 39.1]
j) Pay the Owner liquidated damages at the rate specified in the appendix.
[Clause 40.3]
awang295@[Link]
THE ROLE OF CONTRACTOR
Duties (cont'd):
k) Notify in writing to S.O. (Architect/Engineer) any cause of delay.
[Clause 10.1(f)]
l) Provide the S.O. (Architect/Engineer) with sufficient information to
enable him to exercise his duties as regard extension of time. [Clause
43.0]
m) Make good defects, shrinkage and other faults at no cost to the Owner.
[Clause 48.1(b)]
n) Give up possession of site of work in the event of termination.
[Clause 51.1(c)]
o) Remove from works any temporary buildings equipment goods etc
when instructed by S.O. on termination of employment. [Clause51.1(c)]
awang295@[Link]
POWERS
awang295@[Link]
CONTRACT DOCUMENTS (CLAUSE 8)
"Contract" or "Contract Documents" mean the documents forming the
tender and acceptance of the contract including:
Articles of Agreement
Form of Tender
Letter of Acceptance of Tender
Conditions of Contract and the Appendix annexed thereto
Special Provisions to the Conditions of Contract
Contract Drawings
Bills of Quantities
Specifications
Treasury’s Instructions as are set out in the Appendix to the Conditions
of Contract
awang295@[Link]
CONTRACT DOCUMENTS (CONT'D)
In Clause 8 of PWD FORM 203A, the Contract Documents has the following
conditions:
a) The Contract Documents shall be in the S.O’s custody and produced as
required by the Contractor. [Clause 8.1(a)]
b) The S.O. shall make copies of Contract Documents to the Contractor
without any charge (unless he shall have been previously furnished)
with: [Clause 8.1(b)]
i) One certified true copy of the Contract Documents
ii) Two copies of the Contract Drawings
iii) Two copies of unpriced Bills of Quantities and (if requested by the
Contractor) one copy of the priced Bills of Quantities
awang295@[Link]
CONTRACT DOCUMENTS (CONT'D)
c) The S.O. shall make copies of working drawings as required by the
Contractor without charge to enable the Contractor to construct and
complete the works in accordance with the contract. [Clause 8.1(c)]
d) The Contractor shall keep one copy of the Contract Drawings,
Specification, unpriced Bills of Quantities and other documents on site
and the S.O. shall at all reasonable times have access to the same
documents. [Clause 8.1(d)]
e) The Contractor shall return to the S.O. all Drawings, Specifications,
unpriced copy of bills of Quantities and other documents upon the
final payments on The Final Certificate [Clause 8.1(e)]
f) The contract documents are restricted in used for any purpose other
that in the contract. [Clause 8.1(f)]
awang295@[Link]
VARIATIONS (CLAUSE 24)
a) The S.O. has power to order and subsequent confirmation in writing of
any oral instruction requiring a variation to the works and it will not
vitiate the contract. [Clause 24.1]
b) The term “variation” means the alteration or modification of the design,
quality or quantity of the works as shown upon the Contract Drawings,
Bills of Quantities, and/or Specifications, and includes the addition,
omission or substitution of any work, the alteration of the
kind/standard/any of the materials/goods to be used in the works and
the removal from the site of any work, materials/goods executed,
brought thereon by the Contractor for the purposes of the works other
than work, materials or goods which are not accordance with this
contract. [Clause 24.2]
awang295@[Link]
PRIME COST AND PROVISIONAL
SUMS (CLAUSE 34)
a) The term “Prime Cost” or P.C. Sums as provided in the BQ shall means a
sums for works or services to be executed by a Nominated Sub-
Contractor or materials or goods to be obtained from Nominated
Supplier. The sums due to the Contractor in respect of NSC or NS shall
be determined by deducting the relevant P.C. Sums and the relevant
profit charges from the contract sum. Then substituting the amount due
to the relevant NSC or NS as specified in the relevant sub-contract and
the sums due to the Contractor by way of profit charges at the rates or
prices that may have been priced by the Contractor in the BQ. [Clause
34.1(a)]
awang295@[Link]
PRIME COST AND PROVISIONAL
SUMS (CLAUSE 34)
b) The term “Provisional Sums” provided in BQ shall means a sums for
work or for the supply of goods or materials which cannot be entirely
foreseen, defined or detailed at the same time the tender documents
are issued and such sum may be paid and expended at such times and
in such amounts in favor of such persons as the S.O. may direct. If such
sums is not used either wholly or in part shall as to, the amount not
used will be deducted from the contract sum. At the settlement of the
accounts, the said value of executed work done by Contractor shall be
set off against all such Provisional Sums and the balance shall be added
to or deducted from the contract sum. [Clause 34.1(b)]
awang295@[Link]
PRIME COST AND PROVISIONAL
SUMS (CLAUSE 34)
awang295@[Link]
PERFORMANCE BOND (CLAUSE 13)
a) Paid by cash, treasury deposits, banker's draft or insurance guarantee
from approved bankers where the sum is equal to 5% of the total
contract sum. [Clause 13.1]
b) It shall be held or remain valid effective for the period as is provided in
the approved Banker's or Insurance Guarantee. [Clause 13.1]
c) Applied if the Contractor fails to execute the contract or commits any
breach of his obligations under the contract, the government or the S.O.
on its behalf may utilize and make payments out of or deductions from
the Performance Bond or any part thereof in accordance with the terms
of the contract. [Clause 13.3]
d) The Performance Bond may be released or refunded to the Contractor
on the completion of making good of all defects, shrinkages or other
faults which may appear during the Defects Liability Period and upon
the giving of the Certificate of Completion of Making Good Defects for
the whole of the works under Clause 45. [Clause 13.5]
awang295@[Link]
POSSESSION OF SITE (CLAUSE 38)
awang295@[Link]
POSSESSION OF SITE (CONT'D)
awang295@[Link]
COMPLETION OF WORKS (CLAUSE 39)
awang295@[Link]
DAMAGES FOR NON-COMPLETION (CLAUSE 40)
awang295@[Link]
LIQUIDATED AND ASCERTAINED DAMAGES (LAD)
awang295@[Link]
LIQUIDATED AND ASCERTAINED DAMAGES (LAD)
Characteristics of LAD:
As a compensation to Owner due to late completion of project by
the Contractor.
Sum payable is based on day/week/month.
The rate must be realistic and reflect actual cost incurred by Owner
in renting similar facilities.
Advantages of LAD:
Discourage Contractor from completing construction project late.
Convenient method of getting payment from the Contractor.
awang295@[Link]
PENALTY AND BONUS
awang295@[Link]
DELAY AND EXTENSION OF TIME (CLAUSE 43)
a) By force majeure* [Clause 58.0]
b) By reason of any exceptionally inclement weather
c) By reason of S.O. directions, consequential upon disputes with
neighbouring owners. [Clause 50.0]
d) By reason of the loss or damage due to Clause 44.
e) By reason of S.O.’s instruction issued under Clause 5.
f) By reason of Contractor not receive in due time necessary
instructions or drawings.
g) By reason of delay in giving possession of site under Clause 38.4.
h) By reason of local combination of workmen, strike, or lockout
affecting trades.
i) By delay of artists, tradesmen or others engaged by Government
to execute the work.
j) By the Contractor’s inability for reason beyond his control at the
date the tender closed.
k) By delay of NSC/NS, caused by sub-clauses (a) to (j) as stated above.
awang295@[Link]
*FORCE MAJEURE
awang295@[Link]
DELAY AND EXTENSION OF TIME (CONT'D)
awang295@[Link]
CLAUSE 43 (B) -EXCEPTIONAL INCLEMENT WEATHER
From the monthly summary of rainfall for area XYZ for the past 5 years (20XX – 20XX) as
compiled by MMD/DID, the average rainfall for the month of Jan to Dec can be tabulated as
follows:-
awang295@[Link]
Thus the actual daily rainfall which exceeds the average rainfall of every month for the last
5 years can be categorized as "Exceptional Weather Conditions".
DEFECT LIABILITY PERIOD (DLP) (CLAUSE 48)
a) Defect Liability Period (DLP) is a period where the Contractor shall
make good the defects at his own costs against any defect,
imperfection, shrinkage or any other faults which may appear and
which are due to materials or goods or workmanship not in
accordance with this contract. DLP is stated in the Appendix (if not
stated is six (6) months after Date of Practical Completion).
b) S.O. shall specify in Schedule of Defects and deliver to Contractor
not later than 14 days after the expiration of DLP. Contractor
shall make good not later than three (3) months after the receipt
of the said Schedule.
awang295@[Link]
DEFECT LIABILITY PERIOD (DLP) (CLAUSE 48)
c) If the Contractor failed to comply with the previously mentioned
sub-clause (a) or (b), S.O. may departmentally or employ others to
make good the defects and deduct from:
i) Remaining sum to be paid to the Contractor
ii) Performance Bond
iii) As liquidated demand in money
b) If it is impractical or inconvenient to Government to have
Contractor remedy the defects, S.O. shall ascertain the value of
the Works and deduct from:
i) Remaining sum to be paid to the Contractor
ii) Performance Bond
iii) As liquidated demand in money
c) When Contractor has made good all defects, S.O. shall issue
“Certificate of Completion of Making Good Defects” on the date.
awang295@[Link]
CONTRACT ADMINISTRATOR
IN CHARGE
“S.O.” under JKR 203 Form of Contract
awang295@[Link]
SUMMARY
Bills Of Quantities Form Part Of The Contract
Contained of 81 Clauses
Mostly applied in Traditional Contract Delivery System.
awang295@[Link]
ACKNOWLEDGEMENTS
Janidah Eman (UiTMPP)
Nur Muizzah Nawi (UiTMJ)
Muhammad Isha Ismail (UiTMP)
Noor Raifana Ab Rahim (UiTMJ)
REFERENCES
Chitkara, K. K. (2014). Construction Project Management.
Tata McGraw-Hill Education.
Additional notes:
awang295@[Link]
INTRODUCTION
awang295@[Link]
WORK BREAKDOWN STRUCTURE (WBS)
Level – WBS numbered based on main and subsections. Ex. Level 1 for
“Project”, Level 2 (coded as L1.1) for “Section” and Level 3 (coded as L1.1.1) for
“Work” within the “Section”
awang295@[Link]
WORK BREAKDOWN STRUCTURE (WBS)
awang295@[Link]
EXAMPLE 1 OF WBS DIAGRAM
awang295@[Link]
EXAMPLE 2 OF WBS DIAGRAM
PROJECT
SUBPROJECT
SUBNETWORK
ACTIVITY
SUBACTIVITY
awang295@[Link]
EXAMPLE 1 OF WBS (LABEL)
1.2 ……………………
1.2.1 …..……………….
awang295@[Link]
EXAMPLE 2 OF WBS (LABEL)
awang295@[Link]
OBJECTIVES OF WBS
To breakdown the project to visible items that can be controlled and are
small enough for accurate estimates.
To specify work packages for accountability and responsibility which will be
assigned to specific personnel.
To ensure the progress of the work packages can be measured.
awang295@[Link]
BAR CHART PLANNING METHOD
Bar Chart (also known as Gantt Chart) was developed by Henry L. Gantt.
In a typical Bar Chart, the horizontal scale is divided into time elements (days, weeks,
etc) while the vertical axis displays the activities.
The length of a bar is used to represent the duration of an activity while its position on
the chart indicates when the work should begin and end.
awang295@[Link]
BAR CHART PLANNING METHOD
Nowadays Bar Chart was modified and named as Link Bar Chart which manages to
show the interrelationship between activities, thus integrate costs to the schedule.
Typical Bar Chart is drawn by using a horizontal bar or line chart with the following
features:
‒ Activities identified on the left hand side.
‒ Time scale drawn on the top or bottom of the chart along the x-axis.
‒ A horizontal open bar or line is drawn against each activity indicating the estimated
time duration.
‒ At a review point, the oblongs or bars are shaded to represent the actual time spent.
awang295@[Link]
EXAMPLE 1 OF BAR CHART
awang295@[Link]
EXAMPLE 2 OF BAR CHART
awang295@[Link]
SOLUTION
awang295@[Link]
PROJECT MANAGEMENT BASIC TERMINOLOGIES
awang295@[Link]
EXERCISE 1
Based on the table given, without overlapping activities, draw a Bar Chart.
awang295@[Link]
EXERCISE 2
Based on the table given and without overlapping work, draw a Bar Chart.
awang295@[Link]
EXERCISE 3
Based on the table given, with overlapping activities, draw a Bar Chart.
awang295@[Link]
TUTORIAL
awang295@[Link]
BAR CHART PLANNING METHOD
Advantages: Disadvantages:
Widely accepted because Networking of the activities is not shown.
most people readily The interrelationship and dependency of activities
understand it. are not defined.
Does not indicate the exact date, thus hard to
Easy to use and interpret.
interpret when is the activity start and finish times
Suitable for use in office and
as separate events.
site due to its compact Does not indicate critical path and critical activities.
format. Does not indicate the float (total float, free float, and
Able to show visually the etc.), therefore cannot illustrate tolerances for the
proposed and the actual completion of various activities.
progress of work. Does not integrate costs or resources with the
Able to present project schedule.
Cannot be easily modified to reflect the actual
progress graphically.
situation.
Simple and quick to
Not a good controlling device because it is in a
generate. compact format.
Hard to handle for large projects.
awang295@[Link]
CRITICAL PATH METHOD NETWORK ANALYSIS
Critical Path Method (CPM) was developed in 1956 as effective technique for overall
detailed scheduling of construction project.
It is often referred to a network analysis system (NAS) and provides interrelationship
of activities and scheduling of cost and resources.
This up-front format planning and scheduling helps the project team to identify
conflicts in resources before it occur.
The CPM scheduling is a graphic network that shows the sequence of the project
tasks, the task duration and the relationship of tasks to one another.
The CPM network will also provide the 'critical path' that is, those tasks that are
required to be done on time and is sequenced to meet the overall project dateline or
completion date.
awang295@[Link]
CRITICAL PATH METHOD NETWORK ANALYSIS
awang295@[Link]
CRITICAL PATH METHOD NETWORK ANALYSIS
Determine the time, cost and resources required to complete each activity.
Analyse costs and resources for the project:
‒ Compute the cost per day for each activity and for the entire project.
‒ Compute the resources that are required to complete the project.
awang295@[Link]
CRITICAL PATH METHOD NETWORK ANALYSIS
awang295@[Link]
CRITICAL PATH METHOD NETWORK ANALYSIS
Advantages
awang295@[Link]
CRITICAL PATH METHOD NETWORK ANALYSIS
Limitations Disadvantages
Project activities have to be clearly defined, CPM is not easily understood by
independent and stable in their most people.
relationships. Not easy to use and interpret.
Precedence relationships must be specified Not suitable for use in office and
and networked. site, because it gives all details.
Time estimates tend to be subjected to the Not able to show visually the
estimates of the planners or project proposed and the actual progress of
manager. work.
There is tendency or inherent danger of Not able to present all project
overlap focusing on the critical path and the progress graphically.
critical activities only, in which there are also It is time consuming to generate.
other important factors such as costs, Awkward for more complex
quality, compliance to standard and projects.
customer and legal requirements that need Use of dummy activities can be
to be tended to. confusing.
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM
B D F
A H
C E G
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM
Each activity has a begin and end point. The begin and end point is expressed as
Event.
Therefore, in this case the node is the Event. An Event represents the start of
activity and the finish of the activity.
The arrows connecting the two (2) events represent the AOA. Tasks or activities are
represented by the arrows (or the arrows represented the activity).
Using this AOA, there is a Dummy Activity where we may need to use to indicate
precedence when no activity exist. Dummy activity is represented by a dashed
arrow and has a time duration of ZERO. Dummy activity is only used in AOA
network format for two reasons:
‒ To help in the unique identification of activities
‒ To show certain presidential relationships that otherwise could not be shown.
In AOA, there cannot be two activities, having the same predecessor―successor
relationship. Thus, the insertion of dummy activity allows such combinations.
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM
B F
A B' H
C G
E
Activity ES : EF
Duration LS : LF
awang295@[Link]
BUILD A NETWORK/PRECEDENCE DIAGRAM 1
awang295@[Link]
BUILD A NETWORK/PRECEDENCE DIAGRAM 2
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM
Time
Earliest Start Time (ES) = EF - Activity Duration (D)
Earliest Finish Time (EF) = ES + D
Latest Start Time (LS) = LF - D
Latest Finish Time (LF)
Total Float (TF) = LF - EF or LS -ES
Free Float (FF)
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM (TIME)
Earliest Finish Time (EF)
Earliest Finish Time (EF) is the earliest time by which a particular activity can be
completed.
It is calculated by adding the activity's duration estimate to the activity's Earliest Start
Time.
EF = ES + Activity Duration
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM (TIME)
LS = LF + Activity Duration
LF is the latest time by which a particular activity must be completed in order for the
entire project to be finished by its required completion time.
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM (TIME)
TF = LF - EF or
= LS - ES
If the TF is positive, it represents the maximum amount of time that the activities on
a particular path can be delayed without jeopardizing completion of the project by its
required completion time.
If the TF is negative, it represents the amount of time that the activities on a
particular path must be accelerated in order to complete the project by its required
completion time.
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM (TIME)
For AON,
Where the subscript i represents the preceding activity and the subscript j represents
the following activity.
For AOA,
ES : EF ES jk : EF
i j k
LS : LFij LS : LF
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM (ACTIVITY)
Dummy Activity
Dummy Activity is a virtual activity that does not require cost or time. Any
activity follows Dummy Activity cannot start until the activity or activities
precede the Dummy Activity are completed. It is included to avoid having two
activities possess the same from-to event numbers.
Symbol
Critical Activity
If the TF is zero, the activities on the path cannot be delayed at all.
An activity that has zero float is called critical activity.
A critical activity means that the activity cannot be delayed at all; otherwise
the delay of this activity will affect the project completion time.
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM (ACTIVITY)
Critical Path
A project cannot be completed until the longest path (most time consuming)
path of activities is finished.
This longest path in the overall network diagram is called as Critical Path.
A Critical Path is the path that consist of activities with no delay, that is, ZERO
float. The path with positive float value is therefore a Non-Critical Path.
The Critical Path indicates the project duration, i.e. the minimum time needed
to complete the project. A project may have more than one Critical Path.
Symbol
awang295@[Link]
EXAMPLE 1 OF PRECEDENCE DIAGRAM (ACTIVITY
ON NODE @ AON)
The activities of a construction project are listed below.
awang295@[Link]
SOLUTION EXAMPLE 1
a) Network Diagram:
B F
A C E H I
D G
awang295@[Link]
SOLUTION EXAMPLE 1
b) i. Precedence Diagram:
awang295@[Link]
SOLUTION EXAMPLE 1
awang295@[Link]
SOLUTION EXAMPLE 1
awang295@[Link]
EXAMPLE 2 OF PRECEDENCE DIAGRAM (ACTIVITY
ON ARROWS @ AOA)
awang295@[Link]
SOLUTION EXAMPLE 2
a) Network Diagram:
D
2 6
4
A
F
1 6
E J
B H
1 3 5 8 9
2 5 4 2
C I
3
3
G
4 7
5
awang295@[Link]
SOLUTION EXAMPLE 2
b) Tabulate Data:
awang295@[Link]
SOLUTION EXAMPLE 2
b) Arrow Diagram:
1:5
2 6
9:13
0:1
7:13
8:9
7:13
0:2 2:7 20:22
1 3 5 13:17 8 9
0:2
2:7 13:17 20:22
0:3 17:20
9:12 17:20
3:8
4 7
12:17
awang295@[Link]
SOLUTION EXAMPLE 3
awang295@[Link]
SOLUTION EXAMPLE 3
awang295@[Link]
SOLUTION EXAMPLE 3
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM (TIME)
For AON,
Where the subscript i represents the preceding activity and the subscript j represents
the following activity.
For AOA,
ES : EF ES jk : EF
i j k
LS : LFij LS : LF
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM (TIME)
Diagram below shows the network for a project with all the relevant data compute on a table.
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM (TIME)
According to above, if activity 2-4 uses all TF of 6 weeks, activity 4-5 will have no float. If activity
2-4 only uses TF of 4 weeks or less, activity 4-5 will remain TF of 2 weeks. Therefore activity 2-4
has 6 weeks of TF which 4 can be used without reducing the float in any succeeding activity (i.e.
activity 4-5). It is say that activity 2-4 has an INTF of 2 weeks and a FF of 4 weeks that make up
the TF of 6 weeks.
awang295@[Link]
BASIC DEFINITIONS OF TERMS IN CPM (TIME)
Time span in which the completion of an activity may occur and not delay the
termination of the project nor delay the start of any following activity, and not be
delayed by any preceding activity. Interfering float is rarely used in any subsequent
calculations.
For AON,
Where the subscript h, i and j represents 3 activities in continuous; i.e. the subscript
h represents the preceding activity, I represents the current activity, and j
represents the following activity.
For AOA,
ES jk : EF ES jk : EF
h i j k
LS : LFhi D ij LS : LF
awang295@[Link]
PROJECT MANAGEMENT USING MICROSOFT PROJECT
The best project management tool in the world can never replace humans
good judgement. However the tool may help to accomplish the following to
increase project productivity:
Track any gathered information regarding the work, duration and resources
required in the project.
Visualize the project plan in a well-define formats.
Schedule tasks and resources consistently and effectively.
Exchange information with all stakeholders online.
awang295@[Link]
PLAN USING MICROSOFT PROJECT
Based on your own developed WBS, create scheduling Microsoft Project. Take note
that Ms. Project is only one of the available options in the market.
RESOURCES REQUIRED IN CONSTRUCTION PROJECT
awang295@[Link]
RESOURCE SHEET
awang295@[Link]
ASSIGN 4M RESOURCES IN MS. PROJECT
Based on the previous schedule in MS. Project, now assign suitable 4M resources for
each tasks.
(Machineries)
(Manpower)
(Materials)
(Money)
awang295@[Link]
1
awang295@[Link]
2
awang295@[Link]
3
awang295@[Link]
RELATIONSHIP OF ACTIVITIES
Other than Predecessor and Successor, there are four (4) other types of relationship
named as “Dependencies”.
awang295@[Link]
OTHER TERMINOLOGIES
need a 2 days delay between the finish of Delay due to unknown condition of soil.
awang295@[Link]
RELATIONSHIP OF ACTIVITIES
The independent activity (A) in the relationship must finish before the
dependent activity (B) can start.
FS
A B
However it does not say that the dependent activity must start then. The
activity could start later than that time, but it is not allowed to start any
sooner than the finish of the independent activity.
awang295@[Link]
RELATIONSHIP OF ACTIVITIES
Example
Formwork FS
Concreting
Activity
awang295@[Link]
RELATIONSHIP OF ACTIVITIES
(SS)
A B
The independent activity in the relationship (A) must start before the
dependent activity (B) can start. It does not say that the dependent
activity must start then.
The activity could start later than that time, but it is not allowed to start any
sooner than the start of the independent activity.
awang295@[Link]
RELATIONSHIP OF ACTIVITIES
Example
(SS)
awang295@[Link]
RELATIONSHIP OF ACTIVITIES
A B
The independent activity (A) in the relationship must finish before the
dependent activity (B) can finish. (B) can’t finish before (A) is finished. It
does not say that the dependent activity must finish then.
The activity could finish later than that time, but it is not allowed to finish
any sooner than the finish of the independent activity.
awang295@[Link]
RELATIONSHIP OF ACTIVITIES
Example
Maintenance Project
Activity Completion
awang295@[Link]
RELATIONSHIP OF ACTIVITIES
(SF)
A B
Independent activity (A) must start before the dependent activity (B) can
finish. It does not say that the dependent activity must finish then.
The dependent activity (B) could finish later than that time, but it is not
allowed to finish any sooner than the start of the independent activity (A).
awang295@[Link]
RELATIONSHIP OF ACTIVITIES
Example
(SF)
awang295@[Link]
RELATIONSHIP OF ACTIVITIES
awang295@[Link]
MILESTONES
We intuitively talk about milestones, not tasks. Because we will be asked,
“When are you going to finish the roof?” and so on.
awang295@[Link]
S-CURVE
awang295@[Link]
EXAMPLE OF S-CURVE
The scheduled and actual duration for each activities of a project are given as below.
awang295@[Link]
SOLUTION
44
)MR( ssergorP evitalumuC
42 43
38
33
26
24
19 23
21
14 18
9
6
3 4
1
Week
awang295@[Link]
SOLUTION
awang295@[Link]
PROJECT FINANCING
“A financing of a major independent capital investment that the sponsoring company has
segregated from its assets and general purpose obligations”.
“The financing of long-term infrastructure, industrial projects and public services based
upon a non-recourse or limited recourse financial structure, in which project debt and equity
used to finance the project are paid back from the cash flow generated by the project”.
“Project financing is a loan structure that relies primarily on the project's cash flow for
repayment, with the project's assets, rights and interests held as secondary security or
collateral. Project finance is especially attractive to the private sector because companies
can fund major projects off balance sheet”.
awang295@[Link]
QLASSIC
Quality assessment
system in construction
awang295@[Link]
awang295@[Link]
INTRODUCTION
Quality Assessment System in Construction
(QLASSIC) is a system or method to measure
and evaluate the quality of workmanship of a
construction work based on the relevant
approved standard.
QLASSIC enables the quality of workmanship
between construction projects to be objectively
compared through a scoring system.
QLASSIC are based on standard developed in
Construction Industry Standard (CIS 7:2006) by
CIDB on November 2006.
awang295@[Link]
OBJECTIVES
To benchmark the quality of workmanship of the
construction industry.
To establish a standard quality assessment
system on quality of workmanship of construction
work.
To assess the quality of workmanship of a
construction project based on the relevant
approved standard.
To be used as a criterion to evaluate the
performance of contractors based on quality of
workmanship.
To compile data for statistical analysis.
awang295@[Link]
QLASSIC SCOPE
Sets out the standard on quality of workmanship for
various construction elements of building and
infrastructure construction work.
The quality of workmanship of a construction work is
assessed according to the requirement of the relevant
standard and marks are awarded if the workmanship
complies with the standard. These marks are then
summed up to calculate the QLASSIC Score (%) for a
construction project.
QLASSIC assessments are carried out through site
inspection and use the principles of first time
inspection.
Construction works that are rectified after an
assessment will not be re-assessed.
The objective of this principle is to encourage the
contractor to "Do Things Right the First Time and
Every Time".
awang295@[Link]
QLASSIC
ASSESSORS
QLASSIC assessment on a construction project
shall be carried out by assessors that have no
interest and any relationship with that project.
All assessors shall fulfill requirements and
undergo training set by CIDB. Only assessors
that pass the training will be registered with CIDB
as qualified QLASSIC assessors.
awang295@[Link]
Assessment approach
& sampling process
Prior to carrying out the assessment,
construction elements that need to be assessed
are determined through a sampling statistical
approach.
These samples shall be distributed evenly
throughout the project or various construction
stages.
Assessment samples are selected from drawings
and plans of the relevant construction project.
All locations in the construction project shall be
made available for the assessment.
This is to ensure that the selected sample
adequately represent the entire construction
project.
Assessment
process
The QLASSIC assessment will be
conducted after the completion of
building construction works and
awang295@[Link]
Who why
No charges for assessment and
Project owner
processing fee for the time being.
Real estate and housing developer
Enables you to benchmark the
Contractor
quality of workmanship of your
Others
awang295@[Link]
construction project.
Provides you a standard assessment
system for quality of workmanship of
construction work.
Enhances quality control of your
construction work.
Specified as a quality criterion for
contractors performance scorecard.
qlassic weightage table
awang295@[Link]
top 10 projects
awang295@[Link]
top 10 projects
implementation
(Source: Che-Ani et. al, 2013)
support its function are the major differences compared to other spaces in a
building.
The uniqueness of lavatory space can be seen after the building is occupied.
At this stage, issues relating to its maintenance would emerge, in public buildings
in particular, including lavatories in higher education institutions.
Due to the presence of the large number of visitors and staff, lavatories in public
buildings and the corresponding high intensity of use, breakdown or malfunction of
lavatories are common.
implementation
(Source: Che-Ani et. al, 2013)
Hence, use and maintenance of lavatory space is often argues. Cleanliness and
functionality is the main goal of lavatory maintenance.
In the life cycle of lavatory maintenance, certain stages of building inspection are
needed to ensure the physical status of the building.
In a wider context, the theory of building assessment also emphasizes the
awang295@[Link]
The method used in visual inspection based on the CSP1 Matrix building condition
measurement tool.
Analysis based on the frequency of defects found the connection and damage
factor between the components and elements in lavatory spaces.
awang295@[Link]
lavatory space
inspection criteria
An intensive review of related literature was conducted in developing the criteria
for the inspection of lavatory space.
Written resources include six existing building inspection standards were the main
sources of reference: ASTM (2009), CONQUAS (2008), JKR (2009), MALAYSIAN
awang295@[Link]
Table 1
awang295@[Link]
Table 2
awang295@[Link]
Table 3
awang295@[Link]
defect
lavatory
number of
basic feedback system
awang295@[Link]
A sample of Inspected
Lavatory Plan Tag
Source: Che-Ani et. al (2013)
a conceptual framework
assessing building performance
Inspection Elements
Structural
Architectural
Mechanical & Electrical
External Works
awang295@[Link]
PERFORMANCE LEVEL
CRITERIA FOR LAVATORY
Aspect of Inspection/Bench
Marking
Building Services
Maintainability
Safety & Health
Functionality
examples
awang295@[Link]
Photographic Box with the Photographic Box with the Photographic Box with the
defects in Yellow Green defects in Red Color defects in Yellow Color
Coded Coded Coded
With the house's owners effort for willing to Briefly shared about the background and
provide the platform for the case study. introduced QLASSIC Assessment.
awang295@[Link]
PERRFORMING QLASSIC ASSESSMENT FOR INDIVIDUAL UNIT AT
KOTA MASAI, PASIR GUDANG BASED ON STANDARD CIS 7
,Source: CIDB, 2015
awang295@[Link]
PERRFORMING QLASSIC ASSESSMENT FOR INDIVIDUAL UNIT AT
KOTA MASAI, PASIR GUDANG BASED ON STANDARD CIS 7
Source: CIDB, 2015
awang295@[Link]
SUSTAINABLE DEVELOPMENT
Environment Development
awang295@[Link]
GREEN CONCEPT
How to achieve:
RnD Materials
Method of Construction
Architectural Concept
Law Enforcement
Etc.
awang295@[Link]
RENEWABLE ENERGY (RE)
awang295@[Link]
EXAMPLE 1
Solar Heat
awang295@[Link]
EXAMPLE 2
Ventilation
awang295@[Link]
EXAMPLE 3
Parking Lot
awang295@[Link]
EXAMPLE 4
Design Concept +
Green Technology
awang295@[Link]
awang295@[Link]
EXAMPLE 5
awang295@[Link]
=.='
DO NOT OVERDO IT
SUMMARY
Activities in scheduling are:
QLASSIC:
To benchmark quality of workmanship.
To establish standard quality assessment.
Tho assess quality of workmanship.
To compile data for statistical analysis.
awang295@[Link]
ACKNOWLEDGEMENTS
Janidah Eman (UiTMPP)
Nur Muizzah Nawi (UiTMJ)
Muhammad Isha Ismail (UiTMP)
Noor Raifana Ab Rahim (UiTMJ)
REFERENCES
Chitkara, K. K. (2014). Construction Project Management. Tata McGraw-Hill
Education.
Ritz, G. J., Levy, S. M. (2013). Total Construction Project Management (2nd ed.).
McGraw-Hill Education.
Additional notes:
Pellicer, E., Yepes, V., Teixeira, J. C., Moura, H. P., Catalá, J. (2013). Construction
Management. Wiley-Blackwell. Chapter 12: Resources Management.
awang295@[Link]
CIDB
SITE SECURITY
awang295@[Link]
CIDB
SITE SECURITY
Standard of fencing required for a particular site will depends
on the hazards and environmental conditions of the worksite
as well as its location.
awang295@[Link]
CIDB
SITE SECURITY
Some factors to be considered:-
awang295@[Link]
CIDB
SITE SECURITY
Consideration for level of risk:-
High risk – Areas that the public would normally access or
pass through such as inner city areas. It is necessary to
prevent public access to the work site.
Medium risk – Areas with moderate public traffic such as
sub-urban residential areas. It is necessary to restrict access
to the worksite and provide warning of the hazard.
Low risk – Areas with minimal public access such as rural
areas requires a lower level of protection.
awang295@[Link]
CIDB
awang295@[Link]
CIDB
STORAGE OF MATERIALS
Location of store and storage areas will be determined by:-
The availability of space
The nature of the materials
Any statutory requirements e.g. in relation to highly
flammable materials or explosives.
To suitable off-loading areas and lifting equipment.
awang295@[Link]
CIDB
LIFTING APPLIANCES
Physical features on the site, building under construction and
environmental constraints will determine positioning of
cranes, hoist and other lifting appliances.
awang295@[Link]
CIDB
TEMPORARY SERVICES
The positioning and marking of temporary services should be
carefully undertaken to avoid possibility of accidental damage.
awang295@[Link]
CIDB
TEMPORARY STRUCTURES
Adequate space must be allowed for lighting towers and for
scaffolding and other support work.
awang295@[Link]
CIDB
WASTE MANAGEMENT
Rubbish dumping area must be allocated. Arrangements for
regular disposal must be determined particularly for scheduled
waste.
awang295@[Link]
CIDB
CAR PARKING
Consideration should be given in parking facilities either on or off-site.
awang295@[Link]
CIDB
TEMPORARY TRAFFIC
MANAGEMENT
INTRODUCTION
As with other potential hazards that may arise in the course of any
construction work, a temporary traffic management must be
developed before commencement of work.
The objective is to safeguard not only workers involved in the
work but also members of the public who might be affected by the
work activities.
awang295@[Link]
CIDB
TEMPORARY TRAFFIC
MANAGEMENT
INTRODUCTION
awang295@[Link]
CIDB
TEMPORARY TRAFFIC
MANAGEMENT
INTRODUCTION
awang295@[Link]
CIDB
TEMPORARY TRAFFIC
MANAGEMENT
PROTECTION OF PUBLIC
awang295@[Link]
CIDB
TEMPORARY TRAFFIC
MANAGEMENT
PROTECTION OF PUBLIC
awang295@[Link]
CIDB
TEMPORARY TRAFFIC
MANAGEMENT
PROTECTION OF WORKERS
awang295@[Link]
CIDB
TEMPORARY TRAFFIC
MANAGEMENT
TRAFFIC DIVERSION PLAN
awang295@[Link]
CIDB
PERSONAL PROTECTIVE
EQUIPMENT MANAGEMENT
INTRODUCTION
Unless required by the law, PPE should be opted as the last line of
defense after due considerations have been given to other alternative
controls – elimination, substitution, isolate and administrative control.
awang295@[Link]
CIDB
PERSONAL PROTECTIVE
EQUIPMENT MANAGEMENT
INTRODUCTION
awang295@[Link]
CIDB
PPE MANAGEMENT
SELECTION
awang295@[Link]
CIDB
PPE MANAGEMENT
SELECTION
awang295@[Link]
CIDB
PPE MANAGEMENT
SELECTION
awang295@[Link]
CIDB
PPE MANAGEMENT
SELECTION
awang295@[Link]
CIDB
PPE MANAGEMENT
SELECTION
awang295@[Link]
CIDB
PPE MANAGEMENT
MAINTENANCE & STORAGE
awang295@[Link]
CIDB
PPE MANAGEMENT
MAINTENANCE & STORAGE
awang295@[Link]
CIDB
SAFETY SIGNAGE
INTRODUCTION
awang295@[Link]
CIDB
SAFETY SIGNAGE
COLOURS AND DESIGNS
awang295@[Link]
CIDB
SAFETY SIGNAGE
COLOURS AND DESIGNS
awang295@[Link]
CIDB
SAFETY SIGNAGE
COLOURS AND DESIGNS
awang295@[Link]
CIDB
SAFETY SIGNAGE
DANGER SIGNS
awang295@[Link]
CIDB
SAFETY SIGNAGE
awang295@[Link]
THE OCCUPATIONAL
SAFETY AND HEALTH ACT
1994
The Occupational Safety and Health Act 1994 (Act
514) is a piece of Malaysian legislation which has
been gazetted on the 25 February 1994 by the
Malaysian Parliament.
awang295@[Link]
OSHA 1994 (ACT 514)
CONTENTS
PART I PRELIMINARY
PART II APPOINTMENT OF OFFICERS
PART III NATIONAL COUNCIL FOR OCCUPATIONAL SAFETY AND
HEALTH
PART IV GENERAL DUTIES OF EMPLOYERS AND SELF-EMPLOYED
PERSONS
PART V GENERAL DUTIES OF DESIGNERS, MANUFACTURER AND
SUPPLIERS
PART VI GENERAL DUTIES OF EMPLOYERS
PART VII SAFETY AND HEALTH ORGANISATIONS
PART VIII NOTIFICATION OF ACCIDENTS, DANGEROUS
OCCURRENCE, OCCUPATIONAL POISONING AND OCCUPATIONAL
DISEASES AND INQUIRY
awang295@[Link]
OSHA 1994 (ACT 514)
CONTENTS (cont'd)
awang295@[Link]
FIRST SCHEDULE (OSHA)
Manufacturing
Mining and Quarrying
Construction
Agriculture, Forestry and Fishing
Utilities:
‒ Electricity
‒ Gas
‒ Water
‒ Sanitary Services
awang295@[Link]
FIRST SCHEDULE (OSHA) -cont'd
Transport, Storage and Communication
Wholesale and Retail Trades
Hotel and Restaurants
Finance, Insurance, Real Estate and Business Services
Public Services and Statutory Authorities
awang295@[Link]
THE FACTORY AND
MACHINERY
ACT 1967
The Factory and Machinery Act 1967 (Act 139) is a
piece of Malaysian legislation which was enacted in
1967 as Act No. 64 of 1967 and revised on April 1,
1974 as Laws of Malaysia Act 139. The Act was
gazetted on February 1, 1970.
awang295@[Link]
THE FACTORY AND
MACHINERY
ACT 1967
The principle of the act is "An Act to provide for the control of
factories with respect to matters relating to the safety, health
and welfare of person therein, the registration and inspection
of the machinery and for matters connected therewith".
awang295@[Link]
THE FACTORY AND
MACHINERY
ACT 1967
The jurisdiction of the Act only covers less than 20 percent of
all working areas in Malaysia, the Malaysia government has
enacted the Occupational Safety and Health Act 1994 which
covers almost all areas of work within Malaysia.
awang295@[Link]
The list of regulations under this Act are:
awang295@[Link]
The list of regulations under this Act are:
awang295@[Link]
THE OCCUPATIONAL
SAFETY AND HEALTH ACT
1994
The principle of the Act is "An Act to make further provision
for securing that safety, health and welfare of persons at
work, for protecting others against risks to safety or health in
connection with the activities of persons at work, to establish
the National Council for Occupational Safety and Health and
for matters connected therewith".
awang295@[Link]
Part I ‒ Interpretation
Section 3
“Contract of service” – any agreement whether in oral or in writing and
whether express or implied, whereby one person agrees to employ
another as an employee and that other agrees to serve his employer as an
employee and includes an apprenticeship contract.
“Council” – the National Council for Occupational Safety and Health
established under Section 8.
“Industry” – the public services, statutory authorities or any of the
economic activities listed in the First Schedule.
“Employer” – means the immediate employer or the principal employer or
both.
“Occupier” – in relation to a place of work, means a person who has the
management or control the place of work.
“Place of work” – means premises where persons work or premises used
for the storage of plant or substance.
awang295@[Link]
Part I ‒ Interpretation (cont'd)
Section 3
“Premises” – includes any land, building or part of any building; any
vehicle, vessel or aircraft; any installation on land, offshore installation or
other installation whether on the bed of or floating on any water and any
tent or moveable structure.
“Self-employed person” – an individual who works for gain or reward
otherwise than under a contract of employment or not he himself employs
others.
“Plant” – includes any machinery, equipment, appliance, implement or
tool, any component thereof and anything fitted, connected or appurtenant.
“Substance” – any natural or artificial substance whether in solid or liquid
form or in the form of a gas and vapour or any combination.
“Trade union” – any association or combination of workmen or employers
within the meaning of the Trade Unions Act 1959.
awang295@[Link]
Part II ‒ Objectives of the Act
awang295@[Link]
Part III ‒ General Duties of Employers
and Self-Employed Persons
Ensure the safety, health and welfare of all workers while at work
This includes:
a) Making arrangements and maintenance of plants and work
system.
b) Making arrangements for the use, handling, storage and
transportation of the plant and substances (materials).
c) Provision of information, instruction, training and supervision.
d) Provide and maintain workplace / access routes to and from
work areas.
e) Provide and maintain work environment with adequate welfare
facilities.
awang295@[Link]
Part III ‒ Worker Interpretation
awang295@[Link]
Part III ‒ General Duties of Employers
and Self-Employed Persons
Other duties
Section 16 - Formulate a written Safety and Health Policy.
Section 17(1) - Conduct operations without endangering the safety of
others – non-workers and public.
Section 17(2) - Provide information to others on business operations.
Section 18 - An occupier of non-domestic premises shall take measures to
ensure that the place of work is/are safe and without risks to health to the
persons other than his employees.
Section 19 – A person who contravenes the above section shall be guilty
of an offence and shall on conviction be liable to fine not exceeding RM
50K or imprisonment for a term not exceeding 2 years or to both.
awang295@[Link]
Part III ‒ General Duties of Employers
and Self-Employed Persons
awang295@[Link]
Part IV ‒ General Duties of Employees
Section 24
Ensure personal safety and that of others.
Cooperate with employer and others.
Properly wear and /or use personal protective equipment that are
provided.
Comply to any safety instructions.
Section 25
An Employee:
‒ Who intentionally, recklessly or negligently interfere of misuse
anything provided or done in the interest of safety, health and
welfare in pursuance of the Act shall be guilty of an offence.
awang295@[Link]
Part IV ‒ General Duties of Employees
Section 26
The employer may not charge employees for things done or provided in
pursuance of this Act.
Section 27
Employer/Trade Union may not discriminate – dismiss, injure or change
position of any employee who makes complaint that he is not safe or is
risk to health and also exercises his functions as a member of the Safety
and Health Committee.
awang295@[Link]
Part V ‒ Safety and Health Officer
Section 29
Specific industries gazetted.
Employ a competent person to act as a safety and health officer.
Specific responsibilities to ensure compliance to the Act and promotion of
safe work.
Qualification and training requirements.
awang295@[Link]
Part V ‒ Safety and Health Committee
Section 30
To be established if:
‒ There are 40 or more workers.
‒ Instructed by Director General.
Membership, selection and appointment as prescribed.
Consultation with employer
awang295@[Link]
Part V ‒ Safety and Health Committee Functions
Section 31
To review all safety and health measures that have been taken.
Investigate issues concerning occupational safety and health and bring
to attention of employer.
Other functions may be determined.
awang295@[Link]
Part VI ‒ Notification of accidents, dangerous
occurrence, occupational poisoning & diseases
& inquiry.
Section 32
Employers to inform the nearest Department of Safety and Health
office (DOSH).
Registered Medical Practitioners should report to the Director General.
awang295@[Link]
SUMMARY
Site planning and layout involving a site security, safe means of access,
storage of materials, lifting appliances, temporary services and structures,
waste management and car park.
The factor to be considered in temporary traffic management is width of
road and traffic density, percentage of heavy vehicles, terrain and
environmental factors.
Safety signage and protection for workers and public.
Occupational Safety and Health Act 1994.
awang295@[Link]
ACKNOWLEDGEMENTS
Ritz, G. J., Levy, S. M. (2013). Total Construction Project Management (2nd ed.).
McGraw-Hill Education.
Additional notes:
Pellicer, E., Yepes, V., Teixeira, J. C., Moura, H. P., Catalá, J. (2013). Construction
Management. Wiley-Blackwell. Chapter 9: Health and Safety Management.