Lean Design for Sustainable Buildings
Lean Design for Sustainable Buildings
3.Lean design
The June issue of The Structural Engineer 3. Maximise utilisation 4. Interrogate serviceability criteria
introduced six themes for climate guidance. One Results from the MEICON 2018 survey5 indicate If the limiting utilisation of a structural member is
of these was ‘Lean design’, calling on structural that ease of construction, a perceived risk of for a serviceability criterion (e.g. a deflection limit),
engineers to strive for designs that minimise the construction errors, and a lack of significant then it is worth pursuing the relaxation of those
demand for new material wherever viable. penalties for overdesign all have an adverse criteria in consultation with the client and wider
This article gives pragmatic advice on reducing impact on the final utilisation ratios of our project team.
the impact of your buildings on the environment structural elements. Moynihan and Allwood6 Ò| Facades – are the facade contractor’s limits
today, in order of magnitude of savings. found average utilisation ratios to be below 50% realistic and based on the actual conditions
for typical steel buildings. or generic and can be challenged? Can you
1. Don’t build! Buro Happold has produced guidance for its perceive a span/360 deflection with the naked
It might seem counterintuitive, but a structural structural engineers that focuses on increasing eye?
engineer’s job is to ensure that the underlying minimum utilisations to acceptable levels, Ò| Internal partitions – can larger deflection
objectives behind creating a space are met, and which change as a project progresses (Figure heads and vertical joints be used as standard?
not necessarily to design and create new structure 2). Working to lower utilisation ratios gives Deflection heads can have detrimental impacts
to achieve that. See Ibell et al1 in the June issue. designers leeway for late design changes and on acoustic performance; can the acoustic
flexibility, and so working to higher minimum criteria be relaxed?
2. Upgrade existing buildings utilisations requires appropriate quality controls, Ò| Long-span beams and slab defl ections
wherever viable such as: – can you pre-camber? Can you use a
There are many ways of upgrading existing Ò| contractual obligations for design refinement lower-strength element or material as SLS
buildings, from space planning to significant Ò| colour-coding utilisation ratios within BIM is governing? Can you assume additional
structural interventions. Even if the superstructure models stiffness by assuming that connections are
is demolished, the foundations may be suitable for Ò| recommendations that project managers somewhere between pinned and fixed?
reuse2. allow a certain time/cost in bids or budgets Ò| Dynamic criteria – are the limits set
Using the Brand model3, which considers a for optimisation. appropriate for the intended use; could some
building as a series of layers with varying longevity, localised exceedance be accepted?
these different layers of intervention can be It is important to communicate to the project Ò| Crack width requirements – crack widths
systematically explored (Figure 1)3,4. team the value of the time and fees spent on should only govern if water-tightness is
Alternatively, if it is not viable to reuse an existing design development and refinement, with the necessary.
building, new buildings can be designed with potential material savings leading to cost and
circular principles in mind, such as design for carbon reductions. 5. Refine loading criteria
disassembly or proportionate repair. Conservative loading assumptions can be
appropriate at early design stages where the brief
îFIGURE 1: Building layers3,4 is fluid and there are many unknowns.
For permanent and semi-permanent loads, the
different layers of the building are typically finalised
as the design progresses, and so refinement is
more straightforward. Imposed loads (Figure 3),
though more difficult to refine, can be adapted in
several ways.
5 A0
A 0 1.0
7 A
with the restriction for categories C and D:
0.6
BURO HAPPOLD
where:
+HUH(DVW
6NLQ² *OD]HG)DoDGHWROHWLQOLJKW
$QDO\WLFV
6RFLDO 3HRSOHIORZPRGHOOLQJIRULQFUHDVLQJ ψ0 is the factor according to EN 1990, Annex A1
Table A1.1
6WUXFWXUH² 0H]]DQLQHIORRUVDGGHG SHUIRUPDQFHRIH[LVWLQJEXLOGLQJ
&23<5,*+7%852 +$332/'$//5,*+765(6(59('
A0 = 10.0m2
12
August 2020 | thestructuralengineer.org
íFIGURE 2: Target
utilisation rates for
each design stage
BURO HAPPOLD
A is the loaded area. 7. Concentrate on reducing grids
and fl oor slabs
2 ( n 2) 0 Various studies indicate that floors typically
account for 40–50% of the embodied carbon of a
WE SHOULD NOT
BE DESIGNING
n
n building. Structural sensitivity studies9 show that
where: an infallible way of reducing the material required BUILDINGS
n is the number of storeys (>2) above the loaded
structural elements from the same category
for floors is to reduce the size of the structural grid
(Figure 5)10. WITH INITIAL
ψ0 is in accordance with EN 1990, Annex A1 If time and/or the fee is tight on a project, REDUNDANCIES
Table A1.1. concentrating your efforts on refining the floor
slabs of the structures can make significant
WHICH MAY
Minimum appropriate imposed loading embodied carbon savings. NEVER BE NEEDED
BS EN 1991 gives loading categories to cover
most building uses, and the minimum appropriate 8. Don’t forget substructure movements.
value should be used (e.g. refining a plant room Substructure typically forms 20% of the total Ò| If designing driven steel piles, use
loading of 7.5kN/m2 for the weight of actual embodied carbon that a structural engineer reclaimed steel tubing from the oil and gas
plant proposed for the space). Furthermore, the has direct control over (Fig. 5). Below are a few industry where possible.
appropriate partial factors should be applied substructure-specific considerations: Ò| Specify a low-cement-content concrete
when more than one load value is present. Ò| Avoid basements and suspended fl oor with the lowest strength appropriate, especially
slabs where possible. if a GEO load case is limiting.
Clear brief Ò| Use the superstructure and the site Ò| Design for 56-day strength. Typically,
When preparing options at concept stage, create to minimise foundations. To minimise foundations will not be subject to their full
an option with the minimum appropriate loading foundation sizes, the proposed superstructure design load until later in the construction
available, and the subsequent cost and carbon must work with the ground that it sits on. programme.
savings. These should be discussed with the If the ground is poor, the superstructure Ò| Refine settlement criteria. Settlement
client so that they understand the importance of should be light or designed to accept greater criteria for foundations are often chosen as a
clarifying the uses of the spaces.
13
thestructuralengineer.org | August 2020
REFERENCES
íFIGURE 4: Comparison
of material use in two
alternative designs 1) Ibell T., Norman J. and Broadbent O.
(2020) ‘Nothing is better than something’,
The Structural Engineer, 98 (6), p. 12
BURO HAPPOLD
14
August 2020 | thestructuralengineer.org