MAPÚA UNIVERSITY
SCHOOL OF MECHANICAL AND MANUFACTURING ENGINEERING
ME136P-2/E01
ENGINEERING MATERIALS, PROCESSES AND TESTING
WRITTEN REPORT ON
Design of Concrete Mix in Philippine Peso
Worksheet Exercise 2.1
SUBMITTED BY:
Talan, Jefferson R.
2016142228
SUBMITTED TO:
ENGR. JENNIFER VALDEZ
DATE
March 29, 2021
ABSTRACT
Cement mixture ratio is important in determining the outcome properties. This could be
the difference of having a sound structure and failing structure when external forces act on it.
volume method is done in determining the amount of materials needed for each structure such as
footing, beams, slabs, etc. This is accordance to National Structural Code of the Philippine 2015.
Estimate cost is also determined by comparing the daily wage of mason, constructional engineer,
and construction workers in Quezon City and Bulacan.
OBJECTIVES
1. Compute the total volume of sand, aggregate, cement, and water depending on volume
and ratio
2. Estimate the total cost in Philippine peso with manpower needed depending on location
in the country.
ii
TABLE OF CONTENTS
TITLE PAGE i
ABSTRACT ii
OBJECTIVE ii
TABLE OF CONTENTS iii
THEORIES AND PRINCIPLES 1
DISCUSSION 2
LIST OF APPARATUS / SET-UP 4
CONCLUSION 4
RECOMMENDATION 5
REFERENCES 6
iii
THEORIES AND PRINCIPLES
Ratio in cement combination is important for civil engineering. This could determine the
properties of the mixture once it solidified. According to the National Structural Code of the
Philippine of 2015, the minimum force that a cement structure must withstand for general structure
is 2500 pound per square inch. This means that the structure must withstand a minimum of 2500
psi without breaking under testing. To assure this, ratio of mixture is important to put in mind.
1:2:3:0.5
That is the ratio of mixture of cement that would ensure that the cement mixture could
withstand the minimum force required. This means that for every bag of cement, which is about
40 kg in weight, twice is the amount of sand, thrice is the amount of gravel, and ½ is the amount
of water needed. To ensure this, put it in a wooden box container with a dimension of 0.3 m by 0.3
m by 0.3 m to ensure proper measurement.
Volume of each component is important to know the amount of material needed for
structural parts.
V = length x width x height
To get the quantity of cement needed
𝑣𝑜𝑙𝑢𝑚𝑒 × 36
𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 =
3
To get the quantity of sand
𝑣𝑜𝑙𝑢𝑚𝑒
𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝑠𝑎𝑛𝑑 =
2
The quantity of gravel needed is just equal to the volume of a specific structure.
1
DISCUSSION
Cement mixture is important in construction engineering. This is the very material is used
in building most structure all over the globe. Therefore, it is important that the cement structure
built is strong enough to withstand strong forces in able for the structure to absorb external factors
and forces that can break its structural integrity.
There are a lot of components to a structure that needs cement mixture. Some of which are
footing, connecting tie footing, columns, walls, slabs, etc. All this structure needs cement so
volume computation is done to determine the number of materials needed for the whole structure
depending on the design.
This is a screenshot from the video made by Engineer Jojo Pascua on one of his videos in
YouTube. Here, he shows how to compute the cement needed for a sample footing design that he
made. The volume of the footing is computed by multiplying the length, width, and height.
To get the quantity of cement needed, we use the volume computed for the footing and
multiply it by 36 and divided by 3. Sir Jojo Pascua multiplied the volume of footing to 12 because
2
in his structural design, he needed 12 footing for the overall structure. This computation would
result in approximately 51 bags needed for the footing.
To determine the amount of sand needed, we simply divide the volume of footing in half.
The resulting number would have a unit of cubic meter. Quantity of gravel needed for this would
just be equal to the volume of each footing. These computations would result in the quantity of
cement, sand, aggregate and water needed for the footing alone.
The same process is done for every part of the structure which includes, columns, beam,
slab, and the walls which would all utilize cement for building.
According to the website of PayScale.com, the average salary of constructional engineer is
600,000 Philippine Peso but of course, this is always dependent on the size and design you want
for your structure. On top of that, construction workers are also needed to provide manpower on
the actual building on the structure. Construction workers have an hourly rate of 61.97 pesos.
Multiply that to 8 hours would result in Php. 495.67 which is based on Quezon City, Metro Manila.
Usually on a small-scale structure, one mason and two helpers are needed. According to
the Department of Labor and Employment, mason’s monthly salary range is from Php. 8000-
10,000. Some can even go as high as Php. 13,000. Estimating their daily wage, is about 500 pesos
which is again dependent on the location of the project. Average daily Mason wage here in Bulacan
is about 700 pesos. Adding the two helpers would result in about Php. 1691.34. Remember that
that result is only an estimation for small scale project. Some huge projects can with a land area of
about 6000 square meters could result in labor alone about 150,000 Pesos on a weekly basis.
3
LIST OF APPARATUS / SET-UP
1. Aggregate (20 mm) 24.8 kg
2. Aggregate (10 mm) 24.2 kg
3. Sand 30.2 kg
4. Cement 20 kg (OPC grade)
5. Concrete mixer
6. Foundation design
CONCLUSION
For this exercise, we were able to compute the total amount of required materials needed
to form each structure like footing, beam, etc. This is done through volume method by computing
the total volume of a certain structure and relating it to the necessary formulas for each component
such as sand, aggregate, cement, and water.
Estimation for the total cost of labor for the cement addition in a structure is also computed
which is dependent on the location. This is because city rates and provincial rates differs which
can almost always more expensive in cities. However, this does not other supplies such as metal
rods, plywood, and other important materials in building a sound structure. This exercise is great
for visualizing the number of materials needed to form a structure. Moreover, this could open our
eyes in the cost of building the structure based on the amount of cement mixture needed.
4
RECOMMENDATION
This exercise is great, but I think it could be improve if the discussion on the lessons and
videos is deeper which could strengthen our understanding construction materials such as cement
which could simple in ordinary person’s perspective but complicated once we dealt with it such as
the ratio of materials needed which could vary from different standards.
5
REFERENCE
1. Pascua J. (2020, June 28). Ilang Semento, Graba at Buhangin para sa Poste,
Footing, Beam at Slab at Tamang mixture. Retrieved from:
http://www.youtube.com/watch?v=guGHRcT8pEU
2. (n.d.). Average Project Engineer, Construction Salary in Philippines. Retrieved
from:
https://www.payscale.com/research/PH/Job=Project_Engineer%2C_Construction/Sal
ary
3. (n.d.). Pay Standards and Practices. Retrieved from: https://nwpc.dole.gov.ph/wp-
content/uploads/2020/04/Construction_04.2020_v.2.pdf