Rectification Work Risk Assessment

This document provides a risk assessment for rectification works on the Burj Khalifa project. It identifies potential hazards associated with activities like preparing the work area, manual handling, and unloading/shifting wiring accessories. For each activity, it lists the identified risks to people and property, along with control measures to mitigate those risks. The control measures include requirements for training, inspections, proper lifting procedures, barricades, certified equipment, and checking load limits. The overall goal is to conduct all rectification works safely in order to prevent injuries and property damage on the high-risk construction site.

Uploaded by

adeniyi abiola
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
866 views10 pages

Rectification Work Risk Assessment

This document provides a risk assessment for rectification works on the Burj Khalifa project. It identifies potential hazards associated with activities like preparing the work area, manual handling, and unloading/shifting wiring accessories. For each activity, it lists the identified risks to people and property, along with control measures to mitigate those risks. The control measures include requirements for training, inspections, proper lifting procedures, barricades, certified equipment, and checking load limits. The overall goal is to conduct all rectification works safely in order to prevent injuries and property damage on the high-risk construction site.

Uploaded by

adeniyi abiola
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Project Overview: Provides an introductory overview of the project, including key stakeholders, approval details, and initial assessments.
  • Hazard Considerations: Lists potential hazards associated with the project activities, including control measures and required training.
  • Specific Work Conditions: Details the specific work-related risks and conditions for tasks such as unloading, lifting, and working on scaffolding.
  • Equipment and Testing: Covers equipment specifications, testing requirements, and calibration processes to ensure safety and effectiveness.
  • Completion and Review: Discusses the procedures and evaluations necessary for completing tasks and ensuring compliance with safety standards.
  • Risk Ratings and Briefing: Summarizes risk ratings and includes briefing signatures to document that the risks have been communicated to team members.

Document No:

PROJECT: F066 BURJ KHALIFA Rev : 0


METHOD STATEMENT FOR RECTIFICATION WORKS
Date: 13-02-2023

NO of
ASSESSMENT,
PROJECT/CONTRACT ACTIVITY ASSESSMENT REVIEWED
BY: BY: REVISION &
DATE

PROJECT: F066-BURJ KHALIFA

CLIENT: MR. ALEJANDRO SANCHEZ FERNANDEZ RECTIFICATION PM Sr. P M CH/RA/01


WORKS
MAIN CONTRACTOR: CHERWELL INTERIOR DECORATION LLC. Ahmad Nicolas REV: 00
Javed. Castanheiro
13/02/2023

PREPARED BY: APPROVED BY: APPROVED BY:

ABIOLA FREDERICK ADENIYI PROJECT MANAGER Sr. PROJECT MANAGER

HSE OFFICER

CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 RECTIFICATION WORKS RISK ASSESSMENT


Document No:
PROJECT: F066 BURJ KHALIFA Rev : 0
METHOD STATEMENT FOR RECTIFICATION WORKS
Date: 13-02-2023

POTENTIAL HAZARDS/CONDITIONS TO BE CONSIDERED

Deep Excavations Work on over water Falls from height X Fire risk High winds

Demolition Confined space Falls from level ground X Noise/Dust/Vibration X Adverse

Plant/Machinery X Working Platforms X Slips/Tripping X Fumes Environmental risk

Lifting Operations X Manual Handling X Fuel Storage Traffic X Training Required

Buried/Overhead Service COSHH Storage/Lay Down Area Ground Conditions Health surveillance

NO ACTIVITY HAZARD DESCRIPTION IDENTIFIED AT L S R CONTROL MEASURES L S R ACTION BY


RISK(PEOPLE/PROPER
TY)
1. Prepare · Unauthorized, · Cuts 2 3 6 • TBT/DSTI to be conducted by 1 2 2 SO/PE/SE
work area. Untrained workers. · Abrasion Foreman/Safety officer prior to work
commencement.
• Task specific safety training to be provided.
• Authorized personnel to undertake the job.
• Daily safety inspection should be carried
out and eliminate the hazards.
2. Manual · Incorrect lifting of · Back injuries. 2 2 4 · Deploy enough number of personnel for 2 1 2 PE/ SO/SE
Handling. load. · Cut of finger. lifting shall be appointed to the task
· Sharp edges. · Strain. depending upon the type of load to be
· Placing the object · Musculoskelet lifted.
while fingers al injuries. · Use easy mode of transport like trolly etc.
underneath. · Any lifting task shall be carried out by
· Unsafe posture. persons physically capable to do so.
· Slip/Trip/Fall (same · No employee should be asked to carry
level). loads above his capacity and in any case no
· Poor posture load shall exceed 30kg per man.

CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 RECTIFICATION WORKS RISK ASSESSMENT


Document No:
PROJECT: F066 BURJ KHALIFA Rev : 0
METHOD STATEMENT FOR RECTIFICATION WORKS
Date: 13-02-2023

· Mass of the load is more then to be equally


shared.
3 Unloading · Unauthorized, · Fatality. 2 3 6 • Ensure the crane and forklift engaged is 1 2 2 PE/SE/SO/FM
and shifting untrained workers. · fracture. tested and having valid license and the
wiring · Lifting failure. · Property operator has valid license and approved 3rd
accessories · Unsafe lifting. damage. party certificate.
with using, · Swinging of · Injury to • Engage trained and certified banks man.
trolly, crane material. personnel. • Barrication and warning signs into the area
or forklift. · Damaged · Sprain and where lifting operation is carried out and
sling/wire rope or a strain. restrict the entry.
chain. • Check list should be carried out to their
· Poor maintenance vehicles by the operator prior to start any
of vehicle. work.
· Speedy operation. • Use tagline for control of swing and
· Overturn. alignment.
· Overload. • All lifting equipment’s and gears shall be
having third party certified.
• The crane must be stopped when the wind
speed exceeds 38km/hr.
· SWL should be clearly marked on the crane
and should be check that is functioning.
4 Working · Slip, Trip and Fall · Fatigue. 2 3 6 • All materials shall be stored below 2M 1 2 2 PE/SE/SO/FM
with hand · Damaged worn · Trigger finger height.
tools out hand tools. · Cut and • If the material is too heavy, use hydraulic
(screwdriver, · Flying objects abrasion. trolley to shift the material.
spanner). · Mushroom heads · Damage to • No storage of material to be done in the
· Using incorrect property. workplace, only required quality to be
type taken for the job.
• Personal protective equipment must
always wear during the activity. (Helmet,
Shoes, Vest, Overall, Gloves, Goggles and
Mask)

CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 RECTIFICATION WORKS RISK ASSESSMENT


Document No:
PROJECT: F066 BURJ KHALIFA Rev : 0
METHOD STATEMENT FOR RECTIFICATION WORKS
Date: 13-02-2023

5 Installation · Unauthorized, · Fatigue. 1 3 3 • Authorized/ Trained personnel to 1 2 2 PE/SE/SOFM


of wiring untrained workers. · Cut and undertake the job.
accessories. · Materials fall from abrasion. • Work location shall be inspected by
height. · Back injuries. concerned supervisor / foreman.
· Sharp edges. · Musculoskelet • Close supervision to be always done.
· Unsafe postures. al injuries. • Materials should not be kept in walkways
· Slip/Trip/Fall and edge of the opening.
• Proper communication to be maintained
between the workers while doing the
installation.
• Maintain a good housekeeping policy to
prevent from slip, trip, and fall hazards.
• PPE to be always worn (Gloves, goggles,
mask, helmet, shoe, vest, overall).
• Emergency procedure to be briefed to all
personnel prior to start the activity
6 Working · Materials/equipme · Fatality. 2 2 4 • PTW to be applied and obtained prior to 1 2 2 PE/SE/SO/FM
near nt fall from height. · Property start work.
opening · Slip/Trip/Fall damage. • Rigid Barrication to be provided to all
floors. · Fracture. external Edges and where a fall can occur.
• Warning signboards to be provided in
those areas.
• PPE to be always used (Helmet, Shoes,
Vest, Overall, Harness)
• Authorized person to do the job.
7 Working · Person or material · Spinal cord 2 2 4 • TBT/ DSTI and Visual inspection to be done 1 2 2 PE/SE/SO/FM
with ladder. Falling from damage. before using the ladder.
height. · Fracture. • Jobs specify training to be provide.
· Overreaching. · Sprain and • The ladder should extend minimum one
· Over loading. strain. meter from the top for safe movement.
· Obstructing the · Injury to the • Heavy materials should not be carried.
accessway. person • Do not erect in slippery, uneven surface.
· Slippery or uneven • Should be set up with a 4 vertical to 1
surface. horizontal slope.

CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 RECTIFICATION WORKS RISK ASSESSMENT


Document No:
PROJECT: F066 BURJ KHALIFA Rev : 0
METHOD STATEMENT FOR RECTIFICATION WORKS
Date: 13-02-2023

• Inspection carried out by competent


person on a regular basis.
• Step ladder must fully open and lock and
the devices to be as per manufacturer.
• Defective ladder should not be used and
report it immediately.
8 Working on · Uneven surface. · Sprain and 2 2 4 • Do not stack materials on to the scaffold. 1 2 2 PE/SE/SO/FM
mobile · Over heading strain. • Visual inspection should carry before use
scaffold. structure and · Fracture. (i.e.., rails and toe board place and any
cable. · Spinal cord platform opening are there).
· Materials and damage. • Out rigger fitted and breaks are locked on.
worker fall from · Musculoskelet • Only trained scaffolders shall be involved in
height. al injury erection & dismantling activities.
· Untrained, · fatality • No person to be on the scaffold while it is
Unauthorized being moved.
workers. • Climbing in the scaffold not acceptance
· Collapse of and it should be by the provided ladder.
scaffold. • Scaffold only use in on level and surface
area.
• Safety harness to be used above 2mtr
height and always anchored in above
shoulder height.
• Tagging system to be implemented (i.e., all
safe scaffolds shall be provided with green
tags and unsafe scaffolds with red tag).
• Keep walkways free of obstacles, tools, and
Equipment.
• Work at height is restricted to adverse
weather condition.
• Adequate Lighting shall be provided while
work at night.
• height of scaffold exceeds raker support or
it should be tied to the structure properly.

CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 RECTIFICATION WORKS RISK ASSESSMENT


Document No:
PROJECT: F066 BURJ KHALIFA Rev : 0
METHOD STATEMENT FOR RECTIFICATION WORKS
Date: 13-02-2023

9 Working • Slip, Trip and Fall. • Fatigue. 2 2 4 • Defective tools should not be issued or 1 2 2 PE/SE/SO/FM
with hand • Damaged warn • Trigger finger. used to perform the task, to be checked by
tools out hand tools. · Cuts and storekeeper.
(Hacksaw, • Flying objects. abrasion. • Do not extend the spanner by using a pipe
Torque · Mushroom Heads as an extension bar.
wrench, • Hand tools shall be free from oil, grease &
Hammer< etc.
Spanner) • Chisel’s head shall have safety cap to avoid
finger injury.
• Never use a file as a lever.
• Never use a screwdriver as a chisel.
• Use eye/ face protection when there is
flying materials hazard, wear gloves while
required to protect the hands.
• Use right tools for the job.
10 Working • Defective · Hearing losses. 2 2 4 • PTW to be applied and obtained prior to 1 2 2 PE/SE/SO/FM
with power equipment. · Eye injury. start if spark producing activity is
tools (Drill • Electricity. · Crushing. performed.
machine)). • Improper use of · Back injury. • Defective tools should not be issued or
equipment. · Burns. used to perform a task.
• Poor maintenance. · Electrocution. • Operators must be having their training
• Untrained workers. • Ringing in the card.
• Flying object. ear/Deafness. • Monthly inspection should be carried out
• Noise and by the electrician and record to be kept at
vibration. the store.
• Fire. • All portable power tools should be fitted
• Dust. with adequate fuse protection either in
the tool body or in its electrical plug.
• The weight, size and type of tool should be
selected to suit the job being carried out.
• Do not lay the cables around the access
way, it should be proper routing.
• Industrial distribution board and socket
only to be used at site.

CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 RECTIFICATION WORKS RISK ASSESSMENT


Document No:
PROJECT: F066 BURJ KHALIFA Rev : 0
METHOD STATEMENT FOR RECTIFICATION WORKS
Date: 13-02-2023

1No joints shall be made in electrical


cable.
• Cable hanger shall be used to avoid the
direct contact of power tools cable with
the scaffolding members.
• Electrical connection shall be routed
through ELCB only.
• Correct rate of ELCB should be used (Ex: -
30ma only acceptable).
• Only those persons who have been
adequately trained and experienced in the
use of the tool should be allowed to use
the same.
• Tools shall have monthly checked
inspection sticker.
• Tools should be stored and maintained in
good working condition.
• Appropriate PPE Should use (Goggles,
Mask, Ear plug, Gloves, Shoe, Helmet,
Overall, Vest)
11 Cable · Unauthorized/untr · Electric shock 2 2 4 • Trained person only to do the testing. 1 2 2 PE/SE/SO/FM
testing by ained person. and Burns. · Ensure that the circuit is not live before
multimeter. · Faulty instrument. · Cut and using the instrument.
· Improper abrasion. · Warning boards should be provided and
identification. Barricaded.
• Electrocution. • Lock out tag out (LOTO) procedure to be
followed during testing.
12 Working · Electricity. · Electrocution 2 2 4 • Only those persons who have been 1 2 2 PE/SE/SO/FM
with · Conductors (water, or death. adequately trained and certified in the
electricity. metals, concrete). · Burns and work of electricity to allow for the same.
· Broken wires. shocks. • Temporary live cable management plan
· Improper plug, · Muscle shall develop and implement during the
case. contraction. activity.
· Overloading. · Heart, lung. • Electrical work shall not carry out in wet

CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 RECTIFICATION WORKS RISK ASSESSMENT


Document No:
PROJECT: F066 BURJ KHALIFA Rev : 0
METHOD STATEMENT FOR RECTIFICATION WORKS
Date: 13-02-2023

· Paralysis. Conditions.
· Fire. • Lock out tag out (LOTO) procedure to be
followed during testing & commissioning.
• Do not overload to the circuits.
• Communicate to all personnel about
testing & commissioning.
• Do not use homemade electrical
accessories and use industrial type only.
• Disconnect main supply before
commencing of work.
• Defective tools and equipment should not
be used, report it, and replaced it
immediately.
• Barricade the location and signage to be
placed where circuits and equipment are
energized.
• Temporary power supply shall be taken
through standard rated MCBs & RCBs.
• Temporary power supply cables shall not
have joints.
• PPE should wear always were working in
energized circuits. (Insulated gloves,
Electric resistivity shoe)
13 Electrical · Unauthorized/Untr · Electric shock 2 2 4 • Work notification to be applied and 1 2 2 PE/SE/SO/FM
Testing & ained person. and burns. obtained prior to start the night work from
Commission · Faulty instrument. · Cut and contractor.
ing using · Improper abrasion. • Proper illumination to be provided.
millimeter identification. • light post to be secured from fall.
tester · Electrocution. • Proper cable management system to be
Followed.
• All materials to be staged in proper
manner without obstacles.
• Emergency procedure to be briefed to all
personnel prior to start the activity.

CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 RECTIFICATION WORKS RISK ASSESSMENT


Document No:
PROJECT: F066 BURJ KHALIFA Rev : 0
METHOD STATEMENT FOR RECTIFICATION WORKS
Date: 13-02-2023

• Isotonic drinks to be provided.


• Drink plenty of water.
• Employees shall be trained about heat
stress symptoms & first aid measures.
• Avoid highly physical tasks during the
hottest part of the day
14 Work · Poor · Fire 2 3 6 • Ensure proper housekeeping daily. 1 2 2 PE/SE/SO/FM
Completion housekeeping. • Manual handling training undertaken.
· Slip/Trip/Fall • Employees aware not to lift beyond their
capacity and ask for help.
• Fire awareness undertaken by staff.
• Keep walkways free of obstacles, tools and
equipments.

CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 RECTIFICATION WORKS RISK ASSESSMENT


Document No:
PROJECT: F066 BURJ KHALIFA Rev : 0
METHOD STATEMENT FOR RECTIFICATION WORKS
Date: 13-02-2023

LIKELIHOOD RISKIN RATING The above risk assessment has been briefed as fully
RISK 3 2 1 SEVERITY understood
RATING Name Sign
3 Major/injury/pollution/Damage
S Name Sign
2 Minor/Pollution/Damage/Loss
E
1 Injury/Low Damage/Loss Name Sign
V 3 9 6 3
LIKELIHOOD Name Sign
E
3 Likely Name Sign
R 2 6 4 2
2 Possible
I Name Sign
1 Never/Very Unlikely
T 1 3 2 1 Name Sign

Name of person given risk assessment briefing

Name Date:

Signature Time

CHERWELL HSE DEPARTMENT/[Link]-NO- 01/00 RECTIFICATION WORKS RISK ASSESSMENT