100% found this document useful (2 votes)
17K views7 pages

Block Work Rate Analysis Summary

This document provides a rate analysis for hollow concrete block masonry construction using 16"x8"x8" blocks. It includes costs for materials, labor, tools/plant, and profit/overhead. The total estimated rate per square foot is Rs. 183.40. A second rate analysis is then provided for hollow concrete block masonry using 16"x4"x8" blocks, with a total estimated rate of Rs. 138.18 per square foot. Finally, a rate analysis is given for solid concrete block masonry using 12"x8"x8" blocks, with a total estimated rate of Rs. 221.96 per square foot.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
17K views7 pages

Block Work Rate Analysis Summary

This document provides a rate analysis for hollow concrete block masonry construction using 16"x8"x8" blocks. It includes costs for materials, labor, tools/plant, and profit/overhead. The total estimated rate per square foot is Rs. 183.40. A second rate analysis is then provided for hollow concrete block masonry using 16"x4"x8" blocks, with a total estimated rate of Rs. 138.18 per square foot. Finally, a rate analysis is given for solid concrete block masonry using 12"x8"x8" blocks, with a total estimated rate of Rs. 221.96 per square foot.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
  • Hollow Concrete Blocks Masonry Rate Analysis (16"x8"x8")
  • Solid Concrete Blocks Masonry Rate Analysis (12"x8"x8")
  • Brick Masonry Rate Analysis (9" thick)
  • Brick Masonry Rate Analysis (4.5" thick)
  • Summary of Costs

RATE ANALYSIS

Rate analysis for Hollow Concrete Block Masonry (16"x8"x8")

Unit = Sft Quantity 100

Particulars Unit Quantity Rate (Rs.)

A. MATERIALS

1 Providing of Hollow block (16"x8"x8") Nos 112 55.00 6,160.00

2 Cement (For Laying) (1:5) Bags 2.08 550.00 1,144.00

3 Sand Cft 10 20.00 200.00

4 Cement (For Filling Cavity ) (1:6) Bags 0.44 550.00 242.00

5 Sand Cft 3.334 20.00 66.68

6 MS bar for anchorage to structure at ever third course Nos 20 35.00 700.00

7 Water for mortar and curing etc. ltr. 100 0.50 50.00

8 Scaffolding Sft 100 4.00 400.00

Total 8,962.68

5% wastage % 8,962.68 5% 448.13


Sub Total ( A ) 9,410.81
B LABOUR

Labour for laying block Sft 100 35 3,500.00

For drilling hole for MS bars anchorage Nos 20 10 200.00

For Curing Sft 100 2 200.00

For Scaffolding Sft 100 6 600.00

Sub Total ( B ) 4,500.00

C TOOL & PLANT

3% of (A+B) % 13,910.81 3% 417.32

Sub Total ( C) 417.32

Total (A + B + C) 14,328.14
D Profit, O/H & Income tax

Add 28% against profit, overheads & I/T % 14,328.14 28% 4,011.88

Sub Total ( D) 4,011.88

Total (A + B + C+D) 18,340.02


Cost / Rate per Sft 183.40
RATE ANALYSIS

Rate analysis for Hollow Concrete Block Masonry (16"x8"x8")

Unit = Sft Quantity 100

Particulars Unit Quantity Rate (Rs.)

A. MATERIALS

1 Providing of Hollow block 16"x4"x8" Nos 112 38.00 4,256.00

2 Cement (For Laying) (1:5) Bags 1.00 470.00 470.00

3 Sand Cft 6.00 20.00 120.00

4 Cement (For Filling Cavity ) (1:6) Bags 0.13 470.00 61.10

5 Sand Cft 0.985 20.00 19.70

6 MS bar for anchorage to structure at ever third course Nos 20 35.00 700.00

7 Water for mortar and curing etc. ltr. 100 0.50 50.00

8 Scaffolding (depreciation cost) Sft 100 4.00 400.00

Total 6,076.80

5% wastage % 6,076.80 5% 303.84


Sub Total ( A ) 6,380.64
B LABOUR

Labour for laying block Sft 100 26 2,600.00


For drilling hole for MS bars anchorage (Every third Nos 20 10 200.00
course)
For Curing Sft 100 2 200.00

For Scaffolding Sft 100 6 600.00

Lead & Lift from Basement to 4th Floor Sft 100 5.00 500.00

Sub Total ( B ) 4,100.00

C TOOL & PLANT

3% of (A+B) % 10,480.64 3% 314.42

Sub Total ( C) 314.42

Total (A + B + C) 10,795.06
D Profit, O/H & Income tax

Add 28% against profit, overheads & I/T % 10,795.06 28% 3,022.62

Sub Total ( D) 3,022.62

Total (A + B + C+D) 13,817.68


Cost / Rate per Sft 138.18
RATE ANALYSIS

Rate analysis for Solid Concrete Block Masonry (12"x8"x8")

Unit = Sft Quantity 100

Particulars Unit Quantity Rate (Rs.)

A. MATERIALS

1 Providing of Solid block (12"x8"x8") Nos 144 55.00 7,920.00

2 Cement (For Laying) (1:5) Bags 2.67 550.00 1,468.50

3 Sand Cft 12.85 20.00 257.00

4 MS bar for anchorage to structure at ever third course Nos 20 35.00 700.00

5 Water for mortar and curing etc. ltr. 100 0.50 50.00

6 Scaffolding Sft 100 4.00 400.00

Total 10,795.50

5% wastage % 10,795.50 5% 539.78


Sub Total ( A ) 11,335.28
B LABOUR

Labour for laying block Sft 100 45 4,500.00

For drilling hole for MS bars anchorage Nos 20 10 200.00

For Curing Sft 100 2 200.00

For Scaffolding Sft 100 6 600.00

Sub Total ( B ) 5,500.00

C TOOL & PLANT

3% of (A+B) % 16,835.28 3% 505.06

Sub Total ( C) 505.06

Total (A + B + C) 17,340.33
D Profit, O/H & Income tax

Add 28% against profit, overheads & I/T % 17,340.33 28% 4,855.29

Sub Total ( D) 4,855.29

Total (A + B + C+D) 22,195.63


Cost / Rate per Sft 221.96
RATE ANALYSIS

Rate analysis for Solid Concrete Block Masonry (12"x4"x8")

Unit = Sft Quantity 100

Particulars Unit Quantity Rate (Rs.)

A. MATERIALS

1 Providing of Solid block 12"x4"x8" Nos 144 42.00 6,048.00

2 Cement (For Laying) (1:5) Bags 1.29 550.00 709.50

3 Sand Cft 7.71 20.00 154.20

4 MS bar for anchorage to structure at ever third course Nos 20 35.00 700.00

5 Water for mortar and curing etc. ltr. 100 0.50 50.00

6 Scaffolding (depreciation cost) Sft 100 4.00 400.00

Total 8,061.70

5% wastage % 8,061.70 5% 403.09


Sub Total ( A ) 8,464.79
B LABOUR

Labour for laying block Sft 100 26 2,600.00


For drilling hole for MS bars anchorage (Every third Nos 20 10 200.00
course)
For Curing Sft 100 2 200.00

For Scaffolding Sft 100 6 600.00

Lead & Lift from Basement to 4th Floor Sft 100 5.00 500.00

Sub Total ( B ) 4,100.00

C TOOL & PLANT

3% of (A+B) % 12,564.79 3% 376.94

Sub Total ( C) 376.94

Total (A + B + C) 12,941.73
D Profit, O/H & Income tax

Add 28% against profit, overheads & I/T % 12,941.73 28% 3,623.68

Sub Total ( D) 3,623.68

Total (A + B + C+D) 16,565.41


Cost / Rate per Sft 165.65
RATE ANALYSIS

Rate analysis for Brick Masonry 9" thick

Unit = Sft Quantity 100

Particulars Unit Quantity Rate (Rs.)

A. MATERIALS

1 Providing of 1st Class Solid Burnt bricks Nos 1012.5 16.00 16,200.00

2 Cement (For Laying) (1:5) Bags 3.75 550.00 2,062.50

3 Sand Cft 23.44 20.00 468.80

4 MS bar for anchorage to structure at ever third course Nos 20 35.00 700.00

5 Water for mortar and curing etc. ltr. 100 0.50 50.00

6 Scaffolding Sft 100 4.00 400.00

Total 19,881.30

5% wastage % 19,881.30 5% 994.07


Sub Total ( A ) 20,875.37
B LABOUR

Labour for laying block Sft 100 30 3,000.00


For drilling hole for MS bars anchorage (Every third Nos 20 10 200.00
course)
For Curing Sft 100 2 200.00

For Scaffolding Sft 100 6 600.00

Sub Total ( B ) 4,000.00

C TOOL & PLANT

3% of (A+B) % 24,875.37 3% 746.26

Sub Total ( C) 746.26

Total (A + B + C) 25,621.63
D Profit, O/H & Income tax

Add 28% against profit, overheads & I/T % 25,621.63 28% 7,174.06

Sub Total ( D) 7,174.06

Total (A + B + C+D) 32,795.68


Cost / Rate per Sft 327.96
RATE ANALYSIS

Rate analysis for Brick Masonry 4.5" thick

Unit = Sft Quantity 100

Particulars Unit Quantity Rate (Rs.)

A. MATERIALS

1 Providing of 1st Class Solid Burnt bricks Nos 506.25 16.00 8,100.00

2 Cement (For Laying) (1:4) Bags 2.25 550.00 1,237.50

3 Sand Cft 11.25 20.00 225.00

4 MS bar for anchorage to structure at ever third course Nos 20 35.00 700.00

5 Water for mortar and curing etc. ltr. 100 0.50 50.00

6 Scaffolding Sft 100 4.00 400.00

Total 10,712.50

5% wastage % 10,712.50 5% 535.63


Sub Total ( A ) 11,248.13
B LABOUR

Labour for laying block Sft 100 30 3,000.00


For drilling hole for MS bars anchorage (Every third Nos 20 10 200.00
course)
For Curing Sft 100 2 200.00

For Scaffolding Sft 100 6 600.00

Sub Total ( B ) 4,000.00

C TOOL & PLANT

3% of (A+B) % 15,248.13 3% 457.44

Sub Total ( C) 457.44

Total (A + B + C) 15,705.57
D Profit, O/H & Income tax

Add 28% against profit, overheads & I/T % 15,705.57 28% 4,397.56

Sub Total ( D) 4,397.56

Total (A + B + C+D) 20,103.13


Cost / Rate per Sft 201.03
Sr ParticularsUnit Qty Rate Amount

1 Materials
Cement Bags 1.37 550 753.5
Sand Cft 6.35 20 127
Water CharLitres 100 1 100
Total 980.5
Wastage 5% 49.025
Total 1 1029.525
2 Labour
Labour for Sft 100 17 1700
Curing Sft 100 1 100
ScaffoldingSft 100 3 300
Total 2 2100

3T&P
Add 3% aga% 3129.525 3% 93.88575

Grand Total For Pr 3223.411

4 Profit & Overheads, I/T


3223.411 28% 902.555

Rate for 100 Sft 4125.966

Rate for 1 sft 41.25966

You might also like