0% found this document useful (0 votes)
29 views2 pages

Tutorials Week5 Solution

The document discusses flow time analysis and capacity analysis. For flow time analysis, it provides an example process with activities and calculates the original and new flow times. The critical path is identified. For capacity analysis, it calculates the capacity of resources in minutes and customers/hours. It provides an example where capacity increases by adjusting unit load times. It also provides an example calculating the most profitable product based on margin and capacity. It then calculates the capacity and financial capacity of a mixed product line.

Uploaded by

jenny
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views2 pages

Tutorials Week5 Solution

The document discusses flow time analysis and capacity analysis. For flow time analysis, it provides an example process with activities and calculates the original and new flow times. The critical path is identified. For capacity analysis, it calculates the capacity of resources in minutes and customers/hours. It provides an example where capacity increases by adjusting unit load times. It also provides an example calculating the most profitable product based on margin and capacity. It then calculates the capacity and financial capacity of a mixed product line.

Uploaded by

jenny
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd

CHAPTER 4: FLOW TIME ANALYSIS

Activity Activity
F1 A B

4.4
Process 15 10
a. min min
Loan
And
Officer
Separate

10 Activity 15
min F2 min
C

20
min

b. The flow time is 50 minutes. The critical path is the one of F1 (process and separate,
Activity A, Activity B, Loan Officer).
c. The new flow time of Activity A will be 0.5 * 15 + 0.5 * 30 = 22.5. Activity A is on the
critical path, and so the flow time of the process will be 57.5, an increase of 7.5.
CHAPTER 5: FLOW RATE AND CAPACITY ANALYSIS

5.3
a. The capacity is 6 customers per hour as illustrated below:

Resource Pool Lulu Stylist


Pool Size 1 3
Unit load (min per customer) 3 30
Effective unit capacity (per min) 1/3 1/30
Effective pool capacity (per min) 1/3 1/10
Effective pool capacity (per hour) 20 6

b. The capacity will increase to 7.2 customers per hour as illustrated below:

Resource Pool Lulu Stylist


Pool Size 1 3
Unit load (min per customer) 8 25
Effective unit capacity (per min) 1/8 1/25
Effective pool capacity (per min) 1/8 3/25
Effective pool capacity (per hour) 7.5 7.2

5.4

a. A is more profitable : The capacity of A and B respectively are 900/10= 90 and 900/20= 45
units per day. The margin capacity of the two products are 90*20 =$1800 and 45*35 = $1575
per day respectively.
b. The unit load of the mix is 60%*10 +40%*20 = 14 minutes per unit. The capacity is 900/14 =
64.3 units per day.
c. The margin per unit is 60%*20+40%*35= $26 per unit. The financial capacity is 64.3*26 =
$1671.42 per day.