0% found this document useful (0 votes)
304 views49 pages

15MW DMCI Masbate Thermal Power Plant Overview

The document provides details about the 15MW DMCI Masbate Thermal Power Plant located in Mobo, Masbate Philippines. It discusses the general information including standard voltages and frequencies used. The main components of the electric system are also described, including the turbine generator, 69kV boost substation, auxiliary distribution system, DC system, motor control, protection system, synchronizing system, and turbine/generator interlock. Finally, it classifies the electric equipment into primary, secondary, DC, and control systems.

Uploaded by

Alvin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
304 views49 pages

15MW DMCI Masbate Thermal Power Plant Overview

The document provides details about the 15MW DMCI Masbate Thermal Power Plant located in Mobo, Masbate Philippines. It discusses the general information including standard voltages and frequencies used. The main components of the electric system are also described, including the turbine generator, 69kV boost substation, auxiliary distribution system, DC system, motor control, protection system, synchronizing system, and turbine/generator interlock. Finally, it classifies the electric equipment into primary, secondary, DC, and control systems.

Uploaded by

Alvin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

15MW DMCI Masbate Thermal Power Plant (DMTPP)

Mobo, Masbate Philippines

15MW DMTPP Project


Electric System

September 07, 2019

1
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

TABLE OF CONTENTS
I. GENERAL…………………………............................................................................................................ 3
II. MAIN COMPONETS OF ELECTRIC SYSTEM…………………………………………….....…...………… 6
III. CLASSIFICATION OF ELECTRIC EQUIPMENT…………………………………………….....…...……… 16
IV. OPERATION & MAINTENANCE OF ELECTRIC SYSTEM……………………………….…....…...……… 19
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

I. GENERAL

1.1 Site of Project:


This project is located in Tugbo, Mobo, Masbate City and Owner already has 2 Units of Diesel
Generator with total capacity of 24.4MW. In same site, DMCI will build a new thermal power plant
with capacity of 15MW. After new power plant build, the 2 Units of Diesel Generator is un-running,
used for backup.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

I. GENERAL

1.2 Standard Voltages and Frequencies at local Grid


The following nominal values are applied:

Transmission voltages 69 kV
Generator voltage 13.8 kV
Grid cos phi range 0.85 lagging / 0.90 leading
Medium voltage (aux. supply) 4.16 kV
Low voltage (3phase, 4/5-wire) 460/220(for light) V
Main DC voltage 220 V, 110 V, 24 V
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

I. GENERAL

1.2 Standard Voltages and Frequencies at local Grid

The rated frequency of the AC voltage is 60 Hz.


The steady state operation frequency range is +3% to - 5%.

In this project, the electrical technical data is designed as :


Rated Main Transformer High Voltage: 69KV
Rated Main Transformer Low Voltage: 13.8KV
Rated Generator Voltage: 13.8KV
Rated Auxiliary Distribution Voltage: 480V
Rated Control & Lighting System Voltage: 220V
Rated DC System Voltage: 110V
Rated Frequency: 60Hz
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

II. MAIN COMPONENTS OF ELECTRIC SYSTEM


15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

II. MAIN COMPONENTS OF ELECTRIC SYSTEM


15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

II. MAIN COMPONENTS OF ELECTRIC SYSTEM


2.Turbine Generator

2.1 Turbine Generator Datas:


The Turbine Generator Set is provided by Shin Nippon ,Japan. Rated Capacity:
21875KVA(17500KW)
PF=0.8(Lagging) 60Hz
Reactance: Xd”=19% (with IEC60034 tolerance)

2.2 Excitation System:


Brushless excitation system with PMG

2.3 Generator Auxiliary Panel


1)Generator Voltage & Current Transformer Panel: VT/SA Panel:
2)NGR Panel

2.4 Generator Control & Protection Panel: GCP:


Including Generator Protection Relay, AVR Control System, Synchronizing System.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

II. MAIN COMPONENTS OF ELECTRIC SYSTEM

3. 69KV Boost Substation

3.1 The 69KV boost substation is beside of Main Power House, outdoor arranged. AIS equipment
is used and connected to 69KV Grid through Over Head Line. It is one of Line-Transformer
connection, including CVT,CIT,DS,CB and boost Transformer. The neutral of Boost Transformer
is solid grounded. Data of Boost Transformer as follow:

69±4x2.5%/13.8KV, 20MVA, YN,d11, ONAN, OLTC, Ud%=10.5


15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

II. MAIN COMPONENTS OF ELECTRIC SYSTEM

4. Auxiliary Distribution System

The rated voltage of auxiliary distribution system is of 13.8KV and 0.48KV. One starting Aux.
Transformer is used for auxiliary load during start stage and its power is from existing diesel
power plant. Auxiliary power system is designed as single bus connection. The capacity of
working aux. transformer is 2500KVA and same big standby transformer is set, used for backup
through ATS.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

II. MAIN COMPONENTS OF ELECTRIC SYSTEM

5. DC System

There are two sets of battery of 300Ah, 110V in power plant, used for DC Oil Motor and other DC
load.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

II. MAIN COMPONENTS OF ELECTRIC SYSTEM

6.Motor Control

For most of boiler motor use VFD to make more better power consume. The motor control is
concentrated in DCS or PLC system including motor information respectively.
Motor control in DCS as follow:
1)Boiler Motor;
2)Turbine Motor;
3)Coal and Biomass Handing Motor;
4)Water Intake System Motor;
5)Chlorination System Motor

Motor control in PLC as follow:


1)Water Treatment Motor;
2)Flying Ash and Limestone Motor;
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

II. MAIN COMPONENTS OF ELECTRIC SYSTEM

7. Protection System
Micro-computer Relay is used in this power plant. For Boost Transformer, Generator, the
protection relay is concentrated in protection panel, for auxiliary transformer, the protection relay
is put inside the MV distribution panel.
Especially for generator, there are two sets of protection relay, one is put in GCP(generator
control panel) provided by Shin Nippon, another is put in Generator protection panel. The GCP is
the main protection relay, another is second main protection relay.
For Line-Transformer protection, there is Main Transformer protection panel. The Main
Transformer protection relay has function not only for Main Transformer, but also for OVHL.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

II. MAIN COMPONENTS OF ELECTRIC SYSTEM

8. Synchronizing System

There are two sets of synchronizing system, one is in GCP, one is in Synchronizing Panel.
For generator synchronizing, use GCP; for Main Transformer and other point use synchronizing
panel.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

II. MAIN COMPONENTS OF ELECTRIC SYSTEM

9. Turbine and Generator Interlock

The interlock tripping signal between Turbine and Generator through GCP and DCS system is
the first channel. The Generator Protection Panel is the second channel.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

III. CLASSIFICATION OF ELECTRIC EQUIPMENT

Electrical equipment systems includes: primary system, secondary system, DC system, control system:
1. Primary system: The primary system includes generators, motors, transformers, switches, isolator
(isolation switches), high and low voltage feeders and cables, and leads for access systems.
2. Secondary system: The secondary system is a system served for operation, control, protection, automatic
device, monitoring, etc. for a system service.
3, DC system: DC system is DC power supply, which provides power supply for primary and secondary
system, it is also regarded as a safety power supply for the plants.
4. Control system: The control system includes parameter display, operation, and protection automation
device.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

III. CLASSIFICATION OF ELECTRIC EQUIPMENT

1. Primary equipment. The equipment which are used for direct production and transmission and distribution is called
primary equipment (also called primary system). The electric power is generated from the generator and distributed
directly to the electric appliance through a series of primary equipment, thus to complete the entire process of
production, transmission and usage of electric power. The primary equipment mainly includes generators and
transformers.Pressures, circuit breakers, disconnectors, current limiting reactors, busbars, cables and mutual inductors
2. Secondary equipment. Auxiliary equipment which are used for monitoring, measuring, controlling and protecting the
work of primary equipment is called secondary equipment (also called secondary system). The secondary equipment
mainly includes instruments, signals, and relays and automatic control equipment, etc.
3.Main electrical wiring. In power plant and substation, in order to meet the needs of various operating modes, different
electrical equipment are connected in a certain sequence according to requirements, forming a permnent connected
circuit. The circuit connected by primary equipment is called primary circuit or electrical main wiring.
4. Circuit breaker (QF) is a special electrical device used to turn the circuit on and off in the normal or faulty state of
circuit. The contact part of the circuit breaker is equipped with a special arc extinguishing device. The arc extinguishing
device can quickly extinguish the arc between the contacts during the process of cutting off the circuit, so that the
circuit is reliably and quickly disconnected. If the system fails, the relay protection device acts and automatically
disconnects the circuit breaker to disconnecting the fault point from the normal part of the system to keep the normal
part of the electric power system running. Circuit breaker includes the following types: 1, Air circuit breaker 2, vacuum
circuit breaker. 3. SF6 circuit breaker
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

III. CLASSIFICATION OF ELECTRIC EQUIPMENT

5. Isolating switch (QS). There are no special arc extinguishing devices for the contacts of the isolating
switch. It is not able to reliaby extinguish the arc generated between the contacts during the process of
cutting off the circuit. The isolating switch is mainly to isolate the voltage and switch the circuit. The
isolating switch is often connected in series with the circuit breaker to the circuit. In the normal operation,
the circuit breaker is used to cut off the circuit, and then pull off the isolating switch to isolate the voltage:
only if the loop current is small (such as the voltage transformer circuit), can the isolating switch be
allowed to switch on the circuit.
6. Current limiting reactor (L). The current limiting reactor is essentially a large capacity hollow core
inductance coil. Because it has a large reactance value, it is serially connected to the power supply line.
When a short circuit fault occurs on the line side, the short circuit current is limited due to the increase of
the total reactance, and the bus bar has a high residual voltage, thus reducing the impact on normal
power supply to non-faulty lines.
7. busbar. The busbar acts a role to collect and distribute electric power.
8. Transformer:The transformer includes voltage transformer (also called PT)the symbol is TA. The
current transformer (also called CT) is indicated with symbol TV. Transformer is a communicating device
between the primary system and secondary system in electric power system.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


1. Manufacturer:Shanghai Tongbu DC SYSTEM
a.Composition of DC charging cabinet and DC system product: electric power intelligent high-frequency
rectification charging module, touch screen microcomputer monitoring unit, insulation monitoring device, battery
inspection unit, voltage regulator, AC and DC power distribution, battery and cabinet. Two sets of intelligent
microcomputer monitoring devices are used for the DC busbar; the DC power supply has two charging cabinets;
b. The battery pack consists of lead-acid batteries, with a total of 104 pieces grouped to supply the DC busbar;
2. Battery Specification
Name Type Rated Rated No. Of Battery Charging Current
Capacity Voltage
Battery GZS-300 300AH 110V 104 10A

3. DC panel Specification
Name Type Current Inlet Voltage No. Of Charger Outlet Voltage
Module
Charger TB11040-5 20ADC 460V±20% 6 78VDC~
Module 160VDC
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Charger Module Alarm and Handling
Abnormal Situation Reason for Abnormity Handling Suggestion
Power supply indicator AC lost Inspect whether the AC input is normal.
light(green) off
Internal fault of charger Send them back for maintenance.

Protection indicator Output under voltage Inspect whether the output voltage is normal.
light(yellow) on E31
Charger over Ambient temperature is too high.The thermal design
temperature E31 of system is unreasonable.
AC under voltage E33 Inspect whether the input voltage is normal.
AC phase shortage E34 Inspect whether the AC input voltage is normal in
phase shortage
Fault indicator light(red) Output over voltage E36 Turn off AC power an reenergize
on
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


DC System Alarm and Handling
Abnormal Situation Reason for Abnormity Handling Suggestion
Busbar over voltage and The output voltage of Inspect the output voltage of charger
under voltage charger is abnormal
The voltage adjuster is Inspect whether the voltage adjuster silicon is burned
abnormal out or the voltage adjuster relay is damaged
Battery pack over voltage The output voltage of Inspect the output voltage of charger
and under voltage charger is abnormal
Batteries are damaged Inspect the voltage of single battery
Battery pack over Inspect the voltage of single battery pack
discharge
Busbar poorly insulated DC components are Inspect whether the charger, voltage adjuster and
poorly insulated battery are poorly insulated.
External feed line is Disconnect all busbar feed-out switches. If the poor
poorly insulated insulation phenomenon disappears, it is indicated that
the external feed line is poorly insulated
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Specification
Item The generator
Type no.
The efficiency of 97.3% or higher
Rated power (KW) 21.8
Rated voltage (V) 13.8
Rated current (A) 915
Rated speed (RPM) 1800
Field voltage
203/50
(full/no load V)

Excitation current
259/90
(full/no load A)
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Specification
Item The generator
Number of phase 3
Number of poles 2
The power factor 0.8 (delay)
frequency 60 hz
connection Y

Insulation grade stator/rotor F/F

Cooling way Air cooling

Excitation way Static thyristor


Manufacturer MEIDENSHA
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Excitation Specification

Excitation transformer Excitation screen

Model:

Rated power(kVA) Operation voltage DC220V

High voltage/low
Output voltage 220V
voltage(Kv)
High voltage/low
Output current
voltage(A)
Rate frequency
60HZ Frequency 60HZ
(Hz)

Rated phase Three phases


15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Start-up Conditons
After major and minor maintenance of the transformer, the following conditions should be met before startup:
Work tickets for generator and power distribution unit and auxiliary equipment have been terminated and safety
measures for maintenance have been removed.
The relevant holes have been sealed and the relevant cable covers are intact.
The generator and power distribution unit and auxiliary equipment are clean, tidy and well illuminated.
The generators, power distribution unit and auxiliary equipment, protection, control and automatic devices should
be in good condition.
Check that the excitation system is in good condition.
The protection commissioning and ceasing plate and outlet plate of the generator transformer protection device is in
the normal state.
Voltage transformer, current transformer, switch, isolator and busbar should be clean, in good contact, and secured,
in accordance with the regulations of the power distribution equipment.
The excitation regulator is intact.
The large shaft grounding carbon brush is of a suitable length and in good contact.
The main switch and the field breaker are in the off position, the parameter indications are normal and all are in the
zero position.
Start the turning device to rotate the rotor and check that there is no stuck in the rotating part.
The air cooler is switched on and the fire fighting device is in good condition.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Start-up Conditons
The newly installed unit should be tested as follows when it is first started:
Generator no-load test.
Short circuit characteristic test.
The CT and PT phases for measurement protection are correct.
The stator and rotor insulation resistance should be measured qualified.
The switching on/off test of the generator circuit breaker and the field breaker should be normal.
The linkage test of the generator circuit breaker and the field breaker should be normal.
The action of interlock test of the turbine main valve and electric switch is normal.
Check and verify that the phase and sequence of the generator and system are correct.
Measurement and allowable values of insulation resistance of generator stator circuit and its excitation circuit:
After major maintenance of the generator, the following tests should be performed before starting up:
After all electrical inspections are completed, the insulation resistance should be measured. However, if the outage
time does not exceed 24 hours and the maintenance work is not performed, it may not be measured.
The CT and PT phases for measurement protection are correct.
The stator and rotor insulation resistance should be measured.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Increasing Voltage
(1) The process of boosting the generator should be carried out slowly.
(2) Check the generator three-phase stator current should have no indication;
(3) Check that the three-phase stator voltage of the generator should be balanced;
(4) Check that the insulation of the generator is qualified; no grounding signal appears.
(5) Record the rotor voltage, current and stator voltage of the generator
(6) Check the no-load characteristics of the generator when the generator stator voltage
rises to the rated value;

no-load characteristics of the generator


Rated Excited currrent Excited voltage
voltage(KV) (A) (V)

13.8 444 110


15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Synchronization Conditon
Conditions for quasi-synchronization:
The frequency of the generator is the same as the system frequency; (△f<0.1Hz)
The terminal voltage of the generator is equal to the system voltage; (△U<5%)
The phase and phase sequence of the generator are consistent with the phase and phase sequence
of the system.
Precautions for quasi-synchronization:
non-synchronization or automatic synchronization of the generator is strictly prohibited.
When the pointer of synchronous meter stops at 12 o'clock or the pointer has reached the 12 o'clock
position, paralleling connection is not allowed.
When the pointer of synchronous meter is turning too fast or swinging back and forth at the 12 o'clock
position, paralleling connection is not allowed.
When the pointer of synchronous meter is not stably passing 12 o'clock and there is a beating
phenomenon, paralleling connection is not allowed.
For paralleling connection of the generator, the duty personnel shall be careful and decisive.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Synchronization Procedure

1.1. Push the generator main switch cart to the “working” position.
1.2. Insert the power plug of the handcart.
1.3. Put the switching off fuse of the main switch .
1.4. Put operation fuse of the main switch of the generator.
1.5. Check that the automatic excitation regulator is intact.
1.6. Operation of automatic quasi-synchronous connection to grid:
1.6.1.Switch the grid connection mode to the “automatic” position;
1.6.2. When the circuit breaker has been switched off, increase the generator's reactive
power, check the stator three-phase current is indicated and balanced;
1.6.3. Generallyt the stator coils are allowed to carry 30% of the rated current after they are
connected the grid, and then evenly increase to the rated value within 40 minutes.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Synchronization Procedure

1.7. Manual quasi-synchronous grid connection steps:


1.7.1. Cut the on-screen grid connection mode selection switch to the “manual” position;
1.7.2. The operation panel selects the button of the synchronous circuit breaker;
1.7.3. According to the voltmeter and the synchronization table indication, the operation of
magnetization, demagnetization, speed increase and deceleration is performed;
1.7.4. When the conditions of the same period are met, press the closing button at the appropriate
time;
1.7.5. When the generator breaker has been closed, send the “connected” signal to the turbine to
increase the generator's active and reactive power and check.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Disconnection Operation
1.1. Normal shutdown
The electric duty officer can perform the following operations after receiving the value long
disaggregation or the stop command:
1.1.1. Transfer active and reactive loads to another unit as needed;
1.1.2. Slowly reduce the generator's active and reactive power close to zero;
When the generator three-phase stator current reaches zero, the motor main switch can be
developed;
1.1.3. “Excitation input” is open before pulling down the excitation screen;
1.1.4. Pull open the de-excitation switch;
1.1.5. Send a "decomposed" signal to the turbine;
1.1.6. Deactivate the automatic excitation device;
1.1.7. Pull the generator switch trolley to the "test" position;
1.1.8. Remove the generator switch car closing fuse and unplug the power plug;
1.1.9. Pull out the 1PT and 2PT isolation knives of the motor chamber and remove the PT
primary and secondary high and low voltage fuses;
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Disconnection Operation
1.2. Emergency stop
When the following phenomenon occurs, the duty officer should not wait for the value command,
emergency stop:
1.2.1 The steam engine personnel issued a "machine hazard" signal, while the generator active load
dropped to zero.
1.2.2. There is friction and impact inside the generator, and the vibration suddenly increases by 5 wires
or more than 10 wires.
1.2.3. The generator explodes, smokes, and catches fire.
1.2.4. Generator internal fault, switch and protection refused.
1.2.5. A long time short circuit occurs outside the generator, the stator current points to the maximum,
the voltage drops seriously, and the generator backup protection refuses.
1.2.6. Generator transformer unprotected operation (except for DC system instantaneous grounding
and DC fuse blowing, if contact failure can be immediately restored)
1.2.7. The excitation circuit is grounded at two points and the protection is rejected.
1.2.8. When the demagnetization operation exceeds 15 minutes (with 50% load) and the excitation
cannot be recovered.
1.2.9. Critical situations on the generator transformer that endanger personal safety.
1.2.10. The generator current transformer smokes and ignites.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Disconnection Operation
In the above case, the steps are as follows:
a. Pull development motor main switch;
b. Pull open the de-excitation switch;
c. The de-listed signal is sent to the turbine.
d. If the main switch is rejected, the corresponding main transformer high voltage side and
low voltage side switch should be disconnected immediately.
1.3. After the generator is cranked, work should be done:
1.3.1. That is to measure the stator winding of the generator and the insulation resistance of
all excitation circuits. If the measurement is unqualified, the treatment should be arranged.
1.3.2. Check the excitation circuit of the exciter and the connection points on the excitation
device. If there is heat or melting, you must try to eliminate it.
1.3.3. Check the generator cooling ventilation system and close the cooling water inlet valve.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Generator Disconnection Operation

In the above case, the steps are as follows:


a. Pull development motor main switch;
b. Pull open the de-excitation switch;
c. The de-listed signal is sent to the turbine.
d. If the main switch is rejected, the corresponding main transformer high voltage
side and low voltage side switch should be disconnected immediately.
1.3. After the generator is cranked, work should be done:
1.3.1. That is to measure the stator winding of the generator and the insulation
resistance of all excitation circuits. If the measurement is unqualified, the treatment
should be arranged.
1.3.2. Check the excitation circuit of the exciter and the connection points on the
excitation device. If there is heat or melting, you must try to eliminate it.
1.3.3. Check the generator cooling ventilation system and close the cooling water
inlet valve.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Specification of Transformer
1#、2# Auxiliary & Standy Sea Water Transformer
Name Main Transformer
Transformer
Model SF10-40000/69 SCB10-2500/13.8 SCB10-1000/13.8
Capacity 20000 2500 1000
Voltage(KV) 69±2×2.5%/13.8 13.8/0.46 13.8/0.46
Current(A) 167.3.9/836.7 104.6/3007 46.2/1155
Tapping range ±2×2.5% ±2×2.5% ±2×2.5%
Wiring group Y/△ YNd11 △/Y Dyn11 △/Y Dyn11
Rated frequency 60Hz 60Hz 60Hz
Cooling mode ONAF AN/AF AN/AF
Usage Outdoor Indoor
No-load loss 19.816kW 2.814 kW 1.501kW
No-load current 0.16 0.2% 0.28%
Regulating mode No-load regulation No-load regulation No-load regulation
ABB
Manufacturer Changzhou Pacific Transformer ABB
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Transformer Operation & Maintenance
1.1. Monitor the operation of the transformer on the monitor of the main control room. Each parameter
should be metered once every hour. On the local control panel, the meter should be transcribed
during the inspection. The oil level thermometer (winding temperature of the dry type transformer)
mounted on the transformer body is transcribed when the transformer is patrolled.
1.2. For transformers in operation or hot standby, regular external inspection should be carried out,
inspection cycle:
1.2.1. Perform at least one nightly light-off check every week;
1.2.2. When the climate changes (cold, heat, thunder, heavy rain, strong wind, heavy fog, heavy snow,
etc.) should be checked every two hours, paying special attention to the change of oil surface;
1.2.3. After the gas relay sends a signal;
1.2.4. When the transformer is overloaded or the cooling device is faulty, the number of inspections
should be increased according to the situation;
1.2.5. Newly installed or overhauled transformers should be increased in number of inspections.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Transformer Operation & Maintenance
1.3. The general items of the periodic external inspection of the main transformer are as follows:
1.3.1. Check that the oil level of the oil lining is normal, and there is no gas in the gas relay, which is
full of oil;
1.3.2 The sound of the monitor transformer should be normal, no noise;
1.3.3. Check whether the insulating bushing of the transformer is clean, whether there is crack or
flashing discharge, whether the connection of the connecting end of the bushing is good, and whether
there is overheating;
1.3.4. Is the safety release valve normal?
1.3.5. Check that the moisture absorber should be in good condition and the desiccant should not
absorb moisture to saturation;
1.3.6. Check the fuel tank, radiator, oil valve and other components of the transformer should be free
of oil leakage and oil leakage. The temperature of each part should be uniform, the oil temperature
should be within the allowable value, and the main transformer should also be indicated with the
shaking temperature of the control room. Phase check
1.3.7. Check that the throttles of the radiator, the oil purifier and the gas relay should be in the
passage, and the accident drain should be closed;
1.3.8. Whether the grounding wire of the outer casing is firm and reliable.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Transformer Operation & Maintenance
1.4. The general items of periodic external inspection of dry-type transformers are as follows:
1.4.1. Check whether the body and insulation support of the transformer are clean, with or without cracks
and flash discharges;
1.4.2. Check if the contact of each connection terminal is good and there is no overheating;
1.4.3. The sound of the monitor transformer should be normal, no noise;
1.4.5. The temperature and temperature rise of the transformer are within the allowable range, the fan is
running normally, and there is no vibration. When the temperature is above 100 °C, try to turn the fan;
1.4.6. The grounding wire of each component of the transformer should be firm and reliable, and the casing
should be intact.
1.5. During the inspection, the transformer is found to have the following phenomena. The cause should be
ascertained, and measures should be taken. If necessary, report to the superior leader and record the
inspection in the equipment defect record book and operation log:
1.5.1. Seepage and oil leakage, the oil level of the oil pillow is outside the upper and lower limits;
1.5.2. The sound is not normal;
1.5.3. Temperature or temperature rise does not match the load and ambient temperature (more than
normal);
1.5.4. Fan damage;
1.5.5. The joint is hot or has a discharge phenomenon.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Transformer Operation & Maintenance
1.6. Before the transformer is put into use, it should be carefully inspected and confirmed that the transformer is in
good condition and has electrification conditions. The transformer after the maintenance is put into operation
should have the following conditions:
1.6.1. Recover and terminate the relevant work ticket, remove the short-circuit grounding wire, pull open the
relevant grounding knife, recover the temporary obstruction and the relevant signage, and clean and tidy around
the transformer;
1.6.2. Measure the insulation resistance should be qualified;
1.6.3. Carefully check that the primary and secondary circuits are in compliance with operational requirements.
1.7. Measurement and regulation of insulation resistance of main transformer:
1.7.1. The transformer must measure the insulation resistance before each operation.
1.7.2. In the same level of the shake table, the insulation resistance value converted to the same temperature is
compared with the last measured result, if it is less than 70%, it is considered unqualified. The insulation resistance
value and oil temperature for each measurement shall be recorded.
1.7.3. The transformer winding is measured with a 2500V shaker, and its value must not be less than 1MΩ/1KV.
1.7.4. The insulation resistance of the high and low voltage windings to the ground is measured by the absorption
ratio method. If R60/R15 ≥ 1.3, it is considered qualified.
1.7.5. Transformers with unsatisfactory insulation resistance drop should be identified and approved by the
relevant leaders before they can be put into operation.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Transformer Operation & Maintenance
1.6.Before the transformer is put into operation, carefully inspect and confirm that the transformer is in good
condition and ready to be charged. For the transformer after maintenance, the following conditions should be met
before operation:
1.6.1.Collect and terminate the relevant work tickets, remove the relevant short-circuit grounding wire, pull off the
relevant grounding isolator, recover the temporary obstruction and the relevant signboard, the surrounding of the
transformer should be clean and well organized;
1.6.2.The insulation resistance measured should be qualified;
1.6.3.Carefully check that the primary and secondary circuits should be in compliance with the operation
requirement.
1.7.Measurement of insulation resistance of the main transformer and regulations:
1.7.1.The insulation resistance of transformer should be measured before each operation.
1.7.2.For measurement by megameter with same grade, compare the insulation resistance value converted under
the same temperature with the previous result measured, , if it is less than 70%, it is considered unqualified. The
insulation resistance value and oil temperature measured should be recorded every time.
1.7.3.The transformer winding is measured with a 2500V megameter and measurement should not be less than
1MΩ/1KV.
1.7.4.The insulation resistance of the high and low voltage windings to the ground should be measured by the
mothod of absorption ratio. If R60/R15 ≥ 1.3, it is considered qualified.
1.7.5.The cause of unqualified transformer with insulation resistance declining should be identified and it can be
put into operation only approved by relevant leader.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Transformer Operation & Maintenance
1.8.Measurement of insulation resistance of dry transformer and regulations:
1.8.1.The insulation resistance of transformer should be measured before each operation.
1.8.2.For transformer winding of which the voltage level is below 500V, measure with a 500V megameter, for voltage level above
500V, measure with a 2500V megameter. The insulation resistance value required in dry cricumstance: high voltage to low voltage
and ground ≥ 300MΩ , low pressure to ground ≥100MΩ .
1.8.3.The insulation resistance of the transformer will decline in moisture circumstance: generally, that the insulation resistance for
every 1KV is not less than 2MΩ (1min , 25 °C reading) can satisfy the operational requirements. However, if the transformer is
exposed to abnormal moisture and condensation occurs, it should be dried before being put into operation regardless of its
insulation resistance.
1.8.4.Transformers with unqualified insulation resistance should be identified the cause and approved by the relevant leaders
before put into operation.
1.9.Auxilairy transformer allows short-time loop closing operation during switching operations.
1.10.During operation of the main transformer, unless there is special reason, the heavy gas protection should be put into trip, and
the light standby protection of the transformer in the cold standby state should still be put into signal to monitor the oil level. During
operation of the transformer heavy gas protection, the switching to signal should be agreed with the specialty personnel of relay
protection and approved by the chief engineer.
1.11.When filling the transformer in operation, the heavy gas protection should be switched to signal.
1.12.When the oil level indicated on the oil level gauge is abnormally elevated, open each venting or draining plug and valve to
identify the cause. It is necessary to. When checking the moisture absorber or performing other work, the heavy gas should be
switched to signal before it starts working to prevent the gas protection from malfunctioning tripping. After the work is completed,
check that the gas relay is normal and re-switch the heavy gas to trip.
1.13.During the earthquake forecast, or there is strong vibration nearby, (such as foundation piling of the house), the “ heavy gas
action ” protection should be switched to “ signal ”.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Plant Power Supply System
1.1.Auxiliary Power includes two voltage levels: 13.8KV and 460V.
1.2.Auxiliary power 13.8KV is single segment; auxiliary power 460V consists of two segments by the corresponding change of the main ,
auxiliary transformer, the transformer and the standby transformer of water.
1.3.The automatic switching device of the auxiliary standby power supply should be in good condition. After each maintenance, the
linkage test should be conduted accordingly.
1.4.When the low-voltage standby transformer works on a low-voltage bus-bar, the automatic switching device of the other low-voltage
bus-bars should be withdrawn.
1.5.Two auxiliary transformers in the same system are not allowed to be in parallel operation for long period of time regardless of whether
there is circulating current or scale of circulating current, they are only allowed to be in close loop operation for short-term during switching
operation.
1.6.After major maintenance, the phase of the transformer may change. During power transmission, the sequence and phase should be
verified on the low voltage side.
1.7.Close loop switching can be adopted to change the power supply mode of the auxiliary busbar, Before the switching operation, it is
necessary to check whether the working power supply and the standby power supply are operating in the same system, asynchronous
paralleling through auxiliary busbar of two systems should be strictly prevented.
1.8.The power for auxiliary worshop panel and standby power supply is generally not supplied by the same busbar. The switching should
not be in paralleling operation for a long period of time except it is necessary for operation.
1.9.Since the switching for some of the auxiliary workshops panels is mechanical blocking type, the panel will suffer power loss for a short
period of time when switching. Therefore, it should be prudent when switching the power supplies, take various measures to ensure that it
will not affect the production.
1.10.Connection of temporary power supply for maintenance from 460V auxiliary busbar and workshop panel of the operating unit is not
allowed, the temporary power supply for maintenance should be from the maintenance workshop panel.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Plant Power Supply System
Operation Regulation
2.1.13.8KV auxiliary busbar insulation resistance should not be lower than 20MΩ (2500V megameter), 0.4KV busbar
insulation resistance should not be lower than 0.5MΩ (500V megameter).
2.2.The auxiliary load current should be three-phase equilibrium as far as possible. The neutral point current flowing
through each auxiliary transformer should not exceed 25% of the rated current of the low-voltage side, and the current of
the largest phase should not exceed the rated value.
2.3.Auxiliary power systems protection regulations:
2.3.1.The protection device of the auxiliary transformer should be put into use correctly under the conditions of operation
or hot standby. In case of abnormality, switching on and off the auxiliary transformer protection device should be instructed
by chief engineer.
2.3.2.The capacity of fuse for the auxiliary system shall meet the technical requirements, do not arbitrarily enlarge or
replace it with unqualified materials. If the fuses are continuously blown, identify the cause in time and report to the duty
head.
2.4.In the event of emergency, the auxiliary transformer is allowed to be overloaded and controlled according to the
“Transformer Regulations”, however the inspection and monitoring of the overloaded auxiliary should be strengthened.
2.5.The voltage of all busbars for the auxiliary power should be kept within ±10% of the rated voltage. In special cases
such as low voltage and difficulty in starting up the motor, the secondary load can be allowed to be removed to ensure the
startup of important auxiliary equipment.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Specification of Motor
Rated Rated insul
High voltage Rated power Qty
Model voltage current ation Phase
motor (KW) (set)
(KV) (A) grade
feed water
280 460 484 2 3
pump
Induced draft
185 460 320 2 3
fan
Primary fan 110 460 320 2 3

Secondary fan 280 460 190 2 3


15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Specification of Motor
Rated power Rated voltage Rated current Qty Insulation
Low voltage motor Model Phase
(KW) (KV) (A) (set) grade

Condensate pump 45 460 78 2 3


AC lube oil pump 18.5 460 32 1 3
Control oil pump 7.5 460 13 1 3
single
DC lube oil pump 5.5 DC220V 30.3 1
phase
Drain pump 11 460 19 2 3

oil feeder pump 4 460 7 2 3


Rubber ball
4 460 2 3
cleaning pump
Condensate pump 220 460 380 2 3
Reverse washing
15 460V 26 1 3
pump
DM water pump 22 460V 39 2 3
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Specification of Motor
Low voltage Rated Power Rated voltage Rated current Insulatio
Model Qty(set) Phase
motor (KW) (KV) (A) n grade
Circulating
185 460V 320 2 3
pump
Bridge crane 22 460 3
EDI water pump 7.5 460V 12 2 3
Primary high
132 460 229 2 3
pressure pump
Secondary high
37 460V 125 2 3
pressure pump
Ventilator 460 3
Air compressor 90 460 155 2 3
Raw water pump 15 460V 25 2 3
Grab crane 460V 3
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Motor Operation & Maintenance
1.1.After maintenance of the motor, inspection should be proceeded as follows:
1.1.1.Collect all maintenance work tickets, remove temporary safety measures, restore fixed safety facilities;
1.1.2.The insulation resistance of the motor is measured qualified;
1.1.3.Check that the primary and secondary equipment such as switches, cables & joints, control and protection circuit meters of
the motor, should be in good condition and equipped with startup condition required;
1.1.4.The motor casing grounding wire and the safety cover of the coupling are firmly installed, and the revolving direction of the
mechanical part of the motor is indicative;
1.1.5.The motor incoming lines are well connected and the junction box is firmly installed;
1.1.6.Report to the duty head, then power transmission can be proceeded upon the receipt of permission.
1.2.The motor should be checked before startup:
1.2.1.The motor is clean, free from debris and no personnel working;
1.2.2.Turn the rotor to verify that the stator and rotor are not rubbed with each other, and that the mechanical part is not stuck;
1.2.3.Check the motor with the sliding bearing that the oil level should be normal oil level and there is no dirty object in the bearing;
1.2.4.For the winding motor, check whether the carbon brush on the slip ring is good contact and the startup position is correct;
1.2.5.For slip motor, check that all parts of the electromagnetic clutch are in good condition and the adjustment device is in good
condition;
1.2.6.When starting up, check whether the motor is normally started up according to the indication of the ammeter, and check if
the revolving direction is correct.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

IV. OPERATION & MAINTENANCE OF ELECTRIC EQUIPMENT


Motor Operation & Maintenance
1.3.Motor inspection content during normal operation:
5.1.1.The sound is normal, the displacement and vibration are in accordance the requirements;
5.1.2.No abnormal sound and smell;
5.1.3.The core bearing temperature is normal;
5.1.4.The three-phase current is balanced, if necessary, measure with a clip-type ammeter;
5.1.5.The mechanical equipment are in good condition and works normally;
5.1.6.The components of the startup circuit are in good condition and work normally;
5.1.7.The casing is well grounded, the anchor screws are fastened, and the protective cover is intact;
5.1.8.The equipment is clean and free of foreign matters.
15MW DMCI Masbate Thermal Power Plant (DMTPP)
Mobo, Masbate Philippines

End of Presentation

You might also like