Bill of Quantity
Project date: 17/07/2023
Location
PRICE BREAKDOWN
Price Total Price
No. Item Descriptions Unit Vol. Material Man Power Unit Total Remarks
(Rp) (Rp) (Rp) (Rp)
A INDIRECT COST
1 Preparation works lot 1,00 5.000.000 5.000.000
2 Transportation lot 1,00 15.000.000 15.000.000
3 Tools & equipment lot 1,00 15.000.000 15.000.000
4 Safety & protection lot 1,00 6.000.000 6.000.000
5 Site expence lot 1,00 25.000.000 25.000.000
SUB TOTAL A - 66.000.000
B DIRECT COST
1 Earth works
- Excavation m3 671,58 Exclude
- Disposal m3 182,00 Exclude
- Back fill m3 489,58 Exclude
- Compaction m3 489,58 Exclude
- Finishing road ex. excavation m2 42,00 Exclude
2 Stone masonry m3 182,00 720.000 420.000 1.140.000 207.480.000
3 Concrete base / pedestal m3 5,71 Exclude
- Re-bar D10 & D13 @ 150 kg 701,60
- Form works m2 21,12
- Concrete K-300 m3 5,71
4 Steel bridge fabrication kg 12488,50 33.000 - 33.000 412.120.500
- WF. 500x200x10x16 kg 8600,00
- CNP. 150x65x20x3,2 kg 225,50
- CNP. 100x50x20x3,2 kg 3663,00
- Anchor dia. 1" pcs 32,00
5 Hand rail fabrication kg 640,78 40.200 - 40.200 25.759.356
- Flat bar, 65x12 kg 183,70
- Flat bar, 100x6 kg 226,08
- Round bar dia. 25 kg 231,00
- Bolt, nut, & washer set 36,00
6 Painting kg 13129,28 4.200 - 4.200 55.142.976
7 Loading Undloading Bridge 4 Segmen kg 13129,28 7.200 - 7.200 94.530.816
8 Structural Steelwork Bridge Test for EHS
set 4,00 2.072.000 1.250.000 3.322.000 13.288.000
SUB TOTAL B 795.033.648
Bill of Quantity
Project date: 17/07/2023
Location
PRICE BREAKDOWN
Price Total Price
No. Item Descriptions Unit Vol. Material Man Power Unit Total Remarks
(Rp) (Rp) (Rp) (Rp)
TOTAL AMOUNT (A + B) 861.033.648