FORM STRIPPING REQUEST
EEI CORPORATION
Construction Division
Control No. : Date :
Contract Package : Level :
Reference Concrete Pouring Request No. : Casting Time : From hrs to hrs
Casting Dates : Location :
- Proceed to Form Stripping Remarks:
- Do not Proceed to Form Stripping
Checked and Verified
Trade / Discipline REMARKS
EEI Corporation DATE CLIENT DATE
- Civil / Structural
Notes:
1) As per Section 03300 Div. [Link], (Structural Plans), stripping of forms are as follows:
Walls, columns, sides of beams, Girders and SOG ----------------------------- 1 day
Pan joist forms (Side only):
30 inches wide or less ----------------------------------------------------------------- 3 days
Over 30 inches wide -------------------------------------------------------------------- 4 days
Joists, Beams or Girders soffit
clear span between structural supports
Under 10 feet ------------------------------------------------------------------------------ 7 days
10 to 20 feet --------------------------------------------------------------------------------14 days
Over 20 feet -------------------------------------------------------------------------------- 21 days
One way floor slabs:
Under 10 feet ------------------------------------------------------------------------------ 4 days
10 to 20 feet --------------------------------------------------------------------------------7days
Over 20 feet -------------------------------------------------------------------------------- 10 days
2) Forms may be removed earlier that specified if ASTM C39 test result of field cured samples from a representative portion
of the structure indicate that the concrete has reached a certain design strength capable of supporting the induced
construction loads. Earliest will be after 4 days where concrete is expected to reach 60% of the design strength and there
exist adequate permanent undisturbed shorings.
Requested by: EEI CORPORATION
QC Engineer: Construction Manager:
Sign over printed name Sign over printed name
Date: Date:
Approved by: CEBU LANDMASTERS INC.
Site Engineer: Construction Manager:
Sign over printed name Sign over printed name
Date : Date :
QC Form 041 Rev. 0