0% found this document useful (0 votes)
102 views1 page

Concrete Form Stripping Guidelines

This form requests approval to strip forms from a concrete pour. It provides details of the contract package, reference concrete pouring request, casting dates and location. Notes specify stripping times per structural element according to standards, and that forms can be removed earlier if test results show concrete has reached 60% design strength and adequate shoring exists. EEI Corporation requests approval for form stripping, with spaces for signatures from QC Engineer, Construction Manager, Site Engineer and Construction Manager of Cebu Landmasters Inc. to approve.

Uploaded by

Edward Tamayo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
102 views1 page

Concrete Form Stripping Guidelines

This form requests approval to strip forms from a concrete pour. It provides details of the contract package, reference concrete pouring request, casting dates and location. Notes specify stripping times per structural element according to standards, and that forms can be removed earlier if test results show concrete has reached 60% design strength and adequate shoring exists. EEI Corporation requests approval for form stripping, with spaces for signatures from QC Engineer, Construction Manager, Site Engineer and Construction Manager of Cebu Landmasters Inc. to approve.

Uploaded by

Edward Tamayo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

FORM STRIPPING REQUEST

EEI CORPORATION
Construction Division

Control No. : Date :

Contract Package : Level :

Reference Concrete Pouring Request No. : Casting Time : From hrs to hrs

Casting Dates : Location :

- Proceed to Form Stripping Remarks:

- Do not Proceed to Form Stripping

Checked and Verified


Trade / Discipline REMARKS
EEI Corporation DATE CLIENT DATE

- Civil / Structural

Notes:
1) As per Section 03300 Div. [Link], (Structural Plans), stripping of forms are as follows:
Walls, columns, sides of beams, Girders and SOG ----------------------------- 1 day
Pan joist forms (Side only):
30 inches wide or less ----------------------------------------------------------------- 3 days
Over 30 inches wide -------------------------------------------------------------------- 4 days
Joists, Beams or Girders soffit
clear span between structural supports
Under 10 feet ------------------------------------------------------------------------------ 7 days
10 to 20 feet --------------------------------------------------------------------------------14 days
Over 20 feet -------------------------------------------------------------------------------- 21 days
One way floor slabs:
Under 10 feet ------------------------------------------------------------------------------ 4 days
10 to 20 feet --------------------------------------------------------------------------------7days
Over 20 feet -------------------------------------------------------------------------------- 10 days
2) Forms may be removed earlier that specified if ASTM C39 test result of field cured samples from a representative portion
of the structure indicate that the concrete has reached a certain design strength capable of supporting the induced
construction loads. Earliest will be after 4 days where concrete is expected to reach 60% of the design strength and there
exist adequate permanent undisturbed shorings.

Requested by: EEI CORPORATION

QC Engineer: Construction Manager:

Sign over printed name Sign over printed name

Date: Date:

Approved by: CEBU LANDMASTERS INC.

Site Engineer: Construction Manager:

Sign over printed name Sign over printed name

Date : Date :