Name of Scheme CONS OF CHATAL WITH SOAK PIT
Location of Scheme Sansad Name
WEST BENGAL PWD SCHEDULE OF RATES VOLUME -II : SANITARY & PLUMBING WORKS [With effect from 01.11.2017]
VOLUME -I : BUILDING WORKS [With effect from 01.11.2017]
Sl Description of Items Quantity Unit Rate Amount
no
Nos. L W H
1 Page 1 & Item 2/a
Earth work in excavation of foundation trenches or drains, in all sorts of soil including
mixed soil but excluding laterite or sandstone) including removing, spreading or stacking
the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides
of trenches, levelling, dressing and ramming the
bottom, bailing out water as required complete.
a) Depth of excavation not exceeding 1,500 mm.
Soakpit = 3.14 X 0.50 X 0.50 X 1.50 = 1.18 m3
(πr2h)
Total = 1.18 m3 1.18 m3 119.27 Rs. 140.44
3 Page 226, Item- 1/a
Brick soling with picked jhama bricks including preparation of bed as necessary with
brick joints properly filled in and packed with powdered earth and including necessary
cushion of similar material below the soling (and in between layers when more than one
layer is used) completes as per direction
(a) Single brick flat soling (thickness 75 mm.)
Soakpit = 3.14 X 0.50 X 0.50 = 0.79 m2
Total = 0.79 m2 0.79 m2 339.00 Rs. 266.12
4 Page 26, Item-10
Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size)
excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes.
a) Pakur Variety
Soakpit = 3.14 X 0.50 X 0.50 X 0.075 = 0.059 m3
(πr2h)
= 3.14 X 0.50 X 0.50 X 0.075 = 0.059 m3
Total = 0.118 m3 0.12 m3 6194.92 Rs. 729.45
6 Page 16 & Item-16
125 mm. thick brick work with 1st class bricks in cement mortar (1:4) in ground floor.
(Honey Comb Brick work)
Fourmula = 2πrh + 2πRh + 2(πR2– πr2)
= 2x3.14x0.75x1.5+2x3.14x1x1.5+2(3.14x1x1-3.14x0.75x0.75)
=7.065+9.42+4.31
= 20.79m2
Area = = 20.79 m2 10.40 m2 724.00 Rs. 7,529.60
10 Page 299 & Item 3/b
Jhama metal (kiln burnt) 50mm. To 65mm.
Volume = Lump sum = 1.00 m3 1.00 m3 1667.00 Rs. 1,667.00
Total Rs. 10,332.61
Adding CGST 6% Rs. 619.96
Adding SGST 6% Rs. 619.96
Cost of civil works excluding labour welfare cess Rs. 11,572.52
Labour welfare cess 1% Rs. 115.73
Cost of civil works including labour welfare cess Rs. 11,688.25
Say Rs. 11,689.00
file:///conversion/tmp/activity_task_scratch/689137541.xlsx Page 1 of 2
RATE ANALYSIS OF CEMENT CONCRETE ITEMS
Railway Yards Barasat
Type of Concrete Ordinary Cement Conctre (Mix 1:1.5:3)
Zone Kolkata / 24 Pgs (N & S)
District /Area
North of
24Kalyani
Pgs. Sub Div
Work Site Haroa Block
Distance from respective Railway yard to work site = 40.00 Km
SL No. Description Volume (Cum.) Rate (Rs.) Amount
(Rs.)
1 Ordinary Cement Concrete (Mix 1:1.5:3) 4482.00
2 Pakur
Rates of Variety
Pakur[Page-15, 7(i)] aggregate at Barasat
variety stone
Railway Yards [Table:T-1,P-313] 20mm Nominal Size 0.573 1520.00 870.96
10mm Nominal Size 0.287 1353.00 388.31
Corse Aggregate 0.86
3 Road carriage from Barasat Railway Yard to Work Site
=i) Carrage
30.00 Km [Table:
Up to T-2]= @ Rs.124.00
5.00 Km 124.00
ii) Carrage Above 5.00 Km upto 10.00 Km = 5 Km @ Rs.10.90/Km 54.50
iii) Carrage Above 10.00 Km upto 20.00 Km = 10 Km @ Rs.10.10/Km 101.00
iv) Carrage Above 20.00 Km upto 30.00 Km = 20.00 Km @ Rs.9.50/Km 190.00
469.50
20mm Nominal Size 0.573 469.50 269.02
10mm Nominal Size 0.287 469.50 134.75
4 Loading and unloading [Table: T-3]
20mm Nominal Size 0.573 58.00 33.23
10mm Nominal Size 0.287 58.00 16.65
Total Cost at site per Cum. 6194.92