STS - (2500K, 6000K) Smart Transformer Station User Manual
STS - (2500K, 6000K) Smart Transformer Station User Manual
User Manual
Issue 01
Date 2019-06-20
and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.
Notice
The purchased products, services and features are stipulated by the contract made between Huawei and
the customer. All or part of the products, services and features described in this document may not be
within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements,
information, and recommendations in this document are provided "AS IS" without warranties, guarantees or
representations of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.
Website: http://e.huawei.com
Overview
This document describes the STS-2500K and STS-6000K smart transformer station
(transformer station for short) in terms of its installation, electrical connections,
commissioning, maintenance, and troubleshooting. Before installing and operating the
transformer station, read through this document, get familiar with the features, functions, and
safety precautions provided in this document.
Figures used in this document are for reference only.
Intended Audience
This document is intended for photovoltaic (PV) plant operating personnel and qualified
electricians.
Symbol Conventions
The symbols that may be found in this document are defined as follows.
Symbol Remarks
Indicates an imminently hazardous situation which, if not avoided,
will result in death or serious injury.
Indicates a potentially hazardous situation which, if not avoided,
could result in death or serious injury
Indicates a potentially hazardous situation which, if not avoided,
may result in minor or moderate injury.
Indicates a potentially hazardous situation which, if not avoided,
could result in equipment damage, data loss, performance
deterioration, or unanticipated results.
NOTICE is used to address practices not related to personal injury.
Calls attention to important information, best practices and tips.
NOTE is used to address information not related to personal injury,
equipment damage, and environment deterioration.
Change History
Changes between document issues are cumulative. The latest document issue contains all the
changes made in earlier issues.
Issue 01 (2019-06-20)
Updated 5.7 Connecting Cables for the Distributed Power System.
Updated 8.2 Remote Control.
Contents
9 System Maintenance................................................................................................................... 59
9.1 Shutdown and Power-Off ........................................................................................................................................... 59
9.2 Routine Maintenance .................................................................................................................................................. 59
9.3 Troubleshooting .......................................................................................................................................................... 62
9.4 Component Replacement ............................................................................................................................................ 68
9.4.1 Replacing the Heat Exchanger ................................................................................................................................. 68
9.4.2 Replacing the Measurement and Control Device..................................................................................................... 68
9.4.3 Replacing the Power Meter...................................................................................................................................... 69
9.4.4 Replacing the Temperature and Humidity Controller .............................................................................................. 69
9.4.5 Replacing the MCB ................................................................................................................................................. 69
9.4.6 Replacing the Light .................................................................................................................................................. 70
9.4.7 Replacing the Smoke Sensor ................................................................................................................................... 70
9.4.8 Replacing the Fuse of the Fuse-Switch-Disconnector ............................................................................................. 70
1 Safety Precautions
Before performing operations, read through this manual and follow all the precautions to
prevent accidents. The "DANGER", "WARNING", "CAUTION" and "NOTICE"
statements in this document do not represent all the safety instructions. They are only
supplements to the safety instructions.
Only certified personnel are allowed to install, connect cables for, commission, maintain,
and troubleshoot the product, and they must understand basic safety precautions to avoid
hazards.
When operating Huawei products and devices, in addition to following the general
precautions in this document, follow the specific safety instructions given by Huawei. Huawei
will not be liable for any consequence caused by the violation of the safety operation
regulations and design, production, and usage standards.
Disclaimer
Huawei shall not be liable for any consequence caused by any of the following events:
Damage during transportation.
Storage conditions that do not meet the requirements specified in this document.
Incorrect storage, installation, or use.
Installation or use by unqualified personnel.
Failure to obey the operation instructions and safety precautions in this document.
Operation in extreme environments which are not covered in this document.
Operation of the product beyond specified parameter ranges.
Unauthorized modifications to the product or software code or removal of the product.
Device damage due to force majeure (such as lightning, earthquakes, fire, and storms).
Warranty expiration without extension of the warranty service.
Installation or use in environments which are not specified in related international
standards.
Personnel Requirements
Only certified electricians are allowed to install, connect cables for, commission, maintain,
troubleshoot, and replace the transformer station. Operators need to meet the following
requirements.
Have basic knowledge of safe operation, be trained to master correct operation methods,
and have appropriate job qualifications.
Read through this manual and master related safety precautions.
Be familiar with related safety regulations on electrical systems.
Understand the components and functioning of a grid-tied PV power system and relevant
local standards.
Wear proper personal protective equipment (PPE) all the time.
When operating or maintaining the transformer station, wear insulation gloves, safety
clothing, safety helmet, and safety shoes. When commissioning the ring main unit,
operate the general protection room using an insulating stool.
Protecting Labels
Do not scrawl, damage, or block any warning label on the transformer station.
Do not scrawl, damage, or block any nameplate on the transformer station.
System Installation
When heavy objects are being hoisted, do not walk below the cantilever or the objects.
No flammable or explosive materials should exist in and around the equipment.
The equipment must be built far away from the living quarters. If required, take
soundproofing measures.
The transformer station is installed in environments with good ventilation to ensure
system performance.
Ensure that the transformer station is not connected to a power supply and is not
powered on before starting installation.
When hoisting a container, do not drag steel ropes or hoisting tools on the top of the
container and do not bump the container against hard objects.
If there is a probability of personal injury or equipment damage during installation,
immediately stop operations on the transformer station, report the case to the project
owner, and take feasible protective measures.
Do not install, use, or operate the transformer station outdoors (including but not limited
to transporting and installing the transformer station, and connecting cables) under bad
weather conditions such as thunderstorms, raining, snowing, and strong winds.
Before installing, operating, or maintaining the transformer station, remove any
conductive objects such as watches or metal jewelry like bracelets, rings, and necklace.
Measure the contact point voltage with a multimeter before handling a conductor surface
or terminal. Ensure that there is no risk of electric shock.
After installing the transformer station, remove idle packing materials such as cartons,
foam, plastics, and cable ties from the equipment area.
Repaint any paint scratches caused during container transportation or installation in a
timely manner. A container with scratches cannot be directly exposed in outdoor
environment for a long period of time.
Do not install other equipment on the top of a container without evaluation of Huawei
personnel.
Do not perform operations such as arc welding, drilling, and cutting on the top of a
container. Otherwise, the top of the container may be damaged, which may cause water
leakage. When performing operations (such as hoisting) over the top of a container, take
measures to protect the top of the container against damage. After construction, check
the container for protective paint damage. If the top of the container is damaged, repair it
in a timely manner.
Electrical Connections
Before electrical connections, ensure that the transformer station and electrical equipment
inside it are intact and hazard-free. Otherwise, electrical shock or fire may be triggered after
power-on.
For the transformer station that requires grounding, install the permanent PE cable before
installing the transformer station. When uninstalling the transformer station, remove the
PE cable at last.
Ensure that all electrical connections comply with local electrical standards.
Obtain approval from the local electric utility before connecting the transformer station
to the grid.
Ensure that the cables to the solar power system are properly connected and insulated,
and meet specifications.
Before making electrical connections, switch off the disconnector on the upstream device
to cut the power supply if people may contact energized components.
Before connecting cables to loads (electrical equipment), ensure that the input voltage is
within the rated voltage range.
When routing cables, ensure that a sufficient distance exists between the cables and heat
emitting equipment to prevent damage to the insulation layers of cables.
Route and bind signal cables and strong-current cables or high-voltage cables separately.
Ensure that the cables you prepare meet local cable regulations.
Operation
The power system is powered by high-voltage power sources. Direct or indirect contact
(through damp objects) with high-voltage power sources may result in electric shocks.
Non-standard and improper operations may result in fire or electric shocks. Perform
operations in strict accordance with the safety precautions specified in this document.
Only professionals are allowed to set initialization parameters during the first power-on
of the transformer station. Incorrect settings may affect the transformer station operation
and cause it to conflict with the local certification.
Comply with local laws and regulations when operating the transformer station.
Before connecting the power supply, ensure that electrical connections are correct.
When the transformer station is running, ensure that the heat exchanger and air vent of
the device are not blocked to prevent high temperature alarms and fire from damaging
the transformer station.
When the STS is powered on for the first time, the initial password, provided in the
component documentation, is used by default. Change the password immediately after
login. To ensure account security, change the password periodically and keep the new
password in mind. Not changing the initial password may cause password disclosure. A
password left unchanged for a long period of time may be stolen or cracked. If a
password is lost, it cannot be restored to the default password. Therefore, the device
cannot be accessed and needs to be returned for troubleshooting. In these cases, the user
is liable for any loss caused to the PV plant.
Wait for at least 10 minutes after the device stops running. Ensure that the voltage drops
below the safe voltage range, the conversion switches are in the local position, the ground
switch of cabinet V of the ring main unit is switched on, and that the low-voltage cabinet
is grounded before maintenance or repair.
Before maintaining the transformer station, power off the switch at the high-voltage side
and the air circuit breaker at low-voltage side. Attach warning labels to ensure that the
transformer station will not be powered on by accident.
Place temporary warning labels or erect fences to prevent unauthorized access to the
maintenance site.
Rectify the faults that compromise the safety performance of the transformer station
before restarting it.
Maintain the transformer station after you get familiar with this document and prepare
the tools and testing equipment.
If the transformer station has multiple power inputs, disconnect all the inputs before
operating it.
Before replacing the transformer station, ensure that it has been powered off.
2 Overview
Features
Smart
Detects the operating status of the ring main unit, transformer, and low-voltage cabinet in
real time.
Detects power parameters online, with the current and voltage detection accuracy up to
0.5.
Supports the remote control of the general circuit breaker for the low-voltage cabinet and
ring main unit as well as the remote query of the running information about the
transformer station.
Simple
Internal equipment has been prefabricated and installed.
Compact 20-feet container structure that facilitates transportation and installation.
Reliable
Solid and reliable structure design
IP rating of medium-voltage/low-voltage rooms: IP54
Fast deployment
Fast deployment can be implemented.
Only low-voltage cables need to be routed in and medium-voltage cables need to be
routed out onsite.
Network Application
The transformer station applies to the grid-tied systems in large PV plants. Typically, a
grid-tied PV system consists of the PV string, SUN2000, AC combiner box/switch box, and
the transformer station.
2.2 Appearance
2.2.1 STS-2500K Appearance
Appearance
system (MV)
(E) Installation position for the smart array controller
Layout
Bottom View
Interior
Layout
(1) Low-voltage room double door (2) Low-voltage (3) Low-voltage room
cabinet B single door
(4) Transformer double-swing (5) Transformer (6) Ring main unit
screen door
(7) Medium-voltage room double (8) Auxiliary (9) Low-voltage cabinet A
door transformer
Bottom View
(A) AC input power cable hole (B) AC input power cable hole (low-voltage
(low-voltage cabinet A) cabinet B)
(C) Trench entry (D) Pressure relief channel and cable hole
(ring main unit)
Interior
Figure 2-10 Front view of low-voltage cabinets (with the door closed)
PV string Description
Component Description
PV string A PV string is composed of PV modules connected
in series.
SUN2000 inverter Model: SUN2000-90KTL-H1 (≤ 60 PCS),
SUN2000-100KTL-H1 (≤ 60 PCS), or
SUN2000-105KTL-H1 (≤ 56 PCS, no more than 28
PCS in one cabinet)
AC combiner box/Switch box Model: ACBox-2/1-D-S or ACBox-2/1-D-C
Transformer station Model: STS-6000K
Smart array controller Model: SmartACU2000B-D-2PID/2PLC or
SmartACU2000B-D-2PLC
SmartLogger software version: SmartLogger
V200R002C20SPC116 or later
Transportation Requirements
Select proper transportation tools according to the dimensions and weight of the product.
The product should be placed horizontally during transportation.
Prevent the product from colliding or scratching.
Road transportation requirements: Lane width ≥ 3 m; a maximum slope of 1:10. The
shortest distance of the parking visual line is 25 m. The minimum headroom is 4.5 m.
The subgrade is solid and the road surface is flat.
Railway transportation requirements: Meets the freight requirements for standard gauge,
narrow gauge, and wide gauge technical specifications.
Waterway transportation requirements: Meets the requirements of full-load voyage.
Air transportation requirements: The container can be hoisted and transported by
helicopter. The hoisting weight of the helicopter must be greater than 35 tons.
Storage Requirements
Close the container door.
The ambient temperature and humidity are suitable for the storage.
The equipment should be stored in a clean and dry place and be protected from dust and
water vapor corrosion.
Service Scope
The following services and operations are not included in the product delivery scope:
Transport the equipment to the construction site (the contract prevails).
Prepare a crane for unloading the product at the construction site.
Prepare the concrete foundation for installing the equipment.
Install the optional oil tray (including the grounding of the oil tray).
Conduct all installation and connection work at the construction site.
Prepare door locks.
Prepare some auxiliary materials that are used for securing the support feet of the
equipment to the foundation.
Test the system protection.
Check the grounding.
4 Equipment Installation
----End
Checking Appearance
Before installing the equipment, check the container for damage, such as holes and cracks,
and check the equipment model. If the appearance is abnormal or the equipment model is
incorrect, contact your dealer.
Checking Accessories
Check whether the deliverables are complete, whether any screw is loose, and whether there
is any obvious external damage. If any component is missing, any screw is loose, or any
damage is found, contact your supplier.
For details about the supplied number of accessories, see the packing list in the packing case.
Type Tool
Keep the equipment far away from dust, oil smoke, harmful gas, and corrosive,
flammable, or explosive objects.
Keep the equipment at least 500 m away from airports, landfills, river banks, seacoasts,
and dams.
Ensure the equipment is free from obstacles within 10 m.
Keep the equipment at least 50 m away from residential areas to avoid noise pollution
Temperature: –25°C to +60°C. If the ambient temperature exceeds 55°C, install the
equipment in a sheltered place or install an awning over it. Ensure that the sheltering is
reliable.
Foundation Requirements
Before installing the equipment, build a concrete platform and trenches on the selected ground.
The foundation construction requirements are as follows:
The dimensions of the foundation meet the installation and load-bearing requirements of
the container.
The average foundation strength must exceed 100 kg/cm2.
The horizontal deviation between the foundation and the contact surface of the container
is less than 5 mm.
Bury the ground grid and reserve a ground copper bar at the ground position of the
container. The ground copper bar should be a hot-dip galvanized flat steel with a
cross-sectional area of 60 mm x 5 mm. Connect one end to the pre-installed ground grid,
and the other end to the ground point of the container. When a ground grid is buried, the
ground lug must be long enough to connect to the ground point of the container.
The ground resistance for the container is within 0.1 ohm.
Route the cables of the transformer station from the bottom. The cables should be
pre-installed below the low-voltage and the medium-voltage rooms.
The inner diameter of the protective tube should not be less than 1.5 times the outer
diameter of the power cable (including the protective layer).
The foundation construction should meet the drainage requirements for the local
historical maximum rainfall. Dispose of drainage water in accordance with local laws
and regulations.
It is installed in the trench right under the transformer to ensure that the foundation
dimensions meet the requirements for installing the oil tray and that the top of the oil tray
can be attached to the bottom of the container.
Construct a foundation of the correct dimensions based on the site design drawing. This figure is for
reference only.
Check Items
No. Check Item Acceptance Criteria
1 Platform space Scenario in which the distance between the platform and
the ground is less than or equal to 0.2 m: The distance
between the container and the platform is 0.1 m to 0.2 m.
Scenario in which the distance between the platform and
the ground is 0.2 m to 0.5 m: The distance between the
container and the platform is greater than or equal to 0.8 m.
Scenario in which the distance between the platform and
the ground is greater than 0.5 m: The distance between the
container and the platform is greater than or equal to 1.3 m.
2 Cabling space If there is no maintenance space at the bottom, it is
at the bottom recommended that the cabling space at the bottom of the
If an oil tray is configured, ensure that the oil tray has been installed.
Before hoisting, ensure that the crane and hoisting belts meet the load-bearing
requirements.
When installing or removing the equipment to be hoisted, do not drag it on the container to
prevent the container from being scratched.
Hoisting Precautions
Stage Precautions
Before hoisting Ensure that the crane can hoist a load greater than 50 tons, and the
working radius is within 10 m. If the onsite environment does not
Stage Precautions
meet the required working conditions, ask professionals to assess the
conditions.
The weather condition is good without wind when the container
needs to be hoisted outdoors.
Ensure that the crane and steel hoisting ropes provide the required
bearing capacity before the hoisting.
All doors of the container are closed and locked.
Ensure that the steel ropes are securely connected.
It is recommended that containers be hoisted from left to right or
from right to left to ensure smooth hoisting.
During hoisting Do not allow any unauthorized people to enter the hazardous areas
and never stand under the crane arm.
Ensure that the crane is properly located and avoid long-distance
hoisting.
Keep the container stable and horizontal during hoisting, and ensure
that the diagonal gradient of the container is within 5 degrees.
Lift and land the container slowly to prevent shock to equipment
inside it.
Remove the ropes after ensuring that the container is placed evenly
on the container bases.
Secure the container you have hoisted before hoisting another one.
Procedure
Step 1 Determine the installation position of the container based on the foundation design drawing.
Step 2 Measure the support points for the container on the foundation. Ensure that the support points
are on the same plane and the deviation is no more than 5 mm.
Step 4 Adjust the container, level the container using spacers, and ensure that the support points at
the bottom evenly supporting the container and are not floated.
The container can be secured using channel steel brackets or on the concrete floor.
1. If channel steel brackets are used, secure the container to the brackets with bolt
assemblies.
2. Secure the container to the concrete floor using expansion bolts.
This section uses the securing of the container to the concrete floor as an example.
There are four mounting holes where angle steel brackets contact the base. Mark all mounting holes.
Each angle steel bracket must be secured by two mounting holes. Preferentially drill the outer two
mounting holes. If steel bars in a concrete base block the drill bit, drill the inner mounting holes.
----End
Installation Verification
Check Item Criterion
Bolts and nuts Bolts and nuts are tightened.
Contact between the container and the The container is in good contact with and evenly
base supported by the bases underneath.
Open and close each container door. All container doors can be smoothly opened and
closed.
5 Electrical Connections
The cables between the transformer station and the smart array controller are prefabricated: the
RS485 communications cable, the PLC/PID power cable, and the power cable.
To connect cables for the site auxiliary power supply, refer to the electrical drawing of the
low-voltage cabinet.
Procedure
Step 1 Install the ground flat steel on the ground point of the container.
----End
Procedure
Step 1 Cut the cable inlet according to the cross-sectional area of the cable.
Step 2 Lay out the cables according to the design, route the cables to the corresponding wiring
positions on switches, and mark the wiring positions.
Step 3 If aluminum alloy cables are used, install copper-aluminum conversion ports. If copper cables
are used, there is no need to install copper-aluminum conversion ports.
Do not connect aluminum wiring terminals to the switch copper bar. Otherwise, the
electrochemical corrosion will occur and affect the reliability of cable connections.
When using a copper-aluminum conversion port, pay attention to the upper and lower
terminals. Ensure that the aluminum end of the port is in contact with the aluminum wiring
terminal, and that the copper end is in contact with the switch copper bar.
The screw assembly model is subject to the delivery. The screw assembly should be
tightened according to the corresponding standard torque.
Heat shrink tubing must be installed in the crimping area of the cable conductor of the
wiring terminal to ensure that the electrical clearance between the conductors is greater
than 20 mm.
Procedure
Step 1 Cut the cable inlet according to the cross-sectional area of the cable.
Step 2 Lay out the cables according to the design, route the cables to the corresponding wiring
positions on switches, and mark the wiring positions.
Step 3 Prepare terminals and secure them by referring to the installation guide to the split-type
shielded cable connector.
Figure 5-5 Connecting the AC output power cable (a single transformer station)
Figure 5-6 Connecting the AC output power cable (multiple transformer stations cascaded)
The cable room of the load switch cabinet supports the access of two rows of cables.
Step 4 Seal the bottom cable hole using firestop putty, clear the cable room sundries, and close the
door.
----End
The installation position of the smart array controller is reserved outside the medium-voltage room.
The RS485 communications cable and power cable of the smart array controller have been reserved
on the auxiliary transformer side in the medium-voltage room before the delivery of the transformer
station.
Step 1 Take the conversion brackets out of the accessories. Install conversion brackets for the smart
array controller.
Step 6 Use firestop putty to seal the cable hole in the container.
----End
Context
You have obtained the distributed power system and its auxiliary materials.
Procedure
Step 1 Install the distributed power system.
1. Install the wall mounting kit.
2. Move the mounting kit from the rear of the lithium battery to the left side, and install the
lithium battery on the wall.
3. Install the connecting kit and combine the PSU with the lithium battery.
Step 3 Connect the cables between the PSU and lithium battery.
Step 4 Remove the jumper between 1UPS-0-L and 1UPS-1-L. Remove the jumper between
1UPS-0-N and 1UPS-1-N. Connect the AC power cables.
----End
Routine Check
No. Check Item Acceptance Criterion
1 Equipment The equipment is intact, and free from rust and paint
appearance flake-off. Repaint areas with paint flake-off (if any).
The labels on the equipment are legible. The damaged
labels must be replaced in time.
2 Cable Cable sheathings are properly wrapped and free from
appearance obvious damage.
Hoses that contain cables are intact.
3 Cable Cables are connected in the designed positions.
connection Terminals are prepared as required and securely connected.
Labels on both ends of each cable are clear and specific,
and attached in the same direction.
4 Cable routing Strong-current and weak-current cables must be routed
separately.
Cables are neat and tidy.
The joints of cable ties are evenly cut without burrs.
Cables are placed properly and not tense at turning points.
Cable routes are straight and smooth, and do not intersect
inside a cabinet.
5 Container The container is clean and tidy inside, without any unnecessary
tidiness cables, cable heads, terminals, or tools. No obvious garbage is
found outside the equipment.
Container Check
No. Check Item Acceptance Criterion
1 Installation The installation conforms to the design requirements.
The container is level, and each door can be opened
Transformer Check
No. Check Item Acceptance Criterion
1 Appearance There is no crack, dent, or scratch on the transformer surface.
2 Oil leakage No oil leakage occurs on the transformer surface.
3 Oil temperature The oil temperature indicator of the transformer is close to the
ambient temperature. The cover of the oil temperature meter is
The handover test and system power-on need to be carried out by professional electrical
technicians in accordance with local regulations according to relevant standards of the country
or region.
After the handover test is complete, install the lightning arrester for the circuit breaker cabinet.
For details, refer to the installation guide of the lightning arrester.
8 Man-Machine Interaction
For details about the measurement and control device, see the user guide.
If the SmartLogger software version is earlier than V200R002C20SPC116, you can add a
device by importing a configuration file. The figure is for reference only.
Step 1 Configure an information point table and generate a .cfg file based on the Modbus protocol.
Step 2 Log in to the SmartLogger WebUI as Advanced User.
Parameter Description
Language Select the language as required.
User Name Supports Common User, Advanced User,
and Special User.
Select Advanced User.
Password Initial password: Changeme.
Use the initial password upon first
power-on and change it immediately
after login. To ensure account security,
change the password periodically and
keep the new password in mind. Not
changing the initial password may cause
password disclosure. A password left
unchanged for a long period of time may
be stolen or cracked. If a password is
lost, devices cannot be accessed. In these
cases, the user is liable for any loss
caused to the PV plant.
Step 3 Set RS485 parameters for the equipment to connect to the COM port.
Protocol Protocol, Baud rate, Parity, and Stop Set this parameter to Modbus.
Bit should be consistent with those of
Baud rate the transformer station. Set this parameter to 9600.
Parity Set this parameter to None.
Stop Bit Set this parameter to 1.
Start address Start address ≤ Communication address Retain the default value 1.
of the transformer station ≤ End address
End address Retain the default value 247.
Parameter Description
Device Type Supports user-defined device 1/2/3/4/5.
Select a device based on the generated .cfg
file. For example, import the
modbus_equip_custom_1.cfg file. If the
number in the file is 1, select Custom
Device 1.
Port number Set this parameter based on the actual COM
port number of the transformer station.
Address Set this parameter based on the actual
address of the transformer station.
Step 6 Check the running information to ensure that the transformer station data is correct.
----End
If the SmartLogger software version is V200R002C20SPC116 or later, you can directly add a
device. The figure is for reference only.
Parameter Description
Language Select the language as required.
User Name Supports Common User, Advanced User,
and Special User.
Select Advanced User.
Password Initial password: Changeme.
Use the initial password upon first
power-on and change it immediately
after login. To ensure account security,
change the password periodically and
keep the new password in mind. Not
changing the initial password may cause
password disclosure. A password left
unchanged for a long period of time may
be stolen or cracked. If a password is
lost, devices cannot be accessed. In these
cases, the user is liable for any loss
caused to the PV plant.
Step 2 Set RS485 parameters for the equipment to connect to the COM port.
Protocol Protocol, Baud rate, Parity, and Stop Set this parameter to Modbus.
Bit should be consistent with those of
Baud rate the transformer station. Set this parameter to 9600.
Parity Set this parameter to None.
Stop Bit Set this parameter to 1.
Start address Start address ≤ Communication address Retain the default value 1.
of the transformer station ≤ End address
End address Retain the default value 247.
Parameter Description
Device Type Set this parameter to STS.
Parameter Description
Port number Set this parameter based on the actual COM
port number of the transformer station.
Address Set this parameter based on the actual
address of the transformer station.
Step 4 Check the running information to ensure that the transformer station data is correct.
----End
9 System Maintenance
9.3 Troubleshooting
Alarm Name Signal Fault Cause Troubleshooting Suggestion
Meaning
Transformer Tripping The transformer is 1. A short circuit fault usually
pressure release signal short-circuited. affects the gas relay from which
you can take the gas sample first.
The transformer is not
If the gas is colorless,
breathing well.
odourless, and not flammable,
The pressure relief valve is
it is air. In this case, identify
faulty.
the air inlet and the reason for
The transformer is not air intake, which may be
properly operated during oil improper oil charge.
recharge. If the gas has a peculiar smell
or even flammable, it
If you cannot rectify faults with the measures listed in troubleshooting suggestions, contact Huawei
technical support.
For details about how to replace a component inside the transformer station, see the
component installation guide.
Before replacement, check that a spare component of the same model is available and
functional.
When replacing the component, disconnect the power supply. High voltage is dangerous.
Do not operate with power on.
Replace components not listed in this document following manufacturer instructions.
Dispose of faulty components in accordance with the local disposal act for waste electrical
equipment.
Step 3 Install the new fuse and close the switch box of the fuse-switch-disconnector.
----End
10 Technical Specifications
Input
Technical Specifications STS-2500K STS-6000K
Capacity 2500 kVA @50°C 6000 kVA @40°C
Rated input voltage 800 V 800 V
Frequency 50 Hz/60 Hz 50 Hz/60 Hz
Maximum input current under 2199.6 A 2403 A
rated voltage
Transformer
Technical Specifications STS-2500K STS-6000K
Rated output voltage 20/22/30/33/34.5 kV 20/22/30/33/34.5 kV
Tapping range ±2 x 2.5% ±2 x 2.5%
Short-circuit impedance 6.5% (0 to +10%) @2800 kVA 6.5% (0 to +10%) @6000 kVA
Protection
Technical Specifications STS-2500K STS-6000K
IP rating of IP54 IP54
medium-voltage/low-voltage
rooms
Surge protection Type II Type II
(Optional) Surge protection Type I + II Type I + II
Common Parameters
Technical Specifications STS-2500K STS-6000K
Dimensions (H x W x D) 6058 mm x 2896 mm x 2438 mm 6058 mm x 2896 mm x 2438 mm
Weight < 15 t < 23 t
Operating temperature –25°C to +60°C –25°C to +60°C
Relative humidity 0%–95% RH 0%–95% RH
Highest operating altitude 2000m@50Hz/2500m@60Hz 2000m@50Hz/2500m@60Hz
Feature Parameters
Technical Specifications STS-2500K STS-6000K
Note a: When the AC low-voltage side is connected to the PID module, do not ground the
neutral point of the transformer.
A FAQ
When operating the transformer, ensure that the transformer is in the no-excitation state, that
is, the high and low voltage sides of the transformer are not powered on.
Figure A-1 Adjusting the off-load tap changer (to Level 1 for example)
----End
----End
There is a sealing washer between the flange cover and dehydrating breather. When tightening
the bolt, ensure that the sealing washer is 1/4 compressed in height.
----End
Step 4 Tighten the bleeder plug screw, put the nut back, and reinstall the cover of the gas relay.
----End
(A) Oil drain valve, for the hose (B) Oil feeding and drain valve for the oil cabinet,
with a 60 mm diameter for the hose with a 35 mm diameter
The transformer has two oil drain ventages: DN50 cast-iron oil drain valve at the bottom of
the transformer and DN25 copper oil feeding and drain valve at the bottom of the oil cabinet.
The oil drain valve is recommended.
Step 1 Ensure that the oil drain valve is switched off.
Step 2 Remove the cover from the oil drain valve.
Step 3 Secure the hose connector. Connect one end of the steel hose to the hose connector and the
other end to the oil tank.
Step 4 Open the oil drain valve. The oil slowly moves from the transformer to the oil tank.
Step 5 Check the position indicated by the oil level gauge according to the local ambient temperature
and oil level curve. When the transformer oil drops to the corresponding indication position,
stop oil draining.
Step 6 Close the oil drain valve and remove the hose connector and hose.
Step 7 Reinstall the cover on the oil drain valve.
----End
Context
The container should be intact. If paint has flaked off in a specific area, repaint that area.
Check the damage to the container paint and prepare appropriate tools and materials. The number of
materials depends on site requirements.
Procedure
Step 1 Gently polish the damaged areas using fine sandpaper to remove smudges or rust.
Step 2 Dip a piece of cotton cloth into anhydrous alcohol and wipe the polished or damaged area to
remove the dirt and dust. Then wipe off the alcohol with a clean and dry cotton cloth.
Step 3 Paint zinc-rich primer on the damaged coat using a brush or painting gun.
If the base material is exposed in the area to be repaired, apply epoxy zinc-rich primer,
wait until the paint has dried, and then apply acrylic acid top coating.
Select epoxy zinc-rich primer or acrylic acid top coating with a color the same as the
surface coating color of the equipment.
Step 4 Apply paint evenly to the damaged area based on the damage degree of the paint using a spray
bottle, brush, or painting gun until all damage traces are invisible.
Step 5 Wait for 30 minutes and check whether the painting meets the requirements.
The color of the repainted part should be the same as surrounding areas without bulging or traces of
damages, and the paint should not flake off.
If you choose to spray paint instead of applying paint using a brush, it is recommended that you
spray paint three times before checking the result. If the color does not meet the requirements, paint
more times until the painting meets the requirements.
----End
A
ACB Air Circuit Breaker
C
COM Communication
E
EMC Electromagnetic Compatibility
I
ID Identifier
L
LCD Liquid Crystal Display
LV Low Voltage
M
MV Middle Voltage
P
PEI Peak Efficiency Index
S
STS Smart Transformer Station
T
TR Transformer