PROJECT :
CONSTRUCTION AND COMPLETION OF 144 UNITS OF HOUSES CONSISTS OF:
1) PACKAGE A - 28 UNITS OF SEMI-D HOUSE (TYPE RB4), 46 UNITS OF TERRACE HOUSE (TYPE RT5), 1 UNIT OF
GUARD HOUSE AND 1 UNIT OF TNB DOUBLE-CHAMBER SUBSTATION AT PHASE 2C1
2) PACKAGE B - 32 UNITS OF SEMI-D HOUSE (TYPE RB4), 38 UNITS OF TERRACE HOUSE (TYPE RT5) AT PHASE 2C2
ON PART OF LOT 15967, PEKAN TEMPLER, MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN
SELAYANG, SELANGOR DARUL EHSAN.
FOR MESSRS. SETIA ECO TEMPLER SDN. BHD
SITE MEETING NO. 14
Ref : DTLMG077 /Min /SM /14 Venue : Meeting Room, Setia Eco Templer Sales Gallery
Date : 23rd Aug 2023 Time : 3.30 p.m.
Attendance: Absent with Apologies: *( )
*Idvan Goh Yong Cheng SETIA Eco Templer Sdn. Bhd SET
*Safwan bin Mat Amin SETIA Eco Templer Sdn. Bhd SET
*Mohd Shafiq Bin Mohd Zolkfali SETIA Eco Templer Sdn. Bhd SET
Mohamad Syahrir bin Zulkifli SETIA Eco Templer Sdn. Bhd SET
*Faizul Ikmal B Mohd Nasir SETIA Eco Templer Sdn. Bhd SET
*Zidi Rasyidi Bin Mohd. Ariff SETIA Eco Templer Sdn. Bhd SET
*Tan Chai Seng SETIA Eco Templer Sdn. Bhd SET
Kok Kim Sen SETIA Eco Templer Sdn. Bhd SET
Tan Wei Chong SETIA Eco Templer Sdn. Bhd SET
*Muhammad Hazriq B Mohd Razali SETIA Eco Templer Sdn. Bhd SET
*Rahimie bin Othman SETIA Eco Templer Sdn. Bhd SET
*Vincent Lau Puong Hung SETIA Eco Templer Sdn. Bhd SET
*Zuraidy bin Juraimy SETIA Eco Templer Sdn. Bhd SET
*Raudzoturrahmah Sarbani SETIA Eco Templer Sdn. Bhd SET
Song Wei Sin SETIA Eco Templer Sdn. Bhd SET
*Norfadilahyati SETIA Eco Templer Sdn. Bhd SET
*Ar. Foo Mau Jack DTLM Design Group Sdn. Bhd DTLMG
*Ar. Pua Shih Shing DTLM Design Group Sdn. Bhd DTLMG
Mohd Shahir Bin Saad DTLM Design Group Sdn. Bhd DTLMG
*Nur Izzati Rosli DTLM Design Group Sdn. Bhd DTLMG
Nurul Nuha bt Mohd Nor Fikeri DTLM Design Group Sdn. Bhd DTLMG
*Ir. Lai Joo Seng Jurutera Perunding Sdn. Bhd JPT
Alexander Sebastiraj Jurutera Perunding Sdn. Bhd JPT
*Muhammad Yusoff bin Zaini Jurutera Perunding Sdn. Bhd JPT
*Ir. Ho Choon Fei KVA Konsult Sdn. Bhd KVA
*Nur Irdina KVA Konsult Sdn. Bhd KVA
Trishia KVA Konsult Sdn. Bhd KVA
*Mr. Kong Mun Seng ST Projects Sdn. Bhd STP
*Mr. Cheah Hoon Win ST Projects Sdn. Bhd STP
*Mr. Kenny Lim Teck Keong ST Projects Sdn. Bhd STP
Mr. Yap Chee Hau ST Projects Sdn. Bhd STP
*En. Zailan ST Projects Sdn. Bhd STP
Mr. Ling Ngie Hui ST Projects Sdn. Bhd STP
*Nazrul Azren SETIA-WOOD Industries Sdn. Bhd SWI
*Zanzuhaida SETIA-WOOD Industries Sdn. Bhd SWI
Nor Azlina Said SETIA-WOOD Industries Sdn. Bhd SWI
Firdaus Cemerlang (KJM) Sdn. Bhd CEMERLANG
ITEM MATTERS ACTION DATE
CONFIRMATION OF MINUTES
Project Info:
Form of Contract: PAM Contract 2018 (Without Quantities)
Contract Sum: RM59,925,731.96
Date of Commencement: 1st March 2023
Date of Completion: 30th November 2024
Contract Period: 21 months
L.D: RM 43,000.00/ Day
INO
D.L.P: 24 months from the date of issuance of CPC
Performance bond: 5% of Contract Sum
Mock Up Unit
Date of Commencement: 1st March 2023
Date of Completion: 31th December 2024
Contract Period: 10 months
L.D: RM 1,000.00/ Day
12.1.0 INTRODUCTION
12.1.1 Nil
12.2.0 Previous Meeting Minutes
12.2.1 - -
12.3.0 Safety & Health Matters
TLQ Matters
12.3.1
DTLMG Aug 2023
Date Events Remarks
26/06/2023 OSC online submission Submitted
17/08/2023 Bill paid to OSC Receipt issue to SET & STP.
Pending OSC comment to submit hard copy
STP to obtain JTK approval after TLQ approval. STP Sept 2023
12.3.2 Inspection by SET done with no NCR. DOE to maintain performance. STP
SET HSE remind STP to maintain silt trap in a good condition; desilt for earth drain, need to
12.3.3 Info
reroute the drain or pump to avoid water ponding.
12.3.4 HSE Site Memo
Safety Score
No. Month Score Remarks
12.3.5 SET
1.
SET to forward the score report to DTLMG by email.
12.4.0 PROGRESS REPORT & SITE ISSUES
12.4.1 Summary of work progress: STP
Progress Report No. –
Overall
Block Construction Period Schedule Actual Current Previous
01/03/2023- -11 -1.96% -9 -1.69%
Overall 16.38% 14.42%
30/11/2024
01/03/2023-
Section 30/09/2023 40.92% 36.14% -10 -4.78% -8 -3.95%
1B
01/06/2023- 0.00% 0.00% 0 0.00% 0 0.00%
Section 31/12/2023
2B
01/03/2023-
TNB 30/09/2023 70.96% 66.43% -10 -4.52% -8 -3.83%
(PE)
01/03/2023-
Phase 31/08/2024 25.87% 26.68% 4 0.81% 3 0.51%
2C1
01/06/2023-
Phase 30/11/2024 6.88% 2.15% -26 -4.73% -21 -3.88%
2C2
i. SET highlighted there is an issue of unset pile and short pile issue at Phase 2C2. STP STP
is informed SET will hand over 2 blocks (Block 4H,4I) by early September.
STP to record down the hand over date of:
a) Block 4H, JPT to send pile enlargement detail to STP.
b) Block 4I, JPT to send as built drawing to STP.
Block 4F and 4G, JPT informed next target is for PD testing by early September.
Guard House and TNB fencing, TNB received the fencing footing design and to clarify
after the meeting. Mock-up TNB will start plastering by early September
ii. STP informed the brick work to complete by end of Aug for Mock Up unit.
iii. STP to proceed the installation of timber door frame after the completion of mock-up
unit by mid-September.
iv. Setia highlighted about the roof gradient of mock-up unit. 1 unit is already fabricated.
12.5.0 Contract Matters
12.5.1 Variation Order (V.O) (refer page No.29a) (remain)
No Item AI/EI Addition Omission Remarks VOR
No. Status
1. Rain Sump AI_03 √ Submitted
2. NSC (Cold Water & AI_04 √
Sanitary Plumbing
Services), (Electrical,
Telephone, & Home
Alarm System
Services)
4. 4.1 Fencing Design √ STP to
revised cost
4.2 Footing Design √ STP to
revised cost
5. Floor Trap - - No addition SET to
cost issue
VOR
6. Pile Cap Enlargement √ STP to
submit
quotation
12.6.0 Authority Matters
12.6.1
No Item Date Remarks
1. TLQ approval (MPSelayang) 26/6/2023 Pending comment to submit INFO
hardcopy
2. JTK approval
12.7.0 Site Matters
12.7.1 STP informed to mobilize the workers on site and to add more gang when P2C2 work started.
Trade Current Worker Previous Worker
Carpenters 40 31
Bar bender 15 15
Concretor 9 9
Electrical 6 4 STP
Plumber 13 10
A/C 2 2
Brick layer 21 -
Plaster To add by end of Aug -
12.7.2 Site Training Schedule (remain)
Item Date Remarks
NIRO tiles 17/5/2023 Done
Painting (Jotun) 09/8/2023 Done
Plastering STP
Water Proofing (Pentens) 15/6/2023 Done
Water Proofing (Sika) 27/6/2023 Done
Feature Wall (Facing Brick)
SAE Piping 13/7/2023 Done
12.7.3 RFI (refer page No. 6) (All in order)
12.7.4 NCR/Site Memo (refer page No. 21)
No Item Remarks
1. Unsatisfactory compressive strength of concrete core JPT requested 3rd coring STP 24/8/2023
for Semi-D Block 6A-2370&2371 and block 6B test
Ground Beam Structure
Ref SET/PH2C1/MAINBUILDING/23/04
12.8.0 Contractor Matters
DTLMG highlighted the following: -
Shop Drawings / Submissions
12.8.1
a. All materials / shop drawings must be submitted & obtain confirmation from the respective
consultants prior to commencement of any works on site. Consultant has the right to reject
any work done due to non-conformance of the above requirement
b. All confirmed materials / samples & copies of confirmed material specifications must
always be stored and well-kept at site for viewing. Photos shall be taken and distributed to STP to
all parties for safekeeping. take note
c. All approved materials / samples must be with signing off record, sticker, or tag.
d. All warranties in respect of materials, goods, and system to be submitted to SET for safe
keeping and/or comments.
e. Material submission to refer progress report.
STP to update latest drawing list and all consultants to send the latest shop drawing.
Material Sample Approval
No. Item Proposed Status Remarks
Submisison
Date
CIVIL & STRUCTURE
ARCHITECTURAL
1. Fiber Mesh from 4 inch to 04/08/2023 To submit a
6inch sample
MECHANICAL & ELECTRICAL
STP informed to conduct a Timber door frame species identification and Salt Retention
12.8.3
Testing after material delivery on site and material will be delivered by end of Aug. STP Aug 2023
12.8.4 DTLMG received a brick test official report. STP Aug 2023
12.9.0 Architectural Matters
12.9.1 -
12.10.0 C&S Matters
STP is informed to provide and cast the ceiling fan hook together at the first-floor slab. STP to
12.10.1
propose a method of statement and catalogue (submit a good quality on the anchor bolt and
need full loop hook) to JPT. JPT to review the sample. STP
STP to conduct a pull-out test. No issue on MOS.
12.10.2 STP to confirm on settlement monitoring which is stated in the Tender Clarification item no. 9
STP 23/8/2023
by 23rd August 2023.
12.11.0 M&E Matters
12.11.1 STP to submit Method of Statement for ACMV to KVA (Pending). STP
12.12.0 NSC Matters
NSC ROOFING & CEILING WORKS
SWI
12.12.1 SWI to submit material submission and method of statement for laminated flooring to STP.
SWI to prepare ACP sample mock up.
12.12.2 DTLMG requested SWI to submit a roof tile flashing, fascia board with paint colour as per
SWI/STP
specification.
A discussion on solar panel, SWI informed NSC not yet awarded. KVA to review the position of
12.12.3 KVA
solar panel followed architect drawing.
NSC TIMBER FLOORING WORKS
SWI 24/8/2023
12.12.4 SWI to submit method of statement to STP by 24/8/2023
NSC AIR-CONDITIONING AND MECHANICAL VENTILATION SERVICES
CEMERL
24/8/2023
12.12.5 KVA commented Cemerlang to resubmit shop drawing and method of statement to STP by ANG
24/8/2023. KVA to review the submission.
12.13.0 Landscape Matters
12.13.1 No Landscape matters recorded.
12.14.0 Other Matters
-
12.15.0 Conclusion & Next Meeting
12.15.1 Meeting was adjourned at 4.05 p.m.
Next meeting is scheduled as follows: -
INFO
Date : 6th Sep 2023 (Wednesday)
Time : 2.30 pm
Venue : Site Office P2C1, Setia Eco Templer
PLEASE NOTE THE ACTION COLUMNS AND UNDERTAKE TO COMPLETE YOUR RESPECTVE TASK AS AGREED
Prepared by
Izzati Rosli
DTLM Design Group Sdn Bhd