PT.
TRITAN METALINDO MANDIRI
Nama Proyek : MOC 0276-PROJECT SOURSOP
Owner : PT. Energi Sejahtera Mas
MANPOWER PLANING
BULAN KE I BULAN KE II BULAN KE II BULAN KE IV BULAN KE V
MANPOWER JUMLAH
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20
Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Site Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Keuangan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Engineering 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Safety Officer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Electrical 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Supervisor / Mandor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Welder 5 0 3 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Fitter 8 6 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Semi Fitter 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Helper 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Scafolder 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Helper Scfolder 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
TOTAL 43 36 41 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43