0% found this document useful (0 votes)
98 views2 pages

Pastor's HQ Expansion Costs

This document provides a bill of materials and cost estimate for the proposed expansion of the GKMCC in Canlubang, Philippines. The expansion includes construction of an additional third floor of 81 square meters. The total estimated project cost is 891,228.80 Philippine Pesos. This cost covers preparation works, civil/structural works, electrical works, drainage, water supply, and a 12% fee for profit, design and supervision. Completion of the project is estimated at 70 working days.

Uploaded by

Allan Lopez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
98 views2 pages

Pastor's HQ Expansion Costs

This document provides a bill of materials and cost estimate for the proposed expansion of the GKMCC in Canlubang, Philippines. The expansion includes construction of an additional third floor of 81 square meters. The total estimated project cost is 891,228.80 Philippine Pesos. This cost covers preparation works, civil/structural works, electrical works, drainage, water supply, and a 12% fee for profit, design and supervision. Completion of the project is estimated at 70 working days.

Uploaded by

Allan Lopez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

BILL OF MATERIALS & COST ESTIMATE

11/25/23

PROJECT : PROPOSED GKMCC EXPANSION PROJECT


OWNER: PASTOR J. PELLEJERA
LOCATION : KAPAYAPAAN VILLAGE BRGY. CANLUBANG CALAMBA CITY
SUBJECT: BILL OF MATERIALS FOR THIRD FLOOR EXPANSION WORKS
TOTAL FLOOR AREA = 81 Square Meters
Scope of Works : Construction of Third Floor Pastor's Haedquarter

ITEM WORK DESCRIPTION QTY UNIT UNIT COST MATL'S COST LABOR COST AMOUNT
THIRD FLOOR AREA = 85.5m2
I PREPARATION
Mobilization / Demobilization 1 lot 20,000.00 20,000.00
Lay out & staking 1 lot 4,600.00 4,600.00 1,840.00 6,440.00
Health and Safety 1 lot 5,000.00 5,000.00 2,000.00 7,000.00

33,440.00

A. CIVIL/ARCHITECTURAL WORKS

Masonry, Plastering & CHB


1 Laying of Perimeter/Firewall 162 m2 350.00 56,700.00 22,680.00 79,380.00
Includes Wterproofing Works
2 Tile Works 60x60 Granite Tiles 75 m2 550.00 41,250.00 16,500.00 57,750.00
Steel Rebar
Reinforcement/Concreting Works
3 81 m2 1,300.00 105,300.00 42,120.00 147,420.00
for New Column Extension and
Roof Beams
4 Tile Works of New Stair 1 lot 14,500.00 14,500.00 5,800.00 20,300.00
Provision of New Stair Railing and
1 sets 17,500.00 17,500.00 7,000.00 24,500.00
5 Balcony Railing
Provision of Common Toilet
Includes Tile works and fixture 1 sets 15,400.00 15,400.00 6,160.00 21,560.00
6 Installation
7 Finishing / Painting Works 1 lot 41,000.00 41,000.00 16,400.00 57,400.00
Provision of New Panel Doors and
8 Door Jambs and Analoc Windows 1 lot 43,500.00 43,500.00 17,400.00 60,900.00
and sliding Doors
Roofing Works Includes Roof
Framing Insulation and bended 81 m2 800.00 64,800.00 25,920.00 90,720.00
9 Materials
Gypsum Ceiling Works Includes
75 m2 350.00 26,250.00 10,500.00 36,750.00
10 Metal Framing Works
11 Formworks & Scaffolding 1 lot 18,700.00 18,700.00 7,480.00 26,180.00

622,860.00

B. ELECTRICAL WORKS
1 Provision of New lighting Fixture 1 lot. 18,500.00 18,500.00 7,400.00 25,900.00
2 Provision of New Power Outlet 1 lot. 11,500.00 11,500.00 4,600.00 16,100.00
3 New Wiring Rounghing Ins 1 lot. 33,000.00 33,000.00 13,200.00 46,200.00
4 Supply and Install of new Switch 1 lot. 3,500.00 3,500.00 1,400.00 4,900.00
Supply and Install of ACU CO/.
1 lot. 3,500.00 3,500.00 1,400.00 4,900.00
5 Breaker
6 PVC Pipe 1/2" 1 lot. 5,500.00 5,500.00 2,200.00 7,700.00
7 PVC Pipe 3/4" 1 lot. 3,450.00 3,450.00 1,380.00 4,830.00
8 accessories 1 lot. 4,500.00 4,500.00 1,800.00 6,300.00
9 Consumables 1 lot. 9,000.00 9,000.00 3,600.00 12,600.00

129,430.00
-
C. STORM/SANITARY DRAINAGE LINE
Provision of new drain line and
1 lot 3,700.00 3,700.00 1,480.00 5,180.00
storm drain line

- - 5,180.00
D. WATER LINE
Provision of New Waterline 1 lot 3,450.00 3,450.00 1,380.00 4,830.00

4,830.00
Total Labor and Material Cost in Php 795,740.00

Profit, Design and Supervision 12% 95,488.80

Total Project Cost in Php 891,228.80

SUMMARY of BILL OF MATERIALS & COST ESTIMATE


ITEM WORK DESCRIPTION

I. PREPARATION 33,440.00

A. CIVIL WORKS 622,860.00

B. ELECTRICAL WORKS 129,430.00

C. STORM DRAINAGE LINE 5,180.00

D. WATERLINE 4,830.00

TOTAL LABOR & MATERIALS 795,740.00

PROFIT, DESIGN AND SUPERVISION 12% 95,488.80


TOTAL PROJECT COST 891,228.80

Terms
50% Downpayment , 45% Progress Billing and 5% Retention
Completion : 70 workings Days
Warranty : 6 months upon final acceptance and completion
Quotation Valid for 1 Week Only

Exclusion :
1 Temporary Water and Power Consumtion
2 Loose Furniture, Equipment and Appliances
3 Mechanical and Electromechanical Works
4 CCTV Provision
5 Overhead Water Tank, pump and Piping Works
Note:
1 Any works that is not included in the scope shall be considered as additional
2 All other materials that we will removed as a result of the renovation will become the property of the Contractor.

Prepared by: Approved by:

Ar. Pol A. Pe Benito, UAP Pastor Joshue Pellereja


Time and Space Construction GKMCC Canlubang

You might also like