Moyale Water Supply Payment Certificate
Moyale Water Supply Payment Certificate
1.2 Maintain full Services for whole duration of the Project LS 1.00 0.50 0.50 2,100,000.00 2,100,000.00 1,050,000.00 1,050,000.00
1.3 Progress photograph and Reporting LS 1.00 0.50 0.50 150,000.00 150,000.00 75,000.00 75,000.00
1.4 Provision and survey labour for the Engineer LS 1.00 0.50 0.50 650,000.00 650,000.00 325,000.00 325,000.00
65,000.00
1.5 Establishment of site sign boards as per the specifiation No. 2.00 0.00 130,000.00 - -
1.6 Independent testing of concrete and geotechnical as 75,000.00
required by the Engineer LS 4.00 3.00 3.00 300,000.00 225,000.00 225,000.00
2,400,000.00
1.7 Mobilization to site all machineries, material, personnel etc. LS 1.00 0.50 0.50 2,400,000.00 1,200,000.00 1,200,000.00
1.8 380,000.00
Transport to site and to tranch all pipes, fittings and
including lining pipes to tranch etc.
LS 1.00 0.20 0.20 380,000.00 76,000.00 76,000.00
1.11 Preparation of asbuilt drawing of the works LS 1.00 0.00 213,000.00 213,000.00 - -
1.12 Motor Cycle for service utility nr 2.00 0.00 80,000.00 160,000.00 - -
Pumping test of BH-3 and BH-6 for constant discharge test
of 24 hours withen the presence of the engineer or it's nr 2.00 2.00 2.00 110,000.00 220,000.00 220,000.00 220,000.00
representative
Car Service for the Engineer nr 12.00 0.00 0.00 - - -
2.2 From 500M3 SR to Moyale Booster Station to Moyale 250m3 Service Reservoir
Item Description Unit Quantity Rate in Birr Amount in Birr
Supply of HDPE Pipe to PN 10, PN12.5 and PN 16 PE100, with outer sizes as
indicated in the table here below
2.2.1 -
2.2.2 HDPE OD225 PN10 PE100 m 33281 9,529.80 9,529.80 2,600.00 86,530,600.00 24,777,480.00 24,777,480.00
2.2.3 HDPE OD225 PN12.5 PE100 m 953 0.00 3,350.00 3,192,550.00 - -
2.2.4 HDPE OD225 PN16 PE100 m 6,616.00 6,369.00 6,369.00 3,450.00 22,825,200.00 21,973,050.00 21,973,050.00
Sub-Total - 2.2 40,850 15,899 112,548,350.00 - 46,750,530.00 46,750,530.00
2.3 From 500M3 SR to Elgof Village
Item Description Unit Quantity Rate in Birr Amount in Birr
2.3.1 HDPE OD 75 m 3,800.00 50.00 50 430.00 1,634,000.00 21,500.00 21,500.00
2.3.2 HDPE OD 90 m 1,100.00 - 410.00 451,000.00 - -
2.3.3 HDPE OD 110 m 850.00 - 720.00 612,000.00 - -
2.3.4 HDPE OD 125 m 1,800.00 - 740.00 1,332,000.00 - -
2.3.5 HDPE OD 140 m 400.00 - 950.00 380,000.00 - -
2.3.6 HDPE OD 160 m 3800.00 - 1000.00 3,800,000.00 - -
Sub-Total - 2.3 11,750 0,050
8,209,000.00 - 21,500.00 21,500.00
Supply and Installation of HDPE fittings for HDPE BUTT WELD for 20,079
2.4
Transmission Main
2.4.1
2.4.1 DCI All Flanged Tee DN 225 * DN 160 * DN 225 PN 16 No 2 25,000.00 50,000.00
2.4.2 HDPE Stright Reducer OD 225 X OD 180 No 2 13,430.00 26,860.00
2.4.3 Stright Reducer OD 225 X OD 160 No 1 12,000.00 12,000.00
2.4.4 HDPE Stub Flange With Backling Ring OD 225 PN 16 No 4 11,000.00 44,000.00
2.4.5 HDPE Stub Flange With Backling Ring OD 160 PN 16 No 2 10,000.00 20,000.00
2.4.6 Gate Valve PN 16 -
2.4.7 DN 225 No 4 28,000.00 112,000.00
2.4.8 DN 160 No 4 27,000.00 108,000.00
2.4.9 DN 90 No 3 12,000.00 36,000.00
2.4.10 DN 75 No 6 10,500.00 63,000.00
HDPE Bends PE 100 PN 16 -
45o -
2.4.11 DN 225 No 20 6,000.00 120,000.00
2.4.12 DN 160 No 2 7,800.00 15,600.00
90o -
2.4.13 DN 225 No 6 12,000.00 72,000.00
2.4.14 Bolt , Nut & washer , M-30 No 600 1,200.00 720,000.00
2.4.15 Bolt , Nut & washer , M-24 No 1000 1,400.00 1,400,000.00
2.4.16 Dia. 225mm*2" flanged Saddle clamp No 10 8,000.00 80,000.00
Airvalve & Washout Fitting
2.4.17 For OD 225 PN 16 Line
2.4.18 DCI All Flanged Tee OD 225 * DN 50 * OD 225 PN 16 No 44 12,800.00 563,200.00
2.4.19 Double Flanged Spigot pipe with Puddle 1 m Length No 11 19,000.00 209,000.00
2.4.20 Flanged Spigot pipe OD 225 1m Length No 4 20,200.00 80,800.00
2.4.21 Dismantling Joint OD 225 PN 16 No 8 18,100.00 144,800.00
2.4.22 Double orfice Airvalve DN 50 PN 16 No 44 13,000.00 572,000.00
2.4.23 HDPE Stub Flange With Backling Ring OD 225 PN 16 No 74 5,300.00 392,200.00
2.4.24 DCI All Flanged Tee OD 225 * DN 80 * OD 225 PN 16 No 30 1,700.00 51,000.00
2.4.25 Gate Valve DN 80 PN 16 No 30 3,200.00 96,000.00
2.4.26 GS Pipe DN 80 All Flanged Pcs 30 2,100.00 63,000.00
2.4.27 Flap Check Valve DN 80 No 30 13,000.00 390,000.00
Sub-Total - 2.4 5,441,460.00 - - -
Supply and Installation of HDPE fittings for HDPE BUTT WELD
2.5
FLANGE AND
and GS Flanged type for Cross Tee, Equal Tee, Reducers and Ga GS
2.5.1 FLANGED SOCKET FOR CONNECTION TO PVC PIPES
2.5.2 FLANGED SOCKET FOR CONNECTION TO PVC PIPE DN150 No. 11 3,500.00 38500.00
2.5.3 FLANGED SOCKET FOR CONNECTION TO PVC PIPE DN200 No. 1 4,200.00 4200.00
2.5.4 GS 90 DEG BEND 0.00
2.5.5 GS FLANGED 90 DEG BEND DN80 No. 1 3,800.00 3800.00
2.5.6 GS CROSS TEE 0.00
2.5.7 GS FLANGED TEE DN50 No. 12 2,900.00 34800.00
2.5.8 GS FLANGED TEE DN80 No. 10 4,100.00 41000.00
2.5.9 GS FLANGED TEE DN150 No. 6 5,320.00 31920.00
2.5.11 GS EQUAL TEE 0.00
2.5.12 GS FLANGED EQUAL TEE DN50 No. 12 2,800.00 33600.00
2.5.13 GS FLANGED EQUAL TEE DN80 No. 14 3,900.00 54600.00
2.5.14 GS FLANGED EQUAL TEE DN140 No. 3 5,300.00 15900.00
2.5.15 GS FLANGED EQUAL TEE DN160 No. 1 5,750.00 5750.00
2.5.16 HDPE BUTT WELD FLANGE WITH BACKING RINGS 0.00
2.5.17 HDPE OD63 BWF No. 6 2,930.00 17580.00
2.5.18 HDPE OD75 BWF No. 8 3,420.00 27360.00
2.5.19 HDPE OD90 BWF PN16 No. 10 4,250.00 42500.00
2.5.20 HDPE OD140 BWF PN16 No. 6 4,600.00 27600.00
2.5.21 HDPE OD160 BWF PN16 No. 2 1,380.00 2760.00
2.5.22 FLANGED GS GATE VALVE 0.00
2.5.23 GS FLANGED GATE VALVE DN50 No. 10 3,800.00 38,000.00
2.5.24 GS FLANGED GATE VALVE DN65 No. 5 4,000.00 20000.00
2.5.25 GS FLANGED GATE VALVE DN80 No. 12 4,600.00 55200.00
2.5.26 GS FLANGED GATE VALVE DN110 No. 7 5,000.00 35000.00
2.5.27 GS FLANGED GATE VALVE DN140 No. 4 2,700.00 10800.00
2.5.28 GS FLANGED GATE VALVE DN160 No. 2 3,000.00 6000.00
2.5.29 FLANGED GS REDUCER 0.00
2.5.30 GS FLANGED REDUCER DN65 x DN50 No. 4 2,100.00 8400.00
2.5.31 GS FLANGED REDUCER DN80 x DN50 No. 4 2,220.00 8,880.00
2.5.32 GS FLANGED REDUCER DN80 x DN65 No. 3 3,150.00 9450.00
2.5.33 GS FLANGED REDUCER DN100 x DN50 No. 8 3,400.00 27200.00
2.5.34 GS FLANGED REDU8CER DN100 x DN80 No. 2 3,400.00 6800.00
2.5.35 GS FLANGED REDUCER DN150 x DN75 No. 2 4,340.00 8680.00
2.5.36 GS FLANGED REDUCER DN75 x DN90 No. 3 3,950.00 11850.00
2.5.37 GS FLANGED REDUCER DN90 x DN110 No. 3 4,600.00 13800.00
2.5.38 GS FLANGED REDUCER DN110 x DN140 No. 2 3,950.00 7900.00
2.5.39 GS FLANGED REDUCER DN140 x DN160 No. 1 4,600.00 4600.00
2.5.41 GS BLANK FLANGE DN50 No. 10 5,300.00 53000.00
Sub-Total - 2.5 707,430.00 - - -
m 3,360,420.00 - -
Conduct Pressure Testing of this line as per the specification
and check for no leakage, the cost includes supply of all the
3.2.8.2 required equipments and water as indicated in the 12,330 0.00 80.00
specification
m 986,400.00 - -
3.2.9 TRUST AND ANCHOR BLOCKS 0.00 - - -
Construct concrete thrust blocks (C-25), volume not exceeding
3.2.9.1 No. 50.00 0.00 1800.00
0.25m3 as shown in the 90,000.00 - -
Construct concrete anchore blocks (C-25), volume not
3.2.9.2 No. 50.00 0.00 2600.00
exceeding 0.25m3 as shown in the 130,000.00 - -
3.2.10 VALVE CHAMBERS AND ANCILLARY PIPE WORKS 0.00
- - -
Construction of Valve Chambers for all Tee and cross Tee
3.2.10.1 No. 20.00 0.00 17500.00
junctions as per the Standard 350,000.00 - -
Sub-Total - 3.2 48,047,763.10 - 13,161,000.00 13,161,000.00
Item No. Item Description Unit Quantity Amount in
Birr
3.3 EARTHWORK -From 500m3 GCR - To Elgof Village
Site Clearing , along Pipe route to a max width of 4 m of all
3.3.1 m2 17,500 34,800 34,800 40
bushes and trees including 700,000.00 1,392,000.00 1,392,000.00
Excavation for trench in normal soil not less than 1.2 m deep
3.3.2 for installation of Transmission Main pipe, including disposal m3 11,000.0 0 540.00
of surplus excavated material 5,940,000.00 - -
Distribution line pipes, including disposal o Excavation for
3.3.3 trench in soft rock formation m3 5,500.00 0 540.00
2,970,000.00 - -
3.3.4 Excavation for trench in hard rock formation m3 5500.00 0 800.00 4,400,000.00 - -
Bedding and Pipe Cover 0.35 mm by imported selected
3.3.4 m3 4,600.00 0 600.00
material 2,760,000.00 - -
Backfilling the trench with imported select material as per
3.3.5 m4 5,600.00 0 600.00
drawing 3,360,000.00 - -
3.3.7 Backfilling the trench excavated native material m3 9,700.00 0 130.00 1,261,000.00 - -
3.3.8 Leakage and Commissioning Test 0 - - -
Conduct Testing of this line as per the specification and check
for no leakage, the cost includes supply of all the required
3.3.8.1 equipments and water as indicated in the specification 3,800 0 40.00
m 152,000.00 - -
3.3.9 TRUST AND ANCHOR BLOCKS 0 - - -
Construct concrete thrust blocks (C-25), volume not exceeding
3.3.9.1 No. 25 0 1800.00
0.25m3 as shown in the 45,000.00 - -
Construct concrete anchore blocks (C-25), volume not
3.3.9.2 No. 25 0 2800.00
exceeding 0.25m3 as shown in the 70,000.00 - -
12,000.00 m2
from- 1000M3 SR- Moyale Distribution
1.3 site clearing to remove the top soil
L= 5,800 m W =6 m
5,800.0
6.0
34,800.00 m2
4.5.4 Supply and install external water level indicator complete with No 1.00 - 7,500.00 7,500.00 - -
necessary accessories
Supply and fix external galvanised steel (6m) and internal
4.5.5 stainless steel (4.5m) ladder complete with safety cage as per the No 1.00 - 12,500.00 12,500.00 - -
design to the satisfaction of the engineer.
4.5.6 Provide & install uPVC water stops m 44.61 - 3,000.00 133,830.00 - -
Provide and fix 6mm sheet metal 800x800mm access cover with
4.5.7 40x40 angle iron frame with latck and lock for valve chamber no 1.00 - 3,200.00 3,200.00 - -
and reservoir
4.6 Supply and Installation of Pipes, Valves and Fittings - - -
Supply and Install Steel DN200 Inlet pipes, fittings and
4.6.1 valves of PN10 with all required accessories - - -
4.6.1.1 Flanged Bell Mouth No 1.00 - 6,200.00 6,200.00 - -
4.6.1.2 Double Flanged Pipe With Central Puddle L=1.0m No 1.00 - 16,100.00 16,100.00 - -
4.6.1.3 Double Flanged 90 Degree Bend No 1.00 - 14,060.00 14,060.00 - -
4.6.1.4 Double Flanged Short Pipe L=3.34m No 1.00 - 36,000.00 36,000.00 - -
4.6.1.5 Double Flanged 90 Degree Duck Foot Bend No 1.00 - 14,060.00 14,060.00 - -
4.6.1.6 Double Flanged Short Pipe L=0.25m No 2.00 - 4,500.00 9,000.00 - -
4.6.1.7 Double Flanged Gate Valve No 1.00 - 21,400.00 21,400.00 - -
4.6.1.8 Dismantling Piece No 1.00 - 13,050.00 13,050.00 - -
4.6.1.9 Flanged Adapter No 1.00 - 9,500.00 9,500.00 - -
Supply and fix Pipe support including pipe clamp, wall bracket,
4.6.1.10 foot plate and anchor bolts LS 1 - 10000 10,000.00 - -
Supply and Install Steel DN200 Outlet pipes, fittings and
4.6.2 valves of PN10 with all required accessories - - -
4.6.2.1Flanged Suction Strainer No 1.00 - 20,100.00 20,100.00 - -
4.6.2.2Double Flanged Pipe With Puddle L= 1.0m No 1.00 - 8,500.00 8,500.00 - -
4.6.2.3Double Flanged Gate Valve No 1.00 - 21,400.00 21,400.00 - -
4.6.2.4Double Flanged Woltman Water Meter No 1.00 - 15,000.00 15,000.00 - -
4.6.2.5Dismantling Piece No 1.00 - 13,050.00 13,050.00 - -
4.6.2.6Double Flanged Short Pipe L=0.25m No 1.00 - 4,500.00 4,500.00 - -
4.6.2.7Flanged Adapter No 1.00 - 9,500.00 9,500.00 - -
Supply and Install Steel Over Flow and Drainage pipes,
4.6.3 fittings and valves - - - -
4.6.3.1 DN65, PN10 Steel Flanged Bell Mouth No 1.00 - 4,500.00 4,500.00 - -
4.6.3.2 No 1.00 - 3,500.00 3,500.00 - -
DN65, PN10 Steel Double Flanged Pipe With Puddle L=1.42m
4.6.3.3 DN65, PN10 Steel Double Flanged 90 Degree Bend No 1.00 - 7,500.00 7,500.00 - -
4.6.3.4 DN65, PN10 Steel Double Flanged Short Pipe L=2.92m No 1.00 - 7,500.00 7,500.00 - -
4.6.3.5 DN65/DN65, PN10 Steel All Flanged Tee No 1.00 - 8,500.00 8,500.00 - -
4.6.3.6 DN65, PN10 Steel Flanged Adapter No 1.00 - 3,200.00 3,200.00 - -
4.6.3.7 DN50, PN10 Steel Single Flanged Pipe Short L=0.1m No 1.00 - 3,000.00 3,000.00 - -
4.6.3.8 DN50, PN10 Steel Double Flanged Pipe With Puddle L=1.0m No 1.00 - 2,300.00 2,300.00 - -
4.6.3.9 DN50, PN10 Steel Double Flanged Gate Valve No 1.00 - 7,800.00 7,800.00 - -
DN65/DN50, PN10 Steel Double Flanged Eccentric Reducer
4.6.3.10 No 1.00 - 6,500.00 6,500.00 - -
Supply and fix Pipe support including pipe clamp, wall bracket,
4.6.3.11 foot plate and anchor bolts LS 1.00 - 15000 15,000.00 - -
1.8 50mm thick lean concrete with mix ratio (1:3:6) under the reservoir
base slab
radius (r)= 4. m r2 = 16 Π=3.142 t=0.07m
1 16.00
3.14
50.27 m3 Total
BASE SLAB
bottom
reinforcemnt 12 8.02 1.00 2 16.04
12 8.00 2.00 2 32.00
12 7.99 2.00 2 31.96
12 7.96 2.00 2 31.84
12 7.97 2.00 2 31.88
12 7.86 2.00 2 31.44
12 7.79 2.00 2 31.15
12 7.70 2.00 2 30.80
12 7.60 2.00 2 30.40
12 7.49 2.00 2 29.94
12 7.49 2.00 2 29.94
12 7.35 2.00 2 29.42
12 7.20 2.00 2 28.80
12 7.00 2.00 2 28.00
12 6.65 2.00 2 26.60
12 6.40 2.00 2 25.60
12 6.17 2.00 2 24.68
12 5.89 2.00 2 23.56
12 5.56 2.00 2 22.24
12 5.23 2.00 2 20.92
12 4.83 2.00 2 19.32
12 4.37 2.00 2 17.48
12 3.84 2.00 2 15.36
12 3.19 2.00 2 12.74
12 2.30 2.00 2 9.20
12 0.50 2.00 2 2.00
WALL
12 4.60 222.00 1 1,021.20
Provided and install access internal and external hatches LS 1 - 21,300.00 21,300 - -
constructed out of 25 mm dia GS pipe and hooked to
5.7.4 the wall as per the drawing; including safety cages
Provide and install water stops made of natural or
synthetic rubber or elastometric plastic compound with m 109 - 650.00 70,850 - -
5.7.5 basic risen
Provide and fix 6 mm sheet metal access cover with No 2 - 3,200.00 6,400 - -
5.7.6 latch and lock for valve chamber and reservoir
Provide and apply two coats of bituminous asphalt over
the plastered surface of the embedded part of the m2 381.69 - 950.00 362,606 - -
5.7.7 reservoir
Provide and place single brick layer cover to protect the m2 54.35 - 1,201.00 65,274 - -
5.7.8 asphalt coat from the backfill material
Supply and Installation of Pipes, Valves and Fittings
5.8 - - -
Supply and Install Steel DN200 Inlet pipes, fittings
and valves of PN10 with all required accessories - - -
Supply and fix Gage 28, EGA-500 Iron sheet roof cover m2 126.00 - 1,540.00 194,040 - -
5.11.4 and wall, price includes 2 coats of synthetic painting
5.11.5 Agitator for installation in the solution tanks pcs 2.00 - 21,500.00 43,000 - -
5.11.6 PVC Chlorine Solution Preparation tank 50lt volume pcs 2.00 - 15,400.00 30,800 - -
Gravity dozer tank 3-100lt/hr, with built in rotameter 3- pcs 2.00 - 5,400.00 10,800 - -
5.11.7 100lt/hr range inlet outlet adaptors for connection DN20
DN20 GS Service Water Supply System, connected to pcs 2.00 - 5,000.00 10,000 - -
5.11.8 water pump, to feed the solution preparation
Solution pipe system, made of DN20 uPVC pressure
Pipes & fittings, connected rom the preparation tank to pcs 2.00 - 9,500.00 19,000 - -
5.11.9 the inection point of the reservoir
Barbed wire fencing fixed to 150mmx150mm Concrete
5.11.1 Post of 2500 mm high spaced at every 2000 mm, m 100.00 - 30,000.00 3,000,000 - -
0 including all necessary material as per the drawing
Total Construction for 1000m3 Reservoir 13,953,984.75 - 3,971,638.72 3,971,638.72
Project:
TOC Moyale Water Supply Construction project
Client: SRS Irrigation and Development Bureau
Consultant: SRS, Study, Design & Supervistion Works Enterprise
Contractor: Iqra General Construction Company
TAKE OFF SHEET FOR 1000 Service reservior
ITEM L*W*H QTY DESCREPTION
A. SUB - STRUCTURE
1.Excavation & earthwork
site clearing to remove of grupppng trees
1 12.00 A1= L X W L= 12 m w=12 m
12.00
577.52 m2
Provide, cut, bend and fix in position reinforced steel bar. All
6.7.1.2 - - -
according to structural drawing. Price shall include tying wires
L= 7.1 m W = 5.1 m
1 7.10
5.10
36.21 m2 total
MASONRY WORK
Bellow NGL
7.40
2 0.40
0.70
4.14 m3 total
2 5.40
0.40
0.70
3.02 m3
7.17 m3 total
2. Concrerte Work
a) In grade beam
2 7.40
0.20
0.20
0.59 m3
2 5.40
0.20
0.20
0.43 m3
1.02 m3 total
Formwork
a) to grade beam
Parimeter= ( 7.4x 2 x 2) + (5.4 x2 x2 ) = 51.2
51.20
0.20
10.24 m3 Total
2 5.40
0.20
0.20
0.43 m3
1.02 m3 total
2. BLOCK WORK
2.01 Class B, 200mm thick HCB wall
2 7.40
3.20
47.36 m2
2 5.40
3.20
34.56 m2
81.92 m2 Total Area of Wall (A)
2 1.50
2.00
7.50 m2 w1
2.98
2.40
7.15 m2 D1
14.65 m2 total window nad door dedaction
COLMAN
10 3.38 32.00 108.16
6 0.64 128.00 81.92
GENERATER SEAT
12 3.58 36.00 128.88
12 2.66 36.00 95.76
12 2.38 10.00 23.80
12 1.46 10.00 14.60
Remark
ITEM Contract Prev Exec Curr Exec To Date UNIT Contract Total Prev Exec Curr Exec To Date Exec
DESCRIPTION UNIT
NO Qtty Qtty Qtty Exec Qtty PRICE Amount (Birr) Amount Amount Amount
7.1 Earth Work
7.1.1 Clearing of site to remove top soil to a depth of 200 mm m2 158.40 150.00 150.00 40.0 6,336.0 6,000.00 6,000.00
7.1.2 Excavation for foundation wall m3 82.00 82.28 82.28 540.0 44,280.0 44,431.20 44,431.20
Cart away and deposit excavated surplus material to a
7.1.3 m3 72.59 82.28 82.28 320.0 23,228.8 26,329.60 26,329.60
distance not exceeding 1km from site
7.1.5 Fill 250 mm thick hard core m2 51.70 48.40 48.40 535.0 27,659.5 25,894.00 25,894.00
7.2 Concrete, Masonry and Block Work - - -
Reinforced concrete grade C-25 with minimum cement
content 360 kg/m3 cast into formwork and vibrated - - -
around reinforcement bars in
7.2.1 R.C. grade beam m3
1.64 - 7,500.0 12,300.0 - -
7.2.2 R.C. column and lintels m3 1.47 - 7,500.0 11,025.0 - -
7.2.3 R.C. top tie beams m3 1.64 - 7,500.0 12,300.0 - -
7.2.4 R.C.pump seat m3 4.75 - 7,500.0 35,625.0 - -
7.2.5 Mass concrete fill on floor slab m3 5.17 - 7,500.0 38,775.0 - -
Provide, cut, bend and fix in position reinforced steel
bar. All according to structural drawing. Price shall - - -
include tying wires
7.2.6 Diameter 6 mm bar kg 93.78 93.78 93.78 135.0 12,660.3 12,660.30 12,660.30
7.2.7 Diameter 10 mm deformed bar kg 1,852.15 1,000.00 1,000.00 135.0 250,040.3 135,000.00 135,000.00
7.2.8 Diameter 12 mm deformed bar kg 417.15 417.15 417.15 135.0 56,315.3 56,315.25 56,315.25
Stone Masonry - - -
Provide and construct 400 mm thick pointed stone
7.2.10 m3 39.78 - 3,800.0 151,164.0 - -
masonry for Foundation Wall
7.3 Provide, cut and fix formwork to - - -
7.3.1 Grade beam m2 16.39 - 520.0 8,522.8 - -
7.3.2 Tie beam m2 14.74 - 520.0 7,664.8 - -
7.3.3 Generator seat m2 4.62 - 520.0 2,402.4 - -
7.3.4 Column and lintels m2 16.98 - 520.0 8,829.6 - -
7.4 Block work - - -
Supply and raise 200mm thick concrete block wall
7.4.1 (class A of the ES CD3.301) with cement mortar mix m2 173.80 - 630.0 109,494.0 - -
1:3
Supply and raise 100mm thick concrete block wall
7.4.2 (class A of the ES CD3.301) with cement mortar mix m2 11.11 - 630.0 6,999.3 - -
1:3
7.5 Carpentry and Roofing - - -
Supply, assemble and fix in position eucalyptus roof
7.5.1 truss price shall include the application of three coats No 4.4 - 2,200.0 9,680.0 - -
and external anti-termite treatment as per the drawing
Supply, assemble and fix in position equalyptus Rafters
7.5.2 DN 100mm including three coats of anti - termite m 134.53 - 570.0 76,682.1 - -
external treatment
Supply and fix purlin in Zigba wood size 50 x 70 mm
7.5.3 nailed into eucalyptus truss including three coats of anti m 75.67 - 570.0 43,131.9 - -
- termite external treatment
7.5.4 Verticals, diagonals and chords (DN 100mm) m 33.55 - 570.0 19,123.5 - -
Supply and fix roof cover in G-28 mm corrugated
galvanized iron sheet fixed into zigba wood purlin with
7.5.5 m2 64.06 - 1,350.0 86,481.0 - -
dome headed galvanized nails (purlin and ridge cover
measured separately)
7.5.6 Supply and fix 25 x 250 mm facia board m 24.53 - 1,200.0 29,436.0 - -
Supply and fix edge gutter formed in G-28 flat
galvanized metal sheet including support brackets 1mm
7.5.7 thick shaped steel plate spaced at a maximum spacing of m 22.88 - 950.0 21,736.0 - -
1000 mm c/c and fixed to purlin - price includes metal
primer and two coats of synthetic enamel pa
2. Concrerte Work
BILL No. 8: CONSTRUCTION OF GUARD HOUSE AT BOREHOLE, BOOSTER STATION AND 1000M3 RESERVOIR
Item No. Item Description Unit Contract Pev Exec Curr Exec Upto Date Rate in Cotract Prev Exec Current Exec Upto Date
Qtty Qtty Exec Qtty Amount in Amount Amount Exec
Qtty Birr
Birr Amount
8.1 Earth Work and Excavation
8.1.1 Top soil stripping to 200mm depth m2 25.00 25.00 25.00 540.00 13500.00 13,500.00 13,500.00
8.1.2 Stripped level to a depth not exceeding 1m m3 29.70 12.29 12.29 540.00 16038.00 6,635.52 6,635.52
Trench excavation for stone masonry foundation wall in
normal material to a depth not exceeding 1.5m m3 3.04 6727.50 1,974.70 1,974.70
8.1.3 10.35 3.04 650.00
8.1.4 Excavation for foundation in soft rock formation m3 1.50 1.30 1.30 450.00 675.00 585.90 585.90
8.1.5 Ditto but in hard rock formation m3 1.00 0.00 500.00 500.00 - -
Filling and compacting at every 15 cm layer selected
m3 2.88 1937.00 1,873.95 1,873.95
8.1.6 granular materials under floor slab 2.98 2.88 650.00
8.1.7 Ditto but around the stone masonry foundation wall m3 1.73 1.40 1.40 1460.00 2525.80 2,036.70 2,036.70
8.1.8 250mm thick hard core well blinded with crushed stone m2 2.98 9.00 9.00 535.00 1594.30 4,815.00 4,815.00
1 3.00
3.00
9.00 m2 total
MASONRY WORK
Bellow NGL
3.00
4 0.40
0.50
2.40 m3 total
4 3.00 Masnry above OGL
0.40
0.50
2.40 m3
4.80 m3 total
2. Concrerte Work
A. under Grade beam 50mm thick lean concrete
2.80
2.80
7.84 m3
b) Under masonery
Along Y-axis
3.10
2 0.50
3.10 m2
Along X-axis
2 3.10
0.50
3.10 m2
6.20 m2
C In Ground floor slab
2.80
2.80
0.20
1.57 m3
a) In grade beam and top tie beam Concrete work
4 3.10 Grade beam
0.20
0.20
0.50 m3
c In Elevation Column
In Elevation Column= (0.2 x 4) x 4 = 3.2 m
16 3.20
0.22
11.26 m2 Total
26.76 m2 Total for all
2. BLOCK WORK
2.01 Class B, 200mm thick HCB wall
4 3.10
3.20
39.68 m2 all area of the wall
1 0.90
2.50
2.25 m2 area of door
1 1.20
1.50
1.80 m2 area of window
35.63 m2 Total Area of Wall (A)
6.Roofing Work
Roof cover in G28 CIS
4.40
4.40
19.36 m2
7. Plastering work
3.10
8 3.20
79.36 m2
2 0.90
2.50
4.50 m2 area of door
2 1.20
1.50
3.60 m2 area of window
71.26 m2 Total Area of Wall (A)
9.3.3 cement screeding m2 10.00 10.40 10.40 320.00 3200.00 3,328.00 3,328.00
Provide,cut,bend and fix in position 10mm reinforced
steel bar for foundation @200mm c/c in both direction
for top and bottom mesh.price shall include tying wires - 0.00 - -
9.4
9.4.1 Diameter 10mm ribbed bar kg 4.80 87.58 87.58 120.00 576.00 10,509.00 10,509.00
supply and install the required pipes,fittings,gate,water
han,water meter and other fitttingss as per the drawing IS 1.00 0.75 0.75 9500.00 9500.00 7,125.00 7,125.00
9.4.2
9.5 Fencing and Gate Work - 0.00 - -
Excavation for foundation of posts for fencing, dimensions
50 x 50 x 70cm including disposal of surplus material m3 2.00 - 230.00 460.00 - -
9.5.1
Supply & fix mesh wire up to a height not less than 2.50m,
fixed to the concrete poles by caped including all m 24.00 - 1200.00 28800.00 - -
9.5.2 necessary fixing materials.
Supply & installation precasted concrete poles 13X13cm
Pcs 8.00 - 1150.00 9200.00 - -
9.5.3 for fencing, length 3m fixed at 2m interval
9.5.4 Cyclopean concrete work for foundation of fencing Poles m3 2.00 - 3989.00 7978.00 - -
Supply and fix (2x2m)double leaf grilled size gate made of
nr 1.00 - 1615.00 1615.00 - -
9.5.5 60x60mm RHS frame of thickness 10mm
9.6 Drainage system and water disposal - 0.00 - -
Supply & installation of mesh wire of height not less than
2.20meter ,tied to the posts by tying wires, including all m2 46.64 - 650.00 30316.00 - -
9.6.1 necessary fixing materials
Stone pitched trapizoidal drainage ditch pointed with
mortar (1:3) (top width=40cm,bottom width =20cm and m 24.80 - 453.00 11234.40 - -
9.6.2 depth=30cm)around the public tap as per the drawing
Supply and instalaltion of HDPE OD 75 PN10 pipe for
connections to water points from the new pipe m 50.00 - 467.00 23350.00 - -
9.7
Total for Bill No 9 244,649.40 - 120,867.24 120,867.24
1
7.60 m3
Concrete work
lean concrete over hard core mix (1:3:6) under slab
L= 4.5 m W= 4m
3.80
4.00
15.20 m2
15 mm thick Mass concrete mix (1:3:6) under slab
3.80 L= 4.5 m W= 4m
4.00
0.15
2.28 m3
87.58 kg Diameter 10mm ribbed bar for slab mass concrete
pointing work
3.38 L= 1,3 X 1.3 X 2 = 3.38 W= 2X 1.3X2 =5
5.20
17.58 m2
cement screening
L= 4.5 m W= 4m
1.30
4 2.00
10.40 m2
13.1.2 Excavation for stone masonry foundation; 0.6m width and 1.0 m3 20.45 18.84 18.84 540 11,043.00 10,173.60 10,173.60
m depth
13.1.3 Backfill to depth of not less than 450mm m3 7.1575 7.54 7.54 720 5,153.40 5,425.92 5,425.92
13.1.4 Cart away and deposit excavated surplus material to a distance m3 41.037 38.84 38.84 320 13,131.84 12,428.80 12,428.80
not exceeding 1km.
13.1.5 Supply, fill and compact layer by layer of selected material m3 24.31575 17.52 17.52 720 17,507.34 12,614.40 12,614.40
13.6.7 Supply and fix 25 x 250 mm fascia board to purlin m 35.4 148.00 148.00 570 20,178.00 84,360.00 84,360.00
13.6.8 Supply and fix 40 x 50 mm ceiling battons m 313 - 150 46,950.00 - -
13.6.9 Supply and fix chipwod ceiling m2 41.035 - 1200 49,242.00 - -
13.6.10 Supply and fix ribbed sheet m2
21.06 - 120 2,527.20 - -
Supply and fix metal door size 900 x 2200 mm price includes
13.6.11 4mm thick glass and three layers of synthetic paint to the No 2 - 28000 56,000.00 - -
frames
Supply and fix wooden door size 900 x 2200 mm price
13.6.12 includes scynthetic paintings No 1 - 27000 27,000.00 - -
Supply and fix metal door size 800 x 2200 mm price includes
13.6.13 4mm thick glass and three layers of synthetic paint to the No 2 - 28000 56,000.00 - -
frames
Supply and fix metal door size 700 x 2100 mm price includes
13.6.13 4mm thick glass and three layers of synthetic paint to the No 1 - 26000 26,000.00 - -
frames
Supply and fix metal window size 1000 x 1000 mm price
13.6.15 includes 4mm thick glass and three layers of synthetic paint to No 1 - 21000 21,000.00 - -
the frames
Supply and fix metal window size 1200 x 1400 mm price
13.6.16 includes 4mm thick glass and three layers of synthetic paint to No 2 - 24000 48,000.00 - -
the frames
Supply and fix metal window size 750 x 500 mm price
13.6.17 includes 4mm thick glass and three layers of synthetic paint to No 1 - 17500 17,500.00 - -
the frames
13.7 Finishing - - -
Finishing work shall include all surface pre-cleaning,
polishing and cleaning at the end of finishing - - -
13.7.6 Apply 3 coats of plastic paint to internal walls m2 168.185 - 120 20,182.20 - -
13.8 Electrical Installation - - -
Pvc Pipe - - -
PVC conduit of 16mm diameter including junction boxes with
13.8.13 covers and insulating screw cap connectors. M 40 - 100 4,000.00 - -
13.9.3 Cart away of surplus excavated materials to a distance of 1- m3 23.49 - 320 7,517.44 - -
2kms
13.9.4 Supply and compact approved backfill selected material m3 7.56 - 720 5,443.20 - -
13.9.5 Basaltic or equivalent stone masonry wall bedded in cement m3 17.1 - 3800 64,980.00 - -
mortar 1:3
13.9.6 Lean concrete in C-15 under foundation slab. m2 7.56 - 520 3,931.20 - -
13.9.7 Reinforced concrete slab (C-25) as per the drawing m3 2.56 - 7500 19,200.00 - -
13.9.8 Provide, cut and fix in position zigba formwork including m2 9.84 - 520 5,116.80 - -
soffit and scaffolding for cover slab.
13.9.9 Supply and construct H.C.B baffle partition wall m2 4.2 - 650 2,730.00 - -
13.9.10 Plastering of internal wall and partition wall in cement mortar m2 8.4 - 303 2,545.20 - -
1:3
13.9.11 Supply and install PVC vent pipe with cover cap as per the Ls 2 - 350 700.00 - -
drawing
13.9.12 Supply and install drainage PVC pipe DN100 m 6 - 1200 7,200.00 - -
13.9.13 Supply and install reinforced precast concrete cover to septic No. 2 - 9500 19,000.00 - -
tank.
Provide, cut, bend and fix in position reinforced steel bar. All
according to structural drawing. Price shall include tying - - -
wires
13.9.13 Diameter 8 mm plain bar kg 78.42 - 135 10,586.70 - -
13.10 Construction of Soakaway Pit - - - -
13.10.1 Site clearing to depth of 20cm m2 23.04 - 40 921.60 - -
13.10.2 Excavation of soil to depth of 2.5mts. In ordinary soil m3 17.5 - 540 9,450.00 - -
13.10.3 Cart away of surplus excavated materials to a distance of 1- m3 22.108 - 320 7,074.56 - -
2kms
13.10.4 Supply and compact approved backfill selected material m3 7 - 720 5,040.00 - -
13.10.5 Basaltic or equivalent stone masonry wall bedded in cement m3 16.8 - 3800 63,840.00 - -
mortar 1:3
13.10.6 Lean concrete in C-15 under masonry wall. m2 6.72 - 720 4,838.40 - -
13.10.7 Reinforced concrete slab (C-25) as per the drawing price m3 1.18 - 7500 8,850.00 - -
includes dia, 8 bar with a spacing of 200 mesh
13.10.8 Provide, cut and fix in position zigba formwork including m 2
7.84 - 520 4,076.80 - -
soffit and scaffolding for cover slab.
13.10.9 Supply and install PVC vent pipe with cover cap Ls 1 - 700 700.00 - -
13.10.10 Supply and install reinforced precast concrete cover to septic No. 1 - 9500 9,500.00 - -
tank.
13.10.11 Supply and put in place coarse gravel, fine gravel and sand Ls 1 - 7500 7,500.00 - -
depth as per the drawing
Total to be carried to Summary 2,589,991.77 - 1,537,662.33 1,537,662.33
Project:
TOC Moyale Water Supply Construction project
Client: SRS Irrigation and Development Bureau
Consultant: SRS, Study, Design & Supervistion Works Enterprise
Contractor: Iqra General Construction Company
TAKE OFF SHEET FOR OPERATOR DWELLING AND SERVICE QUARTER
ITEM L*W*H QTY
1 10.00
10.00
100.00 m2
1 31.40
1.00
0.60
18.84 m3
1 31.40
0.60
0.40
7.54 m3
38.84 m3
1 8.00
7.30
0.30
17.52 m3
1 8.00
7.20
57.60 m2
8.20
2 1.00
0.50
8.20 m3
2 7.50
1.00
0.50
7.50 m3
15.70 m3
1 8.00
7.20
57.60 m2
2 8.20
0.30
0.30
1.48 m3
2 7.50
0.30
0.30
1.35 m3
2.83 m3
2 8.20
0.20
0.20
0.66 m3
2 7.50
0.20
0.20
0.60 m3
1.26 m3
4.08 m3
3.20
9 0.20
0.20
1.15 m3
62.80
0.32
20.10 m3
141.30
0.21
29.67 m3
49.77 m3
9 12.80
0.21
24.19 m2
1 8.20
7.20
0.15
8.86 m3
2 8.20
3.20
52.48 m2
2 7.50
3.20
48.00 m2
1 8.20
3.20
26.24 m2
126.72 m2
2 1.50
2.00
7.50 m2
2 2.98
0.90
5.36 m2
12.86 m2
113.86 m2
10.00
9.00
90.00 m2
10 10.00 100.00 ml
9 8.50 76.50 ml
176.50
8 10.00 80.00
8 8.50 68.00
148.00
For Contractor For Consultant For Client
Name__________ Name__________ Name_________
Sign.__________ Sign.__________ Sign.___________
Date________ Date________ Date_____________
Construction project
elopment Bureau
n & Supervistion Works Enterprise
ruction Company
ET FOR OPERATOR DWELLING AND SERVICE QUARTER
DESCREPTION
A. SUB - STRUCTURE
1.Excavation & earthwork
1.1 site clearing to remove the top soil
L= 9m W= 9m
Total
1.2 Excavation for stone masonry foundation; 0.6m width and 1.0 m
depth
L= 8.2 m W = 7.5 m D= 0.6m
Total
1.3 Backfill to depth of not less than 450mm
L= 8.2 m W = 7.5 m D= 0.3 m
Total
total
MASONRY WORK
Bellow NGL
total
2. Concrerte Work
2.1 Provide 50mm thick lean concrete with mix ratio (1:3:6)
total
b) top beam
total
Total of grade beam and top tie beam
1.2 In Elevation Column
Total
Formwork
a) to grade beam
Parimeter= ( 8.2x 2 x 2) + (7.5 x2 x2 ) = 62.8
Total
Formwork for top tim beam
Parimeter= ( 8.2x 3 x 3) + (7.5 x3 x3 ) = 141.3
total
w1
D1
total window nad door dedaction
6.Roofing Work
Roof cover in G28 CIS
5*7 zigba
Facia board
For Consultant For Client
Name__________ Name_________
Sign.__________ Sign.___________
Date________ Date_____________
radius (r)= 4.05 m D = 16.4 m2 Π=3.142 t= 0.35m
3.14
7.1
#REF! 2 6.6
#REF!
3.14
8.1
0.1
2.5434
7.4
4 29.6
5.4
4
21.6
51.2
7.1
#REF! 2 6.6
#REF!
3.14
TOC MOYALE WATER SUPPLY PROJECT
BILL No.15: ACCESS ROAD (3km) TO 1000 m3
15 EARTH WORK For 3km (ACCESS ROAD TO 1000 m3)
Contract Prev Exec Curr Exec Upto Date Contract Prev Exec Curr Exec Upto Date Exec
S/N Description Unit Rate
Qtty Qtty Qtty Exec Qtty Amount Amount Amount Amount
15.1 CLEARING AND GRUBBING
Clearing, grubbing and disposing of excavated
materials along both sides road alignment
15.1.1 ha 0.75 1.56 1.56 55,000.00 41,250.00 85,984.25 85,984.25
including excavtion not exceeding 200mm as
directed
m2
10.1.1 Site clearing up to adepth of 20cm to remove top vegitative soil 100 40.00 4,000.00
Excavation work up to a depth of 50 cm to reduce level for m3
10.1.2 placing hard core 150 550.00 82,500.00
10.1.3 Excavation in soft rock formation m3 1 850.00 850.00
10.1.4 Ditto but in hard rock farmation m3 0.8 1100.00 880.00
cart away surplus excavated material to a distance not
10.1.5 m3 100 65.00
exceeding 1kmfrom the site 6,500.00
Filling and spread under hard core with selected site material &
compact in layers not exceeding to a thickness of 15cm as per
10.1.6 the recommendation of the supervising Engineer m3 30 640.00 19,200.00
10.2 Standard Masonary works including finishing works -
Construction of Camel, cows, sheeps and goats cattle troughs as
10.3 No. 3 18,000.00
per the drawings 54,000.00
Supply and installation of all pipe works as per the standard
10.3.1 ls 1 19,000.00
drawings 19,000.00
Total for Bill No 10 186,930.00
Grand Total of 5 Cattle Troughs 934,650.00
TOC
BILL No.11: FENCEING WORK
Item No. Item Description Unit Quantity Unit Rate Total Amount
11.1 AT TWO BORE HOLES (Birr) (Birr)
Excavation for foundation of posts for fencing, dimensions 50 x 50 x 70cm
11.1.1 including disposal of surplus material and foundation for the gate having area m3 9.00 340.00 3,060.00
of 60x60x100cm.
11.1.2 Cyclopean concrete work for foundation of fencing Poles m3 8.60 4,300.00 36,980.00
Supply & installation precasted concrete poles 13X13cm for fencing, length
11.1.3 3m fixed at 2m interval Pcs 40.00 2,400.00 96,000.00
11.1.4 Supply & fix mesh wire up to a height not less than 2.50m, fixed to the concret m 100.00 400.00 40,000.00
Construction of concrete columns to support the gate having area of 60x60cm
11.1.5 having a total height fo 4m with it foundation under the surface having a depth No. 2.00 13,000.00 26,000.00
of 1m.
11.1.6 Supply & fix metal gate with its locks -
11.1.7 a/ 2x2.5m No. 1.00 21,500.00 21,500.00
Sub-Total 223,540.00
Sub-Total for two - 447,080.00
11.2 FENCEING WORK AT CONTROLE STATION
Unit Rate Total Amount
Item No. Item Description Unit Quantity (Birr) (Birr)
Excavation for foundation of posts for fencing, dimensions 50 x 50 x 70cm
11.2.1 including disposal of surplus material and foundation for the gate having area m3 28.22 340.00 9,594.80
of 60x60x100cm.
11.2.2 Cyclopean concrete work for foundation of fencing Poles m3 21.96 2,300.00 50,508.00
Supply & installation precasted concrete poles 13X13cm for fencing, length
11.2.3 3m fixed at 2m interval Pcs 96.00 13,500.00 1,296,000.00
Supply & fix mesh wire up to a height not less than 2.50m, fixed to the
11.2.4 concrete poles by caped including all necessary fixing materials. m 196.00 1,800.00 352,800.00
Construction of concrete columns to support the gate having area of 60x60cm
11.2.5 having a total height fo 4m with it foundation under the surface having a depth No. 2.00 52,300.00 104,600.00
of 1m.
11.2.6 Supply & fix metal gate with its locks -
11.2.6.1 a/ 2x2.5m No. 1.00 19,400.00 19,400.00
11.2.6.2 b/ 1x2m No. 1.00 19,000.00 19,000.00
Sub-Total 1,851,902.80
TOTAL CARRIED TO SUMMARY 1,851,902.80
13.1.2 GS Flange 8" to be welded to the 8" steel casing No. 1 165,000.00 165,000.00
GS Wellhead with a 8" flange, DN100 short piece with a DN100
PN25 threaded socket welded on the inside & DN100 short
13.1.3 piece with a DN100 PN25 flange welded on the outside & all No. 1 80,000.00 80,000.00
accessories as shown in the drawing & as per the specification
13.2.2 GS Flange 8" to be welded to the 8" steel casing No. 1 165,000.00 165,000.00
13.2.3 GS Wellhead with a 8" flange, DN80 short piece with a DN80
PN25 threaded socket welded on the inside & DN80 short piece
with a DN80 PN25 flange welded on the outside & all No. 1 80,000.00 80,000.00
accessories as shown in the drawing & as per the specification
13.2.4 GS riser pipe, heavy grade, threaded DN80, PN40 L = 3000mm 35,691.00
No. 10 356,910.00
c/w socket
13.2.5 Double flanged GS bend DN80 PN25 - 90° No. 3 21,250.00 63,750.00
13.2.6 Single flanged GS pipe DN80, PN25 L = 4000mm No. 1 35,963.00 35,963.00
13.2.7 dismantling piece DN80 PN25 No. 2 19,723.00 39,446.00
13.2.8 14,711.00
Double flanged GS pipe with puddle DN80, PN25,L = 500mm No. 1 14,711.00
13.2.9 21,250.00
Double flanged GS pipe with puddle DN80, PN25,L = 1200mm No. 1 21,250.00
13.2.1 17,850.00
Double flanged GS pipe with puddle DN80, PN25,L = 1000mm No. 1 17,850.00
13.2.11 Double flanged GS pipe DN80, PN25 L = 1000mm with two 1/2" 17,850.00
female sockets welded for the attachment of pressure gauge No. 1 17,850.00
and pressure switch
13.2.12 Double flanged GS pipe DN80, PN25 L = 1000mm, with one 17,980.00
No. 1 17,980.00
DN 3/4" welded socket
13.2.13 Single flanged GS pipe DN80, PN25 L = 2000mm No. 1 24,480.00 24,480.00
13.2.14 Double flanged GS tee DN80/50/80 PN25 - 90° No. 2 22,335.00 44,670.00
13.2.15 Double Air relief valve DN80, PN25, with isolating gate valve No. 1 24,990.00 24,990.00
13.2.16 Double flanged Dismantling piece DN80, PN25 No. 1 19,720.00 19,720.00
13.2.17 Pressure gauge, glycerin filled, 100mm dia., 1/2” male 12,240.00
No. 1 12,240.00
connection, 0-15 bar with isolating cock
13.2.18 3/4" pipe, elbows, nipples, unions and faucet for sample water 19,635.00
Sum 1 19,635.00
tapping & compound supply
13.2.19 26,299.00
Double Flanged woltman water meter, turbine type, DN80, PN25 No. 1 26,299.00
13.2.2 Double flanged Non return valve DN80 PN25- spring-loaded 19,720.00
No. 1 19,720.00
type
13.2.21 Double Flanged Gate valve DN80 PN25 No. 1 14,535.00 14,535.00
13.2.22 Double Flanged Gate valve DN80 PN25 No. 1 15,700.00 15,700.00
13.2.23 single flanged GS elbow DN80 PN25, 90° No. 1 14,000.00 14,000.00
13.2.24 double flanged reducer, GS, DN80/150 PN25 No. 1 23,800.00 23,800.00
13.2.25 flanged Socket piece, PVC DN150 PN25 No. 1 19,728.00 19,728.00
13.2.26 Pipe support with pipe clamp, foot plate, anchor bolts etc. Sum 1 30,600.00 30,600.00
13.2.27 Necessary pipes, fittings bolts, nuts, gaskets etc. required to 840.00
complete installation & to connect to the discharge (collector) Sum 1 840.00
pipe
Sub-Total .13-2 4,841,667.0
13.3 BH'S ELECTRICAL EQUIPMENTS @ El-gof
Item Unit Rate Total Amount
Description of works Unit Qty
(Birr) (Birr)
13.3.1 PART1g-SUPPLY OF PLANT, BOREHOLES ELECTRICAL
Borehole Electrical Equipment
Main Switchgear complete, consisting of generating set manual
control switch panel, and distribution panel, including all
13.3.1 protection, metering relays, controls, surge- diverters, glands, No. 1 397,500.00 397,500.00
contactors, starter panels etc. as specified at MBH1.
13.4.12 Cable tray, cable trunking, cable supports etc. as required Sum 1 100,800.00 100,800.00
DN25 Service water supply system, connected to water pump, 179,200.00
13.4.13 to feed the solution preparation tanks including all valves & Sum 1 179,200.00
fittings
Solution pipe system, made of DN20 uPVC pressure pipes & 112,000.00
13.4.14 fittings, connection from the preparation tank to the injection Sum 1 112,000.00
point at the top of the reservoir
swiveling type gantry crane 1/4 ton to be installed on top of the 134,400.00
13.4.15 Sum 1 134,400.00
reservoir
Sub-Total .13-4 2,217,600.00
Total Amount
13.5 PART 7-BH'S POWER PLANTS @ El-gof
(Birr)
Item Unit Rate
Description of works Unit Qty
(Birr)
13.5.1 PART 7-SUPPLY OF PLANT, POWER PLANT
Power Plant
Diesel generator set, PRIME RATING, as per the technical
specification, engine & alternator pre-installed on a common
rigid frame, switchgear including manual changeover switch
panel, day tank incorporated into the frame, exhaust piping
system and all accessories required for installation, alternator:
13.5.3 No. 1 6,500,000.00 6,500,000.00
150 KVA, 3 phase, 400 V, 1500 RPM (woking environment =
45 degree centigrade at an average elevation of 888 masl).and
with all fast moving spare parts, to be installed at MBH3.
49,500.00
13.5.7 Hot air discharge louver for wall installation with all accessories No. 2 99,000.00
Ducting & framework between hot air discharge wall outdoor 46,500.00
13.5.8 louver and engine radiator with all accessories required for No. 2 93,000.00
installation
90,750.00
13.5.9 Storage fuel storage tank, 5000 ltr capacity with all accessories No. 2 181,500.00
Fuel pipe work consisting of DN1 1/2" black mallable iron pipes, 19,500.00
13.5.1 No. 2 39,000.00
fittings & valves
Fuel hand pump suitable for standard oil barrels with three 16,950.00
13.5.11 No. 2 33,900.00
meters long flexible hose 1"
Sub-Total .13-5 11,446,400.00
TOTAL CARRIED TO SUMMARY 26,870,846.00
BILL
TOC
5 CONSTRUCTION OF 500 m3 BOOSTER STATION
ITEM DESCRIPTION UNIT QNTY UNIT PRICE TOTAL
Birr Birr
BILL 5: CONSTRUCTION OF 500 m3 RESERVOIR
5.1 EARTH WORK
Site Clr m2 60.00 40.00 2,400.00
5.1.1 Bulk excavation in normal soil to a depth not exceeding 1m m3 153.94 540.00 83,126.54
5.1.2 Ditto but in soft rock formation m3 30.79 450.00 13,854.42
5.1.3 Ditto but in hard rock formation m3 15.39 1100.00 16,933.18
5.1.4 Cart away all excavated material, deposit to appropriate distance not exceeding 1 km m3 200.12 320.00 64,038.22
5.1.5 Provide and fill with suitable selected granular material not exceeding 50cm m3 76.97 720.00 55,417.69
5.1.6 Provide and fill hard core with hard basaltic or equivalent stone, well compacted and blinded with m2 535.00
crushed stone to a finished thickness of 25 cm under the reservoir and valve chamber 132.73
71,011.77
5.2 CONCRETE WORK -
5.2.1 50mm thick lean concrete C-10 under the reservoir base slab and valve chamber m2 132.73 230.00 30,528.43
5.2.3 Reinforced concrete type C-30 filled into form work and vibrated around reinforced bar
-
5.2.3.1 Base slab m3 46.84 7500.00 351,302.26
5.2.3.2 Concrete wall m3 56.80 7500.00 426,023.53
5.2.3.3 Concrete column m3 1.11 7500.00 8,340.85
5.2.3.5 Top slab m3 66.37 7500.00 497,746.09
5.2.2.5 Valve Box m3 14.48 7500.00 108,624.75
5.2.4 Provide and fix formwork to: -
5.2.4.1 Base slab m2 14.29 525.00 7,504.48
5.2.4.2 Wall m2 378.69 525.00 198,810.98
5.2.5 Column m2 7.70 525.00 4,040.87
5.2.4.4 Top slab m2 9.82 525.00 5,154.18
5.2.4.5 Valve Chamber m2 0.06 525.00 33.60
5.2.5 Provide, cut, bend and fix in position reinforced steel bar. All according to structural drawing.
Price should include tying wires -
5.2.5.1 Diameter 8 mm plain bar kg 11.49 135.00 1,551.15
5.2.5.2 Diameter 10 mm deformed bar kg 5,351.25 135.00 722,418.75
5.2.5.3 Diameter 12 mm deformed bar kg 9,918.05 135.00 1,338,936.75
5.2.5.4 Diameter 20 mm deformed bar kg 117.53 135.00 15,866.55
5.3 ACCESSORIES AND FINISHING -
5.3.1 Provide and apply 50mm cement screed to the reservoir floor and roof slab m2 245.44 290 71,176.71
5.3.2 40cm thick masonry wall (1:3) for valve chamber house m2 30.00 320 9,600.00
5.3.3 Stone Pavement around the reservoir embedded with mortar (1:4) m2 19.43 290 5,634.92
5.3.4 300mm dia half ditch concrete drainage around the stone pavement embedded with mortar (1:4) 850.00
m 43.98
37,384.95
5.3.5 Provide and apply 3 coats of plaster to internal walls, columns and to embedded part of external
wall surface m2 386.38 303.00
117,074.50
5.3.6 Rendering external wall m2 193.96 59.00 11,443.75
5.3.7 Provided and install access internal and external ladder constructed out of 1 1/2" dia GS pipe and
hooked to the wall as per the drawing; including safety cages LS 2.00 21,300
42,600.00
5.3.8 Provide and install water stops made of natural or synthetic rubber or elastometric plastic 650
m 81.37
compound with basic risen polyvinyl chloride (PVC) 52,888.71
5.3.9 Provide and fix 6 mm sheet metal access cover with latch and lock for valve chamber and reservoir No 3200
2
6,400.00
5.3.10 Provide and apply two coats of bituminous asphalt over the plastered surface of the embedded part
of the reservoir m2 40.68 950.00
38,649.44
5.3.11 1201
m2 40.68
Provide and place single brick layer cover to protect the asphalt coat from the backfill material 48,861.03
5.3.12 Metal doors, size.1.50 x 2.10m Pcs 1.00 10080 10,080.00
5.4 PIPES, VALVES AND FITTINGS -
5.4.1 Installation of K9 DCI inlet pipes and fittings and valves of PN10 with all required accessories,
rubber sealing flat gaskets, bolts, nuts with washers, as per the specifications
-
5.4.1.1 DN 225 DCI flanged bell mouth No 1 6200 6,200.00
5.4.1.2 DN 225 DCI 90 deg double flanged bend No 2 7250 14,500.00
5.4.1.3 DN 225 DCI double flanged pipe, L = 5.0 meters No 1 40200 40,200.00
5.4.1.4 DN 225 DCI double flanged pipe, L = 500 mm No 1 40200 40,200.00
5.4.1.5 DN 225 DCI duckfoot 90 deg double flanged bend No 1 14060 14,060.00
5.4.1.6 DN 225 flanged gate valve No 1 21400 21,400.00
5.4.1.7 DN 225 dismantling joint No 1 13050 13,050.00
5.4.1.8 DN 225 DCI double flanged anchoring pipe with single puddle flange, L = 1.0 meters, puddled at 8500
the centre No
2 17,000.00
5.4.1.9 DN 225 flange adopter No 1 6200 6,200.00
5.4.1.10 DN 225 float valve No 1 8250 8,250.00
5.4.1.11 Pipe support with pipe clamp, wall bracket, foot plate and anchor bolts LS 1 7500 7,500.00
5.4.2 Installation of K9 DCI outlet pipes and fittings and valves of PN10 with all requred accessories,
rubber sealing flat gaskets, bolts, nuts with washers as per the spicifcations -
5.4.2.1 DN 225 flanged suction strainer No 1 20,100.0 20,100.00
5.4.2.2 DN 225 DCI 90 deg double flanged bend No 1 14,050.0 14,050.00
5.4.2.3 DN 225 DCI double flanged anchoring pipe with single puddle flange, L = 0.6 meters, puddled at
the centre No 8,500.0
2 17,000.00
5.4.2.4 DN 225 DCI double flange pipe, L= 250 mm No 2 8,500.0 17,000.00
5.4.2.5 DN 225 double flanged gate valve No 1 21,500.0 21,500.00
5.4.2.6 DN 225 flanged dismantling piece No 1 16,000.0 16,000.00
5.4.2.7 DN 225 flanged water meter No 1 15,000.0 15,000.00
5.4.2.8 DN 225 flanged adopter No 1 6,150.0 6,150.00
5.4.2.9 Pipe support with pipe clamp, wall bracket, foot plate and anchor bolts LS -
5.5 Installation of K9 DCI over flow and drainage pipes and fittings and valves of PN10 with all
requred accessories, rubber sealing flat gaskets, bolts, nuts with washers as per the specifications
-
5.5.1 DN 225 DCI flanged bell mouth No 2 12,400.0 24,800.00
5.5.2 DN 225 DCI double flanged 90 deg bend No 3 14,050.0 42,150.00
5.5.3 DN 225 DCI double flanged pipe, L= 1.0m No 2 16,100.0 32,200.00
5.5.4 DN 225 DCI double flanged anchoring pipe with single puddle flange, L = 1.0 meters, puddled at
the centre No 8,600.0
1 8,600.00
5.5.5 DN 225 DCI double flanged pipe, L= 50m No 1 644,000.0 644,000.00
5.5.6 DN 225 all flanged tee No 1 8,500.0 8,500.00
5.5.7 DN 225 flanged gate valve No 1 14,500.0 14,500.00
5.5.8 DN 225 flanged dismantling piece No 1 14,000.0 14,000.00
5.5.9 DN 225 flanged spigot piece No 1 8,100.0 8,100.00
5.5.10 Pipe support with pipe clamp, wall bracket, foot plate and anchor bolts LS 1 7500 7,500.00
5.4.4 Supply and install level indicator pcs 1 15,000.00 15,000.00
5.4.5 Supply and install DN 50 ventillation pipe with dome, L =1.0 meters pcs 2 650.00 1,300.00
Total of Bill 5. Construction of 500m3 reservoir 5,611,469.06
BILL
TOC
4 CONSTRUCTION OF 500 m3 RESERVOIR
ITEM DESCRIPTION UNIT QNTY UNIT PRICE TOTAL
Birr Birr
BILL 4: CONSTRUCTION OF 500 m3 RESERVOIR
4.1 EARTH WORK
Site Clr m2 60.00 40.00 2,400.00
4.1.1 Bulk excavation in normal soil to a depth not exceeding 1m m3 153.94 800.00 123,150.43
4.1.2 Ditto but in soft rock formation m3 30.79 950.00 29,248.23
4.1.3 Ditto but in hard rock formation m3 15.39 1100.00 16,933.18
4.1.4 Cart away all excavated material, deposit to appropriate distance not exceeding 1 km m3 200.12 650.00 130,077.64
4.1.5 Provide and fill with suitable selected granular material not exceeding 50cm m3 76.97 720.00 55,417.69
4.1.6 Provide and fill hard core with hard basaltic or equivalent stone, well compacted and blinded with m2 550.00
crushed stone to a finished thickness of 25 cm under the reservoir and valve chamber 132.73
73,002.76
4.2 CONCRETE WORK -
4.2.1 50mm thick lean concrete C-10 under the reservoir base slab and valve chamber m2 132.73 280.00 37,165.04
4.2.3 Reinforced concrete type C-30 filled into form work and vibrated around reinforced bar
-
4.2.3.1 Base slab m3 46.84 7500.00 351,302.26
4.2.3.2 Concrete wall m3 56.80 7500.00 426,023.53
4.2.3.3 Concrete column m3 1.11 7500.00 8,340.85
4.2.3.4 Top slab m3 66.37 7500.00 497,746.09
4.2.2.5 Valve Box m3 14.48 7500.00 108,624.75
4.2.4 Provide and fix formwork to: -
4.2.4.1 Base slab m2 14.29 900 12,864.82
4.2.4.2 Wall m2 378.69 800 302,950.06
4.2.4 Column m2 7.70 530 4,079.36
4.2.4.4 Top slab m2 9.82 530 5,203.26
4.2.4.5 Valve Chamber m2 0.06 530 33.92
4.2.5 Provide, cut, bend and fix in position reinforced steel bar. All according to structural drawing.
Price should include tying wires -
4.2.5.1 Diameter 8 mm plain bar kg 11.49 135.00 1,551.15
4.2.5.2 Diameter 10 mm deformed bar kg 5,351.25 135.00 722,418.75
4.2.5.3 Diameter 12 mm deformed bar kg 9,918.05 135.00 1,338,936.75
4.2.5.4 Diameter 20 mm deformed bar kg 117.53 135.00 15,866.55
4.3 ACCESSORIES AND FINISHING -
4.3.1 Provide and apply 50mm cement screed to the reservoir floor and roof slab m2 245.44 560 137,444.68
4.3.2 40cm thick masonry wall (1:3) for valve chamber house m2 30.00 460 13,800.00
4.3.3 Stone Pavement around the reservoir embedded with mortar (1:4) m2 19.43 400 7,772.30
4.3.4 300mm dia half ditch concrete drainage around the stone pavement embedded with mortar (1:4) 740.00
m 43.98
32,546.90
4.3.5 Provide and apply 3 coats of plaster to internal walls, columns and to embedded part of external
wall surface m2 386.38 240.00
92,732.28
4.3.6 Rendering external wall m2 193.96 326.00 63,231.59
4.3.7 Provided and install access internal and external ladder constructed out of 1 1/2" dia GS pipe and
hooked to the wall as per the drawing; including safety cages LS 2.00 16,000
32,000.00
4.3.8 Provide and install water stops made of natural or synthetic rubber or elastometric plastic 450
m 81.37
compound with basic risen polyvinyl chloride (PVC) 36,615.26
4.3.9 Provide and fix 6 mm sheet metal access cover with latch and lock for valve chamber and reservoir No 1500
2
3,000.00
4.3.10 Provide and apply two coats of bituminous asphalt over the plastered surface of the embedded part
of the reservoir m2 40.68 580.00
23,596.50
4.3.11 750
m2 40.68
Provide and place single brick layer cover to protect the asphalt coat from the backfill material 30,512.72
4.3.12 Metal doors, size.1.50 x 2.10m Pcs 1.00 11000 11,000.00
4.4 PIPES, VALVES AND FITTINGS -
4.4.1 Installation of K9 DCI inlet pipes and fittings and valves of PN10 with all required accessories,
rubber sealing flat gaskets, bolts, nuts with washers, as per the specifications
-
4.4.1.1 DN 225 DCI flanged bell mouth No 3 14000 42,000.00
4.4.1.2 DN 225 DCI 90 deg double flanged bend No 6 12000 72,000.00
4.4.1.3 DN 225 DCI double flanged pipe, L = 5.0 meters No 3 22000 66,000.00
4.4.1.4 DN 225 DCI double flanged pipe, L = 500 mm No 3 25000 75,000.00
4.4.1.5 DN 225 DCI duckfoot 90 deg double flanged bend No 3 14060 42,180.00
4.4.1.6 DN 225 flanged gate valve No 3 28000 84,000.00
4.4.1.7 DN 225 dismantling joint No 3 56000 168,000.00
4.4.1.8 DN 225 DCI double flanged anchoring pipe with single puddle flange, L = 1.0 meters, puddled at 13500
the centre No 6
81,000.00
4.4.1.9 DN 225 flange adopter No 3 6200 18,600.00
4.4.1.10 DN 225 float valve No 3 8250 24,750.00
4.4.1.11 Pipe support with pipe clamp, wall bracket, foot plate and anchor bolts LS 3 7500 22,500.00
4.4.2 Installation of K9 DCI outlet pipes and fittings and valves of PN10 with all requred accessories,
rubber sealing flat gaskets, bolts, nuts with washers as per the spicifcations -
4.4.2.1 DN 225 flanged suction strainer No 3 20,100.0 60,300.00
4.4.2.2 DN 225 DCI 90 deg double flanged bend No 3 14,050.0 42,150.00
4.4.2.3 DN 225 DCI double flanged anchoring pipe with single puddle flange, L = 0.6 meters, puddled at
the centre No 6 8,500.0
51,000.00
4.4.2.4 DN 225 DCI double flange pipe, L= 250 mm No 6 8,500.0 51,000.00
4.4.2.5 DN 225 double flanged gate valve No 3 21,500.0 64,500.00
4.4.2.6 DN 225 flanged dismantling piece No 3 16,000.0 48,000.00
4.4.2.7 DN 225 flanged water meter No 3 15,000.0 45,000.00
4.4.2.8 DN 225 flanged adopter No 3 6,150.0 18,450.00
4.4.2.9 Pipe support with pipe clamp, wall bracket, foot plate and anchor bolts LS -
4.4 Installation of K9 DCI over flow and drainage pipes and fittings and valves of PN10 with all
requred accessories, rubber sealing flat gaskets, bolts, nuts with washers as per the specifications
-
4.4.1 DN 225 DCI flanged bell mouth No 6 12,400.0 74,400.00
4.4.2 DN 225 DCI double flanged 90 deg bend No 9 14,050.0 126,450.00
4.4.3 DN 225 DCI double flanged pipe, L= 1.0m No 3 16,100.0 48,300.00
4.4.4 DN 225 DCI double flanged anchoring pipe with single puddle flange, L = 1.0 meters, puddled at
the centre No 3 8,600.0
25,800.00
4.4.5 DN 225 DCI double flanged pipe, L= 40m No 3 108,000.0 324,000.00
4.4.6 DN 225 all flanged tee No 3 8,500.0 25,500.00
4.4.7 DN 225 flanged gate valve No 3 25,000.0 75,000.00
4.4.8 DN 225 flanged dismantling piece No 3 14,000.0 42,000.00
4.4.9 DN 225 flanged spigot piece No 3 8,100.0 24,300.00
4.4.10 Pipe support with pipe clamp, wall bracket, foot plate and anchor bolts LS 3 9000 27,000.00
4.4.4 Supply and install level indicator pcs 3 41,000.00 123,000.00
4.4.5 Supply and install DN 50 ventillation pipe with dome, L =1.0 meters pcs 6 8,000.00 48,000.00
Total of Bill 4. Construction of 500m3 reservoir 6,785,369.30
TOC
5-73
Unit Quantity Unit Rate Amount
Item No. Description
(Birr) (Birr)
B/F
6.1.4.3 F2 Finish to curved vertical forms to walls m2 166 530.00 87,980.00
6.1.4.4 F2 Finish -plane vertical forms to columns m 2
1060 530.00 561,800.00
6.1.4.5 F2 Finish to curved vertical forms to shaft
m2 26 530.00 13,780.00
6.1.4.6 F3 Finish -plane horizontal to soffit of suspended
slab m2 15 530.00 7,950.00
6.1.4.7 F3 Finish to curved vertical forms to walls m2 161 530.00 85,330.00
6.1.4.8 F3 Finish to curved vertical forms to shaft
m2 35 530.00 18,550.00
6.1.4.9 F2 Finish plane horizontal forms to 250 step
round the reservoir m2 12 530.00 6,360.00
6.1.5 Pipe Laying 0.00
6.1.6.1 Laying DN 225 mm DCI inlet pipe including
excavation and backfilling m 38 5,082.00 193,116.00
6.1.5.2 Laying DN 225 mm DCI outlet pipe including
excavation and backfilling m 32 5,082.00 162,624.00
6.1.5.3 Laying DN 200 mm DCI drain pipe including
excavation and backfilling m 40 5,082.00 203,280.00
6.1.6 Surface Finishing 0.00
6.1.6.1 U2 Finish to vertical walls to reservoir (including
for ribbed finish) m2 116 70.00 8,120.00
6.1.6.2 U2 finish to reservoir roof m2 15 70.00 1,050.00
6.1.6.3 U3 finish to reservoir floor slab m2 6 70.00 420.00
6.1.6.4 Waterproof sheeting of 500 gauge polythene to
upper surfaces inclined at an angle n.e. 30
degree to the horizontal; between floor slab and
blinding m2 111 1,400.00 155,400.00
6.1.6.5 2 layers bituminous ply on bituminous paint at
wall/roof slab interface (250mm wide) m 30 1,200.00 36,000.00
6.1.7 Pipe work 0.00
6.1.7.1 Install 200 nominal bore inlet pipe stack and
fittings as detailed LS 4,200.00 4,200.00
6.1.7.2 Install 200 nominal bore outlet pipe stack and
fittings as detailed LS 4,200.00 4,200.00
6.1.7.3 Install 200 nominal bore overflow pipe stack and
fittings as detailed LS 4,200.00 4,200.00
6.1.8 Miscellaneous work 0.00
6.1.8.1 Open grid flooring at upper platform level m2 3 680.00 2,040.00
6.1.8.2 Approved hinged manhole cover to fit
726x762mm opening (including for frame) nr 2 12,500.00 25,000.00
Carried forward 1,581,400.00
5-74
TOC Name of Project:-Construction of Moyale Supply Civil Works
7.1.4 Extra over for bulk excavation in soft rock m3 19.2 800.00 15,360.00
7.1.5 Cart away all excavated material, deposit to appropriate m3 33.60 540.00 18,144.00
distance not excedding 1 km
7.1.6 250 mm thick hard trachyte stone hard core m2 76.97 500.00 38,485.00
7.1.7 Provide and fill hard core with hard basaltic or m 3
132.73 1,800.00 238,914.00
equivalent stone, well compacted and blinded with
7.2 crushed
Concretestone
and masonary work
7.2.2 50 mm thick lean concrete with mix ratio (1:3:6) under m2 132.73 2,500.00 331,825.00
the reservoir base slab and valve chamber
7.2.3 Reinforced concrete type C-25 filled into form work and
vibrated around reinforcement bar mix ratio should be
1:2:3
7.2.4 In base slab m3 7.98 7,500.00 59,850.00
7.2.5 In concrete wall m3 7.98 7,500.00 59,850.00
7.2.6 In top slab m3 7.98 7,500.00 59,850.00
7.2.7 Valve box m3 14.48 7,500.00 108,600.00
7.2.8 Provide and fix formwork
7.2.9 In base slab m2 9.90 3,500.00 34,650.00
7.2.10 To wall m2 9.9 3,500.00 34,650.00
7.2.11 To top slab m2 9.90 3,500.00 34,650.00
total of sheet 1,046,748.00
7.30 Provide, cut, bend and fix in position reinforced steel
bar. All according to structural drawing. Price should
include tying wires.
7.3.1 Diameter 8 mm deformed bar kg 11.5 135.00 1,551.15
7.3.2 Diameter 10 mm deformed bar kg 900.0 135.00 121,500.00
7.4 Accesssories and finishing
7.4.1 Provide and install access internal and external ladder Ls 1.0 18,000.00 18,000.00
constructed out of 1 1/2'' dia GS pipe and hooked to the
wall as per the drawing; including safety cages
4.13 Install DN 225 DCI double flanged pipe L=5.0m No 3 35,500.00 106,500.00
4.14 Install DN 225 DCI double flanged pipe L=5.0 m No 2 35,500.00 71,000.00
4.15 Install DN 225 DCI 90o degree double flanged bend No 3 21,240.00 63,720.00