Eirene - Tower 6ABCD
Lift Installation - Activity Schedule - as on 24 July 2023
Tower 6A Tower 6B Tower 6C Tower 6D
Sl. No Description of Activity Remarks
L1 L2 L3 L4 L1 L2 L3 L4 L1 L2 L3 L4 L1 L2 L3 L4
1 Lift Pit water proofing
2 Scaffolding erection by Lift Vendor
3 Plump reading by Lift Vendor
4 Civil finishing & painting
5 Shaft Electrical Works
6 Template fixing & Plump dropping
7 Shaft Reading & Measurement
8 Marking, Drilling for Brackets
9 Bracket Fixing
10 Rail Hoisting
11 Rail alignment
12 Door frame fixing
13 Architrave works
14 LMR Works, Motor Installation
15 Control Panel & cabling within LMR
16 Door fixing after architrave works
17 Door alignment
18 Roping
19 Cabin frame fixing
20 Cabin sides, top & bottom panels
21 Scaffolding removal
22 Startup checks
23 Slow speed testing
24 Buffer fixing, top to bottom alignment
25 Pit screen guard installation
26 High speed testing
27 Quality & Safety checks
28 Maintenance Checks
29 Load Test
30 LOP & ARD Fixing & Testing
31 Final Testing
32 Handing Over with PWD license
T6B - L4 Chipping work in progress - shall be completed by 29 July 2023
T6A - L4 Civil finishing & chipping work in progress - Shall be completed by 05 Aug 2023
T6D - L2 Civil finishing work in progress - shall be completed by 26 July 2023
T6D - L4 Civil finishing & chipping work in progress - Shall be completed by 05 Aug 2023