KING ABDULLAH INTERNATIONAL GARDENS - PHASE # 3
INSPECTION & TEST PLAN ITP No :
TESTING and COMMISSIONING OF AIR HANDLING UNIT KAIG3‐ ITP‐GN‐M‐0012‐04
OWNER : ENGINEER: CONTRACTOR: DATE:
Riyadh Municipality Dar Alhandasah ZAID ALHUSSAIN 11‐Sep‐23
LEGEND: A = APPROVAL FOR SUBMITTAL; W = RFI FOR APPROVAL ; H = HOLD POINT NEED RFI AND HPR ; SR = SURVEILANCE / VISUAL INSPECTION W/OUT FRI ; T = TESTING
Inspection/Test requirements Method of verification
ITP
Test or Report / Verification Thir
Clause Description of Activity Reference document Sub ZAI DA REMARKS
Inspection Stage/ Frequency Verifying record Personnel (ZAID) d
No. Cont. D R
Performed Part
1.0 Sequence of work activities
1.1 Preparation
Document As per project specification Approved submital‐ RFI for installation to be
1.1.1 AHU MIR to be accepted For each area prepared Engr. PE / QC N/A SR SR N/A
review 15855 minimum Code B attached
Connection of chilled & hot
Visual
water piping and hockup to be
inspection/D As per project specs. Approved submital‐ RFI(MECH) for insulation
1.1.2 installed according to approved For each area prepared Engr. PE / QC SR w A N/A
ocument 15680&15996. minimum Code B after test accepted
shop drawings(also test to be
review
done and insulation )
Connection with duct works to Visual
be installed according to inspection/D As per project specs. Approved submital‐ RFI(MECH) for insulation
1.1.3 For each area prepared Engr. PE / QC SR w A N/A
approved shop drawings(also ocument 15890&15996. minimum Code B after test accepted
test to be done and insulation) review
Connection of drain piping and Visual
required trap to be installed inspection/D As per project specs. Approved submital‐
1.1.4 For each area prepared Engr. PE / QC SR T A N/A RFT(MECH)
according to approved shop ocument 15855&15996. minimum Code B
drawings(also test to be done) review
Visual
supports, hangers and brackets
inspection/D As per project specification Approved submital
1.1.5 refer to material approval and For each area prepared Engr. PE / QC N/A w A N/A
ocument 15511(mech) minimum code B
shop drawing approval
review
BMS works related to AHU Visual
according to approved shop inspection/D As per project specification Approved submital RFI(low current)as a part of
1.1.6 For each area prepared Engr. PE / QC N/A w A N/A
drawings&approved material ocument 15180(MECH) minimum code B BMS work
and specs review
Electric current works related to Visual
As per project specification
AHU according to approved inspection/D Approved submital RFI/ELEC.(as a part of
1.1.7 For each area prepared 15855(mech)/16120&1624 Engr. PE / QC N/A w A N/A
shop drawings&approved ocument minimum code B Electric work)
0(ELEC)
material review
2.0 Testing
Visual
inspection/D As per project specification Approved submital
2.1 Blancing and Test for Noise For each area prepared Engr. PE / QC SR T A N/A RFT/MECH.
ocument 15513 minimum code B
review
Visual RFT/MECH.(will be done
inspection/D As per project specification Approved submital
2.2 Commissioning For each area prepared Engr. PE / QC SR T A N/A through the part of BMS
ocument 15996 and 15855 minimum code B
review work station of AHUs
Note:Testing and Commissioning will be done by third party referring to project specs
Prepared By: Verified By: Approved By:
Signature & Date Signature & Date Signature & Date
1/1