0% found this document useful (0 votes)
51 views5 pages

Milton Hershey School Mechanical Redesign

The document summarizes the redesign of the mechanical systems for the Milton Hershey School New Supply Center. The goal of the redesign is to integrate building systems for total energy optimization. Key aspects of the redesign include replacing air handling units with DOAS systems and a parallel water source heat pump cooling system. The chilled water plant will be redesigned using direct fired absorption chiller-heaters that can provide both cooling and heating. Waste heat from walk-in freezers will be recovered and used to pre-heat domestic water and supplement the condenser water loop. Load profiles are presented to compare the existing and redesigned systems and illustrate how the redesigned integrated systems impact plant loads.

Uploaded by

shahas nahas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views5 pages

Milton Hershey School Mechanical Redesign

The document summarizes the redesign of the mechanical systems for the Milton Hershey School New Supply Center. The goal of the redesign is to integrate building systems for total energy optimization. Key aspects of the redesign include replacing air handling units with DOAS systems and a parallel water source heat pump cooling system. The chilled water plant will be redesigned using direct fired absorption chiller-heaters that can provide both cooling and heating. Waste heat from walk-in freezers will be recovered and used to pre-heat domestic water and supplement the condenser water loop. Load profiles are presented to compare the existing and redesigned systems and illustrate how the redesigned integrated systems impact plant loads.

Uploaded by

shahas nahas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Justin Bem Milton Hershey School Supply Center

Mechanical Option Hershey, Pennsylvania

alternatives are selected as the best, pay back periods longer than 2 to 4 years
will not justify their use in this application.

5.2 REDESIGN SUMMARY


Integration of as many building systems as possible for total building energy
optimization is the goal of the mechanical systems redesign for the Milton
Hershey School New Supply Center. The air side mechanical systems as well as
the chiller and boiler plants are all altered in the redesign. The walk-in freezers
condenser water loop is also used in an effort to integrate more building systems
as well as recover the waste heat. The mechanical redesign directly affects
other building systems that need attention as well. The structural system and
electrical service all will change due to the mechanical changes which paves
the way for a variety of cost analyses that will prove whether or not the redesign
beneficial.

The redesign of the air side mechanical system will comprise of the replacement
of ten VAV or CAV air handling units with dedicated outdoor air systems (DOAS).
The remaining four air handling units that are direct fired make-up air units that
serve the kitchen, bakery, and loading dock spaces will remain. Since the DOAS
can not meet the cooling load of the spaces they serve, a water source heat
pump system will act as the parallel cooling scheme.

The chilled water plant redesign will eliminate the electric driven centrifugal
chillers and replace them with direct fired absorption chiller-heaters. The chiller-
heaters will utilize their simultaneous heating and cooling ability and meet the
cooling loads while handling most (if not all) of the HVAC and domestic hot
water demands.

The waste heat rejected from the walk-in freezers will pass through heat
exchangers and account for the water source loop heat addition as well as pre-
heat the domestic water. As in the original design of the supply center, if
recovering this waste heat is not sufficient to cool the condenser water loop
back to operating temperatures (65°F), chilled water from the plant will meet
the remaining load.

6.0 BUILDING LOAD ANALYSIS


The chilled water plant at the supply center sees various load profile changes
throughout the year. However, since the chilled water system also handles the
walk-in freezers heat rejection, it forms a base load that is near constant for the
existing system. Figure 6-1 illustrates a typical cooling load profile during cooling
season. Carrier’s Hourly Analysis Program (HAP) is used to generate the data.

Building System Integration - 18 -


Justin Bem Milton Hershey School Supply Center
Mechanical Option Hershey, Pennsylvania

Daily Cooling Load Profile

450

400

350

300
Plant Load (Tons)

250

200

150

100

50

0
0 4 8 12 16 20 24
Hour

Figure 6-1 Existing Chiller Plant Daily Load Profile

As the figure illustrates, the supply center operates like most buildings, having
peak cooling demand during the building’s operational hours. The proposed
redesign thermal load profile is much different in the fact that less cooling
demand is required due to the use of a DOAS and a water source loop. Figure
6-2 shows the redesigned plant’s load profile and is shown on the next page.

As the graph shows, the 106 ton base load produced from cooling the walk-in
freezers’ condenser loop forms the base load in this particular example. As the
building becomes occupied the load increases, but not drastically. The
domestic hot water demand increases when the building is occupied, and this
water is pre-heated by the condenser water loop. For most cases during the
year, this pre-heat process transfers enough heat out of the condenser loop so
that it operates at the appropriate temperature (65°F). When this occurs, the
chilled water plant no long has to meet this base load.

The following sections, 7.0 and 8.0, explain how the HVAC systems operate in
more detail, and contain schematics that illustrate how the heat recovery
scheme shifts the plant load profile downward.

Building System Integration - 19 -


Justin Bem Milton Hershey School Supply Center
Mechanical Option Hershey, Pennsylvania
Redesign Plant Load Profile

300

250

200
Plant Load (Tons)

150

100

50

0
0 4 8 12 16 20 24
Hour

Figure 6-2 Redesigned Chiller Plant Daily Load Profile

Using Carrier’s software, the heating loads also are easily obtainable. However,
using a dedicated outdoor air system slightly raises the required amount of
heating done by the boiler plant. Figure 6-3 shows the existing systems daily
heating plant load profile (with the load in MBH). This data is from a winter day,
therefore, shows a high HVAC heating demand.

Figure 6-4 illustrates the boiler plant’s heating load profile with the redesigned
system. The profile is slightly shifted upward, unlike in the cooling scenario, and
the peak heating load is close to 200 MBH higher. The space loads are the
same in both situations, however, the majority of the heating is now performed
by the parallel water source heat pump system, and this is not directly seen by
the boiler plant. The boiler plant is needed occasionally to add heat in the
water source loop to maintain the winter temperature of 68°F, but this is a much
smaller demand than continuous hot water production required for terminal re-
heat coils and AHU per-heat coils that existing system utilizes. The main reason
for the increase in heating demand in the new system is because the dedicated
outdoor air units need cold outside air heated to 55°F without any type of
recirculation that would pre-heat the air in VAV systems.

Building System Integration - 20 -


Justin Bem Milton Hershey School Supply Center
Mechanical Option Hershey, Pennsylvania
Daily Heating Plant Load Profile

1600

1400

1200

1000
Plant Load (MBH)

800

600

400

200

0
0 4 8 12 16 20 24
Hour

Figure 6-3 Existing Boiler Plant Daily Load Profile


Daily Redesign Boiler Plant Load Profile

1800

1600

1400

1200

1000
Plant Load (MBH)

800

600

400

200

0
0 4 8 12 16 20 24

-200
Hour

Figure 6-4 Redesigned Boiler Plant Daily Load Profile

Building System Integration - 21 -


Justin Bem Milton Hershey School Supply Center
Mechanical Option Hershey, Pennsylvania

The typical domestic hot water production demand is also important in this
redesign. Originally, a separate hot water boiler is used to meet this load. The
redesign system recovers heat from the walk-in freezers to pre-heat this water.
The remaining load is met with the chiller-heater system as explained in section
8.0. Figure 6-5 shows the estimated typical, in-operation daily domestic hot
water demand load profile. Although it is difficult to accurately predict the hot
water usage for a building, this hot water demand estimate follows the
occupancy schedule for the spaces requiring the hot water.

Domestic Hot Water Demand Profile

7000

6000

5000

4000
Load (MBH)

3000

2000

1000

0
0 4 8 12 16 20 24
Hour

Figure 6-5 Domestic Hot Water Demand Profile

The peak load is designed for a 100gpm flow rate, with an entering water design
temperature of 50°F and leaving design temperature of 180°F. This load profile,
although is an estimate, is used for every analysis for consistency and
comparison reasons.

Building System Integration - 22 -

Common questions

Powered by AI

The original heating load profile demonstrates a high demand for continuous heating of terminals and AHU pre-heat coils via the boiler plant. In contrast, the redesigned profile shows an increase in peak heating load by about 200 MBH because the new system requires heating of cold outdoor air without recirculation, as used by VAV systems. This is because the redesigned system employs dedicated outdoor air units that necessitate direct heating from a lower inlet temperature. Additionally, a parallel water source heat pump system performs most space heating, making the boiler plant supplement rather than continuously supply heat .

The redesigned mechanical system at the Milton Hershey School Supply Center reduces cooling loads by replacing traditional VAV/CAV air handling units with Dedicated Outdoor Air Systems (DOAS) and utilizing a water source heat pump system for parallel cooling . This redesign allows for the use of recovered waste heat from walk-in freezers to assist in managing the cooling requirement of the condenser water loop, thus lowering the base cooling demand on the chilled water plant. These changes lead to a load profile with less peak cooling demand, due to enhanced integration of building systems and energy recovery techniques .

Carrier’s Hourly Analysis Program (HAP) plays a crucial role in evaluating the redesign by providing detailed data on the building’s load profiles. It helps in accurately modeling and visualizing changes in thermal load demands due to systemic redesigns, thus allowing for effective planning and verification of anticipated energy savings and efficiencies . This software facilitates the analysis of redesigned plant load profiles to ensure that the integration strategies meet the expected outcomes .

Waste heat from the walk-in freezers at the Milton Hershey School Supply Center is recovered and used to add heat to the water source loop, pre-heating domestic hot water and reducing the need for additional heating from the chiller-heater system . This integration minimizes the cooling load by shifting some of it to heating, thereby optimizing energy efficiency through heat recovery. Benefits include decreased reliance on the chilled water plant and reduced overall energy consumption due to the lowered base load and synergy between systems .

During operational hours, the Milton Hershey School Supply Center shows peak cooling demand, typical of most buildings . However, due to the redesign, this demand is less pronounced because of the Dedicated Outdoor Air Systems (DOAS) and water source loop integration, which lower peak load requirements during these times. The integration provides a steadier load profile by reducing spikes in demand through efficient heat recovery and system synergy .

The interaction between the water source heat pump system and the redesigned chilled water plant at the Milton Hershey School Supply Center enhances efficiency by sharing the cooling and heating load between systems. The water source heat pump works alongside the DOAS to minimize additional cooling load; meanwhile, waste heat recovery pre-heats domestic water, thus reducing reliance on the chiller plant . By redistributing thermal loads, the total system operates more efficiently, resulting in lower energy consumption and balanced operational demands .

The introduction of DOAS in the redesign increases heating requirements as these systems bring in cold outside air that requires heating to 55°F without recirculation, unlike VAV systems which pre-heat return air. This necessitates more energy from the boiler plant to reach the desired air temperature, thus altering the heating load profile by increasing the peak heating demand by around 200 MBH .

Even though water source heat pumps handle most heating requirements, the boiler plant's involvement during winter is necessitated by the need to maintain the water source loop temperature at 68°F . Since the dedicated outdoor air system lacks air recirculation, it depends more on direct heating, requiring the boiler plant to supplement heating during the coldest periods, ensuring system reliability and comfort .

The redesign affects the structural system by potentially introducing new loads or changes due to the installation of DOAS and water source heat pump systems, which could require structural reinforcements or alterations. Electrical service might also need upgrading to accommodate changes in energy use patterns and additional demands from new mechanical equipment. Overall, these changes necessitate comprehensive cost analyses to ensure that any modifications maintain system integrity and economic viability .

Economic implications of the redesign involve complex cost analyses due to altered structural and electrical service requirements stemming from the mechanical changes. While the redesign promises energy savings and efficiency gains, components with longer than 2 to 4 years of payback period may not be justified unless offset by substantial operational savings. The project's profitability largely depends on effectively reducing base loads and utilizing efficiencies from system integration and waste heat recovery .

You might also like