Sl. No. QTY. PARTICULARS RATE (`) VALUE (`)
Residencial Building Vepery
1st Staircase side wall paint: Prepare the surface and apply (1 coat primer + 2
1 7,021.00 12.50 87,762.50
coats color & touchup putty)
SFT
1st Staircase side wall paint: Prepare the surface and apply (1 coat primer + 2
2 8,053.00 13.50 1,08,715.50
coats color & touchup putty)
SFT
1st Staircase MS Handle paint : Prepare the surface and apply (1 coat metal
3 7,977.00 18.00 1,43,586.00
primer + 2 coats blac paint)
SFT
1st Staircase MS Handle paint : Prepare the surface and apply (1 coat metal
4 7,977.00 18.00 1,43,586.00
primer + 2 coats blac paint)
SFT
Fire Wood Door Spray enamel : prepare the surface and apply 1 coat paint GF
5 1,100.00 22.00 24,200.00
to 20th Floor - 2 side ( 1 coat wood primer + 2 coats enamel paint)
SFT
6 32.00 Lift Lobby mirror fixing(8mm Mirror with stud) 460.00 14,720.00
SFT
7 5,909.00 Shaft door vinegar polish GF to 20th Floor 185.00 10,93,165.00
SFT
Basement Bike Parking :1st Staircase side wall paint , prepare the surface and
8 3,400.00 12.50 42,500.00
apply (1 coat primer + 2 coats color & touchup putty)
SFT
9 25.00 Fixing Glass door including lock & handle ground floor lift lobby 2,100.00 52,500.00
SFT
10 5,500.00 Multi purpose court two coats Asian enamel paint 15.00 82,500.00
SFT
1st floor lift lobby wall paint , prepare the surface and apply (1 coat primer + 2
11 725.00 12.50 9,062.50
coats color & touchup putty)
SFT
Lift lobby false ceiling paint, prepare the surface and apply ( 2 coat putty + 1
12 1,000.00 16.50 16,500.00
coat primer + tractor emulsion)
SFT
Lobby mirror beading wood polish, prepare the surface and apply( 2 sealer +
13 7,200.00 75.00 5,40,000.00
touch up putty + 2 coats PU polish) (Note : 2" Beading consider)
RFT
----------
Total Before Tax Value 23,58,797.50
Add : CGST 9% 2,12,291.78
Add : SGST 9% 2,12,291.78
Rounded Off - 0.05
---------------
Total After Tax Value 27,83,381.00
TERMS & CONDITIONS :-
1. Free power & good water to be provided by client at site
2. Free Labour sheed with power, water, and rest room speciality
3. Free Lockable storage provided by client
4. 40% advance along with your work order and balance against our RA bills
5. Floor coverings & cleaning extra. General Cleaning after painting will be done any
additional coverings/cleaning will be extra to client A/C
6. This being a 20 floor raise building we should be allowed to use the service for men &
material movements.
7. Scaffolding providing by client scope
Rupees Twenty Seven Lakhs Eighty Three Thousand Three Hundred Eighty One NET VALUE
27,83,381.00
Only (`)
PREPARED BY : Mr. Harry Jones For BUILDCRAFT INTERIOR PVT. LTD