RISK ASSESSMENT
Contractor: AMLAAK ENERGY RESOURCES LLC Project Manager:
Project Number: Email: Mobile:
Work Description: Installation and Testing and Commissioning of Fuel CWP NO:
Piping .
Location: MSRA Number: Expiration Date:
Sub-Contractors: Civiltech General Contracting Co. LLC
High Risk Activities:
Work at more than 1,8 m Heights Work on Roof Excavations deeper than 1.2 meters Hot Works
Use of Hazardous Materials Demolition Work Heavy Equipment Mechanical Lifting
Working Near Live Station Work in High Voltage Area Confined Space Entry LOTOV
Emergency Preparedness: ASSEMBLY POINT IDENTIFICATION:
Is there a Contractor Nominated First Responder? Yes Name: No
To report incidents: Emergency Response Team: Amlaak HSE Manager:
RISK ASSESSMENT PREPARED BY:
Position Name Signature ID no Contractor Date
1
2
Verified by Name Signature ID No Contractor Date
1
2
HSE/AMER/RA/005/01
Page 1af6
RISK ASSESSMENT
Residual
Personnel Risk
Step Activity Hazard Counter Measures Responsible Risk
Involved
P S T P S T
1 Delivery and Supervisor, Collision with other 3 3 9 Compliance to project Supervisor 1 3 3
receiving of Driver, , vehicle/pedestrian, speed limit and other traffic
HDPE Pipes to Electricians regulations on site.
site . Helpers All drivers and operators
shall be in possession of valid
ROP driving license.
Equipment to be used for
unloading shall pass the
client inspection and shall
have a valid 3rd party
inspection certificate.
All equipment shall have
flashing beacon an orange
rotating light placed on the
top of the vehicle.
All equipments shall have
reverse horn.
Ensure the availability of
competent & trained
banksman that will direct the
moving equipment.
Banksman shall have 4m
distance from machine.
2 Fuel pipe 2 2 4 Supervisor 1 2 2
TBT shall be conducted prior
Installation Technicians Permit Issuer
to start the task.
Helpers
Use approved PPE as per
Oman oil rules and regulation
HSE.
Technicians Slip trip & falls 2 2 4 Supervisor 1 2 2
Ensure all tripping hazard are
HSE/AMER/RA/005/01
Page 2af6
RISK ASSESSMENT
Residual
Personnel Risk
Step Activity Hazard Counter Measures Responsible Risk
Involved
P S T P S T
Helpers
removed and proper
housekeeping to be done.
3
HSE/AMER/RA/005/01
Page 3af6
RISK ASSESSMENT
Residual
Personnel Risk
Step Activity Hazard Counter Measures Responsible Risk
Involved
P S T P S T
4.
5.
HSE/AMER/RA/005/01
Page 4af6
RISK ASSESSMENT
Residual
Personnel Risk
Step Activity Hazard Counter Measures Responsible Risk
Involved
P S T P S T
6. Emergency Electricions 2 3 6 All works will be stopped and Supervisor 1 3 3
situtation Helper staf/workman will be
assembled in the nearest
assembly point.
Amlaak emergency
will be Displayed in the site .
HSE/AMER/RA/005/01
Page 5af6
RISK ASSESSMENT
TASK-BASED RISK ASSESSMENT ATTENDANCE LIST
EMPLOYEE NAME EMPLOYEE SIGNATURE EMPLOYEE NAME EMPLOYEE SIGNATURE
TASK-BASED RISK ASSESSMENT CONDUCTED BY:
Position Name Signature EGA ID no Contractor Date
Construction Supervisor
EHS Representative
Consequence
Probability Insignificant-1 Minor-2 Moderate-3 Major-4
Catastrophic-5 TRA Conducted By (Name &Emp#): TRA Approved By (Name, Emp# &
Signature):
Rare-1 1 2 3 4 5
Possible-2 2 4 6 8 10
Likely-3 3 6 9 12 15
Often-4 4 8 12 16 20
Frequent-5 5 10 15 20 25
HSE/AMER/RA/005/01
Page 6af6