MEP & ICTS Concept Design Report
MEP & ICTS Concept Design Report
OBJECTIVE
DESIGN CRITERIA
MEP DEMANDS
• To communicate the design for the mechanical, electrical and public health engineering
• ICTS Systems design strategies
services to the design team and Client's representatives and obtain approval of the same; • EP & ICTS Strategies
• To be a vehicle to record the origin of and distribute technical information associated with the • MEP demands
mechanical, electrical and public health engineering and fire protection services strategies
and basis of design during the period of the design;
This report covers the Experience Centre, Innovation Labs, Cube, MEP Utility Buildings-1 & 2 and
• To be the sole point of technical reference on the basis of design information for AtkinsRealis Guard Rooms. The MEP Utility Building-2 is part of the Cube. For details of the office building, refer
designers and to an extent, where designers do not have to make any assumptions. to the Section 05 of the Concept Design Report no. 5222557-ATR-OFB-ZZZ-RP-MD-000001 P01.
• To communicate the Concept design strategies, and to record design decisions undertaken
with stakeholders. DESIGN STRATEGY
The project comprises of the Office Building, Experience Centre, Innovation Labs, Cube (also
MEP&ICTS DESIGN REPORT SECTIONS referred as Mini Mukaab), MEP Utility Buildings and Guard Houses. The external car parks, landscape
lighting, road lighting, event space and all the developments outside the buildings are covered
within the Utilities Section.
The building services section of this report comprises of several discrete sections, which have been
written so they can be read in isolation if need be. However, the report should be read as a full The office building and associated MEP Utility Building will be executed as a D&B contract
document, for the reader to understand the inter-relationships and rationale behind several of the following the completion of the concept design, whereas all other buildings will go through the
design decisions taken for the mechanical, electrical and public health engineering services schematic and detailed design stages.
systems. The power supply for this project is planned independently for the office building with the electrical
substation inside the MEP Utility Building-1. The power supply for the southern assets (Experience
The building services section comprises the following sub-sections: -
Centre, Innovation Labs and Cube) is planned to be fed from a separate substation within the utility
• Codes and Standards area of the Cube building. The power provision for the Villa plots has been made in the design,
however, the Villas are not included in the current design.
• Design Criteria
The MEP provisions in the Innovation Lab are planned considering the lab area could be converted
• HVAC design strategies into apartments in the future.
The air-conditioning for all the buildings are standalone system with Variable Refrigerant Flow (VRF)
and Air Handling Units (AHU) provided within each building.
CONCEPT DESIGN REPORT - REMAINING ASSETS
452
The domestic water system is centralized for the whole project. The water tank and associated
pumps are provided in the MEP Utility Building-1. The fire water system is also centralized for the Standard Reference Organization / Publication Title
whole project. The fire water tank and associated pumps are provided in the MEP Utility Building-1.
American Society of Heating, Refrigeration and Air Conditioning
ASHRAE
Engineers
CODES AND STANDARDS
ASHRAE 15 Safety Standards for Refrigeration System
The following Codes, Specifications, Regulations, and industry standards, where applicable, will Method of Testing General Ventilation Air-Cleaning Devices for
cover design, material, and construction of the MEP building services systems. The governing codes ASHRAE 52.2
Removal Efficiency by Particle Size
for Kingdom of Saudi Arabia (SBC) will be the primary basis for the design and for other relevant
international code references within these documents.
ASHRAE 55 Thermal Environmental Conditions for Human Occupancy
If information is not available in KSA codes then USA standards (e.g. NFPA, ASHRAE) or UK standards
(e.g. CIBSE, BS Standards, etc.) will be applied. For information not obtained from the above,
research papers and industry practices will be applied with a clear statement of source and ASHRAE 62.1 Ventilation for Acceptable Indoor Air Quality
reference.
Energy Standard for Building Except Low-rise Residential
ASHRAE 90.1
UNITS Buildings
Peak Cooling and Heating Load Calculations in Buildings Except
ASHRAE 183
The Metric SI system will be used throughout the project unless otherwise stated. Low-rise residential Buildings
Standard Reference Organization / Publication Title Standard Reference Organization / Publication Title
BSRIA Building Services Research and Information Association IPC International Plumbing Code
CIBSE Chartered Institution of Building Services Engineers IOP The Institute of Plumbing
HI Hydraulic Institute
NFPA 11 Standard for Low, Medium, and High-Expansion Foam
IEC International Electro Technical Commission Standard for the Installation of Sprinkler Systems in One- and
NFPA 13D
Two-Family Dwellings and Manufactured Homes
IEE Institution of Electrical Engineers Standard for the installation of Standpipe, Private Hydrant and
NFPA 14
Hose Systems
IET Institution of Engineering and Technology
IFGC International Fuel Gas Code NFPA 15 Standard for Water Spray Fixed Systems for Fire Protection
Standard Reference Organization / Publication Title Standard Reference Organization / Publication Title
NFPA 22 Standard for Water Tanks for Private Fire Protection NFPA 101B Code for Means of Egress for Buildings and Structures
Standard for the Installation of Private Fire Service Mains and Their
NFPA 24 NFPA 110 Standard for Emergency and Standby Power Systems
Appurtenances
NFPA 30 Standard for Flammable and Combustible Liquids Code NFPA 130 Standard for Fixed Guide Way Transit Systems
NFPA 54 National Fuel Gas Code NFPA 170 Standard for Fire Safety and Emergency Symbols
Standard Reference Organization / Publication Title Standard Reference Organization / Publication Title
SBC 701 Saudi Building Code, Section 701, Sanitary UL Underwriters Laboratories
SBC 801 Saudi Building Code, Section 801, Fire Code UPC Uniform Plumbing Code
DESIGN SOFTWARE
Plumbing Systems Design
The following software will be used for the design of plumbing systems during the concept and
HVAC Design detailed design stages of the design, with additional detail being applied as the design
progresses.
The following software will be used for the design of mechanical services to enable mechanical and
associated technical schedules to be completed as part of the detailed design.
Calculation Type Applica ble Software/Calculation
Methodology
Calculation Type Applica ble Software/Calculation Methodology Excel spreadsheet tool (procedure as per
Domestic water demand MEWA regulations) by AtkinsRealis during
HAP or IES 2021 (complete project) concept design stage
Heat gain calculations Excel spreadsheet tool (based on W/sqm) for initial design
stages Cold water transfer and hot & cold-water
booster pump sizing Excel spreadsheet tool
Ductwork system pressure loss
Excel spreadsheet Tool
for primary systems Drainage (Sewage) flow calculations ATK Excel spreadsheet tool (procedure as per
SBC 701 or approved equivalent)
Pipework system pressure
Excel spreadsheet Tool (in case of chilled water pipes only)
loss for primary systems HWS capacity sizing (Point of use water heater) Excel spreadsheet tool based on Table 10:
ASHRAE - Hot water demand per fixture for
various types of usage.
Excel spreadsheet tool (procedure as per ASHRAE 62.1)
Room ventilation calculation
Hot and cold-water pipework sizing Hevacomp V8i or Excel spreadsheet tool based
Specialist Room ventilation on water supply fixture units
Excel spreadsheet tool based on ASHRAE or local
calculations (fire pump room
Standard LPG capacity sizing Excel spreadsheet tool
etc.)
LPG pipework sizing Hevacomp V8i or Excel spreadsheet tool
Table 5-2 HVAC Calculations Design Software Schematic Design
Storm water flow calculations Excel spreadsheet tool (based on SBC 701)
The following software will be used for the design of fire protection systems, to assist with space Applicable Software/Calculation
allocation, utilities provision and general integration and coordination of the firefighting systems. The Calculation Type
Methodology
final design of the all the fire protection systems will be undertaken by the specialist contractor,
based on the performance design intent issued by AtkinsRealis.
Lighting calculations Dialux
DESIGN CRITERIA
Design Criteria-Mechanical and Public Health Services
Parameter Value Data Source
Latitude 24.72'N ASHRAE Fundamentals 2021 Seismic Zone Refer to Structural Report
Exposed Floor 0.30 - - Fan Static Pressure safety factor 10% AtkinsRealis
(1)The margins specified will be applied to room load calculations and air-conditioning
systems and subsequent sizing of cooling and heating systems
Walking, standing Drug store 145 75 75 Retail 23°C +/- 1ºC 20°C +/- 1ºC 40%- 60% (3) NR 35-40
Seated, inactive Theatre, Cinema 105 70 35 Corridors 23°C +/- 1ºC 20°C +/- 1ºC 40%- 60% (3) NR 35
Summer
Winter Design
Design Relative Noise Level Summer
Room Temperature Winter Design
Temperatur Humidity (%) ( N C / N R ) ( 4) Design Relative Noise Level (NC/
(°C
C ) (1) Room Temperature ( °C
C)
e (°C
C ) (1) Temperature (1) Humidity (%) N R ) ( 4)
(°C
C ) (1)
Toilets 26°C +/- 1ºC 20°C +/- 1ºC Uncontrolled NR 35
Server Room / MDF (Served by CBS / UPS Room 23°C +/- 1ºC Uncontrolled Uncontrolled NR 35
19ºC +/- 1ºC 19ºC +/- 1ºC NR 45
Room CCU with N+1)
LV room 28 Max Uncontrolled Uncontrolled NR 45 (3) Relative humidity will not be directly controlled.
Uncontrolled (4) Noise levels are as per CIBSE Guide A, Environmental Design, Table 1.5.
Telecom 23°C +/- 1ºC Uncontrolled NR 35
(Served by FCU)
(m /pers o n) (2) (W/m ) (1) (W/m ) (3) (m /pers o n) (2) (W/m ) (1) Equipment Gain
Galleries / Exhibition 2.5 8.6 As per Actuals Server Room / MDF Room - 10 As per Actuals
Hall
Water meter room - 10 -
Offices 12 8.4 15
Electrical Meter room - 10 As per Actuals
Meeting Rooms 2 9.8 15
Furniture layout / Garbage room - 10 -
Lobbies / Lounge 9.8 15
3.3
ICT / IDF Room - 10 As per Actuals
Retail 6.66 20 15
Staff Dining / F&Bs 1.43 10 5 Main ICT Server room - 10 As per Actuals
Extract Air
Outdoor Air Ventilation Extract Air Ou t d oor Ai r Ve n t i lat i on R at e (1)
Ventilation
Air R at e (1) (N omi n al ) Ventilation Rate Air (Nominal )
Room Room Rate
Changes Changes
Telecom - - 0.3 -
Lift Machinery Room - - 0.3 - Pre-filter on all AHUs MERV 8-9 Panel filter
CBS / Battery Room 6 (5) - Main filters on AHUs MERV 13 Bag filter
Fresh Air Ventilation rates to be generally based on ASHRAE 62.1 Ventilation Standards in
(1)
accordance with the of Estidama requirements. or minimum fresh air required to offset the actual HEPA Filter Module for
MERV 13-14 HEPA Filter
extract rate from each toilet and pantry whichever is greater. Ecology Units
(2) Extract Air Ventilation rates to be generally based on ASHRAE 62.1, Ventilation Standards. Activated Carbon Filter
NFX Grade -
Module for Ecology unit
(3)
otherwise default occupancy rates as per ASHARE 62.1 Standard and as specified elsewhere in
the report shall be used.
(5) Ventilation rates for Battery room shall be based on the Hydrogen concentration.
(4) Velocities in final runouts to outlets should be 50% of values or less Ablution spray 1.5 Cold AtkinsRealis
Elbows and other fittings can increase airflow noise substantially, depending on
(5)
Flow Pressure
Fixture
Fixture Water Supply Fixture Units Source (kPa) As per SBC 701
Bathtub 138
Hose bib 2.0 Cold AtkinsRealis
Room Cold Water Demand Source Parameter / Strategy Data / Description Source
Lavatory Basin 1 SBC 701 Table 709.1 (1 Duty + 1 Assist) sump pump sets flow
Wastewater Sump Pump for fire pump
based on no. sprinkler discharge at AtkinsRealis
Shower 2 SBC 701 Table 709.1 room
plant room
Floor drains 2 SBC 701 Table 709.1 Best international and regional engineering practices.
Drinking fountain 1/2 SBC 701 Table 709.1 A table identifying the same is shown below.
The roof outlets shall be a combination of domed shaped and side outlets with gravel guard.
The vertical rainwater pipe will run within the PH shafts provided in each washroom/ wet area
and the Roof shall be sloped toward those.
Similar Rainwater outlets shall also be provided on different floor terraces with slopes
towards the outlets. For staircases that are open to the sky, rainwater outlets shall be provided
in the higher and lower part of staircases based on the calculated amount of rainfall.
Secondary Storm Water outlets shall be provided as recommended in IPC and SBC 701. From
a simplistic viewpoint, the performance of the secondary stormwater roof drains should be
similar to the main outlet, so that it can drain the roof in the event that the main outlet has
ceased to operate. Considered rainfall intensity of 29mm/hr.
Note:– In the absence of kitchen consultant inputs, MEP has assumed the
above data and this shall be further validated by kitchen consultant in next
design stage .
Lighting Design
Illumination Level
All lighting will follow the design and system criteria below.
Lighting levels will generally be in accordance with BS EN 12464-1 and CIBSE
recommendations as follows.
Other FOH areas: Janitor Room 100 Floor level LED 0.4 CIBSE
BS EN 12464-1
To assessed based on the finishes;
Work
Guard House 300 LED 0.4 CIBSE
Boundary Zone for Maximum 500mm from the wall/ surfaces
BS EN 12464-1
Calculation boundary
Kitchen 500 0.9 LED 0.6 CIBSE
Table 5-26 - Lighting Installation
Laboratories 500 Floor level LED 0.6 CIBSE
Lighting power densities for all spaces will be specified not to exceed the limits set in the
SBC 601. Please refer to the sustainability section of the Concept Design report for the target
reduction of the lighting power density on ASHRAE 90.1-2010 (space-by-space type
methodology) through use of the LED lighting fixtures.
Table 5-28 - Electrical Load Densities Small power devices will generally be provided to meet the following requirements.
Power Demand Load 20% AtkinsRealis Corridors, public areas, and technical rooms.
Single outlets Spacing along corridors shall be 15m maximum AtkinsRealis
LV Switchboards 20% AtkinsRealis between outlets.
Motor Control Centers 20% AtkinsRealis Outlets for fixed and special equipment as
Special purpose outlets AtkinsRealis
required.
Sub Main Distribution Boards 20% AtkinsRealis
Wiring LSZH insulated copper conductors SBC 401
Final Distribution Boards 20% AtkinsRealis
Cable trunking and/or rigid steel conduits for
UPS 20% AtkinsRealis exposed locations and heavy-duty PVC conduits
Containment for concealed installations. Raceways used for AtkinsRealis
Table 5-29 - Spare Capacity wiring above the false ceiling (if the false ceiling
has been provided).
Parameter Description Source Type Three phases, online, double conversion, static type AtkinsRealis
Emergency Power/Uninterruptible Power Supply (UPS) Battery Type Sealed Lead Acid AtkinsRealis
UPS-Battery Room Air conditioned. The need for dedicated exhaust will
To cater the emergency power back-up requirement UPS has been provided in the utility AtkinsRealis
building. Static online UPS will be designed to provide an uninterrupted power supply to the Ventilation be reviewed with design progress.
fire and life safety loads and critical loads (ICT/IT/Data), in the event of power failure. These
critical loads are mainly related to the ICT, IT/Data and security systems. Spare 20% of design load AtkinsRealis
The autonomy of the UPS batteries shall be 2 hours minimum to comply with NFPA 101 Life
Safety Code requirements. Table 5-32 - Uninterruptible Power Supply System
Considering these buildings are temporary buildings; the option of a diesel generator and
UPS has been considered. The running cost of the UPS is lower than the diesel generators
except when replacement of the batteries is required. The life of the batteries is more than 5 Earthing and Equipotential Bonding
years, which is the expected life of the buildings. Hence the running cost of the UPS will be
substantially less than the diesel generators. The capital cost of the UPS and diesel generator The system design and installation will provide a safe and effective earthing system in
is expected to be more or less the same. The plantroom requirement for the UPS is accordance with SBC 401 to achieve the following:
comparatively less. Given the cost benefits for a life cycle of 5 years, UPS has been proposed.
Each circuit, including sub-mains, will include a separate circuit protective conductor (CPC); Lightning Protection, Disturbance, and Interference
size of CPC will be in accordance with the SBC regulations. The earthing system shall follow
TN-S system in accordance with the local authority requirement. The LV grounding system A lightning protection system is designed in accordance with SBC 401 and BS EN 62305-2.
will comprise of earth electrodes, riser conductors; earth terminals located in technical
equipment rooms and will be interconnected using copper conductors and bonding Transient over voltage protection will be provided to all cables that enter or leave buildings in which
conductors from earth terminals to all electrical equipment, metallic enclosures, steel cable critical, sensitive plant and equipment is installed. The basis of design of a surge protection system is to
containment, structural steel members and steel reinforcement of the building. provide protection against induced voltages in power distribution and low current networks arising from
lightning strikes and other electromagnetic discharges. This applies particularly to any cables
Separate earthing networks will be required for ICT systems and clean earths. Grounding entering/leaving the building and any externally mounted equipment.
system for medium voltage power supply system will be separated from low voltage power
supply grounding within the building structure.
Parameter Description Source
The maximum touch and step potentials and earth leakage currents will not exceed those
specified in the applicable standards. Earth fault currents will be sufficient to operate the
Lightning Protection Comply with BS EN 62305 AtkinsRealis
protective devices as specified in the applicable standards. The attainable step and touch
potential will be lower than tolerable level, derived from IEEE 80 equations. The potential
rise in telecommunications circuits due to power system earth faults will be limited to the Comply with IEC 61643 BS
Surge Protection devices AtkinsRealis
prevailing design standard. The sizing and spacing of earth electrodes, PE conductor, EN62305 Part-4
bonding conductors and lightning protection air terminals and down conductors will be
sufficient to meet the above requirements. Table 5-34 - Lightning Protection
The overall resistance of the integrated earthing system to the mass of the earth shall not
exceed limitations imposed by SBC 401.
. Parameter Description Source Analogue Addressable system with integral maintenance free
sealed lead acid battery backup for 24hrs + 15 minutes of Alarm
Comply with TIA/EIA-569-A Condition following mains failure condition and networked
Separation from EMI Sources AtkinsRealis
recommendations. Sub-Main together SBC /
Factory installed to sup- press Control panel with other panels within AtkinsRealis
EMI Filters (Within Luminaires) conducted electro-magnetic AtkinsRealis the facility.
interference as required. - Operating Voltage of 24VDC
Provide adequate grounding on all - UL Listed.
EMI Induced Voltages equipment to prevent the build- up of AtkinsRealis Addressable system with integral maintenance free sealed lead
electromagnetic voltage potentials. acid battery backup for
Provide screening of panels, enclosures, Fire Alarm 24hrs + 15 minutes of Alarm Condition following mains failure SBC /
EMI-Screening devices, or components that emit AtkinsRealis Repeater Panel condition AtkinsRealis
interferences. - Operating Voltage of 24VDC
All monitoring and control and
- UL Listed.
EMI Cable Screens Communication cables shall be AtkinsRealis Smoke Detectors- Photoelectric type
screened with one end grounded Heat Detector- Rate of temperature Rise type.
Multi-sensor Detector- Combined smoke and heat type.
Table 5.-41 - Earthing/LPS and Materials
Alarm Initiating Duct Sensor- Duct mounted photoelectric type SBC /
Devices Beam detectors- Photoelectric type AtkinsRealis
Open Area- Smoke
Fire Alarm System
Imaging Detectors (OSID)
Manual pull station- Non-Break Glass type
Parameter Description Source Sounder- Minimum sound pressure level of 88 dBA / 10ft (3m) @
Analogue Addressable system with integral Alarm 24VDC.
maintenance free sealed lead acid battery SBC /
Notification Flasher- minimum
backup for 24hrs + 15 minutes of Alarm AtkinsRealis
Appliances maximum pulse duration of 2/10 of a second
Main Fire Alarm Control Condition following mains failure condition Combined Sounder with Flasher
SBC / AtkinsRealis
panel and networked together Addressable dry contact Monitoring
with other sub panels within the facility. Module Two Wire Detector Monitoring Module SBC /
- Operating Voltage of 24VDC Fire Alarm
Addressable Control Module AtkinsRealis
- UL Listed Interfaces
Addressable Relay module
Line Isolator Module
. SBC /
Fire pump(s) Protocol Lonworks and BACnet
AtkinsRealis
Elevators
Sprinkler water control valves
SBC /
Access Control System. Spare 10% spare capacity in each fire alarm loop
AtkinsRealis
Air-conditioning equipment SBC /
Interfaced to
Ventilation Fans AtkinsRealis
Motorized fire dampers Table 5-42 - Fire Detection and Alarm and Materials
Building Management System
Smoke Control System including Smoke
Extract Fans
IP Rating
- Addressable and monitored
- Operating Voltage of Parameter Description Source
Auxiliary Field SBC /
24VDC
Power Supplies AtkinsRealis All components shall be IP 2X finger protected such
- Integral Battery Components AtkinsRealis
Charger that live components cannot be accidentally touched.
Remote Alarm SBC / Interior enclosures shall be a minimum of IP 31 unless
Category-5 Remote monitoring System Interior Enclosures AtkinsRealis
Monitoring 24x7 (TBC) AtkinsRealis specifically noted otherwise
Two-Way Telephone Communications Exterior enclosures shall be a minimum of IP 65 unless
Fireman SBC / Exterior Enclosures AtkinsRealis
modules integrated specifically noted otherwise
telephone AtkinsRealis
with Fire alarm system Class B Level 3 Circuits
Voice evacuation SBC / Table 5-43 - IP Rating
Integrated with the Public Address
system AtkinsRealis
Alarm Initiating device -
Class A Level 3 SBC /
Sustainable Design Certifications
Circuit
Alarm Notification Devices Class A circuit AtkinsRealis
Level 3 The project is pursuing formal third-party sustainability certification. The Design is Coordinated with the
appointed sustainability design sub-consultant. The contractor should also refer sustainability report for
Wire type Category CWZ Fire Retardant cable SBC / rating requirements.
AtkinsRealis
Method of SBC /
In conduit / direct clipped
installation AtkinsRealis
Basis of Design for Fire Sprinkler System Wet Fire protection System Design Criteria
Design
Hazard Water Supply
Occupancy Density Design area (m2) Type of System Code Reference
Classification Duration
(mm/ min )
Fire Pump Extra Hazard Actual Area of Fire Standpipe System Class III NFPA 14 / SBC 801
12.2
Room Group-2 Pump Room
120 mins duration as Interconnection of Supply NFPA 13/ SBC 801
Office/Villa Light Hazard 4.1 139
per NFPA-13.
Plant Ordinary Sprinkler System NFPA 13/ SBC801
6.1 139
room/F&B Hazard
Hazard Classification As defined by FLS consultant
Table 5-44 - Fire Sprinkler System
Automatic sprinkler Code reference and Combined Automatic Fire Sprinkler and
Code Requirement NFPA 13 /SBC 801
Standpipe Demand
system interpretation
Depends on construction
Standpipe Riser NFPA 14 /SBC801
Maximum Protection Area type, hazard classification:
NFPA 13 & SBC 801
of Coverage Light Hazard: 20 m 2
Foam fire protection system (generator
Ordinary Hazard: 12 m2 NFPA 16 /SBC801
room)
Light Hazard: 4.6 m
Maximum Spacing NFPA 13 & SBC 801
Ordinary Hazard: 4.6 m
Location of Standpipe Outlets NFPA 14 /SBC801
Table 5-45 - Automatic Sprinkler System
Fire Department Connections NFPA 14 /SBC 801
Handheld or Trolley Mounted Extinguisher System design Criteria
Water Supply Duration NFPA 14 & NFPA 13 / SBC 801
Hand held extinguisher system NFPA 10 / CDFCC The above details shall be further validated by FLS consultant in the next design stage.
ICT Room Clean Agent System NFPA 2001 Mechanical Services Strategies
Server Room Clean Agent System NFPA 2001 Mechanical Cooling System
An initial investigation has been carried out to explore if a district cooling network is
Table 5-48 Clean Agent System located in the vicinity that may serve the development. Based on the information
received, it is confirmed that no district cooling is available, hence an -site
approach has been provided.
Based on the size of the development and the individual buildings and initial cooling
load assessment, the following on-site cooling systems have been taken into
consideration.
There are number of factors that influence the selection of the cooling system most Air-Cooled Chillers:
appropriate to the project. The major factors dictating being the life of the building,
the size of the cooling plant, physical space required by the cooling system that needs
to be well integrated to building architecture and the life cycle cost of each cooling • To meet building aesthetic aspiration, chillers cannot be located on and near to
system. any of the building in the development. Chillers shall then be located on a
dedicated MEP utility yard away from the building.
Following specific planning considerations to incorporate in the design formed basis of
Air conditioning System Selection Criteria for the Activation Centre, which go beyond • Locating Chillers at remote utility compound will assist in dealing with potential
the capital cost/expenditure (CAPEX) of the Air Conditioning System. Key items to noise and vibration issues.
consider are:
• Locating Chillers at remote utility compound will require piping distribution
• high full load and part load efficiency (high COP). network to each building.
• ability to be linked to intelligent Building Management System (BMS). • Chilled water distribution will require coordination with other utility services
within the plot boundary.
• Plant space available.
• Long distribution pipework will require high pump head which will affect overall
system efficiency.
• Operational Expenditure (OPEX) costs both consumption and maintenance.
• System is relatively complex and require more sophisticated controls.
• Outdoor Unit (ODU) heat of rejection criteria
• System has relatively higher operational and maintenance cost
• Maximum vertical lift of refrigerant based systems
• To be in line with operational and building construction phasing philosophy,
• Maximum overall run of refrigerant pipework
Centralized Chillers need to be split to serve various assets within the
development. With proposed construction phasing and with Office Building to
• Ease of operation for the end use
be constructed earlier than the rest of the buildings, following plant
configuration shall be adopted:
• Building Construction Phasing and Operational Philosophy
o Dedicated Chillers for Office Building
Considering the above factors, following outlines main considerations for air-cooled
chillers and VRF system:
o Dedicated Chillers for remaining Buildings
• VRF System:
Based on above review, VRF system is recommended to be an optimal solution and
• Due to the fact that system is local to each building, it offers more flexibility and shall be proposed for the development. Variable Refrigerant Flow (VRF) system is an
in line with development operational and construction phasing philosophy energy efficient and intelligent system works on the principle of direct-expansion (DX)
when system can be installed along with each building construction. cooling with multiple indoor units connected to a common outdoor condensing unit.
The indoors units are similar to fan-coil unit (ducted/non-ducted) and are connected to
• For temporary buildings, the system can be dismantled along with the outdoor unit via refrigerant pipework. Floor-mounted AHU integrated to a VRF
demolished buildings without affecting others and can be more cost effective condensing unit is also available. The outdoor units require open space, clearance
solution compared to the chillers. space for air-circulation and any obstruction is subject to
recommendations. All refrigerant based systems are proprietary systems and need to
come as a matched indoor and outdoor unit setup and this especially critical for VRF
• In terms of space requirements, aesthetics and integration to building
systems, given the system configuration has multiple permutations all of which will
Architecture, VRF system provides more flexibility. Outdoor condensing units
need to be fully checked by the successful supplier with the Contractor to ensure it
can be installed with various configuration including fully open-to-sky spaces
operates correctly. At the most, the combination ratio of over 100-130% is generally
on roof or partially enclosed spaces with aesthetic treatment elsewhere in the
recommended and subject to final selection of VRF manufacturer.
building.
• System offers flexibility to split into multiple system and serve different sections
of the building. Space Heating
• Smaller units can be contained locally in dedicated MEP plant spaces with
Based on the weather conditions experience in Riyadh, space heating is required. For
potential lower noise break-out risks.
VRF based system, heat pump system shall be provided which can offer both heating
and cooling. For buildings with simultaneous heating and cooling requirement, 3-pipe
• No major network pipework distribution within the site is required.
refrigerant system shall be proposed otherwise 2-pipe refrigerant system shall be
provided
• The system has more simplistic controls.
Air-cooled chillers cannot offer both heating and cooling and will require central
• VRF have higher COP (generally over 3.5 compared to over 2.8 for air-cooled heating system (via boilers, heat pumps etc.) which may also require piping network
chillers at AHRI conditions) and part-load efficiencies and has relatively lower distribution in parallel to chilled water piping distribution. Alternatively, local heating
operational and maintenance cost. via heat pump or electric heating can be provided. This option as outlined in Cooling
System is not recommended.
• System offers both heating and cooling options which can provide more holistic
solution to the project.
Comfort Cooling Following considerations shall be required when selecting between these options:
Comfort cooling for the various areas can be provided by a number of different • Ceiling void space availability
systems; however, each system has a particular characteristic that has to be matched to
the building location, built form and function. In general, the comfort cooling for the • Access and maintenance requirements
various assets will be afforded via Ceiling mounted VRF indoor fan coil units. Large
volume spaces shall be served by Air-Handling Units and as outlined in the later • Metering and billing strategy
section of this report. All spaces with AHUs shall be provided with Economizer Mode
during off-peak seasons where AHUs shall use the ambient air as means of cooling and • Acoustics measure and noise criteria to be met.
using minimum or no input from VRF system. Humidifiers shall support to maintain
minimum level of humidity within the space whilst drawing dry ambient air from • Operational Expenditure (OPEX) costs both consumption and maintenance.
outside.
• Ease of operation for the end use
The assets in Activation Centre will require comfort cooling to maintain internal design
conditions in accordance with the HVAC design criteria as defined elsewhere in the • Building Operational Philosophy
report.
Considering above various factors, some of the main items that will affect the type of
comfort cooling options are how the offices are operated, the access and maintenance
Offices and Meeting Rooms philosophy and the physical spaces available in the building. Offices and meeting
room spaces are located in Experience Centre Building where the size is limited and
Offices can be comfort cooled by using various options as outlined below: there are no large open plan offices.
• Option-1: Ceiling Void Mounted VRF indoor Fan Coil Units In general, central AHUs with VAV boxes is more suitable option as it limits the access
and maintenance requirements within the occupied areas. However, given the size of
the office space and the limitation in plant room space, VRF fan coil units shall be
• Option-2: Central VRF based AHUs with VAV terminal boxes on each space.
proposed. This philosophy shall be applied to other similar rooms like meeting rooms
etc.
Mini Cube Entrance lobbies, Atrium and associated connecting circulation space in Experience
Centre Building shall be provided with dedicated recirculation AHUs. Ductwork shall
be reticulated through dedicated risers. The design of the entrance lobbies will be
This is also envisioned to be the prime area and center of excellence for the guest
reviewed further in the next stage based on updated architectural and interior design
experience. Given the nature, usage and operation of this space, dedicated AHUs shall
layouts. The AHU and its associated temperature control will be connected to the BMS
be provided. The AHU and its associated temperature control will be connected to the
to enable monitoring/setback/scheduling, etc.
BMS to enable monitoring/setback/scheduling, etc.
Entrance lobby in Innovation lab building is relatively small and shall be provided with
Given the height of the space and with potential full LED screen, displacement
VRF indoor fan coil units.
ventilation can be proposed. Alternatively, mixed mode ventilation with diffusers at
high level can be provided all subject to ID and Architectural coordination. Return air
shall be free via return air bell mouth with return air diffusers or opening if ceiling is The type and location of grille/diffusers will be selected during the detailed design
provided. This will be developed and coordinated at the later design stage. stage in coordination with the Interior Designer.
Each entrance lobby will have individual temperature and will be connected to the
Innovation Lab respective BMS.
These rooms will be air conditioned by VRF ducted indoor fan coil units (FCUs) to
Utility Block maintain stable conditions given the high heat dissipation. In each case the indoor
FCU installation will comprise of a duty and standby unit so that in the event of the
Utility Block comprise of various MEP spaces which all shall be provided with wall or failure of one there will still be 100% cooling provision to the space concerned.
ceiling mounted, exposed VRF indoor FCUs with common outdoor unit. Outdoor units Indoor FCUs shall be located outside the room in a common corridor or BoH area.
shall be located in appropriate open-to-sky VRF yard within the building.
The indoor FCUs and its associated temperature control will be connected to the BMS
Refuse Rooms to enable monitoring/setback/scheduling, etc.
Wall or ceiling mounted, exposed DX/VRF indoor FCUs will be used for cooling these
and similar areas. Wall mounted controllers will be used. Electrical Rooms
Food waste storage rooms will be cooled using DX type refrigeration unit to ensure the These rooms will be air conditioned by ducted VRF indoor fan coil units (FCUs) to
lower environmental health standard temperature levels can be maintained. maintain stable conditions given the high heat dissipation. Indoor FCUs shall be
located outside the room in a common corridor or BoH area.
Service Equipment Areas
The indoor FCUs and its associated temperature control will be connected to the BMS
Wall or ceiling mounted, exposed VRF indoor FCUs will be provided for cooling and to enable monitoring/setback/scheduling, etc.
heating these and similar areas. Wall mounted controllers will be used. The FCU
controls will be linked to the BMS to enable temperature setback, time scheduling etc.
F&B Restaurants In accordance with sustainability requirements, for areas with occupant density greater
than 25 people per 100 m² and area large than 50m² like Exhibition spaces, energy
efficient controls such as Indoor air quality monitoring and demand control ventilation
Comfort cooling for the Restaurant/Cafe will be provided by the Tenant as part of the
(DCV) shall be provided. A combination of variable and constant airflow for OA-AHUs
fit-out contract works and hence will be designed as and . Treated outside
shall require VSD. Variable outdoor airflow shall be supplied to match occupancy
air for general ventilation will be supplied from the Tenant supplied OA-AHUs. Any
whereas constant outdoor airflow shall be provided to rest of the areas if common OA-
additional make up air to offset tenant kitchen/toilet extract ventilation and ecology
AHUs are provided to meet minimum ventilation airflow rates and to achieve required
unit/exhaust fans shall be provided by the Tenant. Tenant will provide their own VRF
pressurization and air-balancing.
system to cater for total cooling demand.
Offices and Meeting Rooms
Ventilation
The outdoor air supply to all office spaces located in Experience Center Building shall
In order to maintain good indoor air quality within the various zones, minimum outdoor be ducted and supplied by building central Outdoor Air-Air Handling Units (OA-AHU)
(or fresh) air and extract air flow rates to each space shall be in accordance with located at roof floor levels. The outdoor air shall be ducted to the ceiling void. The
ASHRAE 62.1 Ventilation Standard Latest Edition. balance air will be extracted and reticulated back to the OA-AHU to maximize energy
recovery. The total outdoor air will be offset partially by extract air from the adjoining
Dedicated OA-AHUs shall be proposed in each building. The outdoor air ventilation common toilet and pantries whereas the rest of the extract will be via dedicated
systems typically incorporate dedicated outdoor air system via energy with energy extract from the office space. Interconnecting corridors will also be provided with
recovery wheel. Given that local conditions, a VRF based DX cooling coil, steam minimum outdoor air with entire floor plate provided with surplus air to ensure overall
humidifier and electric reheat coil shall be considered and as such outside air can be building positive pressurization by minimum 5%.
dehumidified or humidified, cooled and reheat to desired conditions. In overall
positive pressurization shall be maintained (typically +5%) to reduce the infiltration
which will provide better control of internal humidity levels as well as reduce sand and Exhibition Halls, Galleries, Experience Centre, Mini Cube, Innovation Lab
dust ingress.
These areas shall be served by AHUs with dedicated Outdoor Air-Air Handling Units
ASHRAE 62.1 ventilation standards has been adopted whilst locating air intake and (OA-AHU) adjacent to the AHUs. Fresh air shall be ducted and connected to the mixing
extract outlets to ensure minimum separation distances are maintained to prevent cross box of the AHUs. The balance air will be extracted and reticulated back to the OA-AHU
contamination of clean air with dirty air. to maximize energy recovery.
The outdoor air will typically be decoupled from the comfort cooling systems serving Based on expected high occupancy, demand control ventilation shall be provided to
the various zones regardless of comfort cooling strategy. In general, the outdoor air these spaces. CO2 sensors shall be provided at the main return duct or within the
volume shall be sized to: occupied space. Motorized damper with airflow measuring station shall be provided at
fresh air and extract air branches to the spaces to modulate ventilation air. Extract air
from the space shall also be modulated ensuring positive pressurization of each
• Provide good indoor air quality
building.
• Offset extract air
• Provide building pressurization
Toilets and Pantries The kitchen exhaust point will typically be located at the roof of the building, so as not
to cause disturbance to the occupants.
These areas will be maintained at negative pressure with make-up air scavenged from
adjoining spaces. Extract air from toilets and pantries will be ducted and reticulated All kitchen extract ductwork will be fire rated and fully insulated from the kitchen to
back to OA-AHUs for energy recovery. the exhaust locations; and where practical and possible the kitchen extract ductwork
will be at negative pressure with the kitchen extract fans located at the point of
Dedicated Ventilation discharge, to mitigate any risk of leakage from the ductwork.
For specific areas, it is necessary to have dedicated mechanical extract systems where
Transformer Room Ventilation
the exhaust air is discharged direct to atmosphere. Make-up air will be provided from
central ventilation systems, i.e. the outdoor air systems, or with air channeled directly
from outside, where this is acceptable. Rooms requiring dedicated extract will include, Transformer room shall be ventilated in accordance with SEC regulations. Forced
but are not limited to: ventilation shall be provided with dedicated fans sized to maintain maximum
allowable temperature within the room.
• Garbage rooms;
Smoke Management System
• UPS/Battery charging rooms;
• Chemical Stores; For buildings categorized as low-rise building, no specific pressurization and smoke
extract systems are required as per local FLS Codes.
Retail F&B Ventilation Innovation Lab, Experience Centre and Utility Building are low-rise buildings and do
not require a dedicated smoke management system. However, the main reception /
lounge in Experience Center with more than 2 storeys opening into a common atrium
The F&B retail unit will be designed as & . The ventilation system will be
will require dedicated smoke extract system.
designed, supplied and installed by the respective tenants. Kitchen ventilation systems
will discharge kitchen extract air directly to the atmosphere and will be specified to
Mini Cube is more over 24m high structure and will require pressurization for staircases
comprise of:
extending to the roof deck.
• Kitchen Ventilation hood complete with integral grease and smoke filtration
Fire pump room in utility building shall be provided with dedicated extract and make
systems;
up air fan to maintain temperature during diesel pump operation in accordance with
NFPA-20.
• Dedicated extract from the kitchen cooking areas, as advised by the kitchen
specialist;
Odour control will also be provided and would include UV (ultraviolet) lamps, typically
located at the kitchen canopy and downstream electrostatic precipitator (ESP) or other
applicable odor neutralizer systems comprising of Ecology units and exhaust fans.
Following will be connected to BMS: To meet the Sustainability requirements, Energy efficiency monitoring and control shall
be integrated into the BMS system which will be connected to interactive smart
dashboards and displays to showcase the passive sustainability and energy efficient
• VRF system (Outdoor unit, Indoor unit, thermostats).
systems considered for the development. The dashboards shall also highlight the
energy and water consumptions of the building and compare it to established baseline
• Fans.
benchmarks to help the facilities management team to monitor the building based on
its intended energy usage and carry out the necessary corrective actions.
• AHUs and FAHU.
BMS shall also be intelligent IoT enabled comprehensive, insightful and intuitive
• CCUs/CRAC Units platform that will help connect, collect and analyze data to generate actionable
information and thus drive savings through actionable information and communicating
• Plumbing pumps (booster pump, sump pumps etc.) transparent results to various system users.
• Firefighting equipment
• Water tanks
• Generators
• Switchgear
• EV Charging Stations
Figure 5-4 Innovation Lab & F&B, Ground Floor, AHU Zoning
Figure 5-5 Innovation Lab & F&B, First Floor, AHU Zoning
Figure 5-6 Innovation Lab & F&B, Mezzanine Floor, AHU Zoning
Hot water generation for each building shall be by local ceiling-mounted electric water
heater with storage 2-hour recovery time.
The incoming water supply from National Water Company NWC is of good quality and as
per standards. However, a multimedia filter is proposed to have a minimum level of
protection. Circulation pump shall be provided to recirculate the water in the central
water tank to avoid water stagnation.
Chlorination shall be done in the main filtered water storage tanks, to prevent legionella
growth in the storage tank. Chlorine is effective against most bacteria, viruses, algae, and
fungi. Chlorination is mainly used on systems where the point of use is away from the
source and water is stored in tanks and supplied to usage points.
A chlorine-dosing pump will add a pre-fixed amount of diluted chlorine to the system as
the water passes into the tank. The amount of chlorine in water is monitored by the
residual chlorine analyzer, as the amount of chlorine required for effective treatment will
vary in line with the water quality. It is important to ensure chlorine level stays within the
recommended limits. Lower concentration will make the system ineffective as not all the
contaminants will be destroyed, and higher concentration is not good for human
consumption.
The dosing system shall maintain 0.5 1 mg/litre chlorine concentrations at the point of
dosing. Residual chlorine at the point of delivery shall be minimum 0.2 mg/litre (0.2
mg/litre minimum to 0.5 mg/litre maximum). The chlorine dosing system shall be fully
automatic to achieve the desired level of the chlorination in the distribution network.
The cold water will have sufficient flow and pressure at the water meter to feed water to
the remotest fixture at the desired flow and pressure. The water supply pipes will
reticulate at high level through the ceiling voids. The vertical pipes will run through shafts.
Isolation valves will be provided at the entry to each toilet/kitchen and on every level for
isolation of the floor.
The drainage from the building will be collected by means of gravity and connected to
the infra sewer tie-in-connection allowed for the building. The external sewerage network A separate network shall be installed for the F&B restaurant areas or any Attractions with
outside the building is detailed in the infrastructure section of the report. The gravity kitchen waste. The kitchen waste from the spaces will then be connected to
drainage systems will be designed in accordance with SBC 701 and the local AHJ. underground Automatic grease traps near to kitchen cooking area.
Drainage designs within the buildings will be on the principle of separate stacks for soil A grease bowser connection is provided at the ground floor to collect the grease sludge.
and waste pipes, with long radius bends, at the foot of the stack. An inbuilt grease pump will be discharging the grease to the ground level bowser
connection with a hose coupling arrangement for easy connection to the hose,
Horizontal drainage pipe runs will be provided with enough gradients. An adequate and the clear wastewater from the grease trap will be discharged to the external sewer
number of floor clean-outs shall be provided on long pipe runs and at change in network.
directions, to ensure that the system is easily accessible for maintenance works.
Grease separators shall also be provided with a domestic water supply from the landlord
distribution for internal cleaning of the separator by means of the bundled separator
Soil drainage lines from the toilet shall be connected to manhole, for further connection
cleaning Pump. The cleaning pump delivers water at very high pressure to clean the
to site-wide sewer network.
internal walls of the separator of residual grease and sludge
The wastewater lines inside the building from wet areas like toilet, kitchens, plant rooms,
and other areas will be reticulated by gravity, to discharge into a gully trap and further
connected foul drainage network through a building manhole connection. The location of
the gully trap and tie-in-connection manhole shall be coordinated with the landscape
and infrastructure utilities.
All toilets and kitchens will be provided with floor traps and cleanouts.
Gas system
Fire Protection System
LPG will be provided to meet the F&B restaurant and attractions kitchen cooking
purposes. The LPG gas will be stored in cylinders, and the cylinder will be sized to cater
for the required demand. location of gas cylinder shall be further coordinated with Fire protection system shall be provided to comply with the requirements of SBC 801 Fire
architecture as per civil defense requirements. code and local authority having jurisdiction.
The local authority regulates the installation of LPG systems within chapter 61 of SBC 801, Dedicated fire water storage and fire pumps will be provided at MEP utility building-01
which imposes limitations on LPG capacity, location, and distribution within buildings. and will serve all firefighting demands for the entire plot. There will be one common fire
pump set and fire tank for whole development this will serve both the external hydrants
Supply to the F&Bs in the ground and floors is through dedicated risers located within fire- and all buildings within the development. The fire tank and fire pump are sized to
rated shafts. Then the LPG pipework will be routed and terminated within the F&B 2000GPM for 2hours to meet the fire flow requirements of external hydrants, sprinklers
unit kitchens with a valve and capped off for extension by the tenant. All necessary and standpipe systems for all buildings withing the development. This shall be further
notification for gas cylinder protections, the system and will be in line with local authority validated by FLS consultant next design stage
requirements. The pipework associated with the gas distribution shall be of welded pipe in
pipe with all the risers will be located in a dedicated fire-rated shaft. Gas will be Automatic sprinkler systems shall be proposed in accordance with NFPA 13 and SBC 801
distributed to the building areas and connect to each valve set consisting of isolation for all buildings. Fire extinguishers will be provided according to the maximum travel
valves, solenoid gas safety shut off valve, gas regulator, and gas meter. The safety devices distance as stated in NFPA 10. Each extinguisher will be installed at a conspicuous location
will be linked back to the interface to the building fire alarm panel. The branch connection such as in corridors, near entrances etc., this shall be further validated by FLS consultant.
to each F&B kitchen area will be served and fitted with an electronic gas meter connected
to BMS, a pressure regulator and isolating valve. The fire tank capacity and fire pump flow rate are being currently coordinated with FLS
consultants and shall be confirmed at the end of the concept design stage of the entire
development. The indicative fire tank capacity for the development is 772m3.
The building will be supplied with both an automatic sprinkler system and wet risers. There
will be a 150mm fire main tap off connection provided to the building from the infra fire
network. The fire main shall be extended to the building from the Infra fire main network
into the fire valve room of the building. The alarm check valve shall be located within the
fire valve room and each floor shall be provided with a zone control valve located within a
ceiling void and this shall be further coordinated in next design stage.
MEP Demands
The MEP demands are provided in the tables below.
For large spaces such as exhibition halls, dedicated AHUs are recommended, with systems that may include economizer modes to utilize ambient air and minimize VRF system input . These spaces may also employ displacement or mixed-mode ventilation tailored to high occupancy and specific architectural needs. In contrast, smaller offices might use ceiling VoID Mounted VRF indoor Fan Coil Units or central AHUs with VAV terminals, allowing for flexibility within space constraints while still linking to building management systems for efficient control . Each system's design reflects the differing needs in ventilation, environmental conditions, and spatial management.
Spare capacity in electrical distribution systems, set at 20% across different levels like LV switchboards and UPS, enables future-proofing by allowing facilities to accommodate additional loads and expansion without significant retrofits . This foresight in design ensures that facilities can adapt to technological advancements and increasing power needs, thus enhancing operational longevity and flexibility at a marginal initial cost increment. This strategic buffer mitigates risks of overloading and costly upgrades, ensuring sustainable infrastructure scalability.
The document suggests considering factors such as the ability to link with a Building Management System (BMS), space availability for plant and ceiling voids, access and maintenance requirements, metering and billing strategies, acoustics, and operational costs . Flexibility, such as using VRF systems for variable zoning and the need for simultaneous heating and cooling, are also crucial. The selection must balance initial investment with long-term operational efficiency and adaptability to meet the building's functional and spatial demands.
According to NFPA 72, the standard spacing of heat detectors between each other is approximately 9.1m for ceiling heights up to 3 meters. For ceilings that are 3.0 to 9.1 meters high, the spacing must be reduced according to specific tables provided in the standard, ensuring effective detection by adapting to ceiling height variations . This tailoring ensures that detector response times are optimized regardless of ceiling height, aiming to improve safety by compensating for the changes in heat behavior in larger spaces.
VRF systems with 2-pipe configurations are used when only heating or cooling is needed at any given time, making them suitable for buildings with specific seasonal needs. The 3-pipe configuration allows for simultaneous heating and cooling, making it ideal for buildings with diverse spatial heating and cooling requirements, as found in mixed-use or large multi-zone settings . While the 3-pipe system offers enhanced flexibility, enabling it to adapt to varying climatic demands within a building, it is more complex and typically requires higher initial costs and more complex management .
The document specifies that emergency lighting systems should have distributed standalone units with an autonomy of at least 90 minutes, complying with standards like EN60598 . This aligns with legal safety standards by ensuring that in the event of a power failure, adequate lighting is sustained, providing visibility for safe evacuation. The autonomy requirement ensures that emergency lighting will remain operational long enough to address typical evacuation scenarios and meet regulatory requirements for safety.
Ceiling-mounted VRF fan coil units provide a flexible and efficient option for controlling climate conditions in office environments . Pros include their ability to be easily integrated into varied office sizes and layouts, offering zone control and reducing energy consumption through intelligent Building Management System (BMS) integration. Their unobtrusive installation can also maximize space use. However, they may require significant ceiling space, possibly limiting their application in offices with lower ceilings or structural constraints, and necessitate careful maintenance access planning to avoid disturbing the workspace.
The document specifies that underground ducts for cable containment in outdoor environments should use rigid heavy-gauge PVC ducts that are directly buried or encased in concrete as applicable . This is to ensure durability and protection from environmental factors. Additionally, cable tray systems must adhere to BS EN 61537 for outdoor use . These specifications are critical for safeguarding cables from physical damage and environmental influences, ensuring long-term reliability.
The document outlines a Lighting Control System (LCS) that includes dimming, energy-saving methods, and the exploitation of natural light . Implementing such systems can significantly enhance energy efficiency by reducing unnecessary energy consumption through automatic adjustments. Natural light utilization reduces the dependency on artificial light, and dimming capabilities allow the adjustment of lighting intensity based on the time of day and occupancy, further ensuring minimal energy waste.
The lighting requirement for the Security Control Room is set at 500 lux at 0.75m above the floor level, with LED luminaires specified, as per BS EN 12464-1 and CIBSE standards . This high level of illumination is necessary to ensure that security personnel can effectively monitor systems and maintain vigilance, which is critical for effective situational awareness and the rapid detection and response to any incidents.