0% found this document useful (0 votes)
524 views8 pages

Rate Analysis for Piling Work

The document contains a rate analysis for boring piles of 500mm diameter using hydraulic piling rigs. It provides details of costs for a 20m length pile including materials, machinery, and labor. The total estimated cost is Rs. 30,372 per 20m length pile or Rs. 1,519 per running meter. It also provides estimated labor rates for fabrication and lowering of reinforcement cages excluding binding wire. The site proposed rates are higher than the rates according to the company headquarters, resulting in a variance of Rs. 150,888 for the total job.

Uploaded by

Rajeev Reddy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
524 views8 pages

Rate Analysis for Piling Work

The document contains a rate analysis for boring piles of 500mm diameter using hydraulic piling rigs. It provides details of costs for a 20m length pile including materials, machinery, and labor. The total estimated cost is Rs. 30,372 per 20m length pile or Rs. 1,519 per running meter. It also provides estimated labor rates for fabrication and lowering of reinforcement cages excluding binding wire. The site proposed rates are higher than the rates according to the company headquarters, resulting in a variance of Rs. 150,888 for the total job.

Uploaded by

Rajeev Reddy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

GVPR ENGINEERS LTD.

,
Name of the Project: Ghatkopar WwTF Project
Name of Sub Work: Rate Analysis for Boaring of Piles of Dia 500 mm Dia
No of Pile Total As per GVPR H.O As per Site Proposed
[Link] Description Uom Variance
Piles Depth Depth Rate(Rs.) Amount(Rs.) Rate(Rs.) Amount(Rs.)

Providing, driving with hydraulic piling rigs with power units and installing
driven cast-in-situ reinforced cement concrete piles of grade M-25 of 500mm
diameter and length below the pile cap, to carry safe working load not less than
1 specified, including Piles concreting for completion of work in all respects as per
design drawings and instructions of the Engineer-in-Charge, ( Excluding cost of
Concrete) but including the cost of shoe and the length of pile to be embedded in
the pile cap etc. all complete. (Length of pile for payment shall be measured from
top of shoe to the bottom of pile cap) :

a All Kinds of Soil Rmt 24 13 312 1,012 315,744 1,500 468,000

b Hard Rock Rmt 24 3 72 1,519 109,368 1,500 108,000

2 Labour Charges for Fabrication and Cage lowering in Bored Piles M.T 4.23 6,500 27,484 6,500 27,484

3 Transportation charges for shifting machine Ls 40,000 40,000

Total Amount 492,596 643,484 150,888


GVPR ENGINEERS LTD.,
Name of the Project: Ghatkopar WwTF Project
Name of Sub Work: Rate Analysis for Boaring of Piles of Dia 500 mm Dia( Hydraulic piling rigs )
[Link] Description Uom Qty Rate Amount Remarks

Providing, driving with hydraulic piling rigs with power units and installing driven
cast-in-situ reinforced cement concrete piles of grade M-25 of 500mm diameter
and length below the pile cap, to carry safe working load not less than specified,
including Piles concreting for completion of work in all respects as per design
drawings and instructions of the Engineer-in-Charge, ( Excluding cost of Concrete)
but including the cost of shoe and the length of pile to be embedded in the pile cap
etc. all complete. (Length of pile for payment shall be measured from top of shoe to
the bottom of pile cap) :

Details of cost for 20 m length of pile


A MATERIAL
Concrete Qty for 500 mm Dia 20m Length Cum 3.93 169 664 Labour Rate
B MACHINERY
Hire and running charges of hydraulic piling rig with power unit etc. including Day 0.5 30,000 15,000
complete accessories and shifting at site.

Hire and running charges of light crane. Day 0.1 3,074 307

C LABOUR

Operator Day 0.5 1,000 500

Rigger Day 2 800 1,600


Sub Total 18,071
Add Contractor Profit @12.5 % 12.5% 2,176
Amount for 20m Length 20,247
Amount for 1m Length 1,012 Per Rmt

2 Details of cost for 20 m length of pile


Steel Rreinforcement M.T 0.220 6,500 1,431.44 Labour Rate excluding Binding Wire
Labour Charges for Rmt M.T 0.011 6,500 71.57
GVPR ENGINEERS LTD.,
Name of the Project: Ghatkopar WwTF Project
Name of Sub Work: Rate Analysis for Boaring of Piles of Dia 500 mm Dia( Hydraulic piling rigs )
[Link] Description Uom Qty Rate Amount Remarks

Providing, driving with hydraulic piling rigs with power units and installing driven
cast-in-situ reinforced cement concrete piles of grade M-25 of 500mm diameter
and length below the pile cap, to carry safe working load not less than specified,
including Piles concreting for completion of work in all respects as per design
drawings and instructions of the Engineer-in-Charge, ( Excluding cost of Concrete)
but including the cost of shoe and the length of pile to be embedded in the pile cap
etc. all complete. (Length of pile for payment shall be measured from top of shoe to
the bottom of pile cap) :

Details of cost for 20 m length of pile


A MATERIAL
Concrete Qty for 500 mm Dia 20m Length Cum 3.93 169 664 Labour Rate
B MACHINERY
Hire and running charges of hydraulic piling rig with power unit etc. including Day 0.8 30,000 24,000
complete accessories and shifting at site.

Hire and running charges of light crane. Day 0.1 3,074 307

C LABOUR

Operator Day 0.5 1,000 500

Rigger Day 2 800 1,600


Sub Total 27,071
Add Contractor Profit @12.5 % 12.5% 3,301
Amount for 20m Length 30,372
Amount for 1m Length 1,519 Per Rmt

2 Details of cost for 20 m length of pile


Steel Rreinforcement M.T 0.220 6,500 1,431.44 Labour Rate excluding Binding Wire
Labour Charges for Rmt M.T 0.011 6,500 71.57
PROJECT: PURI GANJAM KRISHNA PRASAD
RATE ANALYSIS

Providing and laying M30 Concrete for Footings / Raft, Column up to 3m

[Link]. Unit-1Cum Description Unit Rate Labour rates

MATERIALS:
1 1 Cum M25 Ready Mix Concrete Cum 5,086.00

MANPOWER
2 0.25 No. Mazsdoor (Unskilled) No 600.00 150.00
150.00
Total: 150.00
Add C.P & O.H @12.5% 12.5% 18.75
18.75
168.75
169.00
Providing cutting, bending and fixing of steel Reinforcement

Unit-1MT MATERIALS: Unit Rate Labour rates

1 1 MT Reinforcement Steel-Fe 500 MT 55,600.00 Excl. GST


2 7 Kg Binding Wire Kg 80.00

MACHINERY :
3 0.10 Day Cutting Machine and bending-Mechanical Type Day 600.00
4 0.15 Day D.G Set Day 500.00
5 0.50 Litr Fuel Charges: Litr -

MANPOWER
6 2 Nos Blacksmith / Bar bender No 800.00 1,600.00
7 7 Nos Mazdoor (Unskilled) No 600.00 4,200.00
5,800.00
Total: 5,800.00
Handling charges steel - 5% 5% -
Add C.P & O.H @12.5% 12.5% 725.00
Total 6,525.00
6,525.00
6,500.00 Say
Sl No Item Make UOM Rate (Rs.) Unit

1 Cement Opc 43Gr Ultratech Bags 246 Bag Excl GST


2 TMT Bar 8MM Tata MT 67,715 MT Excl GST
3 Aggregate 10MM Cft Cum
4 Aggregate 20MM Cft Cum
5 Aggregate 40MM Cft Cum
6 River Sand Cft Cum
7 Ply Wood 12mm Commercials 8'x4' Sqrft Nos
8 Wooden Runner 4"x2" m
9 Binding Wire 18 G kg 80 Kg
10 Nails kg Kg
11 Diesel Ltr Ltr
12 Shuttering Oil Ltr Ltr
13 M.S Pipe 12 kg/40MM Kg
14 L. Angle 40x40x5 Kg
15 Squre Tube 40x40 Kg
16 MS Flat Kg
17 MS Plate Kg
18 White Cement Birla Bag 50 kg
19 Oil Paint Asian 4 ltrs pack 225 Litr
17 Water proof cement paint 20 Kg
Hire charges
[Link]. Description Unit Remarks
(Rs.)

1 Miller mixer machine Day 600


2 Lifting Hoist & Winch Day 833
3 Ajax 4Cum/Batch Month 220,000
4 Cutting & Bending Machine Day 600
5 DG Set Day 500
[Link]. Description Unit Hire charges (Rs.) Remarks

1 Mason Day 800

2 Steel fixer Day 800

3 Carpentor Day 800

4 Helper Day 600

5 Painter Day 800

You might also like