0% found this document useful (0 votes)
21 views2 pages

Culvert

The document provides a detailed estimate for the construction of an RCC culvert including 10 items of work. It lists the quantities, rates, and amounts for each work item such as excavation, brick work, concrete work, reinforcement, plastering and more. Transportation costs for materials and other details are also provided. The total estimated cost is around Rs. 113400.

Uploaded by

chhunuryadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views2 pages

Culvert

The document provides a detailed estimate for the construction of an RCC culvert including 10 items of work. It lists the quantities, rates, and amounts for each work item such as excavation, brick work, concrete work, reinforcement, plastering and more. Transportation costs for materials and other details are also provided. The total estimated cost is around Rs. 113400.

Uploaded by

chhunuryadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

DETAILED ESTIMATE FOR CONSTRUCTION OF R.C.

C CULVERT (3’×3’)

AT: G.P:
BLOCK: DIST:

[Link]: ITEMS OF WORK QTY RATE AMOUNT


(1). Earthwork in excavation in foundation trenches
In hard soil do……do……asper……………………E/I.
2×21’3”×3’0”×3’6”=446.25 cft
w/w: 2×12’0”×3’0”×3’6”=252.00 cft
Bed: 1×19’0”×2’0”×1’0”=38.00 cft
736.25 cft 20.85 m3 Rs 112.53/m3 Rs 2346.00
(2). Providing coarse clean sand filling in foundation
& plinth do…………….do…………………………………E/I.
2×21’3”×3’0”×0’3”=31.88 cft
2×12’0”×3’0”×0’3”=18.00 cft
1×19’0”×2’0”×0’3”=9.50 cft
59.38 cft 1.68 m3 Rs 228.47/m3 Rs 384.00
(3). Providing 75 B brick flat soling in foundation &
Plinth do…………………do…………………………….E/I.
2×21’3”×3’0”=127.50 cft
2×12’0”×3’0”=72.00 cft
1×19’0”×2’0”=38.00 cft
237.50 cft 22.07 m2 Rs 225.81/m2 Rs 4984.00
(4). Providing P.C.C ([Link]) in foundation & plinth
do………………………do………………………………..E/I.
2×21’3”×3’0”×0’6”=63.75 cft
2×12’0”×3’0”×0’6”=36.00 cft
1×19’0”×2’0”×0’6”=19.00 cft
118.75 cft 3.36 m3 Rs 4188.87/m3 Rs 14075.00
(5). Providing 75 B brick work(1:6) inn foundation
Do……………………………….do………………………..E/I.
2×19’7”×2’1”×1’0”=81.45 cft
2×12’0”×2’1”×1’0”=49.92 cft
2×20’0”×1’8”×1’6”=99.60 cft
2×12’0”×1’8”×1’6”=59.76 cft
2×20’0”×1’3”×3’0”=150.00 cft
2×12’0”×1’3”×3’9”=112.50 cft
Parapet:2×12’0”×1’3”×1’6”=45.00 cft
Deduct:2×3’0”×1’3”×3’0”=(-)22.00 cft
575.73 cft 16.30 m3 Rs3820.60/m3 Rs 62,277.00
(6). Providing R.C.C([Link]) in deck slab do..do..E/I.
1×22’6”×5’6”×0’9”=92.81 cft 2.63m3 Rs 5913.66/m3 Rs 15,553.00
(7). Providing Tor steel reinforcementof diff. dia
do………………………………do……………………E/I.
Qty:92.81 cft @ 3.00kg/cft=278.00 kg 0.278/MT Rs 53433.91/MT Rs 14,855.00
(8). Providing 12 mm thick C.P (1:6) with punning
do…………………………….do……………………………E/I.
2×22’6”×3’0”=135.00 sft
2×12’0”×3’0”=90.00 sft
Parapet:2×12’0”×1’6”=36.00 sft
Top:2×12’0”×1’3”=30.00 sft
Side:2×2×1’6”×1’3”=7.50 sft
298.50 sft
Deduct:2×3’0”×3’0”=18.00 sft
280.50 sft
26.07 m2 Rs 170.51/m2 Rs 4445.00
Rs118919.00
Deduct
i. Deduct 9.09% c.p………………………………………………………………………………..……(-) Rs10809.00
ii. Deduct diff. cost of Bangle Bhatha
Bricks 7335 Nos @ Rs(4780.20-3107.17)=Rs1673.03/%………………………………(-)Rs12272.00
iii. Deduct diff. cost of cement 64 bags
@Rs(329.456-255.00)=Rs74.46/bags…………………………………………………………..(-)Rs4765.00
Rs 91073.00
(9). Carriage cost of materials:-
i. Bricks (Lead 8 Km) -7335 Nos @Rs661.72/%.......................................................Rs4854.00
ii. Stone chips (Lead 30 Km)-5.50 m3 @Rs524.02/ m3………………………………………..Rs2882.00
iii. Sand (Lead 10 Km)-13.50 m3 @Rs294.42/ m3………………………………………………..Rs3975.00
iv. Cement (Lead 25 Km)-3.2 MT @Rs293.90/MT………………………………………………Rs940.00
Rs103724.00
(10). Earth filling in road embankment in
Approaching hard soil do-do- of E/I
2×20’-0” ×24’-0”+20’-0” ×3’-0”+2’-0” =2200.00 cft
2 2
3 3
Or 62.34 m @Rs112.53/m …………………………………………………………………………………..Rs 7015.00
Deduct 9.09% c.p……………………………………………………………………………………………….(-)Rs638.00
Rs111377.00
Add for labour cus 1%..................................................................................................Rs114.00
Add for signboard & photography…………………………………………………………………………Rs1000.00
Rs113491.00

Say Rs 113400.00