Sunsynk Hybrid Inverter Installer Manual
Sunsynk Hybrid Inverter Installer Manual
INSTALLER MANUAL
3.6kW/5.5kW/8.8kW PLUS PARALLEL VERSION
SUNSYNK-8K-SG01LP1 SUNSYNK-5K-SG03LP1 SUNSYNK-8K-SG02LP1 SUNSYNK-7.6K-
SG02LP1 SUNSYNK-6K-SG02LP1 SUNSYNK-5K-SG02LP1 SUNSYNK-3.6K-SG02LP1
Global Tech China Ltd, 3 Floor, Wai Yip Industrial Building.171 Wai Yip Street,
Kwun Tong, Kowloon, Hong Kong.
Tel: +852 2884 4318 Fax: +8522884 4816
[Link] / sales@[Link] / [Link]
8.8 kW Type
SUNSYNK-8K-SG01LP1
SUNSYNK-8K-SG02LP1
SUNSYNK-7.6K-SG02LP1
Index
1. SAFETY ................................................................................................................................................5
3. INSTALLATION .................................................................................................................................. 11
4. OPERATION ....................................................................................................................................... 23
APPENDIX A ............................................................................................................................................. 56
APPENDIX B ............................................................................................................................................. 57
APPENDIX C ............................................................................................................................................. 57
APPENDIX D ............................................................................................................................................. 57
APPENDIX E ............................................................................................................................................. 58
1. SAFETY
◼ Always use an individual power supply line protected by a circuit breaker and operating on all wires
with a distance between contacts of at least 3mm for this unit.
◼ The unit must be correctly grounded and the supply line must be equipped with a suitable breaker and
RCD to protect people.
◼ Never touch electrical components immediately after the power supply has been turned off since the
system can still have residual energy, so electric shock may occur. Therefore, after turning off the
power, always wait 5 minutes before touching electrical components.
◼ This unit contains no user-serviceable parts. Always consult an authorized contractor for repairs.
The Sunsynk Hybrid Parity Inverter is a highly efficient power management tool that allows the user to
hit those ‘parity’ targets by managing power flow from multiple sources such as solar, main electrical
grids, and generator, and then effectively storing and releasing electric power as the utilities require.
INTERACTIVE
COMPATIBLE
CONFIGURABLE
SECURE
◼ Overload/over-temperature/short-circuit protection
◼ Smart battery charger design for optimized battery protection
◼ Limiting function installed to prevent excess power overflow to grid
APPLICATIONS
SUNSYNK-8K-
SUNSYNK-5K- SUNSYNK-6K- SUNSYNK-7.6K- SG01LP1/
Model
SG02LP1 SG02LP1 SG02LP1 SUNSYNK-8K-
SG02LP1
Battery Input Data
Battery Type Lead-acid or Lithium-ion
Battery Voltage Range (V) 40~60V
Max. Charging Current (A) 120A 135A 190A 190A
Max. Discharging Current (A) 120A 135A 190A 190A
Charging Curve 3 Stages/Equalisation
External Temperature Sensor Optional
Charging Strategy for Li-Ion Battery Self-Adaptation to BMS
PV String Input Data
Max. DC Input Power (W) 6500W 7800W 9880W 10400W
PV Input Voltage (V) 370V (100V~500V)
MPPT Range (V) 125~425V
Start-up Voltage (V) 150V
PV Input Current (A) 11A+11A 18A+9A 22A+22A 22A+22A
No. of MPPT Trackers 2
No. of Strings Per MPPT Tracker 1+1 2+1 2+2 2+2
AC Output Data
Rated AC Output and UPS Power
5000W 6000W 7600W 8000W
(W)
Max. AC Power (W) 5500W 6600W 8360W 8800W
Peak Power (off-grid) 2 times of rated power, 10 S
AC Output Rated Current (A) 20.8A 25A 31.7A/33A 33.4A/35A
Max AC Output Current (A) 24A 28.8A 36.4A/38A 38.3A/40A
Max Continuous AC Passthrough (A) 48A 80A 90A 90A
Output Frequency and Voltage 50/60Hz; 120/240Vac(split phase), 208Vac(2/3), 230Vac(single phase)
Grid Type Split phase, 2/3 phase, Single phase
Current Harmonic Distortion THD<3%(Linear load<1.5%)
Efficiency
Max. Efficiency 97.60%
MPPT Efficiency 96.50%
Euro Efficiency 99.90%
Protection
PV Arc Fault Detection Integrated (Except European Type)
PV Input Lightning Protection Integrated
Anti-islanding Protection Integrated
PV String Input Reverse Polarity
Integrated
Protection
Insulation Resistor Detection Integrated
Residual Current Monitoring Unit Integrated
Output Over Current Protection Integrated
Output Shorted Protection Integrated
Output Over Voltage Protection Integrated
◼ Areas with high salt content, such as the marine environment. It will deteriorate metal parts, causing
the parts to fail or the unit to leak water.
◼ Areas filled with mineral oil or containing a large amount of splashed oil or steam, such as a kitchen.
It will deteriorate plastic parts, causing the parts to fail or the unit to leak water.
◼ Areas that generates substances that adversely affect the equipment, such as sulfuric gas, chlorine
gas, acid, or alkali. It will cause the copper pipes and brazed joints to corrode, which can cause
refrigerant leakage.
◼ Areas that can cause combustible gas to leak, which contains suspended carbon-fiber or flammable
dust, or volatile inflammable such as paint thinner or gasoline.
◼ Areas where there may be gas leaks and settles around the unit. It can cause fires.
◼ Areas where animals may urinate on the unit or ammonia may be generated.
◼ High altitude areas above 4000 meters above sea level.
◼ Environments where precipitation or humidity are above 95%
◼ Areas where the air circulation is too low.
ALSO CONSIDER:
◼ Select installation locations that adequate to support the weight of the converter.
◼ Install this inverter at eye-level to allow the LCD to be read anytime.
◼ An appropriate ambient temperature is between -25 ~ 60°C to ensure optimal operation.
◼ Be sure to keep other objects and surfaces as shown in the figure to guarantee sufficient heat
dissipation and have enough space to remove wires.
◼ For proper air circulation to dissipate heat, allow a clearance of approximately 50cm to the side.
For safe operation and compliance, an individual DC overcurrent protector or disconnection device is
required for the connection of the battery and the inverter. It is recommended to utilize a suitable fuse
and DC isolator (see next page). In some applications, switching devices may not be required but
overcurrent protectors are still required.
A minimum battery cable size of 35mm diameter and 50mm diameter is recommended for the 5.5
kW and 8.8kW inverter, respectively.
When connecting a Lithium battery, follow the connection steps bellow and then check section 4.13
“Setting Up a Lithium Battery” for setting it up in the inverter:
1. Connect a properly power cable following the battery manufacturer specification and recommend
safety devices.
Without a remote temperature sensor, lead-acid batteries may undercharge or overcharge depending on
the ambient temperature of the installation environment. This may result in a fire hazard.
All wiring and cable sizing must be following the country wiring regulations and code of
practices.
Ensure that suitable disconnection devices and RCDs are fitted.
NOTES
◼ Depending on the battery type, the inverter should be capable of controlling the batteries BMS.
Therefore, you need to set the protocol of the BMS on both the battery and the inverter.
◼ WHEN USING MORE THAN ONE BATTERY, THE FIRST BATTERY WILL BE THE MASTER,
AND THE OTHER BATTERIES WILL BE THE SLAVES. PLEASE, CHECK THE BATTERY
MANUFACTURER SPECIFICATION FOR PROPER OPERATION.
◼ To verify if the battery is actually communicating access the Li BMS menu as detailed in section
4.13 “Setting Up a Lithium Battery” and check whether the values are realistic or not. It is important
that the charge and discharge limits in that page match the numbers expected for the number of
batteries physically connected.
◼ Bottom view of the 3.6kW/5.5kW model
Check that AC power source is isolated before attempting to wire it to the inverter Insert AC output wires
according to polarities indicated on the terminal block and tighten terminal. Be sure to connect
corresponding N wires and PE wires to related terminals and ensure the wires are securely connected.
The CT coil is one of the most important parts of the Sunsynk Parity inverter. This device reduces the
power of the inverter to prevent feeding power to the grid. This feature is also known as "Zero Export".
◼ Fit the coil (sensor) around the live cable on the main fuse feeding the building and run the cable back
to the inverter. This cable can be extended up to an extra 10m using a similar cable.
◼ Connect the other end of the CT coil into the inverter terminals marked as CT coil
Ground cable shall be connected to ground plate on grid side this prevents electric shock. if the
original protective conductor fails.
All neutrals can be linked together to maintain the neutral bond. When Neural Earth bond is required for
off-grid, then it has to be removed on grid-tied operation.
Since the inverter is a true hybrid then the bond must only be made when the inverter is operating in
Islanding Mode. To accommodate this, Sunsynk provides an AC output, which is connected to the A/T/S
connections whenever the inverter is running on Island Mode. Therefore, you can simply connect the coil
of an AC relay to the ATS 240 connections. Next, you need to select Signal Island Mode on the battery
charge menu (click on the gear icon -> battery icon), as shown in the figure below.
NOTE
The grid may still be present, but the inverter is not draining power from it since the unit is working in
Island Mode.
You can verify if there is a voltage when the inverter is disconnected from the grid by using a simple
multimeter.
The 3.6kW and 5.5kW models have only one MPPT controller with a maximum input current of 9Amp.
The 8.8kW inverter has two built-in MPPT controllers, MPPT 1 and MPPT 2. Therefore, two individual
arrays can be connected to each MPPT for better performance. The maximum current of the array
connected to each MPPT is 18Amp.
◼ Before connecting to PV modules, install a separate DC circuit breaker between the inverter and PV
modules.
◼ To avoid any malfunction, do not connect any PV modules with possible current leakage to the inverter.
For example, grounded PV modules will cause current leakage to the inverter. Open-circuit voltage
(Voc) of PV modules does not exceed max. PV array open-circuit voltage open-circuit voltage (Voc)
of PV modules should be higher than min. start voltage.
8.8 kW PV Connection
◼ Before connecting to PV modules, install a separate DC circuit breaker between the inverter and PV
modules.
◼ To avoid any malfunction, do not connect any PV modules with possible current leakage to the inverter.
For example, grounded PV modules will cause current leakage to the inverter. Open-circuit voltage
(Voc) of PV modules does not exceed max. PV array open-circuit voltage open-circuit voltage (Voc)
of PV modules should be higher than min. start voltage.
4.1. Display
Once the inverter has been properly installed and the batteries are connected, press the on/off button
(located on the left side of the case) to turn-on the system.
When the system is connected without a battery but connected with either PV or grid and the on/off button
is switched off, the LCD will still light up (display will show off). In this condition, when switching on the
on/off button and selecting no battery, the system can still work.
1. Customer name
◼ Total daily power into the battery (kWh). ◼ Real-time battery charge power in (kW).
◼ Total daily power out of the battery (kWh). ◼ Real-time grid power in (kW).
◼ SOC (State of charge of the battery) (%). ◼ Serial number.
◼ Total daily solar power produced in (kWh). ◼ Time date.
◼ Total hourly usage of the generator (Time). ◼ Fault condition.
◼ Total daily power sold to the grid (kWh). ◼ Access stats pages.
◼ Total daily power bought from the grid (kWh). ◼ Access status page.
◼ Real-time solar power in (kW). ◼ Access fault diagnostic page.
◼ Real-time load power in (kW).
To access the Status page, click on the “Battery” or “AC Load” dial on the Home page.
Solar Column: Shows total PV power at the top and then details of each of the two MPPT’s below L1 &
L2 voltage.
Grid Column: Shows grid total power, frequency, voltage, and current. When selling to grid the power is
negative. When receiving from the grid the power is positive. If the sign of the grid and HM powers are
not the same when the PV is disconnected and the inverter is only taking energy from the grid and using
the HM CT connected to Limit-2 then please reverse the polarity of the HM current sensor. Important:
See section on CT coil.
Inverter Column: Showing inverter total power, frequency, L1, L2, voltage, current, and power.
Load Column: Showing total load power, load voltage, and power on L1 and L2.
Battery Column: Showing total power from the battery, battery SOC, battery voltage, battery current
(negative means charge, positive means discharge) battery temperature (shows zero if the battery
temperature sensor is not connected). DC transformer temperature and AC heatsink temperature (When
the temperature reaches 90°C it will show in red and start deteriorating when it reaches 110°C. Next, the
inverter will shut down to allow it to cool and reduce its temperature.
To better understand the functioning of your system, take a look at the figure bellow:
To access the Setup page click on the gear icon on the right top of the navigation menu.
◼ Serial number.
◼ Software version.
◼ Time, Date, and MCU.
◼ Time.
◼ Date.
◼ AM/PM.
To set company name click on the “Basic“ icon and then on “Display”.
◼ Reset status.
◼ Whether lock code is used or not.
*Before performing a successful factory reset and locking the systems, to keep all changes you need to
type in a password to enable the setting. The password for factory settings is 9999 and for lock out is
7777.
To configure battery charging settings click on the “Battery” icon and then on “Batt Charge”.
◼ Tick Gen Charge to charge the batteries from the gen I/P.
◼ Tick Grid Charge to charge the batteries from the grid I/P.
◼ Tick Gen Charge signal to auto-switch a relay box.
◼ Tick Grid Charge signal to auto-switch a relay box.
IMPORTANT
Do not run this too often since it will damage the battery.
The generator can be connected either to the grid side or to the gen connection. When connected to the
grid input, the inverter will consider it a grid supply. However, you need to take care to do not export any
power since this could damage the generator. Therefore, you must limit your power to load only.
The nice thing about connecting the generator to the grid input is that it can be paralleled whereas the
Gen/Aux input cannot be paralleled. Also, the inverter will extract what it needs from the grid supply to
charge its batteries.
If you connect the generator to the Gen in part when there is a Gen signal, the inverter will switch 100%
of the load to the generator and then slowly step up the charging currents of the batteries. Therefore, the
generator must be able to supply both the charge current for the battery and the total load current.
The generator can be controlled via a relay, which is a set of dry contacts. The current on these contacts
is limited to 1 Amp 12v, approximately.
Below is a simple reference circuit that I used to auto-start generators on a boat. Sunsynk will release a
new OS E406 with better Gen control.
To configure inverter shutdown settings click on the “Battery” icon and then on “Shut Down”.
NOTE
Shutdown causes the inverter to enter standby mode. It will not completely shut down the inverter.
The total shutdown is below 19V.
The voltage displayed on the Sunsynk Parity Inverter will vary depending on whether the inverter is
charging or discharging the batteries.
State of Charge
Bulk: Involves about 80% of the recharge in which the charger current is held constant (in a constant
current charger), and voltage increases. The properly sized charger will give the battery as much current
as it will accept up to charger capacity (25% of battery capacity in Amp hours)
Absorption: Remaining charge equals 20%, approximately. It makes the charger to hold the voltage at
the charger’s absorption voltage (between 14.1 VDC and 14.8 VDC, depending on charger set points)
and decreasing the current until the battery is fully charged.
Float: The charging voltage is reduced to between 13.0 VDC and 13.8 VDC and held constant, while the
current is reduced to less than 1% of battery capacity. This mode can be used to maintain a fully charged
battery indefinitely.
Equalisation: This is essentially a controlled overcharge (the peak voltage the charger) that attains at
the end of the BULK mode (absorption voltage) an equalisation voltage, but technically it’s not. Higher
capacity wet (flooded) batteries sometimes benefit from this procedure, particularly the physically tall
batteries. The electrolyte in a wet battery can stratify over time, if not cycled occasionally. In equalisation,
the voltage is brought up above typical peak charging voltage well into the gassing stage and maintained
for a fixed (but limited) period. This stirs up the chemistry in the entire battery, “equalising” the strength
of the electrolyte, and knocking off any loose sulfating that may be on the battery plates.
NOTE
Some types of lithium battery the BMS cannot be controlled by Sunsynk inverter. In this case, treat
the battery as a lead-acid type and set the charging and discharging protocol following the battery
manufacturer specification.
It is important to always refer to the documentation of the battery manufacturers when installing the
battery. Below there is a list of batteries that has been examined, tested, and approved by Sunsynk.
48V RS485
Inverter
Brand Model Storage or Notes
Setup
Inverter CAN
CAN 0
US2000 ✓
Pylon or RS485 5
Equivalent US20000- CAN 0
✓
PLUS RS485 5
B4850 ✓ CAN 0
B48100 ✓ CAN 0 Short Lione 6&7 at inverter side
DYNESS POWERBOX F ✓ CAN 0
POWERBOX
✓ CAN 0
9.6
SS4037 ✓ CAN To be used with V2 Logger
SolarMD
SS4074 ✓ CAN [Link]
IMPORTANT
◼ When not using communications between battery and inverter, never overcharge your battery bank
concerning current and voltage. Many lithium batteries are limited to 100A, some are lower and
some are higher. Ensure that voltage and current specifications provided by the battery
manufacturer are followed.
◼ If you're using lead-acid batteries then a good rule of thumb is C X 25, which means that the
maximum charge of discharge you can apply to the battery is a quarter of the AH rating of the
overall battery array. For example, for a 200AH battery array that could be composed of 4×200
power batteries in series has a maximum charge and discharge of only 50A.
◼ Also, ensure the cable is thick enough to support the current and proper fuse following the
recommendations of the battery manufacturers.
To program charge and discharge times click on the “System Mode” icon after clicking on the gear icon.
1. Tick this box to do not export power back to the grid (the CT coil will detect power flowing back to the
grid and will reduce the power of the inverter only to supply the local load).
2. Tick this box if you wish to export your solar power back to the grid.
3. Tick this box if you only want to supply power to the load side of the inverter.
4. Zero export power is the amount of power flowing from the grid to the inverter. Set this value to 20 –
100W to force the inverter to always take this amount of power from the grid to minimise nuisance
“Reverse Power Detection” tripping of sensitive prepaid electricity meters.
5. This controls the maximum overall power, both to the load and grid ports combined. It is set to low if
an over current fault occurs.
Example:
This example shows the battery being charged up to 100% from the grid and PV from 8 AM to 11 AM
and then being allowed to supply up to 4kW of battery power to the “essential” loads on the LOAD port
until the battery SOC drops to 50%. Important: When charging the batteries from the grid or generator
please ensure you have set the correct battery charging settings on the battery charge page as shown
in Section 4.10 “Battery Setup Home Page”. If “Use Timer” is enabled then the inverter will use battery
power according to your settings when the grid is present. If this function is not set the batteries WILL
ONLY be used fot backup when there is no utility grid power.
Example:
Power is supplying the non-essential load and maximum power of the inverter is set as 8kW. The inverter
is connected to the grid, but no export is performed. It allows small amounts of power to flow from the
grid (set as 100W in this case) to prevent any backflow. In this example, the PV generator prioritizes to
supply the load first and then to charge the battery secondarily,
✓ Select the correct Grid Mode in your local area. If you are not sure, please choose General Standard.
✓ Select the correct Grid Type in your local area, otherwise the machine will not work or be damaged.
✓ Select the correct Grid Frequency in your local area.
Active power setting (VW): For example, if setting V start: 250V and Vstop=260V. When the grid voltage
reaches 250V and gradually increases to 260V, the inverter output power will gradually decrease. When
the voltage reaches to 260V, its output power will decrease to 20% of P start.
DRMs, logic interface for AS/NZS 4777.2: 2015, is used to receive and response commands from grid
company and then adjust inverter output power.
The power output or input will vary in response to the AC grid voltage. This function is switched off by
default.
1. DRM 1/5
2. DRM 2/6
3. DRM 3/7
4. RDRM 4/8
5. Ref 0
6. D Ground
7. Net J 4-7
8. Net J 4-7
The Sunsynk parity inverter can be wired standalone or where more power is required it can be connected
in parallel either single or 3 phase configuration. The maximum number of inverters that can be paralleled
in a single phase utility grid is three (10.8kW, 16.5kW, and 26.4kW for the 3.6kW, 5.5kW, and 8.8 kW
model, respectively) and the maximum number that can be paralleled in a three phase utility grid is nine
(32.4kW, 49.5kW, and 79.2kW for the 3.6kW, 5.5kW, and 8.8 kW model, respectively).
To parallel six inverters in a three phase utility grid is necessary to set three inverters as master and three
as slaves:
For stability, all the batteries need to be connected in parallel. It is recommended a minimum cable size
of 50mm diameter with fuse isolators to each inverter.
IMPORTANT
◼ Be careful with bus bar sizes.
◼ The CT coils used to limit export power must only be connected to the master. Therefore, if six
inverters are paralleled, three CT coils will be required.
◼ Connect a RJ45 communication cable between each inverter; the order is not important
since both sockets are the same, so there is no IN or OUT.
◼ Each phase must only have one master and the others set to slave.
◼ Each inverter must have a unique Modbus number.
◼ Each set of inverters must be set to the same phase. For example, when paralleling three
inverters in a three phase utility grid all must be set as Master (Phase A, Phase B, Phase
C).
◼ The maximum length of the communication cables is 2 meters (do not exceed this value)
◼ All batteries must be connected in parallel and the MPPTs must be kept separate.
The picture below shows the data cable between the inverters. It doesn't matter which way round these
go, but their length must not exceed 2 meters.
NOTE
IMPORTANT
If the communication is not working correctly between inverters then errors will show up on
the
◼ Thedisplay. In this case,
load outputs please
can be check in
connected allparallel.
settings and data cable.
◼ The grid input can also be connected in parallel.
◼ You cannot connect the Aux/Gen port in parallel, because this causes a conflict between
the frequency of the generator and the frequency of the grid.
What are the indications that the communication and the system are ok or not?
Parallel errors will be shown as fault F46 on the display.
What are the consequences of not setting one inverter in a parallel mode?
It can damage the inverter.
What are the consequences of having more than one master, or none set to master for that
matter?
It can damage the inverter. There are cases in which it is possible to have more than one master. For
example, as aforementioned, six inverters paralleled in a three phase utility grid (three masters)..
What are the consequences of factory resetting, power cycling, or firmware updating one inverter
in a parallel system?
There is no consequence, but the master inverter will keep controlling the slaves.
What consequences for changing ALL/ANY settings while operating in parallel mode?
It can damage the inverter and fault F46 will be indicated on the display.
This page shows the daily, monthly, yearly, and total grid power export or consumed. Access this page
by clicking on the “Solar/Turbine” icon on the home page.
The table bellow shows the maximum current depending on the voltage of the wind turbine.
IMPORTANT
◼ DO NOT use a wind turbine that exceeds 400V.
◼ Use a self breaking wind turbine. Once the batteries are fully charged and the inverter is not
exporting any power the load can drop. This can cause the turbine to speed up dramatically, which
can be very dangerous and usually happens suddenly. Thus, it is essential to use a self breaking
turbine.
Dump Load: When the battery (battery bank) is fully charged and the water turbine/wind turbine/solar
module is still generating power, a dump load will provide the electricity a path to flow. This can be done
using a switch on by the smart load option or utilizing a wind turbine controller with a built-in dump load.
Also, the hot water tank controlled via smart load can act as a good dump load, but in very windy
conditions it may be necessary to shunt the output.
To configure auxiliary load (previously known as smart load) settings click on the “Aux Load” icon.
Aux Load off Battery % or Voltage Battery level when the Aux load switches off
Aux Load on Battery % or
Battery level when the Aux load switches on.
Voltage
Solar Power Power limiter to the maximum power allowed to the Aux load.
Gen Input Tick this box if using a Generator.
Aux Load Output Tick this box if using an Aux or Smart Load.
Tick this box if intending to connect a supplementary inverter
For Micro inverter Input
or micro inverter (Max. 4kW).
Tick this box to stop exporting power produced by the Aux
Zero Export
Load.
Gen Peak Shaving Tick this box to use peak power shaving.
To configure auxiliary load (previously known as smart load) settings click on the “Aux Load” icon.
To check fault codes click on the “Fault Codes” icon on the settings menu.
If any of the fault messages listed in the following table appear on your inverter and the fault has not been
removed after restarting, please contact your local vendor or service center. The following information is
required:
If you need further help please refer to the Sunsynk website where you will find training videos and
frequently asked questions [Link].
The inverter must be installed by a qualified / licensed electrical engineer in accordance to the countries
wiring regulations.
Only after the engineer has completed the Earth Bond, RCD, and Earth Leakage Tests, check the solar
panel Voc voltage (Must not exceed 480V) and check the battery voltage. Then, the inverter can now be
switched on.
Power on Sequence:
1. Switch on AC
2. Press Start Button
3. Switch on Battery and battery breaker
4. Switch on the DC (PV Isolator)
Shutdown Sequence:
1. Switch off AC
2. Press the start button
3. Switch off the battery and the battery breaker
4. Switch off the DC (PV isolator)
After you have successfully powered up the inverter, the inverter must be programmed and set up as per
the programming feature above.
Check the each bond on Check the VOC does not Ensure both MPPTs are
the solar panels exceed 480V balanced
Measure the supply If it falls our of the setting See Grid set up page
voltage check it matches range it will cause the
the settings of the inverter inverse shut down and
alarm
This is the heart of the Ensure you are familiar See section 4.14
system this controller with this, if you fully
everything understand the controller
you will fully appreciate
the capabilities of there
inverter
Before the inverter starts to connect to the grid, the inverter will first detect the impedance of PV + to
ground, and the impedance of PV – to ground. If any of these impedance values is less than 33 k, the
inverter will not connect to the grid and will report an error F24 on its LCD.
The inverter is low maintenance, however, it is important that at least twice a year (for dusty environments
this may need to be carried out weekly) all the cooling fans, air ducts are cleaned and dust free.
Check if there are no fault codes and Lithium battery communication is correct.
Appendix C
The Sunsynk inverter is compatible with the SolarMan app, via a Wifi or GSM data logger (See solarman
instruction manual).
Copy enclosed
Appendix D
If an external residual current device (RCD) is used, a device of type (A/AC, etc.) should be employed,
with a tripping current of 30mA or higher.
Use of RCDs
Residual current devices (RCDs): An RCD dedicated for an IES may be used to meet the mechanical
cable protection requirements and isolation requirements of AS/ NZS3000 for the cable from the
switchboard to the IES. If an RCD is used, the RCD shall
1. disconnect all live conductors (including the actives and neutral); and
2. be of the type specified in the inverter manufacturer’s instructions or as labelled on the inverter.
We recommend the use of an RCD on all circuits and sub circuits connected to the Sunsynk inverter.
Residual current breaker with overcurrent protection (RCBO)
Appendix E
The Sunsynk inverter can be connected to the internet, but you need to add a data logger to do this.
The inverter is compatible with Solar Man data-loggers, which you can obtain from us with your distributor
1. LAN type of data logger
2. Wi-Fi type data logger
3. GSM type data-logger
For setting up the Internet/data logger, please refer to the App user manual.
The data logger is connected into the bottom of the inverter and uses the connection marked as WIFI.
Appendix F
For more information, training videos, software upgrades, help line, forum please refer to
[Link] Tech Support (Do not forget to register first on the website).