Project Title: Construction of 2- Storey Residential Building
Activity Work Description Duration Precidence
A Preliminary site survey and assessment 3
B Development of design and achitectural plans 3 A
C Obtaining necessary permits 2 B
D Preparing the construction site for work activities 4 C
E Setting up temporary on-site facilities 3 C
F Procurement of materials and equipment 5 D, E
Mobilization of construction equipment and
G 5 F
materials
Foundation and Groundwork
H Excavation for foundation 6 G
I Setting up temporary shoring and support structures 3 H
J Pouring and curing the foundation footings 4 I
K Constructing of foundation walls 4 J
L Installing foundation drainage system 2 J
M Backfilling around foundation walls 4 K, L
N Compacting and leveling the ground floor 4 M
Ground Floor Construction
O Construction of columns 8 N
P Framing of ground floor 6 O
Q Installation of electrical and plumbing lines 2 O
R Concreting of ground floor slab 6 P, Q
S Installation of exterior walls 10 R
T Installation of interior walls 6 R
U Construction of beams 12 S, T
V Construction of stairs 6 U
W Installation of floor slab support 6 V
Second Floor Construction
X Framing of floor slab 6 W
Y Installation of electrical and plumbing lines 2 W
Z Concreting of ground floor slab 6 X, Y
A' Installation of exterior walls 10 Z
B' Installation of interior walls 6 Z
C' Construction of roof beams 12 A', B'
D' Erecting roof trusses 4 C'
E' Installtion of roof insulation foam 2 D'
F' Installation of roofing material 3 E'
Ground Floor Construction Phase 2
G' Exterior Plastering 5 F'
H' Interior Plastering 4 F'
I' Installation of ceiling 6 G, H'
J' Taping, sanding wall for smooth finish 4 I'
K' Painting walls and ceiling 10 J'
L' Installation of doors and windows 3 K'
M' Installing flooring tiles 8 L'
N' Installing cabinets 2 M'
O' Installation of bathroom and kitchen fixtures 2 M'
P' Septic tank excavation 4 N', O'
Q' Installation of septic tank walls 2 P'
R' Installation of septic tank plumbing lines 1 Q'
S' Concreting of septic tank 2 R'
Connecting plumbing fixtures to main water and
T' 2 S'
sewage system
U' Installation of lighting and power fixtures 4 T'
V' Installation of exterior claddings 6 U'
Second Floor Construction Phase 2
W' Exterior Plastering 5 F
X' Interior Plastering 4 F
Y' Installation of ceiling 6 W', X'
Z' Taping, sanding wall for smooth finish 4 Y'
A" Painting walls and ceiling 10 Z'
B" Installation of doors and windows 3 A"
C" Installing flooring tiles 8 B"
D" Installing cabinets 2 C"
E" Installation of bathroom fixtures 2 C"
Connecting plumbing fixtures to main water and
F" 2 D", E"
sewage system
G" Installation of lighting and power fixtures 4 F"
H" Installation of exterior claddings 6 G"
Post- Construction
I" Cleaning interior and exterior spaces 6 H"
J" Conducting final inspection 2 I"
K" Finishing final details 4 I"
L" Obtaining occupancy permit 2 J", K"
M" Handing over keys and documents to the owner 1 L"
Project Title: Construction of 2- Storey Residential Building
Activity Work Description Duration
A Preliminary site survey and assessment 3
B Development of design and achitectural plans 3
C Obtaining necessary permits 2
D Preparing the construction site for work activities 4
E Setting up temporary on-site facilities 3
F Procurement of materials and equipment 5
G Mobilization of construction equipment and materials 5
Foundation and Groundwork
H Excavation for foundation 6
I Setting up temporary shoring and support structures 3
J Pouring and curing the foundation footings 4
K Constructing of foundation walls 4
L Installing foundation drainage system 2
M Backfilling around foundation walls 4
N Compacting and leveling the ground floor 4
Ground Floor Construction
O Construction of columns 8
P Framing of ground floor 6
Q Installation of electrical and plumbing lines 2
R Concreting of ground floor slab 6
S Installation of exterior walls 10
T Installation of interior walls 6
U Construction of beams 12
V Construction of stairs 6
W Installation of floor slab support 6
Second Floor Construction
X Framing of floor slab 6
Y Installation of electrical and plumbing lines 2
Z Concreting of ground floor slab 6
A' Installation of exterior walls 10
B' Installation of interior walls 6
C' Construction of roof beams 12
D' Erecting roof trusses 4
E' Installtion of roof insulation foam 2
F' Installation of roofing material 3
Ground Floor Construction Phase 2
G' Exterior Plastering 5
H' Interior Plastering 4
I' Installation of ceiling 6
J' Taping, sanding wall for smooth finish 4
K' Painting walls and ceiling 10
L' Installation of doors and windows 3
M' Installing flooring tiles 8
N' Installing cabinets 2
O' Installation of bathroom and kitchen fixtures 2
P' Septic tank excavation 4
Q' Installation of septic tank walls 2
R' Installation of septic tank plumbing lines 1
S' Concreting of septic tank 2
Connecting plumbing fixtures to main water and
T' 2
sewage system
U' Installation of lighting and power fixtures 4
V' Installation of exterior claddings 6
Second Floor Construction Phase 2
W' Exterior Plastering 5
X' Interior Plastering 4
Y' Installation of ceiling 6
Z' Taping, sanding wall for smooth finish 4
A" Painting walls and ceiling 10
B" Installation of doors and windows 3
C" Installing flooring tiles 8
D" Installing cabinets 2
E" Installation of bathroom fixtures 2
Connecting plumbing fixtures to main water and
F" 2
sewage system
G" Installation of lighting and power fixtures 4
H" Installation of exterior claddings 6
Post- Construction
I" Cleaning interior and exterior spaces 6
J" Conducting final inspection 2
K" Finishing final details 4
L" Obtaining occupancy permit 2
M" Handing over keys and documents to the owner 1
Project Title: Construction of 2-Storey Residential Building
Start Finish Float Critical
Activity Duration
ES EF LS LF Total Free Activity
A 3 0 0 3 3 0 0 *
B 3 3 3 6 6 0 0 *
C 1 6 6 8 8 0 1
D 4 8 8 12 12 0 -4
E 3 8 9 11 12 -1 1
F 5 12 12 17 17 0 0 *
G 5 17 17 22 22 0 0 *
H 6 22 22 28 28 0 0 *
I 3 28 28 31 31 0 0 *
J 4 31 31 35 35 0 0 *
K 4 35 35 39 39 0 -4
L 2 35 37 37 39 -2 2
M 4 39 39 43 43 0 0 *
N 4 43 43 47 47 0 0 *
O 8 47 47 55 55 0 0 *
P 6 55 55 61 61 0 -6
Q 2 55 59 57 61 -4 4
R 6 61 61 67 67 0 0 *
S 10 67 67 77 77 0 -10
T 6 67 71 73 77 -4 4
U 12 77 77 89 89 0 0 *
V 6 89 89 95 95 0 0 *
W 6 95 95 101 101 0 0 *
X 6 101 101 107 107 0 -6
Y 2 101 105 103 107 -4 4
Z 6 107 107 113 113 0 0 *
A' 10 113 113 123 123 0 -10
B' 6 113 117 119 123 -4 4
C' 12 123 123 135 135 0 0 *
D' 4 135 135 139 139 0 0 *
E' 2 139 139 141 141 0 0 *
F' 3 141 141 144 144 0 0 *
G' 5 144 144 149 149 0 -5
H' 4 144 145 148 149 -1 1
I' 6 149 149 155 155 0 0 *
J' 4 155 155 159 159 0 0 *
K' 10 159 159 169 169 0 0 *
L' 3 169 169 172 172 0 0 *
M' 8 172 172 180 180 0 0 *
N' 2 180 180 182 182 0 -2
O' 2 180 180 182 182 0 0 *
P' 4 182 182 186 186 0 0 *
Q' 2 186 186 188 188 0 0 *
R' 1 188 188 189 189 0 0 *
S' 2 189 189 191 191 0 0 *
T' 2 191 191 193 193 0 0 *
U' 4 193 193 197 197 0 0 *
V' 6 197 197 203 203 0 -59
W' 5 144 153 149 158 -9 -5
X' 4 144 154 150 158 -10 1
Y' 6 149 156 155 164 -7 0
Z' 4 155 164 159 168 -9 0
A" 10 159 168 169 178 -9 0
B" 3 169 178 172 181 -9 0
C" 8 172 181 180 189 -9 0
D" 2 180 189 182 191 -9 -2
E" 2 180 189 182 191 -9 0
F" 2 182 191 184 193 -9 0
G" 4 184 193 188 197 -9 0
H" 6 188 197 194 203 -9 9
I" 6 203 203 209 209 0 0 *
J" 2 209 211 211 213 -2 -2
K" 4 209 209 213 213 0 0 *
L" 2 213 213 215 215 0 0 *
M" 1 215 215 216 216 0 0 *
Project Title: Construction of 2-Storey Residential Building
Critical Path
Legend:
Acitivity
Duration
A B F G H I J M N O R U
3 3 5 5 6 3 4 4 4 8 6 12
M' L' K' J' I' F' E' D' C' Z W V
8 3 10 4 6 3 2 4 12 6 6 6
O' P' Q' R' S' T' U' I" K" L" M"
2 4 2 1 2 2 4 6 4 2 1
Total = 163 days