0% found this document useful (0 votes)
4K views24 pages

Construction Productivity Rates Philippines

Uploaded by

Aliñabo Roque
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4K views24 pages

Construction Productivity Rates Philippines

Uploaded by

Aliñabo Roque
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

MANPOWER RATE 15 JUNE 2010

TENDER
Productivity / Productivity / Productivity /
CODE DESCRIPTION UNIT MH RATE
Man-Day(8hrs) Equipment-Day(8hrs) Crew-Day(8hrs)

VERTICAL STRUCTURES
DEMOLITION AND REMOVAL
DEMOLISH CONCRETE
0 ROAD 0.80 - 0.80 CM 10.000
DEMOLISH BUILDING
1 WOOD CONSTRUCTION 3.77 - 3.77 CM 2.120
2 CHB CONSTRUCTION 2.27 - 2.27 CM 3.530
3 MAJOR CONCRETE FRAME 2.27 - 2.27 CM 3.530
4 MAJOR STEEL FRAME 2.27 - 2.27 CM 3.530

SELECTIVE DEMOLITION
5 ACOUSTICAL CEILING TILES 7.41 - 7.41 SM 1.080
6 AC PAVEMENT 2.67 - 2.67 SM 3.000
7 BUILT-UP ROOFING, 4 PLY 36.36 - 36.36 SM 0.220
8 CEILING PLASTER 7.41 - 7.41 SM 1.080
9 CERAMIC TILE WALL INCLUDING MORTAR 4.97 - 4.97 SM 1.610
10 CERAMIC TILE FLOOR INCLUDING MORTAR 4.97 - 4.97 SM 1.610
11 CMU WALL 8" 29.63 - 148.15 SM 0.270

12 CMU WALL 6" 29.63 - 148.15 SM 0.270

13 CMU WALL 4" 29.63 - 148.15 SM 0.270

14 CONCRETE BEAMS 0.41 - 2.06 CM 19.400


15 CONCRETE COLUMNS 0.76 - 3.78 CM 10.590
16 CONCRETE CURB 1.33 - 6.67 CM 6.000
17 CONCRETE FOUNDATION 2.80 - 13.99 CM 2.860
18 CONCRETE PAVEMENT, 6" 26.67 - 133.33 SM 0.300
19 CONCRETE SLAB ON GRADE, 4" 7.41 - 37.04 SM 1.080
20 CONCRETE SUSPENDED SLAB 0.41 - 2.06 CM 19.400
21 FENCING, CHAIN LINK, 8' HIGH 24.24 - 121.21 LM 0.330
22 FENCING, CHAIN LINK, FIR REUSED 16.00 - 80.00 LM 0.500
FIRE HYDRANT INCLUDING RESET & THRUST
23
BLOCK
0.50 - 1.00 EA 16.000

24 GUARD RAIL 12.50 - 25.00 SM 0.640


25 GYPSUM, 3 TO 4 INCHES 12.31 - 12.31 SM 0.650
26 HOLLOW METAL DOOR AND FRAME 4.71 - 4.71 EA 1.700
27 MANHOLE 6 TO 12 FT. HIGH 2.00 - 8.00 EA 4.000

28 METAL TOILET STALL 2.67 - 2.67 EA 3.000


29 METAL WINDOWS 4.97 - 4.97 SM 1.610
SANITARY LINE INCLUDING PIPES & STORM
30
DRAIN LINE
50.00 - 100.00 LM 0.160

31 TREE REMOVAL INCLUDING STUMP 4.21 - 21.05 EA 1.900

32 WALL PLASTER 7.41 - 7.41 SM 1.080


33 WOOD DOOR AND FRAME 4.00 - 4.00 EA 2.000
34 WOOD PANELLING 12.31 - 12.31 SM 0.650
35 WOOD WINDOW SILL AND TRIM 3.72 - 3.72 SM 2.150

DISPOSAL OF DEMOLISHED ITEMS


CUT TREE, GRUB ROOT
36 WITH 8 IN CALIPER 0.89 - 0.89 EA 9.000
37 WITH 12 IN CALIPER 0.80 - 0.80 EA 10.000
38 WITH 20 IN CALIPER 0.44 - 0.44 EA 18.000
39 WITH 30 IN CALIPER 0.33 - 0.33 EA 24.000

40 DENSELY WOODEN AREA 266.67 - 266.67 SM 0.030


41 LIGHTLY WOODEN AREA 400.00 - 400.00 SM 0.020
42 BRUSH & SCRUB 800.00 - 800.00 SM 0.010
43 BRUSH BY HAND 7.02 - 7.02 SM 1.140

1
MANPOWER RATE 15 JUNE 2010

Actual
PRODUCTION Total Productivity / Productivity /
MANPOWER EQUIPMENT Prod/MH
RATE Manpower Man-Day(8hrs) Equipment-Day(8hrs)

1 0.1

1 0.47169811
1 0.28328612
1 0.28328612
1 0.28328612

1 0.92592593
1 0.33333333
1 4.54545455
1 0.92592593
1 0.62111801
1 0.62111801
5 LABOURERS 2 JACKHAMMER 18.519 5 3.7037037
1 AIR COMPRESSOR
5 LABOURERS 2 JACKHAMMER 18.520 5 3.7037037
1 AIR COMPRESSOR
5 LABOURERS 2 JACKHAMMER 18.520 5 3.7037037
1 AIR COMPRESSOR
5 0.05154639
5 0.09442871
5 LABOURERS 1.748 5 0.16666667
5 0.34965035
5 3.33333333
5 0.92592593
5 0.05154639
5 3.03030303
5 2

2 PLUMBERS 0.125 2 0.0625

2 LABOURERS 3.125 2 1.5625


1 1.53846154
1 0.58823529
4 LABOURERS 2 JACKHAMMERS 1.000 4 0.25
1 AIR COMPRESSOR
1 BACKHOE

1 0.33333333
1 0.62111801

2 LABOURERS 1 BACKHOE 12.500 2 6.25


1-1/2 HYDRO
5 LABOURERS 1 2.625 5 0.52631579
EXCAVATOR
1 DUMP TRUCK

1 0.92592593
1 0.5
1 1.53846154
1 0.46511628

1 0.11111111
1 0.1
1 0.05555556
1 0.04166667

1 33.3333333
1 50
1 100
1 0.87719298

2
MANPOWER RATE 15 JUNE 2010

Average
Productivity / Productivity /
Man-Day(8hrs) Equipment-Day(8hrs)

0.80 -

3.77 -
2.27 -
2.27 -
2.27 -

7.41 -
2.67 -
36.36 -
7.41 -
4.97 -
4.97 -
29.63 -

29.63 -

29.63 -

0.41 -
0.76 -
1.33 -
2.80 -
26.67 -
7.41 -
0.41 -
24.24 -
16.00 -
0.50 -
12.50 -
12.31 -
4.71 -
2.00 -

2.67 -
4.97 -
50.00 -

4.21 -

7.41 -
4.00 -
12.31 -
3.72 -

0.89 -
0.80 -
0.44 -
0.33 -

266.67 -
400.00 -
800.00 -
7.02 -

3
MANPOWER RATE 15 JUNE 2010

TENDER
Productivity / Productivity /
CODE DESCRIPTION
Man-Day(8hrs) Equipment-Day(8hrs)

EARTH WORKS
1 CLEARING AND GRUBBING - 200.00
2 FINE GRADING - 800.00
2 TOPSOILING/STRIPPING - 800.00
3 STRUCUTURAL EXCAVATION, COMMON SOIL MANUAL 1.40 -
5 STRUCUTURAL EXCAVATION, SAND AND GRAVEL MANUAL 1.00 -
4 STRUCUTURAL EXCAVATION, ADOBE AND ROCK - 1.20

5 STRUCUTURAL EXCAVATION, HARD ROCK WITH BLASTING - 2.40

6 STRUCUTURAL EXCAVATION, WITH DEWATERING - 1.00


7 STRUCUTURAL EXCAVATION, COMMON SOIL, MECHANICAL - 800.00
13 STRUCUTURAL EXCAVATION, COMMON SOIL, MECHANICAL - 114.29
14 STRUCUTURAL EXCAVATION, COMMON SOIL, MECHANICAL - 200.00
15 STRUCUTURAL EXCAVATION, SAND AND GRAVEL, MECHANICAL - 80.00
8 STRUCUTURAL EXCAVATION, SAND AND GRAVEL, MECHANICAL - 80.00
17 STRUCUTURAL EXCAVATION, SAND AND GRAVEL, MECHANICAL - 100.00
9 STRUCUTURAL EXCAVATION, SAND AND GRAVEL, MECHANICAL 160.00 -
10 TRENCHING, COMMON SOIL, MANUAL 1.33 -
11 TRENCHING, SAND AND GRAVEL, MANUAL 1.00 -
12 TRENCHING, ADOBE AND ROCK - 1.20

23
13 TRENCHING, COMMON SOIL, MECHANICAL - 80.00
25 TRENCHING, GRAVEL AND SAND, MECHANICAL - 66.67
14 STRUCTURAL FILL, COMPACTED - 2.82
15 STRUCTURAL FILL, COMPACTED, MANUAL TAMPING 4.00 -
28 STRUCTURAL FILL, UNCOMPACTED 8.00 -
16 STRUCTURAL FILL, COMPACTED, MECHANICAL - 800.00
30 STRUCTURAL FILL, UNCOMPACTED, MECHANICAL - 800.00
17 ROADWAY SUBBASE FILL, COMPACTED, MECHANICAL - 800.00
18 ROADWAY BASE COURSE FILL, COMPACTED, MECHANICAL - 400.00
19 RIPRAP, UNGROUT, MANUAL 1.50 -
20 RIPRAP, GROUTED, MANUAL 1 -

1230 RIPRAP, MECHANICALLY DUMPED - 0.00


1231 SAND BEDDING, MANUAL - 0.00
1232 GRAVEL BEDDING, MANUAL - 0.00
GRASS CUTTING 504 -

62.5

4
MANPOWER RATE 15 JUNE 2010

TENDER
Productivity / Total
UNIT MH RATE MANPOWER EQUIPMENT
Crew-Day(8hrs) Manpower

200.00 SM 0.040 5 LABOURERS 1 DOZER/GRADER


800.00 SM 0.010 2 LABOURERS 1 DOZER/GRADER
800.00 SM 0.010 2 LABOURERS 1 DOZER/GRADER
7.01 CM 5.710 5 LABOURERS
5.00 CM 8.000 5 LABOURERS
1.20 CM 6.670 5 LABOURERS 2 JACKHAMMER
1 AIR COMPRESSOR
2.40 CM 3.330 5 LABOURERS 2 JACKHAMMER
1 AIR COMPRESSOR
1 DRILL
1.00 CM 8.000 5 LABOURERS 1 270 HP DOZER
800.00 CM 0.010 1 LABOURERS 1 3/8 CY BACKHOE
114.29 CM 0.070 1 LABOURERS 1 1 CY CLAMSHELL
200.00 CM 0.040 1 LABOURERS 1 270 HP DOZER
80.00 CM 0.100 1 LABOURERS 1 180 HP DOZER
80.00 CM 0.100 1 LABOURERS 1 BACKHOE
100.00 CM 0.080 1 LABOURERS 1 1 CY CLAMSHELL
160.00 CM 0.050 1 LABOURERS
1.33 CM 6.000 1 LABOURERS
1.00 CM 8.000 1 LABOURERS
1.20 CM 6.670 5 LABOURERS 2 JACKHAMMER
1 AIR COMPRESSOR

80.00 CM 0.100 1 LABOURERS 1 3/8 CY BACKHOE


66.67 CM 0.120 1 LABOURERS 1 3/8 CY BACKHOE
2.82 CM 2.840 1 LABOURERS 1 PLATE COMPACTOR
20.00 CM 2.000 5 LABOURERS
8.00 CM 1.000 1 LABOURERS
800.00 CM 0.010 1 LABOURERS 1 COMPACTOR/GRADER/WATER TANKER
800.00 CM 0.010 1 LABOURERS 1 180 HP DOZER
800.00 CM 0.010 1 LABOURERS 1 COMPACTOR/GRADER/WATER TANKER
400.00 CM 0.020 1 LABOURERS 1 COMPACTOR/GRADER/WATER TANKER
15.01 CM 5.330 10 LABOURERS
10.00 CM 8.000 3 MASONS 10
7 LABOURERS

0.00 CM 1 LABOURERS 1 CRAWLER CRANE/ CLAMPSHELL


0.00 CM 1 LABOURERS
0.00 CM 1 LABOURERS
504 SM 8.000 1 GRASS CUTTER

dozer clearing grubbing and stripping


grader levelling

5
MANPOWER RATE 15 JUNE 2010

Actual Average
Productivity / Productivity / Productivity / Productivity /
Prod/MH
Man-Day(8hrs) Equipment-Day(8hrs) Man-Day(8hrs) Equipment-Day(8hrs)

25 400 - 300.00
100 - 800.00
100 - 800.00
0.175131348511 1.40 -
0.125 1.00 -
0.149925037481 - 1.20

0.3003003003 - 2.40

0.125 - 1.00
100 240 - 520.00
14.28571428571 - 114.29
25 - 200.00
10 - 80.00
10 - 80.00
12.5 - 100.00
20 160.00 -
0.166666666667 1.33 -
0.125 1.00 -
0.149925037481 - 1.20

#DIV/0! #DIV/0!
10 - 80.00
8.333333333333 - 66.67
0.352112676056 - 2.82
0.5 4.00 -
1 8.00 -
100 - 800.00
100 - 800.00
100 - 800.00
50 - 400.00
0.187617260788 1.50 -
0.125 1.00 -

#DIV/0! #DIV/0!
- 0.00
- 0.00
- 0.00
63

6
MANPOWER RATE 10 JUNE 2010

TENDER

Productivity / Productivity / Productivity /


CODE DESCRIPTION UNIT
Man-Day(8hrs) Equipment-Day(8hrs) Crew-Day(8hrs)

CONCRETE WORKS
CAST IN PLACE CONCRETE
FORMWORKS
0 MEVA FORMWORKS 3.28 - 6.56 SM

1 FOUNDATION AND FOOTING 2.50 - 25.00 SM

2 SLAB WOODEN FORMS, ELEVATED 1.92 - 19.18 SM

3 SLAB STEEL FORMS, ELEVATED 1.92 - 19.18 SM

4 SLAB WOODEN FORMS, GROUND FLOOR 2.50 - 25.00 SM

5 RETAINING WALL FORMS 1.92 - 19.18 SM

6 BUILDING WALL FORMS 1.92 - 19.18 SM

7 COLUMN WOOD FORMS 4.00 - 40.00 SM

8 COLUMN FIBERBOARD FORMS, CIRCULLAR 1.92 - 19.18 SM

9 BEAMS AND GIREDERS 1.00 - 10.00 SM

10 CONCRETE STAIR FORMS 1.33 - 13.33 SM

11 PARAPET WALL FORMS 1.92 - 19.18 SM

12 LINTEL BEAM WOODEN FORMS 1.92 - 19.18 SM

13 LINTEL COLUMN WOODEN FORMS 16.00 - 160 SM

14 HANGUARD RAIL 53.33 - 533.33 LM

REINFORCEMENTS
15 GRADE 60 REBARS 160.00 - 1600.00 KG

16 GRADE 40 REBARS 160.00 - 1600.00 KG

17 GRADE 33 REBARS 160.00 - 1600.00 KG

18 BAR WELDING 800.00 - 800.00 KG


19 WIREMESH 133.33 - 1333.33 SM

20 DOWEL 57.14 - 571.43 EA

CONCRETE 2000, 3000,3500,4000,5000 ETC.

1 TO 2 BAGGER MIXED, DIRECT POUR BY CHUTE

21 SLAB ON GROUND 1.90 - 17.14 CM


22 FOOTING AND TIE BEAMS 1.74 - 15.65 CM
23 SUSPENDED SLAB 1.60 - 14.40 CM
24 COLUMNS AND BEAMS 1.45 - 13.09 CM

1 TO 2 BAGGER MIXED, USING BAGGIES

25 SLAB ON GROUND 1.58 - 19.01 CM


26 FOOTING AND TIE BEAMS 1.44 - 17.30 CM
27 SUSPENDED SLAB 1.32 - 15.87 CM
1 TO 2 BAGGER MIXED, USING PORTA LIFT AND
BAGGIES

28 SUSPENDED SLAB 1.03 - 11.35 CM


29 COLUMNS AND BEAMS 0.79 - 8.71 CM

7
MANPOWER RATE 10 JUNE 2010

Productivity / Productivity / Productivity /


CODE DESCRIPTION UNIT
Man-Day(8hrs) Equipment-Day(8hrs) Crew-Day(8hrs)

READY MIXED CONCRETE


30 DIRECT POUR OR BY CHUTE 5.52 - 27.59 CM

31 USING BAGGIES 3.48 - 24.35 CM

32 USING PORTA LIFT AND CHUTE 2.86 - 20.00 CM

33 USING PORTA LIFT AND BAGGIES 2.22 - 20.00 CM

34 USING CONCRETE PUMP 6.15 - 61.54 CM

35 USING CRANE AND BUCKET 2.86 - 31.43 CM

36 CONCRETE TOPPING 4.26 - 21.28 SM

37 WATERSTOP 32.00 - 32.00 LM


38 CURING USING CURING COMPOUND 40.00 - 80.00 CM
39 FLOOR HARDENER, IRON BASE 14.81 - 29.63 SM
40 JOINT SEALING MATERIALS 61.54 - 123.08 LM
41 EXPANSION JOINT SEALANT 57.14 - 114.29 LM

PRECAST STRUCTURAL CONCRETE ( NON


PRESTRESSED)

42 BEAMS, GIRDERS, AND COLUMN, 5 TONS MAX. - 8 8.00 LM


43 BEAMS, GIRDERS, AND COLUMN, 10 TONS MIN. - 7.27 7.27 CM
44 WALLS, 5 TONS MIN. - 2.50 2.50 MT

PILES, 12",14",16",18" AND 20" SIZES ON GROUND,


45
VERTICAL, 1 SEGMENT
- 10.26 10.26 LM

8
MANPOWER RATE 10 JUNE 2010

Actual

Total Productivity / Productivity /


MH RATE MANPOWER EQUIPMENT Prod/MH
Manpower Man-Day(8hrs) Equipment-Day(8hrs)

2.440 1 CARPENTERS 2 0.4098360656


1 LABOURS
3.200 8 CARPENTERS 10 0.3125
2 LABOURS
4.170 8 CARPENTERS 10 0.2398081535 12
2 LABOURS
4.170 8 CARPENTERS 10 0.2398081535
2 LABOURS
3.200 8 CARPENTERS 10 0.3125 20
2 LABOURS
4.170 8 CARPENTERS 10 0.2398081535
2 LABOURS
4.170 8 CARPENTERS 10 0.2398081535
2 LABOURS
2.000 8 CARPENTERS 10 0.5
2 LABOURS
4.170 8 CARPENTERS 10 0.2398081535
2 LABOURS
8.000 8 CARPENTERS 10 0.125
JSPiano:
2 LABOURS 0
per sir arman
6.000 8 CARPENTERS 10 0.1666666667
2 LABOURS
4.170 8 CARPENTERS 10 0.2398081535
2 LABOURS
4.170 8 CARPENTERS 10 0.2398081535
2 LABOURS
0.500 8 CARPENTERS 10 2
2 LABOURS
0.150 8 CARPENTERS 10 6.6666666667
2 LABOURS

0.050 5 HELPERS 1 BAR CUTTER 10 20


5 STEEL FIXERS
0.050 5 HELPERS 1 BAR CUTTER 10 20
5 STEEL FIXERS
0.050 5 HELPERS 1 BAR CUTTER 10 20
5 STEEL FIXERS
0.010 1 WELDER 1 WELDER 100
0.060 5 HELPERS 10 16.666666667
5 STEEL FIXERS
0.140 5 HELPERS 10 7.1428571429
5 STEEL FIXERS

6 LABOURERS 1 CONCRETE VIBRATOR

3 MASONS
4.200 9 0.2380952381
4.600 9 0.2173913043
5.000 9 0.2
5.500 9 0.1818181818

3 MASONS 1 CONCRETE VIBRATOR

8 LABOURERS
1 OPERATOR
5.050 12 0.198019802
5.550 12 0.1801801802
6.050 12 0.1652892562

3 MASONS 1 CONCRETE VIBRATOR

8 LABOURERS
7.750 11 0.1290322581
10.100 11 0.099009901

9
MANPOWER RATE 10 JUNE 2010

Total Productivity / Productivity /


MH RATE MANPOWER EQUIPMENT Prod/MH
Manpower Man-Day(8hrs) Equipment-Day(8hrs)

1.450 3 MASONS 5 0.6896551724


2 LABOURERS
2.300 3 MASONS 7 0.4347826087
4 LABOURERS
2.800 3 MASONS 7 0.3571428571
4 LABOURERS
3.600 3 MASONS 9 0.2777777778
6 LABOURERS
1.300 3 MASONS 10 0.7692307692
7 LABOURERS
2.800 3 MASONS 11 0.3571428571
8 LABOURERS

1.880 3 MASONS 5 0.5319148936


2 LABOURERS
0.250 1 CARPENTER 4
0.200 2 LABOURERS 5
0.540 2 MASONS 1.8518518519
0.130 2 MASONS 7.6923076923
0.140 2 MASONS 7.1428571429

2 LABOURERS 1 TRUCK/CRANE

2 WELDERS 1 WELDING MACHINE


2 RIGGERS 1 MISC. TOOLS
1.000 6 1
1.100 6 0.9090909091
3.200 6 0.3125

0.780 1 RIGGER 1 HAMMER 3 1.2820512821

1 WELDER 1 40TONS CRANE


1 LABOURER

10
MANPOWER RATE 10 JUNE 2010

Average

Productivity / Productivity /
Man-Day(8hrs) Equipment-Day(8hrs)

3.28 -

2.50 -

6.96 -

1.92 -

11.25 -

1.92 -

1.92 -

4.00 -

1.92 -

1.00 -

1.33 -

1.92 -

1.92 -

16.00 -

53.33 -

160.00 -

160.00 -

160.00 -

800.00 -
133.33 -

57.14 -

1.90 -
1.74 -
1.60 -
1.45 -

1.58 -
1.44 -
1.32 -

1.03 -
0.79 -

11
MANPOWER RATE 10 JUNE 2010

Productivity / Productivity /
Man-Day(8hrs) Equipment-Day(8hrs)

5.52 -

3.48 -

2.86 -

2.22 -

6.15 -

2.86 -

4.26 -

32.00 -
40.00 -
14.81 -
61.54 -
57.14 -

- 8.00
- 7.27
- 2.50

- 10.26

12
MANPOWER RATE 10 JUNE 2010

- - - -- -- -

13
MANPOWER RATE 10 JUNE 2010

---

14
MANPOWER RATE 10 JUNE 2010

15
MANPOWER RATE 10 JUNE 2010

TENDER
Productivity / Productivity /
CODE DESCRIPTION
Man-Day(8hrs) Equipment-Day(8hrs)

MASONRY WORKS
1920 BRICK MASONRY
1921 BRICK VENEER 3-3/4" x 2-1/2" x 8" 2.70 -

1922 BRICK VENEER 3-3/4" x 2-1/4" x 7-5/8" 2.90 -

1923 JUMBO BRICK VENEER 4" x 4" x 12" 3.81 -

1924 JUMBO BRICK VENEER 6" x 4" x 12" 5.52 -

1925 JUMBO BRICK VENEER 8" x 4" x 12" 6.50 -

1926 FACE BRICK VENEER, ELECTRO MODULAR 3-3/4" x 2-1/4" x 7-5/8 2.25 -

1927 COMMON BRICK WALL, 10" CAVITY 1.08 -

1928 COMMON BRICK WALL, 13" REINFORCEMENT 1.05 -

1929 COMMON BRICK WALL, 16" REINFORCEMENT 0.83 -

1930 COMMON BRICK WALL, 20" REINFORCEMENT 0.73 -

1940 REINFORCED MASONRY


1941 CHB , NLB , 4" 3.20 -

1942 CHB , NLB , 6" 2.91 -

1943 CHB , NLB , 8" 2.67 -

1944 CHB , LB , 4" 3.20 -

1945 CHB , LB , 6" 2.91 -

1946 CHB , LB , 8" 2.67 -

1947 BOND BEAM, 4" 16.00 -

1948 BOND BEAM, 6" 14.55 -

1949 BOND BEAM, 8" 13.33 -

1950 REBARS 160.00 -

1951 PREMOLDED FILLER STRIPS 57.14 -

5000 STONE, CONCRETE AND MASONRY FINISHED


5001 PLASTERING AND STUCCOING 5.41 -

5002 PLASTERING OF METAL LATH 17.78 -

5003 PLASTERING OF METAL SOLID 16.67 -

5004 STUCCO AND PLASTER TEXTURES 2.97 -

5005 STUCCO AND PLASTER FLOAT FINISH 3.01 -

5006 STUCCO AND PLASTER DUSH FINISH 2.91 -

5007 PLAIN CEMENT FINISH 12.50 -


5008 PLAIN CEMENT FINISH, COLORED 4.00 -
5009 PLASTERING ON CONCRETE SURFACE WITH SHIPPING 4.23 -
5010 CONCRETE PATCHING 2.86 -
5011 PLASTERING OF CHB 1/2" THICK 4.57 -
5012 PLASTERING OF CHB 3/4" THICK 4.00 -
5013 TOOL JOINT FINISH 8.00 -

16
MANPOWER RATE 10 JUNE 2010

Productivity / Productivity /
CODE DESCRIPTION
Man-Day(8hrs) Equipment-Day(8hrs)

5014 GYPSUM PLASTER 4.26 -

5015 THIN COAT PLASTER ON WOODEN BOARD 4.21 -


5016 FLOOR HARDENER, IRON BASE 14.81 -
5017 SANDBLAST, LIGHT 12.50 -
5018 SANDBLAST, MEDIUM 11.11 -
5019 SANDBLAST, HEAVY 10.00 -
5020 BUSH HAMMER, LIGHT 7.62 -
5021 BUSH HAMMER, MEDIUM 7.27 -
5022 BUSH HAMMER, HEAVY 6.96 -
5023 WIRE BRUSH FINISH 5.41 -

5024 MONOLITHIC FINISH 1/16" 5.26 -

5025 MONOLITHIC FINISH 3/16" 5.26 -

5026 MONOLITHIC FINISH 1/2" 5.26 -

5027 STONE CUT GRANITE INCLUDING GRANITE SUPPORTS 0.85 -

5028 STONE CUT MARBLE 1.32 -

5029 MARBLE, FLOOR 7/8" 2.03 -

5030 MARBLE, THRESHOLOS 1-1/4" 2.56 -

5031 MARBLE BASE 7/8" x 6" 5.48 -

5032 MARBLE, COLUMN, PLAIN 2.73 -

5033 MARBLE , COLUMN, FLUTED 2.03 -

5034 MARBLE, WINDOW STOOLS 2.03 -

5035 MARBLE, TOILET PATITIONS 2.03 -

5036 PEBBLE WASHOUT, FLOOR 3.20 -


5037 PEBBLE WASHOUT, WALL 3.33 -
5038 TERRAZO, STANDARD, MUD SET 2.68 -

5040 GYPSUM WALLBOARD


5041 GYPSUM WALLBOARD, REGULAR 1/2" THICK, TAPERED 2.13 -

5042 GYPSUM WALLBOARD, TYPE X 5/3" THICK, TAPERED 2.17 -

5043 GYPSUM WALLBOARD, TYPE X 1/2" THICK, TAPERED 2.17 -

5044 WATER RESISTANT GYPSUM WALLBOARD, 1/2" THICK 2.17 -

5045 EDGE TRIM 7.14 -

5050 TILE WORKS


5051 QUARRY TILES, UNGLAZED, FLOOR, 16" 3.20 -

5052 QUARRY TILES, UNGLAZED, FLOOR, 12" 3.17 -

5053 QUARRY TILES, UNGLAZED, BASE, 6" 2.76 -

5054 QUARRY TILES, GLAZED, FLOOR, 6" 2.76 -

2055 QUARRY TILES, UNGLAZED, BASE, 6" 2.76 -

5056 TERRAZO TILES, STANDARD 3.10 -

5057 TERRAZO TILES, GRANITE 2.68 -

5058 CERAMIC TILES, GLAZED, 4" x 4" 3.92 -

5059 CERAMIC TILES, UNGLAZED, 4" x 4" 3.92 -

17
MANPOWER RATE 10 JUNE 2010

Productivity / Productivity /
CODE DESCRIPTION
Man-Day(8hrs) Equipment-Day(8hrs)

5060 CERAMIC MOSAIC TILES, GLAZED 3.92 -

5061 CERAMIC MOSAIC TILES, UNGLAZED 3.92 -

5070 ACOUSTICAL TREATMENT


ACOUSTICAL UNIT INCLUDING SEMI EXPOSED SUSPENSION SYSTEM WITH
5071 4.97 -
1-1/2" CHANNELS AT 4" O.C AND 3/4" CHANNEL AT 2" O.C - 2" x 4" GRID
ACOUSTICAL UNIT INCLUDING EXPOSED SUSPENSION SYSTEM WITH T
5072 3.72 -
RUNNERS AT 2" O.C AND CROSS RUNNERS AT 2" O.C.- 2" x 4" GRID
ACOUSTICAL UNIT INCLUDING EXPOSED SUSPENSION SYSTEM WITH T
5073 12.31 -
RUNNERS AT 2" O.C AND CROSS RUNNERS AT 2" O.C.- 2" x 2" GRID

5080 VINYL COMPOSITION TILE ON CONCRETE


5081 VINYL COMPOSITION TILE ON CONCRETE 18.60 -
5082 WALL BASE 18.60 -

5090 CARPET
5091 CARPET 6.67 -

6000 PAINTING OF BUILDING ( FIELD PAINTING )


6001 CONCRETE OR CMU WALL, 2 COATS 11.27 -
6002 CONCRETE OR CMU WALL, 3 COATS 8.99 -
6003 METAL SURFACES, 2 COATS, BRUSH METHOD 9.20 -
6004 METAL SURFACES, 3 COATS, BRUSH METHOD 7.62 -
6005 METAL SURFACES, 2 COATS, SPRAY METHOD 12.90 -
6006 METAL SURFACES, 3 COATS, SPRAY METHOD 11.76 -
6007 WOOD SURFACES, 2 COATS 11.11 -
6008 WOOD SURFACES, 3 COATS 9.09 -
6009 GALVANIZED IRON SURFACES, 2 COATS 19.05 -
6010 VARNISH 5.48 -

6020 WALL COVERING


6021 VINYL COVER
6022 7 OZ PER SY 4.97 -
6023 15 OZ PER SY 3.72 -
6024 24 OZ PER SY 3.24 -
6025 36 OZ PER SY 2.12 -
6026 PAPER COVER 2.48 -

6030 TOILET PARTITIONS


6031 TOILET ENCLOSURES, METAL SURFACE AREA 1.49 -
6032 URINAL SCRRENS 1.49 -

6040 METAL LOUVERS


6041 METAL LOUVERS 1.45 -
SCREEN 7.41 -

Installation of precast panel (2.9m x 3.5m) 8

Raised Flooring 0.36

18
MANPOWER RATE 10 JUNE 2010

ER Actual
Productivity / Productivity / Productivity /
UNIT MH RATE MANPOWER EQUIPMENT
Crew-Day(8hrs) Man-Day(8hrs) Equipment-Day(8hrs)

5.41 sq.m 2.960 1 MASON


1 HELPER
5.80 sq.m 2.760 1 MASON
1 HELPER
7.62 sq.m 2.100 1 MASON
1 HELPER
11.03 sq.m 1.450 1 MASON
1 HELPER
13.01 sq.m 1.230 1 MASON
1 HELPER
4.51 sq.m 3.550 1 MASON
1 HELPER
6.50 sq.m 7.380 3 MASONS
1 CARPENTER
2 LABOURERS
6.30 sq.m 7.620 3 MASONS
1 CARPENTER
2 LABOURERS
5.00 sq.m 9.600 3 MASONS
1 CARPENTER
2 LABOURERS
4.40 sq.m 10.910 3 MASONS
1 CARPENTER
2 LABOURERS

6.40 sq.m 2.500 1 MASON


1 LABOURER
5.82 sq.m 2.750 1 MASON
1 LABOURER
5.33 sq.m 3.000 1 MASON
1 LABOURER
6.40 sq.m 2.500 1 MASON
1 LABOURER
5.82 sq.m 2.750 1 MASON
1 LABOURER
5.33 sq.m 3.000 1 MASON
1 LABOURER
32.00 sq.m 0.500 1 MASON
1 LABOURER
29.09 sq.m 0.550 1 MASON
1 LABOURER
26.67 sq.m 0.600 1 MASON
1 LABOURER
1600.00 KG 0.050 5 STEEL FIXERS 1 BAR CUTTER
5 HELPERS
114.29 li.m 0.140 2 MASONS

16.22 sq.m 1.480 2 MASONS


1 LABOURER
53.33 sq.m 0.450 2 MASONS
1 LABOURER
50.00 sq.m 0.480 2 MASONS
1 LABOURER
8.92 sq.m 2.690 2 MASONS
1 LABOURER
9.02 sq.m 2.660 2 MASONS
1 LABOURER
8.73 sq.m 2.750 2 MASONS
1 LABOURER
25.00 sq.m 0.640 2 MASONS
8.00 sq.m 2.000 2 MASONS
8.47 sq.m 1.890 2 MASONS
2.86 sq.m 2.800 1 MASON
4.57 sq.m 1.750 1 MASON
4.00 sq.m 2.000 1 MASON
32.00 sq.m 1.000 3 MASONS

19
MANPOWER RATE 10 JUNE 2010

Productivity / Productivity / Productivity /


UNIT MH RATE MANPOWER EQUIPMENT
Crew-Day(8hrs) Man-Day(8hrs) Equipment-Day(8hrs)
1 LABOURER
17.02 sq.m 1.880 3 MASONS
1 LABOURER
8.42 sq.m 1.900 2 MASONS
29.63 sq.m 0.540 2 MASONS
25.00 sq.m 0.640 2 MASONS
22.22 sq.m 0.720 2 MASONS
20.00 sq.m 0.800 2 MASONS
15.24 sq.m 1.050 2 MASONS
14.55 sq.m 1.100 2 MASONS
13.91 sq.m 1.150 2 MASONS
21.62 sq.m 1.480 2 MASONS
2 LABOURERS
52.63 sq.m 1.520 4 MASONS
6 LABOURERS
42.11 sq.m 1.520 3 MASONS
5 LABOURERS
42.11 sq.m 1.520 3 MASONS
5 LABOURERS
6.78 sq.m 9.440 3 MASONS
5 LABOURERS
10.53 sq.m 6.080 3 MASONS
5 LABOURERS
6.09 sq.m 3.940 1 MASON
2 LABOURERS
7.67 sq.m 3.130 1 MASON
2 LABOURERS
10.96 sq.m 1.460 1 MASON
1 LABOURER
5.46 sq.m 2.930 1 MASON
1 LABOURER
6.09 sq.m 3.940 1 MASON
2 LABOURERS
6.09 sq.m 3.940 1 MASON
2 LABOURERS
6.09 sq.m 3.940 1 MASON
2 LABOURERS
3.20 sq.m 2.500 1 MASON
3.33 sq.m 2.400 1 MASON
8.05 sq.m 2.980 2 MASONS
1 LABOURER

6.38 SM 3.760 2 CARPENTERS


1 LABOURER
6.50 SM 3.690 2 CARPENTERS
1 LABOURER
6.50 SM 3.690 2 CARPENTERS
1 LABOURER
6.50 SM 3.690 2 CARPENTERS
1 LABOURER
21.43 SM 1.120 2 CARPENTERS
1 LABOURER

6.40 SM 2.500 1 MASON


1 LABOURER
6.35 SM 2.520 1 MASON
1 LABOURER
5.52 SM 2.900 1 MASON
1 LABOURER
5.52 SM 2.900 1 MASON
1 LABOURER
5.52 SM 2.900 1 MASON
1 LABOURER
9.30 SM 2.580 2 MASONS
1 LABOURER
8.05 SM 2.980 2 MASONS
1 LABOURER
15.69 SM 2.040 2 MASONS
2 LABOURERS
15.69 SM 2.040 2 MASONS

20
MANPOWER RATE 10 JUNE 2010

Productivity / Productivity / Productivity /


UNIT MH RATE MANPOWER EQUIPMENT
Crew-Day(8hrs) Man-Day(8hrs) Equipment-Day(8hrs)
2 LABOURERS
15.69 SM 2.040 2 MASONS
2 LABOURERS
15.69 SM 2.040 2 MASONS
2 LABOURERS

4.97 SM 1.610

3.72 SM 2.150

12.31 SM 0.650

18.60 SM 0.430
18.60 LM 0.430

6.67 SM 1.200

11.27 SM 0.710
8.99 SM 0.890
9.20 SM 0.870
7.62 SM 1.050
12.90 SM 0.620
11.76 SM 0.680
11.11 SM 0.720
9.09 SM 0.880
19.05 SM 0.420
5.48 SM 1.460

4.97 SM 1.610
3.72 SM 2.150
3.24 SM 2.470
2.12 SM 3.770
2.48 SM 3.230

1.49 SM 5.380
1.49 SM 5.380

1.45 SM 5.500
7.41 SM 1.080

pcs 1 towercrane
2 rigger
4 skilled
1.44 sqm 4 skilled

21
MANPOWER RATE 10 JUNE 2010

Average
Productivity / Productivity /
Man-Day(8hrs) Equipment-Day(8hrs)

2.70 -

2.90 -

3.81 -

5.52 -

6.50 -

2.25 -

1.08 -

1.05 -

0.83 -

0.73 -

3.20 -

2.91 -

2.67 -

3.20 -

2.91 -

2.67 -

16.00 -

14.55 -

13.33 -

160.00 -

57.14 -

5.41 -

17.78 -

16.67 -

2.97 -

3.01 -

2.91 -

12.50 -
4.00 -
4.23 -
2.86 -
4.57 -
4.00 -
8.00 -

22
MANPOWER RATE 10 JUNE 2010

Productivity / Productivity /
Man-Day(8hrs) Equipment-Day(8hrs)

4.26 -

4.21 -
14.81 -
12.50 -
11.11 -
10.00 -
7.62 -
7.27 -
6.96 -
5.41 -

5.26 -

5.26 -

5.26 -

0.85 -

1.32 -

2.03 -

2.56 -

5.48 -

2.73 -

2.03 -

2.03 -

2.03 -

3.20 -
3.33 -
2.68 -

2.13 -

2.17 -

2.17 -

2.17 -

7.14 -

3.20 -

3.17 -

2.76 -

2.76 -

2.76 -

3.10 -

2.68 -

3.92 -

3.92 -

23
MANPOWER RATE 10 JUNE 2010

Productivity / Productivity /
Man-Day(8hrs) Equipment-Day(8hrs)

3.92 -

3.92 -

4.97 -

3.72 -

12.31 -

18.60 -
18.60 -

6.67 -

11.27 -
8.99 -
9.20 -
7.62 -
12.90 -
11.76 -
11.11 -
9.09 -
19.05 -
5.48 -

4.97 -
3.72 -
3.24 -
2.12 -
2.48 -

1.49 -
1.49 -

1.45 -
7.41 -

24

You might also like