Substation & Equipment Installation Status

The document provides a status update for electrical work being done at 5 substations. At each substation, the status of tasks like installing cable trays, transformers, panels, lighting fixtures, and fire systems is given. Many tasks are marked as done or finished, but some still require additional work like waiting for vendors, civil work to finish, or sending revised documentation.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
66 views5 pages

Substation & Equipment Installation Status

The document provides a status update for electrical work being done at 5 substations. At each substation, the status of tasks like installing cable trays, transformers, panels, lighting fixtures, and fire systems is given. Many tasks are marked as done or finished, but some still require additional work like waiting for vendors, civil work to finish, or sending revised documentation.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Remarks For Stauts Not for IR to be

SR. AREA ACTIVITY QC (IR) Status


Done

1 SUBSTATION ( 1 ) INSTALLATION OF CABLE TRAYS & EARTHING Done Finished


2 SUBSTATION ( 1 ) INSTALLATION OF TRANSFORMERS Done Finished
3 SUBSTATION ( 1 ) INSTALLATION OF PANELS Done waiting L &T
First Floor is Done &
4 SUBSTATION ( 1 ) INSTALLATION OF LIGHTING FIXTURES & WIRES After Civil Finishing
Other Floors not Done
After finishing all concerns ( routs
5 SUBSTATION ( 1 ) INSTALLATION OF FIRE SYSTEM & CABLES Not Done between buildings, Install Panels after
Vendor Comming)

After Sending the last Revsion For Cable


6 SUBSTATION ( 1 ) CABLE PULLING & TERMINATION Some Cables Done
list and Clear termination sheets

7 SUBSTATION ( 2 ) INSTALLATION OF CABLE TRAYS & EARTHING Done Finished


8 SUBSTATION ( 2 ) INSTALLATION OF TRANSFORMERS Done Finished
9 SUBSTATION ( 2 ) INSTALLATION OF PANELS Done Finished
10 SUBSTATION ( 2 ) INSTALLATION OF LIGHTING FIXTURES & WIRES Not Done Finished
After finishing all concerns (routs
11 SUBSTATION ( 2 ) INSTALLATION OF FIRE SYSTEM & CABLES Not Done between buildings, Install Panels after
Vendor Comming)

After Sending the last Revsion For Cable


12 SUBSTATION ( 2 ) CABLE PULLING & TERMINATION Some Cables Done list and Clear termination sheets

13 SUBSTATION ( 3 ) INSTALLATION OF CABLE TRAYS & EARTHING Done Finished


14 SUBSTATION ( 3 ) INSTALLATION OF TRANSFORMERS Done Finished
15 SUBSTATION ( 3 ) INSTALLATION OF PANELS Done Finished
16 SUBSTATION ( 3 ) INSTALLATION OF LIGHTING FIXTURES & WIRES Not Done After Civil Finishing
After finishing all concerns (routs
17 SUBSTATION ( 3 ) INSTALLATION OF FIRE SYSTEM & CABLES Not Done between buildings, Install Panels after
Vendor Comming)

After Sending the last Revsion For Cable


18 SUBSTATION ( 3 ) CABLE PULLING & TERMINATION Not Done
list and Clear termination sheets

19 SUBSTATION ( 4 ) INSTALLATION OF CABLE TRAYS & EARTHING Done Finished


20 SUBSTATION ( 4 ) INSTALLATION OF TRANSFORMERS Done Finished
ALL PANELS DONE EXCEPT
21 SUBSTATION ( 4 ) INSTALLATION OF PANELS waiting L &T
NOT INSTALLED PANELS
First Floor and third floor are Done
22 SUBSTATION ( 4 ) INSTALLATION OF LIGHTING FIXTURES & WIRES & After Civil Finishing
Other Floors not Done

After finishing all concerns (routs


23 SUBSTATION ( 4 ) INSTALLATION OF FIRE SYSTEM & CABLES Not Done between buildings, Install Panels after
Vendor Comming)

After Sending the last Revsion For Cable


24 SUBSTATION ( 4 ) CABLE PULLING & TERMINATION Some Cables Done list and Clear termination sheets

25 SUBSTATION ( 5 ) INSTALLATION OF CABLE TRAYS & EARTHING Done Finished


26 SUBSTATION ( 5 ) INSTALLATION OF TRANSFORMERS Done Finished
27 SUBSTATION ( 5 ) INSTALLATION OF PANELS Done Finished
28 SUBSTATION ( 5 ) INSTALLATION OF LIGHTING FIXTURES & WIRES Not Done Finished
After finishing all concerns (routs
29 SUBSTATION ( 5 ) INSTALLATION OF FIRE SYSTEM & CABLES Not Done between buildings, Install Panels after
Vendor Comming)

After Sending the last Revsion For Cable


30 SUBSTATION ( 5 ) CABLE PULLING & TERMINATION Some Cables Done
list and Clear termination sheets

31 SUBSTATION ( 6 ) INSTALLATION OF CABLE TRAYS & EARTHING Done Finished


32 SUBSTATION ( 6 ) INSTALLATION OF TRANSFORMERS Done Finished
33 SUBSTATION ( 6 ) INSTALLATION OF PANELS Done Finished
After Civil Finishing & one panel not
34 SUBSTATION ( 6 ) INSTALLATION OF LIGHTING FIXTURES & WIRES Not Done
supply
After finishing all concerns (routs
35 SUBSTATION ( 6 ) INSTALLATION OF FIRE SYSTEM & CABLES Not Done between buildings, Install Panels after
Vendor Comming)

After Sending the last Revsion For Cable


36 SUBSTATION ( 6 ) CABLE PULLING & TERMINATION Some Cables Done
list and Clear termination sheets

37 ECR#7 INSTALLATION OF CABLE TRAYS & EARTHING Not Done Finished


38 ECR#7 INSTALLATION OF PANELS Not Done After Civil Finishing

39 ECR#7 INSTALLATION OF LIGHTING FIXTURES & WIRES Not Done After Civil Finishing & Out door (staire)

After finishing all concerns (routs


40 ECR#7 INSTALLATION OF FIRE SYSTEM & CABLES Not Done between buildings, Install Panels after
Vendor Comming)

After Sending the last Revsion For Cable


41 ECR#7 CABLE PULLING & TERMINATION Not Done list and Clear termination sheets

42 ECR#8 INSTALLATION OF CABLE TRAYS & EARTHING Done Finished


43 ECR#8 INSTALLATION OF PANELS Done Finished
44 ECR#8 INSTALLATION OF LIGHTING FIXTURES & WIRES Not Done
After finishing all concerns ( routs
45 ECR#8 INSTALLATION OF FIRE SYSTEM & CABLES Not Done between buildings, Install Panels after
Vendor Comming)

After Sending the last Revsion For Cable


46 ECR#8 CABLE PULLING & TERMINATION Not Done
list and Clear termination sheets

47 STACKER -RECLAIMER ( 1 ) INSTALLATION OF CABLE TRAYS & EARTHING Done Finished


48 STACKER -RECLAIMER ( 1 ) INSTALLATION OF PANELS Done Finished
49 STACKER -RECLAIMER ( 2 ) INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
50 STACKER -RECLAIMER ( 2 ) INSTALLATION OF PANELS Done Finished
51 STACKER -RECLAIMER ( 3 ) INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
52 STACKER -RECLAIMER ( 3 ) INSTALLATION OF PANELS Not Done
53 STACKER -RECLAIMER ( 4 ) INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
54 STACKER -RECLAIMER ( 4 ) INSTALLATION OF PANELS Not Done Finished

55 PIPE RACK ( CONNECTION BETWEEN SS 1 & SS 2 ) INSTALLATION OF CABLE TRAYS & EARTHING Not Done Finished

After Sending the last Revsion For Cable


56 PIPE RACK ( CONNECTION BETWEEN SS 1 & SS 2) CABLE PULLING & TERMINATION Not Done list, Clear termination sheets, Reducers,
Glands

PIPE RACK ( CONNECTION BETWEEN SS 1 & SS 4 )between ss1 to tt4


57 througth cooling water INSTALLATION OF CABLE TRAYS & EARTHING Not Done Finished

After Sending the last Revsion For Cable


PIPE RACK
58 ( CONNECTION BETWEEN SS 1 & SS 4 )between ss1 to tt4 througth cooling
CABLE
water
PULLING & TERMINATION Not Done list, Clear termination sheets, Reducers,
Glands
PIPE RACK ( CONNECTION BETWEEN SS 5& SS2 ) between muke up
59 water pump house to ss2 INSTALLATION OF CABLE TRAYS & EARTHING Done Finished

After Sending the last Revsion For Cable


PIPE RACK ( CONNECTION BETWEEN SS 5& SS2 ) between muke up
60 CABLE PULLING & TERMINATION Not Done Finished list, Clear termination sheets, Reducers,
water pump house to ss2
Glands
PIPE RACK ( CONNECTION BETWEEN GIS 33KV& SS 2) & cable trench
61 INSTALLATION OF CABLE TRAYS & EARTHING Finished
inside GIS

62 PIPE RACK ( CONNECTION BETWEEN GIS 33KV& SS 1) CABLE PULLING & TERMINATION Done Finished

63 Interconnection Pipe Rack (SS-1 to TT-7 ) INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
64 TT 1 INSTALLATION OF CABLE TRAYS & EARTHING Finished
65 TT 1 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
66 TT 1 INSTALLATION OF PANELS Finished
67 TT 1 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished Remaining Exit Sign
After Sending the last Revsion For Cable
68 TT 1 CABLE PULLING & TERMINATION list, Clear termination sheets, Reducers,
Glands
69 TT 2 INSTALLATION OF CABLE TRAYS & EARTHING Finished
70 TT 2 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
71 TT 2 INSTALLATION OF PANELS Finished
72 TT 2 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished Remaining Exit Sign
After Sending the last Revsion For Cable
73 TT 2 CABLE PULLING & TERMINATION Finished list, Clear termination sheets, Reducers,
Glands
74 TT 3 INSTALLATION OF CABLE TRAYS & EARTHING done Finished
75 TT 3 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
76 TT 3 INSTALLATION OF PANELS
77 TT 3 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished Remaining Exit Sign
After Sending the last Revsion For Cable
78 TT 3 CABLE PULLING & TERMINATION list, Clear termination sheets, Reducers,
Glands
79 TT 4 INSTALLATION OF CABLE TRAYS & EARTHING Finished
80 TT 4 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
81 TT 4 INSTALLATION OF PANELS Done
82 TT 4 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished Remaining Exit Sign
After Sending the last Revsion For Cable
83 TT 4 CABLE PULLING & TERMINATION list, Clear termination sheets, Reducers,
Glands
84 TT 5 INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
85 TT 5 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
86 TT 5 INSTALLATION OF PANELS
87 TT 5 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished Remaining Exit Sign
After Sending the last Revsion For Cable
88 TT 5 CABLE PULLING & TERMINATION Finished list, Clear termination sheets, Reducers,
Glands
89 TT 6 INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
90 TT 6 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
91 TT 6 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished Remaining Exit Sign
After Sending the last Revsion For Cable
92 TT 6 CABLE PULLING & TERMINATION list, Clear termination sheets, Reducers,
Glands
93 TT 7 INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
94 TT 7 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Done
95 TT 7 INSTALLATION OF PANELS Finished
96 TT 7 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished Remaining Exit Sign
After Sending the last Revsion For Cable
97 TT 7 CABLE PULLING & TERMINATION list, Clear termination sheets, Reducers,
Glands
98 TT 8 INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
99 TT 8 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
100 TT 8 INSTALLATION OF PANELS Finished
101 TT 8 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished Remaining Exit Sign
102 TT 8 CABLE PULLING & TERMINATION After Steel Finishing
103 TT 9 INSTALLATION OF CABLE TRAYS & EARTHING Finished
104 TT 9 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
105 TT 9 INSTALLATION OF PANELS
106 TT 9 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished Remaining Exit Sign
107 TT 9 CABLE PULLING & TERMINATION After Steel Finishing
108 TT 10 & Additive Grinding INSTALLATION OF CABLE TRAYS & EARTHING Done Ongoing
109 TT 10 &Additive Grinding INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
110 TT 10 &Additive Grinding INSTALLATION OF PANELS
111 TT 10 &Additive Grinding INSTALLATION OF LIGHTING FIXTURES & WIRES
112 TT 10 &Additive Grinding CABLE PULLING & TERMINATION After Steel Finishing
113 TT 11 INSTALLATION OF CABLE TRAYS & EARTHING Hold After Steel Finishing
114 TT 11 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Hold After Steel Finishing
115 TT 11 INSTALLATION OF PANELS Hold
116 TT 11 INSTALLATION OF LIGHTING FIXTURES & WIRES Hold After Steel Finishing
117 TT 11 CABLE PULLING & TERMINATION Hold
118 TT 12 INSTALLATION OF CABLE TRAYS & EARTHING Hold After Steel Finishing
119 TT 12 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Hold After Steel Finishing
120 TT 12 INSTALLATION OF PANELS Hold Steel
121 TT 12 INSTALLATION OF LIGHTING FIXTURES & WIRES Hold After Steel Finishing
122 TT 12 CABLE PULLING & TERMINATION Hold After Steel Finishing
123 ADDITIVE STORAGE INSTALLATION OF CABLE TRAYS & EARTHING done Finished
124 ADDITIVE STORAGE INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
125 ADDITIVE STORAGE INSTALLATION OF PANELS
126 ADDITIVE STORAGE SHED INSTALLATION OF LIGHTING FIXTURES & WIRES After Steel Finishing
After Sending the last Revsion For Cable
127 ADDITIVE STORAGE CABLE PULLING & TERMINATION list, Clear termination sheets, Reducers,
Glands
128 ADDITIVE STORAGE INSTALLATION OF TUBING & INSTRUMENTATION
129 MAKE UP WATER INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
130 MAKE UP WATER INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
131 MAKE UP WATER INSTALLATION OF PANELS
132 MAKE UP WATER INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
After Sending the last Revsion For Cable
133 MAKE UP WATER CABLE PULLING & TERMINATION Finished list, Clear termination sheets, Reducers,
Glands
134 MAKE UP WATER INSTALLATION OF TUBING & INSTRUMENTATION
135 SOFTWATER INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
136 SOFTWATER INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
137 SOFTWATER INSTALLATION OF PANELS Done
138 SOFTWATER INSTALLATION OF LIGHTING FIXTURES & WIRES
After finishing all concerns ( routs
139 SOFTWATER INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
After Sending the last Revsion For Cable
140 SOFTWATER CABLE PULLING & TERMINATION Some Cables Done list, Clear termination sheets, Reducers,
Glands
141 SOFTWATER INSTALLATION OF TUBING & INSTRUMENTATION
142 COOLING WATER PUMP HOUSE INSTALLATION OF CABLE TRAYS & EARTHING Done After Civil Finishing
143 COOLING WATER PUMP HOUSE INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
144 COOLING WATER PUMP HOUSE INSTALLATION OF PANELS Finished
145 COOLING WATER PUMP HOUSE INSTALLATION OF LIGHTING FIXTURES & WIRES
146 COOLING WATER PUMP HOUSE CABLE PULLING & TERMINATION After Civil Finishing
147 COOLING WATER PUMP HOUSE INSTALLATION OF TUBING & INSTRUMENTATION

148 COMMINUCATION AREA HPGR INSTALLATION OF CABLE TRAYS & EARTHING Done Finished After Both Civil & Steel are Finishing

149 COMMINUCATION AREA HPGR INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Done Finished
150 FIRE WATER PUMP HOUSE INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
151 COMMINUCATION AREA HPGR INSTALLATION OF PANELS
152 FIRE WATER PUMP HOUSE INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
153 COMMINUCATION AREA HPGR INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
154 COMMPROSOER HOUSE INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
155 COMMINUCATION AREA HPGR CABLE PULLING & TERMINATION After Steel Finishing
156 COMMPROSOER HOUSE INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
157 COMMINUCATION AREA HPGR INSTALLATION OF TUBING & INSTRUMENTATION
158 FILTRATION AREA /THIKNER INSTALLATION OF CABLE TRAYS & EARTHING Done After Steel Finishing
159 FILTRATION AREA INSTALLATION OF SecondaryCABLE TRAYS & EARTHING done After Steel Finishing
After finishing all concerns (Glands,
160 FILTRATION AREA INSTALLATION OF PANELS boxes, routs between buildings, Install
Panels)
161 FILTRATION AREA INSTALLATION OF LIGHTING FIXTURES & WIRES After Steel Finishing
162 FILTRATION AREA CABLE PULLING & TERMINATION After Steel Finishing
163 FILTRATION AREA INSTALLATION OF TUBING & INSTRUMENTATION
164 PROCESS WATER INSTALLATION OF CABLE TRAYS & EARTHING Finished After Steel Finishing
165 PROCESS WATER & FIRE PUMP HOUSE INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
166 PROCESS WATER & FIRE PUMP HOUSE INSTALLATION OF PANELS Finished Steel
167 PROCESS WATER & FIRE PUMP HOUSE INSTALLATION OF LIGHTING FIXTURES & WIRES Finished LT & Civil & Steel
After finishing all concerns ( routs
168 PROCESS WATER & FIRE PUMP HOUSE INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
169 PROCESS WATER & FIRE PUMP HOUSE CABLE PULLING & TERMINATION After Steel Finishing
170 PROCESS WATER & FIRE PUMP HOUSE INSTALLATION OF TUBING & INSTRUMENTATION
171 BENEFICATION AREA INSTALLATION OF CABLE TRAYS & EARTHING done After Steel Finishing & access way
172 BENEFICATION AREA INSTALLATION OF SecondaryCABLE TRAYS & EARTHING After Steel Finishing
After finishing all concerns (Glands,
173 BENEFICATION AREA INSTALLATION OF PANELS boxes, routs between buildings, Install
Panels)
174 BENEFICATION AREA INSTALLATION OF LIGHTING FIXTURES & WIRES After Steel Finishing
175 BENEFICATION AREA CABLE PULLING & TERMINATION After Steel Finishing
176 BENEFICATION AREA INSTALLATION OF TUBING & INSTRUMENTATION
177 MAIN WORK SHOP INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
178 MAIN WORK SHOP INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Done
179 MAIN WORK SHOP INSTALLATION OF PANELS After Civil Finishing
180 MAIN WORK SHOP INSTALLATION OF LIGHTING FIXTURES & WIRES After Civil Finishing
After finishing all concerns (routs
181 MAIN WORK SHOP INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
182 MAIN WORK SHOP CABLE PULLING & TERMINATION After Civil Finishing
183 MAIN WORK SHOP INSTALLATION OF TUBING & INSTRUMENTATION
184 REPAIR SHOP Bp INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
185 REPAIR SHOP Bp INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Done After Civil Finishing
186 REPAIR SHOP Bp INSTALLATION OF PANELS After Civil Finishing
187 REPAIR SHOP Bp INSTALLATION OF LIGHTING FIXTURES & WIRES After Civil Finishing & LT drawing
After finishing all concerns (routs
188 REPAIR SHOP Bp INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
189 REPAIR SHOP Bp CABLE PULLING & TERMINATION After Civil Finishing
190 REPAIR SHOP Bp INSTALLATION OF TUBING & INSTRUMENTATION
191 REPAIR SHOP PP INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
192 REPAIR SHOP PP INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Done After Civil Finishing
193 REPAIR SHOP PP INSTALLATION OF PANELS
194 REPAIR SHOP PP INSTALLATION OF LIGHTING FIXTURES & WIRES After Civil Finishing & LT drawing
After finishing all concerns (routs
195 REPAIR SHOP PP INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
196 REPAIR SHOP PP CABLE PULLING & TERMINATION After Civil Finishing
197 REPAIR SHOP PP INSTALLATION OF TUBING & INSTRUMENTATION
198 ADDITIVE UNLOADING AREA INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
199 ADDITIVE UNLOADING AREA INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Done Finished
200 ADDITIVE UNLOADING AREA INSTALLATION OF PANELS
201 ADDITIVE UNLOADING AREA INSTALLATION OF LIGHTING FIXTURES & WIRES
After finishing all concerns (routs
202 ADDITIVE UNLOADING AREA INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
203 ADDITIVE UNLOADING AREA CABLE PULLING & TERMINATION After Civil Finishing
204 ADDITIVE UNLOADING AREA INSTALLATION OF TUBING & INSTRUMENTATION
205 DOSING & MIXING INSTALLATION OF CABLE TRAYS & EARTHING Done After Steel Finishing level 22
206 DOSING & MIXING INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Done After Steel Finishing
After finishing all concerns (Glands,
207 DOSING & MIXING INSTALLATION OF PANELS boxes, routs between buildings, Install
Panels)
208 DOSING & MIXING INSTALLATION OF LIGHTING FIXTURES & WIRES After Steel Finishing
After Sending the last Revsion For Cable
209 DOSING & MIXING CABLE PULLING & TERMINATION list, Clear termination sheets, Reducers,
Glands
210 DOSING & MIXING INSTALLATION OF TUBING & INSTRUMENTATION
211 PELLET TRUCK LOADING & Weighing bridge INSTALLATION OF CABLE TRAYS & EARTHING done Finished
212 PELLET TRUCK LOADING INSTALLATION OF SecondaryCABLE TRAYS & EARTHING done
213 PELLET TRUCK LOADING INSTALLATION OF PANELS
214 PELLET TRUCK LOADING INSTALLATION OF LIGHTING FIXTURES & WIRES After Steel Finishing
After finishing all concerns (routs
215 PELLET TRUCK LOADING INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
216 PELLET TRUCK LOADING CABLE PULLING & TERMINATION
217 PELLET TRUCK LOADING INSTALLATION OF TUBING & INSTRUMENTATION
DFDS Beside Pellet truck loading INSTALLATION OF CABLE TRAYS & EARTHING done Finished
DFDS Beside Pellet truck loading INSTALLATION OF PANELS
DFDS Beside Pellet truck loading CABLE PULLING & TERMINATION
DFDS Beside Pellet truck loading INSTALLATION OF TUBING & INSTRUMENTATION
218 SFC UNLOADING STATION INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
219 SFC UNLOADING STATION INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Done Finished
220 SFC UNLOADING STATION &weigh Bridge INSTALLATION OF PANELS Done Finished Steel
221 SFC UNLOADING STATION & WEIGHBRIDGE INSTALLATION OF LIGHTING FIXTURES & WIRES
After finishing all concerns (routs
222 SFC UNLOADING STATION INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
223 SFC UNLOADING STATION CABLE PULLING & TERMINATION Some Cables Done
224 SFC UNLOADING STATION INSTALLATION OF TUBING & INSTRUMENTATION
225 INTERMEDIATE PIN AREA INSTALLATION OF CABLE TRAYS & EARTHING Ongoing
226 INTERMEDIATE PIN AREA INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Hold
227 INTERMEDIATE PIN AREA INSTALLATION OF PANELS Hold After Steel & Cable tray Finishing
228 INTERMEDIATE PIN AREA INSTALLATION OF LIGHTING FIXTURES & WIRES Hold After Steel & Cable tray Finishing
229 INTERMEDIATE PIN AREA CABLE PULLING & TERMINATION Hold Steel
230 INTERMEDIATE PIN AREA INSTALLATION OF TUBING & INSTRUMENTATION Hold
231 PLANT DEDUSTING & STACK INSTALLATION OF CABLE TRAYS & EARTHING Ongoing
232 PLANT DEDUSTING & STACK INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
233 PLANT DEDUSTING & STACK INSTALLATION OF LIGHTING FIXTURES & WIRES
After Sending the last Revsion For Cable
234 PLANT DEDUSTING & STACK CABLE PULLING & TERMINATION list, Clear termination sheets, Reducers,
Glands
235 PLANT DEDUSTING & STACK INSTALLATION OF TUBING & INSTRUMENTATION
236 ESP-PROCESS GAS AREA & STACK INSTALLATION OF CABLE TRAYS & EARTHING Some Cable trays are Done Ongoing
237 ESP-PROCESS GAS AREA & STACK INSTALLATION OF SecondaryCABLE TRAYS & EARTHING After Steel Finishing
238 ESP-PROCESS GAS AREA & STACK INSTALLATION OF PANELS
239 ESP-PROCESS GAS AREA & STACK INSTALLATION OF LIGHTING FIXTURES & WIRES
240 ESP-PROCESS GAS AREA & STACK CABLE PULLING & TERMINATION
241 ESP-PROCESS GAS AREA & STACK INSTALLATION OF TUBING & INSTRUMENTATION
242 Green pelletizing BUILDING INSTALLATION OF CABLE TRAYS & EARTHING Some Cable trays are Done Ongoing After Steel Finishing
243 Green pelletizing BUILDING INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
244 Green pelletizing BUILDING INSTALLATION OF PANELS
245 Green pelletizing BUILDING INSTALLATION OF LIGHTING FIXTURES & WIRES After Steel Finishing
246 Green pelletizing BUILDING CABLE PULLING & TERMINATION Steel
247 Green pelletizing BUILDING INSTALLATION OF TUBING & INSTRUMENTATION
248 Indurating building INSTALLATION OF CABLE TRAYS & EARTHING Some Cable trays are Done Ongoing
249 indurating building INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
250 indurating building INSTALLATION OF PANELS
251 indurating building INSTALLATION OF LIGHTING FIXTURES & WIRES
After finishing all concerns ( routs
252 indurating building((Burner Control PP) INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
253 indurating building CABLE PULLING & TERMINATION
254 indurating building INSTALLATION OF TUBING & INSTRUMENTATION
255 DG BESIDE SS#1 INSTALLATION OF CABLE TRAYS & EARTHING Finished
256 DG BESIDE SS#1 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
257 DG BESIDE SS#1 CABLE PULLING & TERMINATION
258 DG BESIDE SS#4 INSTALLATION OF CABLE TRAYS & EARTHING Finished
259 DG BESIDE SS#4 CABLE PULLING & TERMINATION
260 DFDS BESIDE SS#5 INSTALLATION OF CABLE TRAYS & EARTHING done Finished
261 DFDS BESIDE SS#5 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING done Finished
262 DFDS BESIDE SS#5 INSTALLATION OF PANELS
263 DFDS BESIDE SS#5 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
After Sending the last Revsion For Cable
264 DFDS BESIDE SS#5 CABLE PULLING & TERMINATION list, Clear termination sheets, Reducers,
Glands
265 DFDS BESIDE SS#5 INSTALLATION OF TUBING & INSTRUMENTATION
266 DFDS BESIDE PELLET TRUCK LOADING INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
267 DFDS BESIDE PELLET TRUCK LOADING INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Done After Civil Finishing
268 DFDS BESIDE PELLET TRUCK LOADING INSTALLATION OF PANELS
269 DFDS BESIDE PELLET TRUCK LOADING INSTALLATION OF LIGHTING FIXTURES & WIRES Finished LT & Civil
270 DFDS BESIDE PELLET TRUCK LOADING CABLE PULLING & TERMINATION
271 DFDS BESIDE PELLET TRUCK LOADING INSTALLATION OF TUBING & INSTRUMENTATION
272 CENTRAL LABORATORY INSTALLATION OF CABLE TRAYS & EARTHING Finished
273 CENTRAL LABORATORY INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
274 CENTRAL LABORATORY INSTALLATION OF PANELS
275 CENTRAL LABORATORY INSTALLATION OF LIGHTING FIXTURES & WIRES Finished LT & Civil
After finishing all concerns ( routs
276 CENTRAL LABORATORY INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
277 CENTRAL LABORATORY CABLE PULLING & TERMINATION
278 CENTRAL LABORATORY INSTALLATION OF TUBING & INSTRUMENTATION
After Both Civil & Steel are Finishing &
279 PELLET SCREENING & COATING ( NEAR INDURATING ) INSTALLATION OF CABLE TRAYS & EARTHING we have many modification for all
system
280 PELLET SCREENING & COATING ( NEAR INDURATING ) INSTALLATION OF SecondaryCABLE TRAYS & EARTHING
281 PELLET SCREENING & COATING ( NEAR INDURATING ) INSTALLATION OF PANELS

282 PELLET SCREENING & COATING ( NEAR INDURATING ) INSTALLATION OF LIGHTING FIXTURES & WIRES After Steel Finishing

After finishing all concerns (routs


283 Additive Grinding (Analyzer Room) INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)

284 PELLET SCREENING & COATING ( NEAR INDURATING ) CABLE PULLING & TERMINATION

285 PELLET SCREENING & COATING ( NEAR INDURATING ) INSTALLATION OF TUBING & INSTRUMENTATION

286 Conveyor UC01-GL002 INSTALLATION OF CABLE TRAYS & EARTHING Finished


287 Conveyor UC01-GL001 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
288 Conveyor UC01-GL002 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
289 Conveyor UC01-GL002 CABLE PULLING & TERMINATION Finished
290 Conveyor UC01-GL003 INSTALLATION OF CABLE TRAYS & EARTHING Finished
291 Conveyor UC01-GL003 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
292 Conveyor UC01-GL003 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
293 Conveyor UC01-GL003 CABLE PULLING & TERMINATION Finished
294 Conveyor UC01-GL006 & GL060 INSTALLATION OF CABLE TRAYS & EARTHING done Finished
295 Conveyor UC01-GL006 & GL060 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
296 Conveyor UC01-GL006 & GL060 INSTALLATION OF PANELS
297 Conveyor UC01-GL006 & GL060 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
298 Conveyor UC01-GL006 & GL060 CABLE PULLING & TERMINATION After Civil Finishing
299 Conveyor UC01-GL007 INSTALLATION OF CABLE TRAYS & EARTHING done Ongoing
300 Conveyor UC01-GL007 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Ongoing
301 Conveyor UC01-GL007 INSTALLATION OF LIGHTING FIXTURES & WIRES Ongoing
302 Conveyor UC01-GL007 CABLE PULLING & TERMINATION
303 Conveyor UC15-GL001/GL011 INSTALLATION OF CABLE TRAYS & EARTHING Finished
304 Conveyor UC15-GL01 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
305 Conveyor UC15-GL001 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
306 Conveyor UC15-GL001 CABLE PULLING & TERMINATION After Civil Finishing
307 Conveyor UC15-GL002 INSTALLATION OF CABLE TRAYS & EARTHING Finished
308 Conveyor UC15-GL02 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
309 Conveyor UC15-GL002 INSTALLATION OF LIGHTING FIXTURES & WIRES Ongoing
310 Conveyor UC15-GL02 CABLE PULLING & TERMINATION Finished
311 Conveyor UC15-GL004/GL014 INSTALLATION OF CABLE TRAYS & EARTHING Finished
312 Conveyor UC15-GL004/GL014 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
313 Conveyor UC15-GL004/GL014 INSTALLATION OF PANELS
314 Conveyor UC15-GL004/GL014& out door lighting INSTALLATION OF LIGHTING FIXTURES & WIRES
315 Conveyor UC15-GL004/GL014 CABLE PULLING & TERMINATION After Civil Finishing
316 Conveyor UC15-GL003/GL013 INSTALLATION OF CABLE TRAYS & EARTHING Done Finished
317 Conveyor UC15-GL003/GL013 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Done Finished
318 Conveyor UC15-GL003/GL013 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
319 Conveyor UC15-GL003/GL013 CABLE PULLING & TERMINATION Finished
320 Conveyor UC15-GL008 INSTALLATION OF CABLE TRAYS & EARTHING Finished
321 Conveyor UC15-GL08 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
322 Conveyor UC15-GL08 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
323 Conveyor UC15-GL008 CABLE PULLING & TERMINATION
324 Conveyor UC21-GL002 INSTALLATION OF CABLE TRAYS & EARTHING done Finished
325 Conveyor UC21-GL02 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING done Finished
326 Conveyor UC21-GL02 INSTALLATION OF LIGHTING FIXTURES & WIRES
327 Conveyor UC21-GL02 CABLE PULLING & TERMINATION Finished
328 Conveyor UC21-GL001 INSTALLATION OF CABLE TRAYS & EARTHING done Finished
329 Conveyor UC21-GL01 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING done Finished
330 Conveyor UC21-GL01 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
331 Conveyor UC21-GL001 CABLE PULLING & TERMINATION
332 Conveyor UC21-GL01 INSTALLATION OF TUBING & INSTRUMENTATION
333 Conveyor UC21-GL05 INSTALLATION OF LIGHTING FIXTURES & WIRES
334 Conveyor UC21-GL04 INSTALLATION OF CABLE TRAYS & EARTHING Finished
335 Conveyor UC21-GL04 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
336 Conveyor UC21-GL04 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
After finishing all concerns (routs
SECUIRTY OFFICE 1 INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)

After finishing all concerns (routs


SECUIRTY OFFICE 2 INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)

After finishing all concerns (routs


SECUIRTY OFFICE 3 INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
Conveyor ZG05-GL031 INSTALLATION OF CABLE TRAYS & EARTHING Finished
Conveyor ZG05-GL031 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
Conveyor SF01-GL042 INSTALLATION OF LIGHTING FIXTURES & WIRES After Steel Finishing
After finishing all concerns ( routs
Green pelletizing (Burner Control PP) INSTALLATION OF FIRE SYSTEM & CABLES between buildings, Install Panels after
Vendor Comming)
Conveyor SS01-GL031 INSTALLATION OF LIGHTING FIXTURES & WIRES
Conveyor SF01-GL031 INSTALLATION OF CABLE TRAYS & EARTHING Finished
Conveyor SF01-GL031 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
Conveyor SF01-GL031 CABLE PULLING & TERMINATION Finished Steel
Conveyor SF01-GL032 INSTALLATION OF CABLE TRAYS & EARTHING done Finished
Conveyor SF01-GL032 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING done Finished
Conveyor SF01-GL032 CABLE PULLING & TERMINATION Finished Steel
Conveyor SF01-GL035 INSTALLATION OF CABLE TRAYS & EARTHING Finished
Conveyor SF01-GL035 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
Conveyor SF01-GL031 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
Conveyor SF01-GL035 CABLE PULLING & TERMINATION Finished Steel
Conveyor SF01-GL036 INSTALLATION OF CABLE TRAYS & EARTHING done Finished
Conveyor SF01-GL036 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING done Finished
Conveyor SF01-GL032 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
Conveyor SF01-GL036 CABLE PULLING & TERMINATION Finished Steel
Conveyor SF01-GL042 INSTALLATION OF CABLE TRAYS & EARTHING After Steel Finishing
Conveyor SF01-GL042 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
Conveyor SF01-GL035 INSTALLATION OF LIGHTING FIXTURES & WIRES
Conveyor SF01-GL042 CABLE PULLING & TERMINATION After Steel Finishing
Conveyor SS01-GL031 INSTALLATION OF SecondaryCABLE TRAYS & EARTHING Finished
Conveyor SF01-GL036 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
Conveyor SS01-GL031 CABLE PULLING & TERMINATION Steel
Conveyor CM01-GL081 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
Conveyor SS01-GL011/12 INSTALLATION OF LIGHTING FIXTURES & WIRES After Steel Finishing
Conveyor ZG05-GL031 INSTALLATION OF LIGHTING FIXTURES & WIRES Finished
Conveyor ZG05-GL011 INSTALLATION OF LIGHTING FIXTURES & WIRES