Irrigation Canal Design Guide
Irrigation Canal Design Guide
(Ver.1.1)
for
Technical Cooperation for Capacity Development
for the Promotion of Irrigation Scheme Development
under the District Agriculture Development Plans (DADPs)
Sept. 2017
Page
1. Introduction ............................................................................................................................ 1
1.1 Background .................................................................................................................... 1
1.2 Objective ........................................................................................................................ 1
1.3 Scope of the manual ....................................................................................................... 1
1.4 Relation to relevant Guidelines and manuals ................................................................. 2
2. Summary of the design for open canals ................................................................................. 3
2.1 Procedure for decision of canal cross-section ................................................................ 3
2.2 Examination item in each step ....................................................................................... 4
3. Detailed description of the components ................................................................................. 8
3.1 Design discharge ............................................................................................................ 8
3.2 Canal route selection .................................................................................................... 10
3.3 Classification of open canal ......................................................................................... 11
3.4 Evaluation of the soil property ..................................................................................... 16
3.5 Hydraulic design by normal calculation ...................................................................... 22
3.6 Hydraulic design using the proposed chart .................................................................. 30
3.7 Economic comparison .................................................................................................. 34
4. Incidental structure ............................................................................................................... 36
4.1 Division structure ......................................................................................................... 36
4.2 Drop structure .............................................................................................................. 37
Annex-1 Calculation Chart for Cross-section Settling .......................................................... 39
Annex-2 Drawing Collection of Standard Design for Irrigation Canal ................................. 69
1. Introduction
1.1 Background
The promotion of irrigation project becomes the urgent matter as a policy to plan improvement
of the farm productivity in Tanzania. However, a great variety of irrigation facilities exist
because the standard guidance about the design of canals and related structures is not arranged.
On the other hand, the staff of Zonal Irrigation Office and District taking the role that is
important to the promotion of the irrigation project largely is in hard situation; lack the number
of engineer or insufficient accumulation of technical know-how, so improvement of these
circumstance is necessary.
1.2 Objective
Problems related to the existing irrigation facilities in selected area from the viewpoint of
policy system and technical aspect are to be grasped and clarified through survey and collection
of data. Objective of this manual is to support smooth enforcement of designing of irrigation
canal by LGA supported by ZIO and NIC using the flowchart for selecting the canal type and
calculation charts for decision of canal cross-section, etc.
On the occasion of the development of the manual, the following points are noted.
- Arranging the problem of existing irrigation facilities and the cause of issue on every stage
of investigation, plan, design, construction and maintenance respectively, standard design
manual of irrigation canal should be made included the measures corresponding to these
problem.
- Confirming the capacity of technical staff and material/tools which can be obtained locally
by execution of survey in cooperation with Counter Part engineer, this standard design
considers Tanzanian situation.
This manual covers standard design of the open canals such as lining canal mainly.
Especially, the method for decision of canal cross-section using calculation chart based on the
direct calculation method will be described. In addition, division structure and drop structure
are attached as incidental structure.
The scope of irrigation canal is as Table 1-1 in next page. Because this manual relatively
intends for the small canal of the scale as it is listed, larger scale irrigation facilities more than
this range needs original detailed design separately.
3
Table 1-1 Scope of application
When there is no explanation in particular, the technical standard and the standard
numerical value described in this manual shall be quoted from “Land Improvement Project
Plan Design Standard, Design, Canal Works”, as Japanese Design Standard (hereinafter called
as JDS) or from small scale irrigation design manual and CGL.
The Guidelines consist of the main part and reference materials. The former shows the
process of the procedure for Formulation, Construction, O&M and training. The latter collects
a series of technical standard to supplement the main body.
The standard design manual improves the ability of Zonal Irrigation Offices and Districts
staff by being made as Technical Guidance in the Comprehensive Guidelines. (Figure 1-1)
GL
I The Comprehensive Guidelines (CGL)
Technical Guidance
II Reference materials
Formulation Irrigation design manual (volume 1,2)
Others
Design Standard design manual
Irrigation design manual (volume 1,2)
Standard Tendering Document (Procurement of Works)
Others
Construction Construction supervision and so on
Others
4
2. Summary of the design for open canals
Start
Study on Need
backfilling replacement
Step-4
Need to set base &
No need backfilling gravel
Study on
Step-5 hydraulic design
Study on
Step-6 economic comparison
Cheaper
Concrete slab / Masonry
lining canal
End
5
2.2 Examination item in each step
For the design discharge of the irrigation canal, the planned maximum discharge for each
season and irrigation water system defined in the irrigation plan is generally used. For
example, design discharge shall be calculated based on CGL: Comprehensive Guidelines, or it
may be determined using another technical documents or in reference to the example of other
scheme.
< For details, refer to 3.1 >
The canal route should be examined taking into consideration of maintenance, operation
and economic efficiency after reviewing result of the field survey. Moreover, main canal
should be located at the higher level of the land surface.
< For details, refer to 3.2 >
In the selection of canal type, several factor such as design discharge, securing functions
required, generality of materials, etc. should be considered comprehensively. Moreover,
irrigation facilities should be designed and constructed to show high performance during the
service period. As a result of examination, masonry lining canals and concrete slab lining
canals are selected as the most suitable canal type in Tanzania.
< For details, refer to 3.3 >
The soil property should be determined using easy method described in the CGL. The side
slope of lining canal shall be decided based on the soil property because there is a difference
in stability of the slope or resistance for scouring against water flow. In this manual, the side
slope of lining canal is proposed as follows.
In case of soft ground such as black cotton soil or high groundwater level, the irrigation
canal possibly deteriorates with differential settlement due to expansion of the soil or uplift
pressure of groundwater, replacement of backfilling using gravel, sand soil or morrum is
proposed while weep hole or under drain is effective as a counter measure.
< For details, refer to 3.4.5 >
6
Step-5 Study on hydraulic design
This manual is introducing a simple design method of canal cross-section settling for small
scale irrigation schemes by using “Calculation Chart” as attached in Annex-1.
After getting Q (discharge), S (canal slope), m (side slope) and assuming the canal type
such as concrete slab lining, masonry lining, you can simply design the cross-section of canals
using the chart.
< For details, refer to 3.5 >
Since the coefficient of roughness between concrete slab and masonry differ, the
cross-section of each canal changes even if the discharge is the same. So, after setting the
cross-section of both lining canal using calculation chart, economic comparison should be
executed.
< For details, refer to 3.7 >
The most suitable cross-section of irrigation canal shall be decided based on this flow chart
mentioned above. Several calculation chart for cross-section settling of concrete slab lining
canal, masonry lining canal and flume are attached in Annex-1.
Moreover, actual construction plan shall be examined using drawings of standard design for
irrigation canal attached in Annex-2.
7
Table 2-1 Classification of open canal
Cross-section
8
Photo-1 Photo-2
Unlined canal Masonry lining canal
(Igongwa, Misunguwi, Mwanza) (Chomachankora, Igunga, Tabora)
Photo-3 Photo-4
Masonry lining canal Concrete slab lining
(Ulyanyama, Sikonge, Tabora) (Msagali, Mpwapwa, Central)
Photo-5 Photo-6
Concrete lining (With RBC) canal Concrete retaining wall canal
(Nyida, Shinanga, Mwanza) (Msufini, Mvomero, Morogoro)
9
3. Detailed description of the components
Design discharge means the planned maximum discharge in the irrigation plan for each
season and irrigation water system, or the planned maximum discharge in the drainage plan.
While the size of canal is expressed in the design discharge, other discharges shall be studied as
well in determining cross sections, structures, water level control, etc.
For the design discharge of the irrigation canal, the planned maximum discharge for each
season and irrigation water system defined in the irrigation plan is generally used. However,
when diversion of discharge not in accordance with the plan can occur in upstream sections, or
when it is possible that the inflow of flood water is unavoidable due to topological restrictions,
the design discharge can be obtained by adding the planned diversion discharge or inflow flood
water volume.
Generally, the design discharge shall be determined after completing comparative studies for
the overall facility costs covering possible new construction of wasteways/spillways for each
section and improvement plan of discharging rivers.
Also, since it is often that planning conditions of the irrigated areas change over time during
each phase of planning, design, and construction, periodical confirmations of determining
factors for irrigation volume (e.g. water requirement rate, cultivation system, irrigated acreage,
diversion points, irrigation methods, etc.) are necessary.
10
Figure 3-2 Parameter for calculation of GWR)
1. Place Arusha
2. Crop Paddy (Clay Loam)
3. Irrigation efficiency 0.40 (Lined)
The design discharge of the drainage canal shall be the planned maximum discharge defined
in the drainage plan. While the flow exceeding the design discharge is not expected in the
normal irrigation canal, the drainage runoff with frequency exceeding the planned probability is
possible. Therefore, thoughtful considerations shall be given for the flow equal to or exceeding
design discharge.
Also, although there is generally no change in catchment area of the drainage plan, runoff
data may vary as hydrological conditions, land use category, site social environment, and other
items change. Therefore, it is necessary to check these items throughout each phase of planning,
11
design, and construction, and to advance the project while implementing necessary response
measures.
The canal route shall be selected in a way that it assures the design discharge and designed
water level that are determined based on the irrigation and drainage plan, and that it shall be
able to accommodate assumed canal types.
In doing so, the route shall be selected with consideration of the canal structure selected for
water conveying facilities, the layout of various facilities, and their structural systems as well.
Also, in canal route selection, problems with social implications, such as site acquisition and
changes in irrigation and drainage practices, may arise. Thus a rigorous comparative study shall
be conducted on map drawings beforehand.
The following are general points to be considered for canal route selection.
- For the irrigation canal, the route selection shall be made with consideration that the canal,
in principle, can irrigate by gravity to the benefited area, and that the available water head at
the intake point will be utilized as much as possible.
- Canal route selection shall be made so that the drainage canal shall, in principal, run
through the section of lowest elevation within the project area.
- Items including spillways, waste-weir, and turnouts in irrigation canals shall be located in
appropriate locations after a thorough investigation of matters such as conditions of rivers
and project area in connection with these facilities, and after coordination with relevant
organizations and bodies.
- When the irrigation canal system is very long or it mainly irrigates upland fields, the
necessity and possibility of establishing regulating reservoirs shall also be studied because
benefits including effective utilization of water and rationalization of water distribution
management can be expected by having intervening regulating reservoirs.
- Agricultural water use has multilateral functions as a region's service water system
including domestic water, water for purification of water quality, groundwater stabilization,
landscape/eco-system conservation water, fire protection water.
- In case of a modification or shifting of canals, those points mentioned above shall be fully
considered in the design as well. In addition, great efforts are needed to ensure that this
project conforms to other regional development projects by studying them carefully.
12
3.3 Classification of open canal
Cross-sections of canals differ depending on the respective canal size, but generally in
cases of canals where quantity of flow is small, bottom width/depth ratio of around 2:1 is
adopted, and where quantity of flow is large, the ratio of up to around 8:1 is applied.
13
Inner side slopes of canals often take values of around 1:1.5 to 1:2.5, and in cases where
soil character is especially of good quality and the canal size is small, inner side slopes shall
be able to be steeper within a range where no trouble occurs on the slope stability.
On the other hand, in cases of soft ground or large-sized canals, it is often difficult to
maintain slope stability, and careful studies are required for adopting gentler side slopes or
other bank protection methods, after grasping accurate geological features by soil tests.
Canal size, purposes, site conditions shall be considered for determining cross-sections of
canals including side slope of the canal. Table 3-2 shows general values for side slope by soil
character.
14
(2) Basement of linings
i. Banking
For basement of banking parts, surface soils shall be peeled away, garbage, etc. shall be
removed, and proper materials shall be filled back, so that the linings and the filling materials
should come into intimate contact with each other.
ii. Cutting
In cases where some or all parts of the lining canal is placed after excavating the foundation
ground, the ground shall be properly treated through a judgment whether the ground is
appropriate or not.
In cases of unsuitable soil such as where slopes are not stable, designs shall be performed
through overall discussions on necessity of replacing banking, conditions of groundwater,
range of the unsuitable ground, and presence/absence of banking materials, etc.
A retaining wall canal is a type of canals where the wall body is independent from the canal
base, and the retaining wall itself maintains stability against earth pressure from behind,
groundwater pressure, inner water pressure, etc., and is often adopted for wide canals such as
drainage canals.
This type has an advantage in its suitability for large-sized canals. From an aspect of
construction works, this type enables partial construction and is employed in cases where works
15
in the canal portion, such as repair works are required.
Meanwhile, semi-gravity type retaining wall canals reduce the concrete volume, comparing
with those of gravity type, and instead steel bar reinforcement is provided at points where
tensile stress is developed.
iii. Flumes
cross-section is not always superior from structural and economical points of view. Therefore,
for decision of the cross-section, it is desirable to carry out a comparison study on safety, ease
of work, cost efficiency, with sufficient considerations for characteristics of the flume and the
site conditions, etc.
16
iv. Precasted reinforced concrete flumes
Precasted reinforced concrete flumes are canals where unit bodies, produced at factories or
the like, or factory-produced members, either of which is manufactured basing on specified
design characteristics, are connected or combined by concrete materials, etc.
Generally, the smaller the canal size is, the more ease of works can be obtained, and this
type is adopted when it is economically advantageous. In area where yearly number of
workable days is small, this type is often used to shorten construction period.
In the selection of canal type, several factor such as design discharge, securing functions
required, generality of materials, etc. should be considered comprehensively. Moreover,
irrigation facilities should be designed and constructed to show high performance during the
service period.
Based on following reason, lining canal is selected as the most suitable canal type in
Tanzania except under special condition such as soft ground, restriction of land use, and so
on.
- It is not necessary to consider influence of the earth pressure from back soil by inclining
canal sidewall because active earth pressure does not act and only examining the measures
to prevent scouring of the side slope with the running water is needed.
17
3.4 Evaluation of the soil property
Those soil materials composed of grain sizes less than 75 mm excluding rock fractions are
classified into major classifications mainly by observations. According to percentage content
(percent by mass,) of coarse-grained fraction or fine-grained fraction, content amount of
gravel faction or sand fraction and so on, soil type shall be divided.
Here, when coarse grained fraction occupies above 50% and sand fraction is more than
gravel fraction, “sandy soil” shall be selected as representative soil type. Similarly, when fine
grained fraction occupies above 50% without organic or volcanic ingredient, “cohesive soil”
shall be selected.
18
3.4.2 Confirmation of soil property
Easy method for confirmation of soil property is as shown in Figure 3-5. The property of
the soil can be estimated by utilizing this method.
Sandy soil
Cohesive soil
19
Note: Black cotton soil (Vertisols: Name of Soil Orders in Soil Taxonomy)
The central concept of Vertisols is that of soils that have a high content (>30%) of
expanding clay known as montmorillonite and that have at some time of the year deep wide
cracks. They shrink when drying and swell when they become wetter. The shrinking and
swelling of Vertisols can damage buildings and roads, leading to extensive subsidence.
Therefore, a form to reduce influence by the expansion of the soil as much as possible is
desirable in the setting of the canal cross-section and the replacement of backfilling and
basement with gravel shall be necessary as a counter measure.
The side slope of lining canal should be decided so that it cannot be scoured or washed out
by water flow. In addition, water loss such as leakage from the canal section have to be
reduced as much as possible to supply irrigation water to the beneficial area certainly.
It is not necessary to consider influence of the earth pressure from back soil by inclining
canal sidewall because active earth pressure does not act.
20
(2) Current situation of canal construction in Tanzania
There is much construction example in the country. Moreover, as for the serious problem
was not supposed in the site survey was executed from 18th, Jan to 18th, Feb, 2016.
Const.
Scheme District Zone W H m Classification
year
Igongwa Misungwi Mwanza 1,00 0.70 1.20 Unlined 1997
Bukigi Mleba Mwanza 1.30 0.60 1.25 Masonry lining 2006
Itilima Kishapu Mwanza 1.00 1.00 1.20 Unlined 2003
Nyida Shinyanga Mwqanza 0.4 0.7 1.20 Con. lining (BRC) 2017
Buhekela Igunga Tabora 0.60 1.00 1.20 Masonry lining 2003
Chomachankora Igunga Tabora 1.50 1.30 1.20 Masonry lining 1994
(Mwamapuli) Igunga Tabora 1.50 1.25 1.20 Concrete slab lining 1986
Lusu Nzega Tabora 1.20 0.80 0.00 Flume 1996
Ulyanyama Sikonge Tabora 0.80 0.50 1.20 Masonry lining 2007
(Inara) Sikonge Tabora 0.45 0.70 1.20 Masonry lining 2015
(Chalinze) Dodoma Central 0.70 0.85 1.00 Concrete slab lining 2012
Bahi-sokoni Bahi Central 0.50 1.00 1.00 Masonry lining 2012
0.70 0.70 0.00 Masonry 2003
Msagali Mpwapwa Central
0.60 0.70 1.20 Concrete slab lining 2013
Msufini Mvomero Morogoro 0.50 0.80 0.80 Conc. retaining wall 2013
Kimbande Nyasa Mtwara 0.60 0.90 0.50 Masonry lining 2008
Since stability of lining canal depends on stability of side slopes and side slope as a
standard shall be determined in the range of 1:1.0 to 1:1.5 at Japanese criteria.
Referring to Table 3-2, side slopes of unlined canals, “Normal soil” as “Consolidated
gravelly clay” and “Sandy soil” as “Sandy mixed clayey loam”, can be employed.
21
(5) Japanese criteria for earth work
The gradient of slop in earth work referring to Table 3-5 (cutting) and Table 3-6 (banking)
is established as rather stable shape after earth work. So, the gradient value of sandy soil (not
dense) and cohesive soil can be handled for a reference.
i. Cutting
Natural ground often shows non-uniformity with reasons including that soil property
significantly differs depending on the extent of weathering and cracking, cutting height, state
of spring water, conditions of stratification, water content, etc.
Therefore, for designing gradient of slopes, investigations should be carried out in advance
for site conditions, state of existing slopes, and then design specifications including cutting
heights or gradient of slope should be determined referring to Table 3-5.
For lining canals where stability of structures heavily depends on the banking conditions, it
is required to fill up good quality soil and compact it sufficiently so that rainwater should not
enter into the backside of linings.
Gradients of banking slopes cannot be defined easily as they depend on the site topography,
banking materials, banking methods, slope protection methods, etc. Design specifications, for
including banking heights or gradients of banking slopes should be determined referring to
Table 3-6.
22
Table 3-6 Standard side banking slope
Banking
Banking material Gradient Notes
height
Sand with good gradation, pebble, and 5m or less 1:1.5 – 1:1.8 Applied to the banking
fine-grain mixed pebble 5 – 10m 1:1.8 – 1:2.0 whose base ground
Sand with bad gradation 10m or less 1:1.8 – 1:2.0 provides sufficient
10m or less 1:1.5 – 1:1.8 bearing capacity that
Rock lump (including muck) will not be affected by
10 -20m 1:1.8 – 1:2.0
5m or less 1:1.5 – 1:1.8 water exposure.
Sandy soil, hard viscous soil, hard clay
5 – 10m 1:1.8 – 1:2.0
Volcanic cohesive soil 5m or less 1:1.8 – 1:2.0
(Quoted from JSD)
3.4.4 Study on backfilling replacement
On the basis of foundation ground conditions that have been grasped through soil
investigations, safety of the canal structures should be studied so that an appropriate design
should be performed. When unfavorable ground exists in the foundation of the canal, it is
normally preferable to make a plan avoiding such a site.
However, if it is inevitable to make such a plan due to various conditions including cost
efficiency of the alignment of the canal or ease of works, suitable soil stabilization works or
foundation works should be selected, so that the design should be executed to take
countermeasures for preventing differential settlement and others.
In canal construction, however, changes in the foundation ground are often realized in the
site working stage, and therefore supplement investigations should be executed for such
occurrences, and it is required to cope with quickly basing on the investigation results.
In case of soft ground such as black cotton soil or high groundwater level, the irrigation
canal possibly floats or deteriorates with differential settlement due to uplift pressure of
groundwater. Moreover, when groundwater moves to the canal inside, hollowing out by a
particle of the soil from backfilling and foundation of the canal may lead to structural collapse
at last.
23
3.5 Hydraulic design by normal calculation
In hydraulic design of the canal, the following equation shall be used generally.
Q = A・v
Q: Discharge (m3/s)
A: Cross-sectional area of flow (m2)
v: Mean velocity (m/s)
The mean velocity of uniform flow in the open channel system is calculated by the
Manning’s equation. The relation of each element is as shown in Figure 3-9 and 3-10.
v = 1/n・R2/3・S1/2
b and d
Change m, S or b/d
Check v (velocity)
End
24
Figure 3-10 Canal parameters
The steeper the side slope, the faster the water will flow and the greater the discharge will
be. Velocity increases with an increase in side slope or longitudinal slope. It therefore follows
that a canal with a steeper side slope but with the same cross-section can discharge more
water than a canal with a smaller side slope.
Generally, if canals constructed by the same materials are compared to each other, the
coefficient of roughness tends to be larger when the velocity is extremely small, or when the
hydraulic mean depth is small. Although commonly used coefficient of roughness are listed in
Table 3-7, standard values are being typically used in design.
Also, in canal, since the smoothness of the inside wall surface are gradually lost due to
wear, scour, sediment from flowing water actions, or due to overgrowth of water weeds, stains
and rusts on the surface generated by suspended solid, thoughtful considerations shall be
provided in design for these items.
The standard values in Table 3-7 are used, taking these factors considered to be common
items into considerations as well. Specifically, when the degree of roughness degradation is
not considered to be common, the minimum or maximum value can be selected.
25
Table 3-7 Values for coefficient of roughness
< Canals constructed by excavation or dredging >
Coefficient of roughness
Material of canal and its condition Minimum Standard Maximum
value value value
Earth, straight and uniform
1. No weed (immediately after completion of the canal) 0.016 0.018 0.020
2. No weed (after the canal has been exposed to weather) 0.018 0.022 0.025
3. Gravels (no weed) 0.022 0.025 0.030
4. Few weeds with short grasses 0.022 0.027 0.033
(Quoted from JSD)
< Lining, retaining wall canals >
Coefficient of roughness
Material of canal and its condition Minimum Standard Maximum
value value value
Concrete (cast-in-place flume, culverts, etc.) 0.012 0.015 0.016
Concrete (reinforced concrete pipe) 0.011 0.013 0.014
Concrete(metal trowel finishing) 0.011 0.015 0.015
Concrete slab masonry 0.014 0.016 0.017
Cement (mortar) 0.011 0.013 0.014
Masonry (rubble stone mortar masonry) 0.017 0.025 0.030
Masonry (rubble stone cavity wall) 0.023 0.032 0.035
Vegetation coverage (sodding) 0.030 0.040 0.050
(Quoted from JSD,JRA)
< Natural flow canals >
Coefficient of roughness
Material of canal and its condition Minimum Standard Maximum
value value value
Small canals in plain area
1. No weed and straight. No fracture or deep water spot when 0.025 0.030 0.033
the high-water level is reached
2. No weed, but meandering. Some shoals and deep water 0.033 0.040 0.045
spots
3. Weeds and deep spots in mild flow sections 0.050 0.070 0.080
4. Section with thick vegetation of weed. Many deep water 0.075 0.100 0.115
spots and trees
Canal in mountainous land, no plant. River banks are steep.
1. River bed is covered by cobble stones and gravels 0.030 0.040 0.050
2. River bed is covered by large cobble stones 0.040 0.050 0.070
(Quoted from JSD)
26
Table 3-8 Values for coefficient of roughness (FAO)
When the Manning’s equation is applied to the cross section of canal which coefficient of
roughness at the wetted perimeter varies depending on spot locations, the velocity shall be
obtained by calculating the composite coefficient of roughness for the entire wetted perimeter.
(Figure 3-11 and Table 3-9)
27
3.5.5 Minimum allowable velocity
Object discharges in studying the minimum allowable velocity are as shown in Table 3-10.
Also, the minimum allowable flow velocities shall follow values provided in Table 3-11.
Minimum allowable
Condition of canal
velocity
Canal where concerns regarding deposition of floating sediment do exist. 0.45 - 0.90 m/s
Canal where concerns regarding overgrowth of water weed do exist. 0.70 m/s
(Quoted from JSD)
Note: The minimum allowable velocity shall be determined by the grain size of floating sediment.
Object discharges in studying the maximum allowable velocity are as shown in Table 3-12.
Based on materials and thickness of the members of the canal and the inside surface of the
canal structure, those values shown in Table 3-13 are considered as approximate limiting
28
values.
Maximum Maximum
Type of
allowable Classification allowable
material
velocity (m/s) velocity (m/s)
Sandy soil 0.45 Thick concrete (approximately 18 cm) 3.00
Sandy loam 0.60 Thin concrete (approximately 10 cm) 1.50
Loam 0.70 Asphalt 1.00
Clayey loam 0.90 Block cavity wall (buttress pier less than 30 cm) 1.50
Clay 1.00 Block cavity wall (buttress pier 30 cm or larger) 2.00
Sandy clay 1.20 Block mortar masonry 2.50
Soft rock 2.00 Reinforced concrete pipe 3.00
Semi-hard rock 2.50 Steel pipe, ductile cast iron pipe 5.00
Hard rock 3.00 Reinforced concrete secondary product canal 3.00
(Quoted from JSD)
3.5.7 Freeboard
The freeboard deals with unanticipated events that a canal may encounter such as water
surface vibration, and its size shall be assessed by the discharge. The basic equations for canal
freeboard calculation by cross section shapes and types of canal are as follows.
Fb = 0.05 d + β • hv + hw
< Retaining wall canals: flumes, retaining wall canals, box culverts, etc.>
Fb = 0.07 d + β • hv + hw
29
3.5.8 Hydraulically effective cross-sections
When a flow area “A” is given, a canal cross-section with the shortest length of wetted
perimeter “P” is capable for the largest quantity of flow. Such a cross-section is called the
most hydraulically effective cross-section, and it is generally accepted that cross-sections
close to the most effective cross-section are usually most cost effective as well.
The most hydraulically effective cross-sections for trapezoid and rectangular cross-sections
are obtained through following equations.
b = 2 d・tan (θ /2)
Here, “K” is the parameter that is obtained by transformation of Manning’s equation and it
is necessary to calculate the cross-section based on the direct calculation method for the depth
of uniform flow.
The most hydraulically effective cross-sections for each side slope “m” in canals of
trapezoid and rectangular cross-section are as shown in Table 3-14.
When each element is determined as shown above, the parameter “d/b” and “K” shall be set
30
as follows on the basis of Table 3-14.
d/b = 1.381
b = (1 / 2.851)3/8 × (Q × n / S1/2)3/8
(2) Calculation
d = 0.48 ×1.381
= 0.663 = 0.66 m
v=Q/A
= 0.80 / 0.85
= 0.941 = 0.94 m/sec
Fb = 0.05 d + β • hv + hw
= (0.05 × 0.664) + (0.5 × 0.9412 / 19.6) + 0.10
= 0.033 + 0.023 + 0.10
= 0.156 = 0.16 m
Height of canal = d + Fb
= 0.664 + 0.156
= 0.82 m
31
3.6 Hydraulic design using the proposed chart
3.6.1 General
This Manual is introducing a simple design method of canal cross-section settling for small
scale irrigation schemes by using “Calculation Chart” as attached in Annex-1. After getting Q
(discharge), S (canal slope), m (side slope) and assuming the canal type such as concrete slab
lining, masonry lining, you can simply design the cross-section of canals using the chart.
32
Item Setting value Remark
Coefficient of Concrete Slab Lining Canal 0.016
roughness Masonry Lining Canal 0.025
Minimum allowable velocity 0.50 m/sec
Maximum allowable velocity 2.50 m/sec
β 0.5 As minimum value in the range
Freeboard (Fb = 0.05 d + β • hv + hw)
hw 0.10 m As average value in the range
Note: 1. When obtained b using Q – b curve, the parameter of “d (Water depth)” shall be obtained
from “d/b” ratio automatically. (Table 3-14, P.28)
2. Freeboard shall be calculated after obtained both of “d (Water depth)” and “v (Velocity of
flow)”. Moreover, “H (Height of canal)” means “d (Water depth)” + Freeboard.
Step-1
Set the “Q” (discharge) in vertical axis of the chart after selecting the line of S (canal
slope).
(1) “b” (Bed width) shall be decided using “Q – b curve” as Chart No. “C-1”.
0.48
33
(2) “v” (Velocity of flow) shall be decided using “Q – v curve” as Chart No. “C-2”.
0.94
(3) “H” (Height of canal) shall be decided using “Q – H curve” as Chart No. “C-3”.
0.82
34
Step-2
Read the value of “b” (Bed width) in horizontal axis at the point to intersect.
An example of how to use “Concrete Slab Lining Canal (Side Slope = 1:1.2)” is as follows.
(Test condition is same as normal calculation mentioned above)
(unit: mm)
As shown in Table 3-17, the result of each calculation factors are same, and the validity of
the calculation chart shall be proved.
35
3.7 Economic comparison
After study on hydraulic design, the economic comparison is necessary because there are
two type of lining canal; concrete slab and masonry. Since the coefficient of roughness
between those types differ, the cross-section of each canal changes even if the discharge is the
same.
So, after setting the cross-section of both lining canal using calculation chart, economic
comparison should be executed.
Each factor of cross-section shall be obtained using calculation chart “Masonry Lining Canal
(Side Slope = 1:1.2): Chart No. M-1, M-2, M-3” in Annex-1.
Step-2 Estimation of the unit cost. (Please calculate based on your local condition.)
Since the construction costs, material costs vary largely for each area in Tanzania and it is
difficult to estimate the accurate unit cost as a standard. However, the construction cost should
be calculated as usually and it is necessary to keep the execution of economical and effective
project in mind.
Moreover, when the estimation of unit cost is carried out, not only material cost but also
labor cost and transportation cost, etc. should be considered.
36
The example of the cost estimation sheet is as shown in Table 3-19.
Finally, concrete slab or masonry lining canal will be selected as a suitable structure.
37
4. Incidental structure
4.1.1 General
When installing division structures, it is necessary to plan with prescribed functions based
on the irrigation network studied in designing the canal system, scrap-and-build plan for
division structures, and the diversion plan and its arrangement of route system which consider
the local irrigation custom and the will of the community.
Accordingly, before designing a facility, design consideration points based on the canal
system must be confirmed; for example, water supply plan, water management system, type
of division structure considering the canal type, scale, and the number of facilities.
To select the installation location, the following matters should be considered from the
view point of maintenance, management and structural design.
Proper type of division structure shall be selected in accordance with the water
management system, water level and discharge control system, and canal type.
An indication of selecting the type of division structure is a diversion ratio which is a ratio of
branch canal discharge to main canal discharge. When the diversion ratio is almost equal to or
more than 20 %, selection of a dividing wall distributor, jet flow distributor, or a cylindrical
proportional distributor shall be considered, and when the diversion ratio is less than 20 %,
selection of a gate offtake regulator or a constant head orifice offtake regulator shall be
considered.
When discharge from a division structure needs to be measured, type of division structure
and a discharge measurement method that match the combination shall be selected. As shown
in Fig 4-1, when a diversion pipe shall be mounted directly to the side wall of the main canal
so as to divert water to the diversion canal, inflow loss shall be taken into consideration.
38
Figure 4-1 Shape of sluice-pipe type division structure
(quoted from JSD)
- Division structures shall not cause hydraulic state of upstream and downstream to change
significantly.
- Although division structures are basically designed based on the design discharge, the
amount of discharge, such as most frequent discharge, minimum discharge shall be
considered according to the functions and purpose of each division structure.
- Head loss for diversion shall be minimized and easily regulated from the view point of
maintenance and management.
- The diversion type shall be united as much as possible so as to save labor for water
management and equalize diversion accuracy.
4.2.1 General
In the design of the canal system, when an excess head is present in spite of the appropriate
distribution of the longitudinal slope of the canal and the appropriate selection of route, drops
or chutes are installed in the canal so as to adjust the head, ensure the safety of the canal, and
make the best use of functions of the entire canal system.
Generally, locations and types of drops or chutes are selected according to topographic
features and other locational conditions. It is desirable that drops or chutes be stable and do
not inhibit functions of the canal and be planned and designed by fully considering the
economic efficiency.
In some cases, drops and chutes may vibrate due to impact resulting from the adjustment of
high heads; therefore, bearing capacity to withstand the impact as well as safety must be
39
ensured. Also, when drops and chutes are planned in the urban area and its vicinity, noise,
vibration, and splash must be considered and studied.
It is desirable that the following matters be considered when selecting a location to install
drop structures.
- A location in which drop structures can blend in with the surrounding topography, such as
a location where there is a topographical level difference, should be selected.
- A location on the base ground, which has bearing capacity to withstand impact of water
flow as well as the drop structures dead weight, should be selected.
- Drop structures shall be linear as long as possible and shall not be an asymmetric structure
so as to avoid generating unfavorable waves to the water flow. Therefore, it is desirable
that the section of the canal be selected in which both the upstream canal and the
downstream canal are in a straight line.
- In most cases, drop structures create vibration and noise due to falling water. Accordingly,
when installing a large-scale drop structures, it is desirable that installation near a residential
district be avoided in considering the effect on the surrounding communal environment.
The water-cushion type drop structures consist of an inlet canal which is normally a
transition section from an upstream canal, outfall, water cushion section for energy dissipation,
and an outlet canal for a downstream canal.
In this type of drop structures, vertical steps are made just below the outfall and energy is
dissipated by the impact resulting from falling water clashing into a water cushion and
disturbance in the water cushion.
40
Annex-1
Calculation Chart
for
Cross-section Settling
41
Contents
42
Flume Q-b b (Bed width) F–1 66
(Rectangular cross-section) - Q-v v (Velocity of flow) F–2 67
Q-H H (Height of canal) F–3 68
Note: If there is not applied slope in the chart in Annex-1, input value of “Q” and “S” directly into the attached electrical data (Excel file
“effective cross-section.xls”), so that you can obtain exact figure of “b (bed width)”, “v (velocity of flow)” and “H (Height of canal)”.
43
Chart number
Concrete Lining Canal (Side Slope = 1:1.2)
C-1
Q – b curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
44
Chart number
Concrete Lining Canal (Side Slope = 1:1.2)
C-2
Q – v curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
45
Chart number
Concrete Lining Canal (Side Slope = 1:1.2)
C-3
Q – H curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
46
Chart number
Concrete Lining Canal (Side Slope = 1:1.5)
C-4
Q – b curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
47
Chart number
Concrete Lining Canal (Side Slope = 1:1.5)
C-5
Q – v curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
48
Chart number
Concrete Lining Canal (Side Slope = 1:1.5)
C-6
Q – H curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
49
Chart number
Concrete Slab Lining Canal (Side Slope = 1:1.2)
CS - 1
Q – b curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
50
Chart number
Concrete Slab Lining Canal (Side Slope = 1:1.2)
CS - 2
Q – v curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
51
Chart number
Concrete Slab Lining Canal (Side Slope = 1:1.2)
CS - 3
Q – H curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
52
Chart number
Concrete Slab Lining Canal (Side Slope = 1:1.5)
CS - 4
Q – b curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
53
Chart number
Concrete Slab Lining Canal (Side Slope = 1:1.5)
C S- 5
Q – v curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
54
Chart number
Concrete Slab Lining Canal (Side Slope = 1:1.5)
CS - 6
Q – H curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.016
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
55
Chart number
Masonry Lining Canal (Side Slope = 1:1.2)
M-1
Q – b curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.025
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
56
Chart number
Masonry Lining Canal (Side Slope = 1:1.2)
M-2
Q – v curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.025
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
57
Chart number
Masonry Lining Canal (Side Slope = 1:1.2)
M-3
Q – H curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.025
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
58
Chart number
Masonry Lining Canal (Side Slope = 1:1.5)
M-4
Q – b curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.025
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
59
Chart number
Masonry Lining Canal (Side Slope = 1:1.5)
M-5
Q – v curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.025
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
60
Chart number
Masonry Lining Canal (Side Slope = 1:1.5)
M-6
Q – H curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.025
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
61
Chart number
Unlined Canal (Side Slope = 1:1.2)
U-1
Q – b curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.027
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
62
Chart number
Unlined Canal (Side Slope = 1:1.2)
U-2
Q – v curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.027
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
63
Chart number
Unlined Canal (Side Slope = 1:1.2)
U-3
Q – H curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.027
- d/b = 1.381
- K = (Q✕n) / (S1/2✕b8/3) = 2.851
64
Chart number
Unlined Canal (Side Slope = 1:1.5)
U-4
Q – b curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.027
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
65
Chart number
Unlined Canal (Side Slope = 1:1.5)
U-5
Q – v curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.027
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
66
Chart number
Unlined Canal (Side Slope = 1:1.5)
U-6
Q – H curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.027
- d/b = 1.651
- K = (Q✕n) / (S1/2✕b8/3) = 5.058
67
Chart number
Flume (Rectangular cross-section)
F-1
Q – b curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.015
- d/b = 0.500
- K = (Q✕n) / (S1/2✕b8/3) = 0.198
68
Chart number
Flume (Rectangular cross-section)
F-2
Q – v curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.015
- d/b = 0.500
- K = (Q✕n) / (S1/2✕b8/3) = 0.198
69
Chart number
Flume (Rectangular cross-section)
F-3
Q – H curve
Remark
1. Calculation condition is as
follows;
- Coefficient roughness: n=0.015
- d/b = 0.500
- K = (Q✕n) / (S1/2✕b8/3) = 0.198
70
Annex-2
Drawing Collection
of
Standard Design for Irrigation Canal
71
Contents
Item Drawing No. page
Side slope = 1 : 1.2 CL - 1 72
With backfilling CL - 2 73
Concrete Lining Canal (With RBC)
Side slope = 1 : 1.5 CL - 3 74
with backfilling CL - 4 75
CSL - 1 76
Side slope = 1 : 1.2
with backfilling CSL - 2 77
Concrete Slab Lining Canal
CSL - 3 78
Side slope = 1 : 1.5
with backfilling CSL - 4 79
ML - 1 80
Side slope = 1 : 1.2
with backfilling ML - 2 81
Masonry Lining Canal
ML - 3 82
Side slope = 1 : 1.5
with backfilling ML - 4 83
Side slope = 1 : 1.2 UL - 1 84
Unlined Canal
Side slope = 1 : 1.5 UL - 2 85
pipe type DI - 1 86
Division Structure
open type DI - 2 87
Dimension setting DR - 1 88
Drop Structure Drawing example DR - 2 89
Reinforcing bar processing DR - 3 90
<Reference: Japanese criteria>
Drawing example - 1 CF - 1 91
Flume Drawing example - 2 CF - 2 92
Drawing example - 3 CF - 3 93
Masonry Retaining Wall Canal Drawing example MR - 1 94
Precasted Concrete Flume Drawing example PF - 1 95
Note: You can use and arrange the attached electrical CAD data (Folder: drawing: cad data, file format is “dwg”.
72
Quick Chart for Selection of Canal Type
Soil Type Side Slope Needs of Backfilling Canal Type Drawing No. page
Concrete Lining CL - 1 72
Masonry Lining ML - 1 80
Cohesive 1 : 1.2
Concrete Lining CL - 2 73
Masonry Lining ML - 2 81
Concrete Lining CL - 3 74
No
Concrete Slab Lining CSL - 3 78
Sandy 1 : 1.5
Concrete Lining CL - 4 75
Masonry Lining ML - 4 83
73
Drawing number
Concrete Lining Canal (Side slope = 1:1.2)
CL - 1
Remark
Cross Section
CL
150
1.2
H
1
Concrete Lining
(Metal Torowel Finishing)
(unit: mm)
74
Drawing number
Concrete Lining Canal (Side slope = 1:1.2 with backfilling)
CL - 2
Remark
Cross Section
1. Assuming each barrel length are
1,000mm (10.0m).
W
1
Concrete Lining
(Metal Torowel Finishing)
75
Drawing number
Concrete Lining Canal (Side slope = 1:1.5)
CL - 3
Remark
Cross Section
1. Assuming each barrel length
W
are 1,000mm (10.0m).
270
CL
150
1.5
H
1
Concrete Lining
(Metal Torowel Finishing)
(unit: mm)
76
Drawing number
Drawing number
Concrete Lining Canal (Side slope = 1:1.5 with backfilling)
CL - 4
Remark
Cross Section
1. Assuming each barrel length
W are 1,000mm (10.0m)
270 270
2. Backfilling and base gravel
CL should be installed when
basement is black cotton soil or
groundwater level is high.
1
Concrete Lining
(Metal Torowel Finishing)
(unit: mm)
77
Drawing number
Concrete Slab Lining Canal (Side slope = 1:1.2)
CSL - 1
Remark
Cross Section
1. Assuming slab size as 450mm
width 450mm length, but various
size is allowable.
(unit: mm)
78
Drawing number
Concrete Slab Lining Canal (Side slope = 1:1.2 with backfilling)
CSL - 2
Remark
Cross Section
(unit: mm)
79
Drawing number
Concrete Slab Lining Canal (Side slope = 1:1.5)
CSL - 3
Remark
Cross Section
(unit: mm)
80
Drawing number
Concrete Slab Lining Canal (Side slope = 1:1.5 with backfilling)
CSL - 4
Remark
Cross Section
1. Assuming slab size as 450mm
width 450mm length, but various
size is allowable.
(unit: mm)
81
Drawing number
Masonry Lining Canal (Side slope = 1:1.2)
ML - 1
Remark
Cross Section
(unit: mm)
82
Drawing number
Masonry Lining Canal (Side slope = 1:1.2 with backfilling)
ML - 2
Remark
Cross Section
(unit: mm)
83
Drawing number
Masonry Lining Canal (Side slope = 1:1.5)
ML - 3
(unit: mm)
84
Drawing number
Masonry Lining Canal (Side slope = 1:1.5 with backfilling)
ML - 4
(unit: mm)
85
Drawing number
Unlined Canal (Side slope = 1:1.2)
UL - 1
Remark
(unit: mm)
86
Drawing number
Unlined Canal (Side slope = 1:1.5)
UL - 2
Remark
(unit: mm)
87
Drawing number
Division Structure (pipe type)
DI - 1
Remark
(unit: mm)
88
Drawing number
Division Structure (open type)
DI - 2
Remark
(unit: mm)
89
Drawing number
Drop Structure (Dimension setting)
DR - 1
Plan Cross Section
Remark
List of dimensions
h H B1 B2 L1 L2 D1 D2
500 500 1000 1500 2800 1400 80 350
500 1000 1000 1500 4100 1600 80 400
500 1500 1000 1500 5200 2000 80 500
700 500 1400 1900 3000 1200 160 300
700 1000 1400 1900 4400 1600 160 400
700 1500 1400 1900 5700 2000 160 500
1000 500 2000 3000 3500 2300 350 300
1000 1000 2000 3000 5100 2300 350 450
1000 1500 2000 3000 6400 2300 350 550
90
Drawing number
Drop Structure (Drawing example)
DR - 2
Plan
Remark
Longitudinal section
(unit: mm)
91
Drawing number
Drop Structure (Reinforcing bar processing)
DR - 3
Cross Section
Section B - B Section C - C Remark
(unit: mm)
92
Drawing number
Flume (Drawing example - 1)
CF - 1
Cross Section Side View
Remark
(unit: mm)
93
Drawing number
Flume (Drawing example - 2)
CF - 2
Cross Section Side View
Remark
(unit: mm)
94
Drawing number
Flume (Drawing example - 3)
CF - 3
Cross Section Side View
Remark
(unit: mm)
95
Drawing number
Masonry Retaining Wall Canal (Drawing example)
MR - 1
<Japanese criteria>
In case the internal frictional
angle of back soil is 30 degrees
and only earth pressure acts to
masonry, wall height (H) can be
applied as following table
corresponding to each side slope.
(unit: mm)
96
Drawing number
Precasted Concrete Flume (Drawing example)
PF - 1
Remark
(unit: mm)
97