FUNDAMENTAL PROGRAM
MID-TERM REVIEW- Unit 2 – Circulating system
1. Pump pressure is the total of all the pressure lost in the entire system that circulates fluids, including
the surface lines.
A) TRUE
B) FALSE
Correct answer: A) TRUE
2. The differences between the Duplex and Triplex pumps are:
A) Duplex pump has two pistons and triplex has three pistons
B) Duplex pump piston is a double-acting piston and the triplex pump is a triplex-acting pump.
C) Duplex pump piston is a double-acting piston and the triplex pump is a single-acting pump.
D) Both A and C are correct
Correct answer: D) Both A and C are correct
3. Which of the following equipment keeps the rotary hose clear of the rig floor as the Kelly travels up
and down the derrick?
A) Desander
B) Standpipe
C) Sand trap
D) Gooseneck
Correct Answer: B) Standpipe
4. Switching to a different liner size is a common repair job done often to manage the flow rate in the
well.
A) True
B) False
Correct answer: A) True
5. What is usually the most hazardous part of maintaining and repairing equipment?
A) Signaling during the task
B) Planning the task
C) Performing the task
D) Restarting the equipment
Correct answer: C) Performing the task
6. True: You would find information about the handling, disposing, and first aid treatment of the
chemicals in the mud system in MSDS (Material Safety Data Sheets).
A) True
B) False
Correct answer: A) True
7. Which equipment removes the gas while drilling?
A) Degasser
B) Gas Detector
C) Gas separator
D) Poor boy
Correct answer: A) Degasser
8. What is set up and hooked to you before you enter the tanks?
A) Tripod
B) Chain sling
C) Wire rope
D) Tank gate
Correct answer: A) Tripod
9. What must you do to the pump before beginning a maintenance or repairing task?
A) Isolate it
B) Prime it
C) Start it
D) Dismantle it
Correct answer: A) Isolate it
10. Hydrocyclone is a part of Desilter or Desander with moving parts to be maintained by the Mechanic
only.
A) True
B) False
Correct answer: B) False
11. Shale shaker screens sometimes need to be repaired with screen plug (Rubber hex plug) or using a
suitable material (Backing Cloth).
A) True
B) False
Correct answer: A) True
12. Shale shaker is a solid control equipment that doesn't need either work permit or isolation to start
the repairing operations.
A) True
B) False
Correct answer: B) False
13. Where do you prepare and store extra or different mud, if not in the active system?
A) Reserve tanks
B) Trip tanks
C) Settling tank
D) Sand trap
Correct answer: A) Reserve tanks
14. Which tank on the mud system receives the mud returning from the wellbore?
A) Suction tank
B) Shaker tank
C) Slug tank
D) Mixing tank
Correct answer: B) Shaker tank
15. What should you do if you notice something unusual?
A) Discuss with other Rigmen
B) Inform the mud engineer
C) Inform the supervisor
D) Act like a supervisor
Correct answer: C) Inform the supervisor
16. What equipment do you use with bulk bags of materials to get them into the mixing hopper?
A) Rig tongs
B) Chain Hoist
C) Jet nozzle
D) Butterfly valve
Correct answer: B) Chain Hoist
17. What makes the bearings and cutting edges of the bit last longer by keeping them cool and well-
lubricated?
A) Mud
B) Oil
C) Diesel
D) Water
Correct answer: A) Mud
18. To avoid injuries, who is authorized to perform maintenance on the vacuum pump?
A) Rig Mechanic
B) Mud Engineer
C) Foreman
D) Derrick man
Correct answer: A) Rig Mechanic
19. Which of the following prevents formation fluids from entering the wellbore?
A) Hydrostatic Pressure
B) Mud agitator
C) Pore pressure
D) Surge Pressure
Correct answer: A) Hydrostatic Pressure
20. Which equipment is used for stirring the mud to keep the weighting materials mixed in the mud?
A) Desilter
B) Mud agitator
C) Charge pump
D) Strainer
Correct answer: B) Mud agitator
21. During Circulation, Rig man may allow small leaks without notifying the driller.
A) True
B) False
Correct answer: B) False
22. Always check that the suction line valves and discharge line valves on the mud pump are …………………
before pumping?
A) Close
B) Open
C) Not open
D) Slightly open
Correct answer: B) Open
23. If the well is not well cleaned, the bit could become …………………… this means that it is full of cuttings.
A) Balled
B) Worn
C) Stuck
D) Rolled
Correct answer: A) Balled
24. What should you do before beginning the mud mixing process?
A) Open the hopper before starting the pump
B) Wear the proper PPE
C) Dump the sack's contents into the hopper
Correct answer: B) Wear the proper PPE
25. When you open the fluid end of the pump, be careful and watch for…………………………….
A) Trapped Pressure
B) Mud sediments
C) Mud additives
Correct answer: A) Trapped Pressure
26. Which procedure ensures that potentially dangerous machinery is shut off correctly and will not start
up while performing maintenance or repairs?
A) Perform a gas test
B) Lock Out/Tag Out
C) Inspection
D) Permit
Correct answer: B) Lock Out/Tag Out
27. Drilling mud serves to lubricate both the drill bit and the drill string while at the same time
transporting the cuttings to the surface.
A) True
B) False
Correct answer: A) True
28. The weight of the mud is usually maintained ………………………………………………………………………
A) Slightly Over the Formation pressure
B) Slightly below the formation pressure
C) Just equal to the formation pressure
Correct answer: A) Slightly Over the Formation pressure
29. If the Weight on Mud column becomes less than the Formation pressure, what will happen to the
well?
A) Having Losses of the circulation
B) Having formation fluid enters the well
C) Have nothing, and everything is okay
Correct answer: B) Having formation fluid enters the well
30. ………………… is commonly added to increase the weight of drilling fluid.
A) Calcium carbonate
B) KCL
C) NACL
D) Barite
Correct answer: D) Barite
31. Mud also transfers power to downhole equipment such as motors and:
A) Conductor
B) Lifting sling
C) Drill collar
D) MWD
Correct answer: D) MWD
32. Air or Gaseous drilling fluid is used to keep pressure in the wellbore lower than the formation
pressure being drilled. This is called …………………………………………..
A) Balance Drilling
B) Underbalanced Drilling
C) Overbalanced
Correct answer: B) Underbalanced Drilling
33. All are advantages of Air/Underbalanced drilling Operations except:
A) Increase ROP
B) Less chance of lost circulation
C) Better bit cooling and extended service life
D) More likely to get stuck due to differential sticking
Correct answer: D) More likely to get stuck due to differential sticking
34. Non-hazardous chemicals are mixed using the mixing hopper but the hazardous ones are added
through a ……………………………………
A) Special type of tank
B) Special type of Mixing Hopper
C) Chemical Barrel
Correct answer: C) Chemical Barrel
35. What do jet mud mixing hoppers use to create a vacuum that draws dry material into the liquid?
A) Hydraulic hoses
B) Caustic barrel
C) Fluid from the nozzle
Correct answer: C) Fluid from the nozzle
36. In the Circulating system, all valves below are related to this system except:
A) Relief Valve
B) Butterfly valve
C) Bleeder Valve
D) Stabbing Valve
Correct answer: D) Stabbing Valve
37. High Pressure gate valves are used in the discharge side of the pump because they are high-pressure
valves.
A) True
B) False
Correct answer: A) True
38. Butterfly valves are used in the suction side of the pump because they are high-pressure valves.
A) True
B) False
Correct answer: B) False
39. Suction stabilizer maintains the mud at the same level as the suction valves on the mud pumps and
contains sufficient volume to fill the pump suction chamber.
A) True
B) False
Correct answer: A) True
40. When cleaning shale shaker screens with a high-pressure cleaner, you should use the following
personal protective equipment:
A) Safety glasses
B) Face shield
C) SCBA
D) Safety Goggles
Correct answer: A) Safety glasses
41. Which device protects the mud pumps, the crewmen, and nearby equipment from excessive
pressure that may build up in the discharge line?
A) Safety Sling
B) Mud Manifold
C) Rubber seal
D) Suction stabilizer
Correct answer: A) Safety Sling
42. Why do most drilling rigs have two mud pumps?
A) Increase flow
B) Efficiency
C) Increase pressure
D) Replacement
Correct answer: D) Replacement
43. In Mud pumps…………………………………………….. is used to remove the Suction/Discharge valves' seats.
A) Ring Gasket
B) Valve Cap
C) Valve seat Puller
D) Hummer Union
Correct answer: C) Valve seat Puller
44. In Mud pumps ………………………… transfer mud from the mud tanks to the mud pump.
A) Suction strainer
B) Charge pump
C) Mixing Pump
D) Bleeder valve
Correct answer: B) Charge pump
45. In Mud pumps, the charge pump is a typical example of ………………………………
A) Centrifugal pump
B) Displace pump
C) High-pressure pump
D) Both A and B
Correct answer: A
46. What is the purpose of a Liner wash pump?
A) Transfer mud from the tank to the mud pump
B) Mix the lubricants with mud
C) Cooling and lubricating the piston and line
D) None of above
Correct answer: C) Cooling and lubricating the piston and line
47. Mixing pumps are centrifugal pumps used for ____________________________
A) Mixing chemical with the base fluid in the mixing hopper
B) Powering the mud guns to stir the mud in the tanks
C) Cooling and lubricating the mud pump's piston and liner
D) A and B
Correct answer: D) A and B
48. What should you avoid wearing while working around the centrifuge?
A) Loose clothing
B) Hearing protection
C) PPE
D) Helmet
Correct answer: A) Loose clothing
49. Trip tank is a small volume tank. The trip tank stores the mud that comes out or pumped in during
tripping operations. It is small so that changes can be seen quickly. This helps to monitor the well for a
…………………………..
A) Blow out
B) Kick
C) ROP during Drilling
D) Torque
Correct answer: B) Kick
50. During drilling operations, your key role includes monitoring the mud system, checking for leaks, and
checking the volume in the mud system.
A) True
B) False
Correct answer: A) True
51. What should you do if, during pump stop for activities like connections, surveys, tripping, or flow
checks, you notice a reverse flow from the flow line back into the mud system?
A) Measure the time of the return
B) Notify Mud Engineer about the return
C) Notify the Driller about the return
D) Do nothing as everything is okay
Correct answer: C) Notify the Driller about the return
52. You must enter the tank to clean or repair the suction valve in it. What Major Hazard do you have to
mention in the Work permit?
A) Electricity Hazard
B) Confined space entry Hazard
C) Chemical Hazard
D) High Pressure
Correct answer: B) Confined space entry Hazard
53. Which equipment, other than the degasser, can receive mud from the degasser tank?
A) Desander
B) Standpipe
C) Mud pump
D) Mixing hopper
Correct answer: A) Desander
54. Which tank holds the cleaned and treated mud and supplies mud to the mud pumps?
A) Shaker tank
B) Trip tank
C) Suction tank
D) Mixing tank
Correct answer: C) Suction tank
55. The shale shaker removes more than ……... of the cutting that the mud transports up from the
wellbore.
A) 60%
B) 70%
C) 80%
D) 90%
Correct answer: C) 80%
56. All of the following are shale shaker components except ……………………….…...
A) Motors
B) Impeller
C) Mud box
D) Screens
Correct answer: B) Impeller
57. The centrifugal degasser can be used in place of …………………………
A) Centrifuge
B) Vacuum Degasser
C) Shale Shaker
D) Desander
Correct answer: B) Vacuum Degasser
58. The mud gas separator is also known as …………
A) Gas Buster
B) Poor boy degasser
C) A & B
D) degasser
Correct answer: C) A & B
59. The following is one of the types of centrifuges on a drilling rig.
A) Low-speed oil field decanter centrifuge
B) Medium-speed oil field decanter centrifuge
C) High-speed oil field decanter centrifuge
D) All of the above
Correct answer: D) All of the above
60. All the following are main parts of the centrifuge except …………
A) Bowl
B) Screw Conveyor
C) Vacuum Pump
D) Filtrate ports
Correct answer: C) Vacuum Pump
61. What is the purpose of using a mud balance?
A) Viscosity
B) PH
C) Water loss
D) Weight
Correct answer: D) Weight
62. The pill/slug tank is a small volume tank that mixes slugs or pills.
A) True
B) False
Correct answer: B) False
63. Which substance is used to seal off gates and prevent the active volume from contaminating the
reserve volumes of mud?
A) Bentonite gel
B) Hydraulic fluid
C) Silicone sealant
D) Concrete slurry
Correct answer: A) Bentonite gel
64. A series of mud tanks stores returning mud so that what can be done to it?
A) Transported
B) Cleaned
C) Gelled
D) Flushed
Correct answer: B) Cleaned
65. The mud cleaning system removes which of the following from the drilling fluid?
A) Cuttings
B) pH
C) Drilling mud
D) The swivel
Correct answer: A) Cuttings
66. Which of the following tasks is not typically carried out by the mud pits?
A) Storing mud
B) Cleaning mud
C) Receiving mud
D) Supplying mud
Correct answer: B) Cleaning mud
67. Which component delivers drilling fluid to the shale shaker?
A) Kelly
B) Mud pit
C) Centrifugal pump
D) Mud return line
Correct answer: D) Mud return line
68. What is the main disadvantage of drilling with air or gas?
A) Decreased rate of penetration
B) May plug the hydrocarbon reservoir
C) Special tools and equipment required
D) Gaseous fluids are used in weak formation
Correct answer: C) Special tools and equipment required
69. What is used to reduce the viscosity of mud?
A) Bentonite
B) Water
C) Barite
D) Diesel Fuel
Correct answer: B) Water
70. What property of the drilling fluid is affected by the non-reactive phase?
A) Density
B) Color
C) Temperature
D) Balance
Correct answer: A) Density
71. What is the ideal consistency of mud for drilling operations?
A) Thick enough to impede cuttings flow
B) Thin enough to clog the circulation system
C) Thin enough to carry cuttings to the surface
D) Thick enough to prevent cuttings from surfacing
Correct answer: C) Thin enough to carry cuttings to the surface
72. In drilling operations, why is it important for the mud to have specific characteristics?
A) To maximize cuttings clogging
B) To minimize flow through the circulating system
C) To optimize cuttings transport to the surface
D) To minimize the thickness of the mud
Correct answer: C) To optimize cuttings transport to the surface
73. What is the primary base fluid in water-based drilling fluids?
A) Diesel oil
B) Natural gas
C) Water
D) Mineral oil
Correct answer: C) Water
74. Which drilling fluid type is known for its thermal stability and resistance to high temperatures?
A) Water-based drilling fluids
B) Oil-based drilling fluids
C) Gas-based drilling fluids
D) Synthetic-based drilling fluids
Correct answer: B) Oil-based drilling fluids
75. Why is it important to prevent fluid from entering the formation during drilling?
A) To increase wellbore stability
B) To improve drilling speed
C) To enhance formation permeability
D) To reduce drilling fluid viscosity
Correct answer: A) To increase wellbore stability
76. What parameter can be evaluated through water loss testing in drilling operations?
A) Drilling bit wear
B) Formation pressure
C) Filter cake quality
D) Mud density
Correct answer: C) Filter cake quality
77. In drilling operations, what equipment is typically used by a rigman to mix drilling mud according to
mud engineer specifications?
A) Rotary drilling rig
B) Shale shaker
C) Jet mixing hoppers and centrifugal pumps
D) Mudlogger unit
Correct Answer: C) Jet mixing hoppers and centrifugal pumps
78. Mixing mud to meet the desired specifications is a crucial aspect of drilling operations to ensure
wellbore stability and drilling efficiency.
A) True
B) False
Correct answer: A) True
79. The mud engineer is primarily responsible for operating the drilling rig and managing drilling
operations.
A) True
B) False
Correct answer: B) False
80. Which of the following is NOT typically used for lifting heavy materials on a drilling rig?
A) Trucks
B) Cranes
C) Air hoists
D) Shale shakers
Correct answer: D) Shale shakers
81. What is the primary purpose of a mud trailer on a drilling rig?
A) To store drilling mud
B) To transport drilling equipment
C) To lift heavy machinery
D) To handle large sacks of materials
Correct answer: D) To handle large sacks of materials
82. Why is it essential to use correct hand signals when handling mud additives with cranes or air hoists
on the rig?
A) To prevent mud contamination
B) To communicate with the mud engineer
C) To ensure proper equipment maintenance
D) To ensure safe and efficient operations
Correct answer: D) To ensure safe and efficient operations
83. Which component is often referred to as the "heart" of the drilling rig's circulating system?
A) Mud reservoir
B) Drill bit
C) Mud pump
D) Shale shaker
Correct answer: C) Mud pump
84. The mud pump's primary role is to mix drilling fluids.
A) True
B) False
Correct answer: B) False
85. What critical role does the mud pump play in the drilling rig's circulating system?
A) Mixing drilling fluids
B) Controlling wellbore pressure
C) Producing drilling fluid
D) Generating circulation pressure
Correct answer: D) Generating circulation pressure
86. What are the two types of pumps found on drilling rigs?
a) Single acting and double acting pumps
b) Duplex and triplex pumps
c) Diaphragm and centrifugal pumps
d) Rotary and reciprocating pumps
Correct answer: b) Duplex and triplex pumps
87. Which type of pump is DOUBLE ACTING and creates pressure on BOTH SIDES of the piston?
A) Duplex pump
B) Triplex pump
C) Centrifugal pump
D) Diaphragm pump
Correct answer: A) Duplex pump
88. In the process of rigging up a well, where does the process typically begin?
A) At the drilling site
B) With the installation of the blowout preventer
C) With the substructure
D) With the drilling mud preparation
Correct answer: C) With the substructure
89. Rigging up a well typically begins with the installation of the blowout preventer.
A) True
B) False
Correct answer: B) False
90. In which parts of the circulating system is the centrifugal pump commonly used?
A) Only in the drilling mud tank
B) In many parts of the circulating system
C) Exclusively at the wellhead
D) Only in the blowout preventer
Correct answer: B) In many parts of the circulating system
91. What are some possible problems that can occur with a centrifugal pump?
A) Lack of lubrication and high speed
B) Noise, lack of volume, and abnormally low pressure
C) Corrosion and fouling
D) Sudden stops and equipment jams
Correct answer: B) Noise, lack of volume, and abnormally low pressure
92. What are some possible problems that can occur with a centrifugal pump?
A) Lack of lubrication and high speed
B) Noise, lack of volume, and abnormally low pressure
C) Corrosion and fouling
D) Sudden stops and equipment jams
Correct answer: B) Noise, lack of volume, and abnormally low pressure
93. When opening the pump for maintenance, it's important to ensure the pump is isolated from other
pumps by closing valves between them.
A) True
B) False
Correct answer: A) True
94. When working with heavy equipment, it's safe to position yourself in a pinch point if necessary to
reach certain components.
A) True
B) False
Correct answer: False
95. Using hand signals and proper manual handling techniques are important safety practices when
working with heavy equipment.
A) True
B) False
Correct answer: A) True
96. What is the primary function of the cleaning equipment in the mud conditioning system?
A) Controlling mud weight
B) Removing cuttings and gas from the mud
C) Mixing dry chemicals and weight materials
D) Adjusting pH and viscosity of the mud
Correct answer: B) Removing cuttings and gas from the mud
97. How are hazardous chemicals typically mixed in the mud conditioning system?
A) Through the mixing hopper
B) In the chemical barrel
C) Using dry chemical additives
D) In the desander
Correct answer: B) In the chemical barrel
98. The Desander and Desilter use cone-shaped separators and centrifugal force to remove sand and silt
from drilling fluids.
A) True
B) False
Correct answer: B) False
99. What components of a drilling rig's mud system can be operated by the mud control system?
A) High-pressure equipment
B) Shakers and centrifuges
C) Low-pressure and mixing/chemical storage systems
D) Bulk storage silos
Correct answer: C) Low-pressure and mixing/chemical storage systems
100. The mud control system monitors the status of all equipment in the mud system, indicating whether
equipment is ON or OFF.
A) True
B) False
Correct answer: B) False
101. Mud cleaning equipment like shakers and centrifuges are typically controlled by the mud control
system and do not require manual starting.
A) True
B) False
Correct answer: B) False