Project Management1
Project Management1
Human Resources
Working Hours per day 8.0 Start Hour 9:00 Phase Definition & Analysis
Project Participants: Hour Analysis
Name Cost/Hr Email Address Factor Project Phases Scheduled Complete
Participant 1 25 email1 100% PREPARATION 0 0
Participant 2 25 email2 100% PROJECT DEFINITION 0 0
Participant 3 25 email3 100% ANALYSIS 0 0
Participant 4 25 email4 100% DESIGN 0 0
Participant 5 25 email5 100% DEVELOPMENT 0 0
Participant 6 25 email6 100% TESTING 0 0
Participant 7 25 email7 100% IMPLEMENTATION 0 0
Participant 8 25 email8 100% ACCEPTANCE 0 0
Participant 9 25 email9 100% REVIEW 0 0
Participant 10 25 email10 100% CLOSE-DOWN 0 0
OPERATIONAL SUPPORT 0 0
Total Available Productivity 1000%
Project Timing
Projected Duration 0.71 Days Deadline 31-Dec-2017 End Date 01-Jan-2015 Overrun -1094.29 Days
Task Description Dependencies & Deliverables HR Costs Capital Staffing Timing (Dates)
ID Phase Description DepID Deliverables Cost Total Costs Person Hours Start
0
1 - -
2 - -
3 - -
4 - -
5 - -
6 - -
7 - -
8 - -
9 - -
10 - -
11 - -
12 - -
13 - -
14 - -
15 - -
16 - -
17 - -
18 - -
19 - -
20 - -
21 - -
22 - -
23 - -
24 - -
25 - -
26 - -
27 - -
28 - -
29 - -
30 - -
31 - -
32 - -
33 - -
34 - -
35 - -
36 - -
37 - -
38 - -
39 - -
40 - -
41 - -
42 - -
43 - -
44 - -
45 - -
46 - -
47 - -
48 - -
49 - -
50 - -
51 - -
52 - -
53 - -
54 - -
55 - -
56 - -
57 - -
58 - -
59 - -
60 - -
61 - -
62 - -
63 - -
64 - -
65 - -
66 - -
67 - -
68 - -
69 - -
70 - -
71 - -
72 - -
73 - -
74 - -
75 - -
76 - -
77 - -
78 - -
79 - -
80 - -
81 - -
82 - -
83 - -
84 - -
85 - -
86 - -
87 - -
88 - -
89 - -
90 - -
91 - -
92 - -
93 - -
94 - -
95 - -
96 - -
97 - -
98 - -
99 - -
100 - -
Totals - - -
Timing (Dates) Progress Completion Calculations
End Hrs Capex Date Last Row
01/Jan/15 17:00
Calculations
Last Date Productivity Hours Days End Date Base Weekends Between Weekend End HR Cost Progress
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
1 0 0
27-Jan-2015
26-Jan-2015
25-Jan-2015
24-Jan-2015
23-Jan-2015
22-Jan-2015
21-Jan-2015
20-Jan-2015
19-Jan-2015
18-Jan-2015
17-Jan-2015
16-Jan-2015
15-Jan-2015
14-Jan-2015
13-Jan-2015
12-Jan-2015
11-Jan-2015
10-Jan-2015
09-Jan-2015
08-Jan-2015
07-Jan-2015
06-Jan-2015
05-Jan-2015
04-Jan-2015
03-Jan-2015
02-Jan-2015
Weeks
01-Jan-2015
Days
Mon
Day Beginning:
Schedule Frequency:
Days
TASKS
### ban vẽ
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
FULL-TIME HOURS
Scheduled
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Completed
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
COSTS (Cumulative)
HR Costs
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Capital Costs
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Total Costs
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
06-Mar-2015
05-Mar-2015
04-Mar-2015
03-Mar-2015
02-Mar-2015
01-Mar-2015
28-Feb-2015
27-Feb-2015
26-Feb-2015
25-Feb-2015
24-Feb-2015
23-Feb-2015
22-Feb-2015
21-Feb-2015
20-Feb-2015
19-Feb-2015
18-Feb-2015
17-Feb-2015
16-Feb-2015
15-Feb-2015
14-Feb-2015
13-Feb-2015
12-Feb-2015
11-Feb-2015
10-Feb-2015
09-Feb-2015
08-Feb-2015
07-Feb-2015
06-Feb-2015
05-Feb-2015
04-Feb-2015
03-Feb-2015
02-Feb-2015
01-Feb-2015
31-Jan-2015
30-Jan-2015
29-Jan-2015
28-Jan-2015
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
13-Apr-2015
12-Apr-2015
11-Apr-2015
10-Apr-2015
09-Apr-2015
08-Apr-2015
07-Apr-2015
06-Apr-2015
05-Apr-2015
04-Apr-2015
03-Apr-2015
02-Apr-2015
01-Apr-2015
31-Mar-2015
30-Mar-2015
29-Mar-2015
28-Mar-2015
27-Mar-2015
26-Mar-2015
25-Mar-2015
24-Mar-2015
23-Mar-2015
22-Mar-2015
21-Mar-2015
20-Mar-2015
19-Mar-2015
18-Mar-2015
17-Mar-2015
16-Mar-2015
15-Mar-2015
14-Mar-2015
13-Mar-2015
12-Mar-2015
11-Mar-2015
10-Mar-2015
09-Mar-2015
08-Mar-2015
07-Mar-2015
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
15-Apr-2015
14-Apr-2015
0 0 0 0 0
0 0 0 0 0