ID Task Task Name Duration Start Finish Predecessors relationship Sep '24
Mode 8 15
1 Phase 1 55 days Tue 10/1/24 Mon 11/25/24
2 Board-up Installation 3 days Tue 10/1/24 Fri 10/4/24
3 Demolition Works 10 days Fri 10/4/24 Mon 10/14/24 2 F-S
4 Hauling, Disposal and Clearing 11 days Fri 10/4/24 Tue 10/15/24 3SS S-S
5 Black Paint Application on Exposed 10 days Sun Wed 10/30/24 12FF F-F
Ceiling 10/20/24
6 Installation of 600x600mm Granite 15 days Wed Thu 11/7/24 5SS,7SS,15FF 5&7:S-S 15: F-F
10/23/24
7 Suspended Ceiling of Entrance lobby 7 days Wed Wed 10/30/24 12FF F-F
10/23/24
8 Installation of Dry Wall Partition 8 days Tue Wed 10/23/24 4 F-S
10/15/24
9 Installation of Featured Wall 6 days Sun Sat 11/23/24 6,8,16 F-S
11/17/24
10 Installation of Vertical Blinds 4 days Thu 11/7/24 Mon 11/11/24 6 F-S
11 Installation of 2 Floor Mounted 5TR AC 12 days Thu 11/7/24 Tue 11/19/24 6,12 F-S
Unit
12 Rough-ins and Cabling Works 15 days Tue Wed 10/30/24 4 F-S
10/15/24
Task Manual Task Deadline
Split Duration-only Critical
Milestone Manual Summary Rollup Critical Split
Project: SAMPLE PROJECT 1 Summary Manual Summary Progress
Date: Thu 5/16/24 Project Summary Start-only Manual Progress
Inactive Task Finish-only Slack
Inactive Milestone External Tasks
Inactive Summary External Milestone
Page 1
ID Task Task Name Duration Start Finish Predecessors relationship Sep '24
Mode 8 15
13 Relocation and Installation of New 3 days Sun Wed 10/30/24 12FF F-F
Panels 10/27/24
14 Installation of Lighting fixtures and 4 days Wed Sun 11/3/24 7 F-S
devices on lobby 10/30/24
15 Installation of Lighting fixtures and 8 days Wed Thu 11/7/24 12 F-S
devices on Main Hall 10/30/24
16 Painting of Walls 10 days Thu 11/7/24 Sun 11/17/24 6,8 F-S
17 Installation of Board-up for Phase 2 3 days Wed Sat 11/23/24 9FF F-F
11/20/24
18 Dismantling of Board-up Installed for 2 days Sat 11/23/24 Mon 11/25/24 17 F-S
Phase 1
19 Phase 2 38 days Sat Tue 12/31/24
11/23/24
20 Masonry and Concreting Works 7 days Sat 11/23/24 Sat 11/30/24 2,3,4,5,6,7,8,9,10,11,12,13,14,15,16
F-S
21 Electrical Rough-ins and Cabling Works 5 days Sat 11/23/24 Thu 11/28/24 20SS S-S
22 Piping Works for toilet and pantry 6 days Sat 11/23/24 Fri 11/29/24 20SS S-S
23 Waterproofing Works 3 days Sat 11/30/24 Tue 12/3/24 20,21,22,27 F-S
24 Inst. Of Dry Wall Partitions 3 days Wed Sat 11/30/24 20FF F-F
11/27/24
Task Manual Task Deadline
Split Duration-only Critical
Milestone Manual Summary Rollup Critical Split
Project: SAMPLE PROJECT 1 Summary Manual Summary Progress
Date: Thu 5/16/24 Project Summary Start-only Manual Progress
Inactive Task Finish-only Slack
Inactive Milestone External Tasks
Inactive Summary External Milestone
Page 2
ID Task Task Name Duration Start Finish Predecessors relationship Sep '24
Mode 8 15
25 Wall Tiles Inst. Of Toilets 10 days Tue 12/3/24 Fri 12/13/24 23 F-S
26 Suspended Ceiling for Toilet and Pantry 5 days Fri 12/13/24 Wed 12/18/24 24,25 F-S
27 Installation of Flush Hollow Core Doors 5 days Mon Sat 11/30/24 20FF,24FF F-F
11/25/24
28 Floor Tiles Installation 5 days Wed Mon 12/23/24 26 F-S
12/18/24
29 Painting Works on Walls and Ceiling 6 days Mon Sun 12/29/24 24,26,28 F-S
12/23/24
30 Installation of ToileT Fixtures and 5 days Mon Sat 12/28/24 28 F-S
Accessories 12/23/24
31 Installation of Pantry Fixtures and 8 days Sat 12/21/24 Sun 12/29/24 29FF F-F
Accessories
32 Dismantling of Board-up for Phase 2 2 days Sun Tue 12/31/24 30,31 F-S
12/29/24
Task Manual Task Deadline
Split Duration-only Critical
Milestone Manual Summary Rollup Critical Split
Project: SAMPLE PROJECT 1 Summary Manual Summary Progress
Date: Thu 5/16/24 Project Summary Start-only Manual Progress
Inactive Task Finish-only Slack
Inactive Milestone External Tasks
Inactive Summary External Milestone
Page 3
Oct '24 Nov '24 Dec '24 Jan '25
15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12
NA
Board-up Installation
NA
Demolition Works
NA
Hauling, Disposal and Clearing
₱ 0.00
Black Paint Application on Exposed Ceiling
NA
Installation of 600x600mm Granite
NA
Suspended Ceiling of Entrance lobby
₱ 0.00
Installation of Dry Wall Partition
NA
Installation of Featured Wall
₱ 0.00
Installation of Vertical Blinds
₱ 0.00
Installation of 2 Floor Mounted 5TR AC Unit
NA
Rough-ins and Cabling Works
Task Manual Task Deadline
Split Duration-only Critical
Milestone Manual Summary Rollup Critical Split
Project: SAMPLE PROJECT 1 Summary Manual Summary Progress
Date: Thu 5/16/24 Project Summary Start-only Manual Progress
Inactive Task Finish-only Slack
Inactive Milestone External Tasks
Inactive Summary External Milestone
Page 4
Oct '24 Nov '24 Dec '24 Jan '25
15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12
₱ 0.00
Relocation and Installation of New Panels
₱ 0.00
Installation of Lighting fixtures and devices on lobby
NA
Installation of Lighting fixtures and devices on Main Hall
NA
Painting of Walls
₱ 0.00
Installation of Board-up for Phase 2
₱ 0.00
Dismantling of Board-up Installed for Phase 1
NA
Masonry and Concreting Works
₱ 0.00
Electrical Rough-ins and Cabling Works
₱ 0.00
Piping Works for toilet and pantry
NA
Waterproofing Works
NA
Inst. Of Dry Wall Partitions
Task Manual Task Deadline
Split Duration-only Critical
Milestone Manual Summary Rollup Critical Split
Project: SAMPLE PROJECT 1 Summary Manual Summary Progress
Date: Thu 5/16/24 Project Summary Start-only Manual Progress
Inactive Task Finish-only Slack
Inactive Milestone External Tasks
Inactive Summary External Milestone
Page 5
Oct '24 Nov '24 Dec '24 Jan '25
15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12
NA
Wall Tiles Inst. Of Toilets
NA
Suspended Ceiling for Toilet and Pantry
NA
Installation of Flush Hollow Core Doors
NA
Floor Tiles Installation
NA
Painting Works on Walls and Ceiling
₱ 0.00
Installation of ToileT Fixtures and Accessories
NA
Installation of Pantry Fixtures and Accessories
NA
Dismantling of Board-up for Phase 2
Task Manual Task Deadline
Split Duration-only Critical
Milestone Manual Summary Rollup Critical Split
Project: SAMPLE PROJECT 1 Summary Manual Summary Progress
Date: Thu 5/16/24 Project Summary Start-only Manual Progress
Inactive Task Finish-only Slack
Inactive Milestone External Tasks
Inactive Summary External Milestone
Page 6