Risk Assessment for Shattering
Risk Assessment for Shattering
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 1 of 33
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
1 Toolbox Talk and RAMS Operatives/Staff • Make sure to only allocate skilled and competent Construction Supervisors
Discussion & activity Briefing personnel.
/ Foreman/Safety officer
• Poor communication • Ensure TBT delivered on their language.
• Perception • Double check the workers understanding about
• Language barrier
the message which delivered.
• lack of understanding. 3 P A/R 3 R A
• TBT to be delivered in calm and quite
• Personals injuries to the
worker due to lack of atmosphere.
awareness • Make sure to discuss the RAMS to involve staff
• Daily activity briefing shall be conducted by
supervisor.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 2 of 33
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
2 Work Permit Operatives/Staff • Ensure work permit system implemented before
• Lack of safety measures the start of activity. Construction Supervisors
/ Foreman/Safety officer
taken before the job • Joint site inspection should be conducted by
began. permit receiver and issuer to ensure all necessary
• Property damage slip, trip precautions are in place before work start.
& fall and personal
• Presence of competent supervisor is mandatory
injuries
prior to start any activity.
• Ensure all the required & relevant valid document
3 P AR 3 R A
and certificates available, along with permit.
• Make sure all safety control measures are in place
prior to execute the activity.
• Implementation of “No Permit, No Work” Policy
• Permit to work and approved MS & JSA must be
available near the work area.
• Work permit receiver must always stay at work area
while the work is being carried out
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 3 of 33
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
3 Access /egress Operatives/Staff • No vehicles or equipment’s granted or allowed Construction Supervisors
to pass the gate without VVS verification system / Foreman/Safety officer
• Security issue
• Poor Access / Egress • All person attends to pass through the site must
• Poor Illumination have NEOM ID
• Delay in emergency • Area must be well lit prior to the activities
evacuation • Suitable work at height access platform for low/
• Slip, Trip & Fall high working conditions must be provided and
shall be erected by competent personnel as per
4 P AR manufacturer requirements 4 R A
• Ladders should be tied or footed
• Lights shall be suitable and sufficient for the task
• Permits to be obtained to access restricted
areas.
• Ensure proper cable management to avoid
tripping over cables
• Do the needful to avoid trailing cables in the
walkways and access area
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 4 of 33
aspect of work:
4 Planning & Mobilization of Operatives/Staff • All tasks carried out by trained and Construction Supervisors
form works / material competent personnel only. Supervision / Foreman/Safety officer
Equipment always by the site supervisor and working
• Poor communication under RAMS and permit requirements.
between work parties. • Coordinate with other parties if applicable
• Vehicle movements. for work hand-over.
• Improper manual • Competent supervision mandatory.
handling. • Pre-planning of route for the activity
• Back strain. • Ensure adequacy of access and egress.
• Bodily Injuries / No • Display sign board and barricade if
3 P AR 3 R A
PPE. applicable.
• Slip, trip and falls. • Unauthorized entrance to be controlled.
• Flag man to be used if using equipment or
reversing heavy vehicle.
• Better to be used one way system.
• 360 checks shall be followed on vehicle
before moving and speed limit 20km must
be followed at site
• Trained employees to be used.
• Use correct manual handling techniques.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 5 of 33
aspect of work:
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 6 of 33
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
before sending them to site
• Use coverall uniforms, safety glasses, steel
toed boots and rubber gloves for the task.
• Ensure all equipment, truck drivers to wear
mandatory PPE’s whenever
visiting/working the site.
• Wearing of required PPE is mandatory to
all workers.
• Arrange the materials orderly.
• Provide planks as walking platform to top
of all rebar reinforcement.
• Provide pail for small materials as
containment.
• Always implement proper housekeeping
before, during and after work.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 7 of 33
aspect of work:
5 Crane Lifting and Rigging Operatives/Staff • All lifts will have an approved lift plan and Construction Supervisors
Activities. appropriate permits / Foreman/Safety officer
• Unauthorized lifts • All crane operators and riggers to produce
• Unauthorized valid qualifications.
personnel for crane • Crane operator to operate only crane that he
usage is qualified to operate
• Damaged or • All Cranes will undergo 3rd party
substandard crane and certification to ensure crane is in proper
equipment operating conditions before entering site
• Lack of • Lifting equipment (i.e. shackles, slings,
Communication with 3 P AR spreader bars etc.) will undergo 3rd party 3 R A
ground crew Unstable certification before using on site
load Entanglement • Cranes and lifting equipment will be
• Untrained operator checked daily by the competent person to
• Falling object ensure its proper operating conditions
• Only qualified rigger will do the rigging
job and give signal to crane operator.
• Load to be lifted approximately 1 meter off
the ground and adjustments made to
determine central gravity point, qualified
rigger to do this operation.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 8 of 33
aspect of work:
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 9 of 33
aspect of work:
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 10 of 33
aspect of work:
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 11 of 33
aspect of work:
7 Form Work and Braces Operatives/Staff • Remove unwanted materials from activity Construction Manager
Installation area. Supervisors /
• Slip and Trip hazard • Conduct good housekeeping before, during Foreman/Safety officer
• Uninspected tools and and after work.
power tools. • Provide magnet and small bucket for nail as
• Possible body injury. containment.
• Pinch in.
• Elevate electrical power tool cords and
• Ergonomics hazards.
from extension cables.
• Struck by nail.
• Arrange temporary material storage area
4 P AR 4 R A
• . All tools and power tools shall be
inspected and documented prior start of
work.
• Inspection stickers shall be provided on all
power tools that will passed safety
inspection.
• Monthly colour code will also provide to
all tools that are safe to use.
• Plugs of power cords will be inspected and
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 12 of 33
aspect of work:
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 13 of 33
aspect of work:
8 Erection & Dismantling of Operatives/Staff • Rubber coated gloves to be worn to avoid Construction Supervisors
shattering materials / form hand and finger Injury. / Foreman/Safety officer
work • All tools are to be tied with tool lanyard
• Structural instability prior to work at height.
leading to collapse • Full body harness to be worn by all and
during installation or 4 L UA 100% tie off to be maintained. 4 R A
dismantling. • Make sure proper working platform is
• Pinch point / finger or provided prior to send work force.
hand injury. • Make sure equipment / form works, and all
• Fall of tools materials fitting equipment’s should not have dents
from height. or any visible damages.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 14 of 33
aspect of work:
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 15 of 33
aspect of work:
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 16 of 33
aspect of work:
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 17 of 33
aspect of work:
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 18 of 33
aspect of work:
10 Using Hand Tools for form Operatives/Staff • Provide non-conductor tools to protect from Construction Supervisors
works: electrical hazard / Foreman/Safety officer
• Improper use of tool • Only color-coded tools will be used.
(using of knife as • Use right tools for the right task
screwdriver) 3 P AR • Do not use modified tools 3 R A
• Use of • Keep your hand clear of line of fire when
modified/damage tools using knife and concentrate on task
• Fall of tools from • Secure the tools by using Tool Kit
heights • Barricade the area under wherever
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 19 of 33
aspect of work:
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 20 of 33
aspect of work:
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 21 of 33
aspect of work:
12 [Link] Scaffolding Operatives/Staff • All scaffold erection shall be carried under Construction Supervisors
• Erection and the supervision on scaffold supervisor and / Foreman/Safety officer
dismantling of scaffold scaffold inspector approved by NEOM
• (Collapse of scaffold) • Scaffold erectors to possess valid third-
• Untrained & party certificates.
Incompetent personnel • Scaffolds only to be erected by competent
• Defective tools and/or and certified scaffolds.
scaffolding material • Scaffold must be inspected by a competent
• Unauthorized, misuse scaffold inspector.
• of scaffold • All scaffold erectors to use Full Body
• Falls from heights 4 L UA Harness with two lanyards, 100% tie off 4 R A
• Falling materials policy to be always enforced.
• Do not move mobile scaffold with workers
on it
• All tools to be carried in tool bag, all
• tools to be previously inspected. hand tools
to be secured with tool lanyards.
• Avoid stacking of materials on hazards.
• Barricade area, post signage and place
watchman where scaffolding is being
erected to warn workers of ongoing task.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 22 of 33
aspect of work:
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 23 of 33
aspect of work:
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 24 of 33
aspect of work:
Ladders ladder that is appropriate for all jobs.
• Fall of personnel • Ladders shall not be tied or fastened together to
• material & tools provide longer sections unless they are
specifically designed for such use.
• Ladders shall not be used in inclement weather
such as rain, muddy conditions without being
evaluated by supervision.
• Ladders shall not be loaded beyond the
maximum intended load for which they were
built, or beyond their manufacturer's rated
capacity.
• Ladders shall be used only for the purpose for
which they were designed
• Ladders shall be used only on stable and level
surfaces unless secured to prevent accidental
displacement.
• Ladders shall not be moved, shifted, or
extended while occupied.
• The top or top step of a stepladder shall not be
used as a step, remove excess oil, grease or mud
from boots before climbing a ladder.
• Ladders shall not be used horizontally as
runways or scaffolds.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 25 of 33
aspect of work:
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 26 of 33
aspect of work:
• If there are no work people should take rest in
the rest shelter. They should not roam around
the working platform
• Provide toilets at a reasonable distance
15 Working in the dark / Operatives/Staff • Workers shall be detailed in pair or buddy Construction Supervisors
nighttime system, not to allow working alone. / Foreman/Safety officer
• Persons get disoriented. • Close monitoring of workers discourages
Failure of body mechanism wandering and staying in the concealed areas.
• Sufficient lighting will be provided, and lighting
shall be arranged in way to reduces the creation
of shadow
• Detail men in pair, close monitoring by HSE and
3 P AR Supervisor. 3 R A
• Count the workers before leaving the site.
• Encourage the person to rest in the designated
area. Never rest / lay on open ground as
poisonous creatures are present the area
• Regular Health check shall be done by the site
nurse.
16 Illumination while working Operatives/Staff • Position light coherently to eliminate shadows. Construction Supervisors
at night / extended hours • Provide extra light to illuminate the working / Foreman/Safety officer
• Shadows due to improper 4 L UA area 4 R A
positioning of lights. • Position light in sufficient distance to avoid
• Glare of light. glare.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 27 of 33
aspect of work:
• Electric shock / fire • Avoid shining objects or cover shining objects
• Driving • Flood lights shall be provided
• Fatigue • Check cables and connectors for damage and
insulation.
• Avoid overloading by providing sufficient
junction boxes.
• Provide safety devices (ELCB & MCCB) to
protect the circuit from overloading.
• Remove all flammable materials from near to
the light point.
• Provide fire exit / fire evacuation route.
• Proper inspection of electrical tools by CP
person and colour code must be updated
• Defective tools must be removed ASAP and put
them out of services
• Proper cable management shall be done
• Restricted entry only authorized person can
make the electrical connection
• Fire extinguisher training must be provided
• Use beacon lights on all site vehicles.
• Maintain the specified site speed limits 20KM
• Do not park vehicles in dark without head
lamps and beacon lights
• Do not park vehicles with the doors wide open
and without engaging hand brake
• No foot on ground in equipment operation area
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 28 of 33
aspect of work:
• MEPI training to all the driver and operators
who engaged in the work
• Have good sleep in the day
• Consume healthy food
• Do not use any drugs before coming to
nightshift.
• If feel tired go to the site office/rest area and
take a rest. Do not go to the dark /
behind/under any vehicles to take a rest.
17 Emergency response Operatives/Staff • Ensure that all workers are aware what action Construction Supervisors
in case of an required during emergency. / Foreman/Safety officer
accident or incident. • All workers should be aware about the
• Miscommunication
ambulance point location.
• Unclear direction
• Congested area • Mask sure ambulance and emergency team are
• Too many onlookers 3 P AR readily available to tackle the emergency. 3 R A
• Unavailability of rescue • Emergency drills are conducted as per schedule
equipment at the place. to enhance the awareness and fulfil the
deficiencies for emergencies.
• All workers should know and aware about
assembly point.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 29 of 33
aspect of work:
• All workers should be aware and familiar with the
emergency contact numbers.
• Clear the area from onlookers Only qualified and
trained personnel to assist in an emergency.
• Minimum critical information to provide in case
of emergency:
- Incident location
- Short description of incident
- State name clearly
- Badge number
-Stay online until further instruction
• Ensure that approved rescue plan on site.
• All rescue equipment stretcher, man basket shall
be at workplace.
• All rescue team should be trained.
• Emergency routes should always be clear.
Exit routes must take the worker direct to
assembly points
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 30 of 33
aspect of work:
18 Housekeeping Operatives/Staff • Housekeeping shall be conducted prior to start the Construction Supervisors
• Trip, Slips & fall activity and after finished the job. / Foreman/Safety officer
• Fire hazard • All unwanted materials shall be kept away from
• Personal injuries walkways, aisle and access.
• Daily housekeeping will be implemented
• Rubbish generated daily shall be pulled out from
3 P AR site to avoid accumulation and infestation of
3 R A
rodents.
• Fire extinguisher shall be provided at site in case of
fire accident.
• Emergency response team and ambulance shall be
available at site to tackle out all kind of emergency.
19 Weather conditions Operatives/Staff • Avoid working outside during sandstorm. Construction Supervisors
• Adverse Weather. • During sandstorm secure all falling and flying / Foreman/Safety officer
• Heat stress materials.
• Hot weather • Keep covered all drinking water and foods to secure
• Rainfall from foreign particles and avoid contamination.
3 P AR 3 R A
• Cold environment • Avoid driving during high sandstorm.
• Accident • Drive slowly with light indicator on during
• Personal injuries, sandstorm.
• Dehydration • Emergency response team and ambulance shall be
available at site to tackle out all kind of emergency.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 31 of 33
aspect of work:
• Heat stroke to worker • Use the required PPE, dust mask and hand gloves,
result in personal injuries goggles, hard hat and safety shoes.
• Floods include risk to • Avoid working on direct under sunlight during
human life /property restricted hours.
damage • Provide adequate rest shelter facility with cooling
• Illness to worker/cough/flu fan.
• Frequent job breaks or work rotation should be
applied to give enough rest to workers and prevent
heat exhaustion.
• Ensure the adequate supply and easily access of
cold drinking water at site.
• Posting of heat stress campaign materials and
signage for workers awareness should be provided
with close supervision.
• Maske sure implementation of heat stress
management system at site during the hot weather.
• Drink more water during hot weather or humid air
conditions.
• Use ORS solution if continuous sweating occurs
from the body.
• Avoid carbonated drink (e.g., Pepsi, Coke, etc.).
• Avoid taking heavy meals during hot weather.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 32 of 33
aspect of work:
• Sleep properly at night at least 6 to 8 hours.
• Assure to take breakfast before performing the
morning task.
• Use loose cotton clothing and body parts should be
covered.
• Used buddy system for lone workers.
• Don't allow to work at height or work on open area
while raining.
• Unplug and remove all the electrical appliance /
tool / equipment from work site and keep it
secured.
• Ensure that all electrical distribution board and
panels are covered and not penetrated by
rainwater. Keep covered all trenches and
excavation.
• All power cable should be double insulated and
protected from water before work commence.
• Don't work or use any electrical appliances while
cloth is wet.
• Be careful while using access and egress.
• Avoid using slippery shoes.
• Do not use wet ladder.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 33 of 33
aspect of work:
• Use proper PPE, raincoat, helmet and safety boot
etc.
• Avoid working in open area if weather is extreme
cold.
• Shield extremely cold surface.
• Provide warm area while working in extreme cold
environment.
• Frequent job breaks and job rotation is required
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible