Risk Assessment for Shattering

This document contains a risk assessment for shattering during construction of industrial support facilities at NEOM. It identifies hazards such as poor communication during toolbox talks or lack of safety measures without a work permit. Controls are identified like ensuring only skilled workers are used and a work permit system is implemented. The risk assessment contains 33 sheets assessing hazards and controls.

Uploaded by

moh abobajee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
249 views33 pages

Risk Assessment for Shattering

This document contains a risk assessment for shattering during construction of industrial support facilities at NEOM. It identifies hazards such as poor communication during toolbox talks or lack of safety measures without a work permit. Controls are identified like ensuring only skilled workers are used and a work permit system is implemented. The risk assessment contains 33 sheets assessing hazards and controls.

Uploaded by

moh abobajee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

NEOM-NLF-FRM-002.

01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 1 of 33
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
1 Toolbox Talk and RAMS Operatives/Staff • Make sure to only allocate skilled and competent Construction Supervisors
Discussion & activity Briefing personnel.
/ Foreman/Safety officer
• Poor communication • Ensure TBT delivered on their language.
• Perception • Double check the workers understanding about
• Language barrier
the message which delivered.
• lack of understanding. 3 P A/R 3 R A
• TBT to be delivered in calm and quite
• Personals injuries to the
worker due to lack of atmosphere.
awareness • Make sure to discuss the RAMS to involve staff
• Daily activity briefing shall be conducted by
supervisor.

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 2 of 33
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
2 Work Permit Operatives/Staff • Ensure work permit system implemented before
• Lack of safety measures the start of activity. Construction Supervisors
/ Foreman/Safety officer
taken before the job • Joint site inspection should be conducted by
began. permit receiver and issuer to ensure all necessary
• Property damage slip, trip precautions are in place before work start.
& fall and personal
• Presence of competent supervisor is mandatory
injuries
prior to start any activity.
• Ensure all the required & relevant valid document
3 P AR 3 R A
and certificates available, along with permit.
• Make sure all safety control measures are in place
prior to execute the activity.
• Implementation of “No Permit, No Work” Policy
• Permit to work and approved MS & JSA must be
available near the work area.
• Work permit receiver must always stay at work area
while the work is being carried out

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 3 of 33
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
3 Access /egress Operatives/Staff • No vehicles or equipment’s granted or allowed Construction Supervisors
to pass the gate without VVS verification system / Foreman/Safety officer
• Security issue
• Poor Access / Egress • All person attends to pass through the site must
• Poor Illumination have NEOM ID
• Delay in emergency • Area must be well lit prior to the activities
evacuation • Suitable work at height access platform for low/
• Slip, Trip & Fall high working conditions must be provided and
shall be erected by competent personnel as per
4 P AR manufacturer requirements 4 R A
• Ladders should be tied or footed
• Lights shall be suitable and sufficient for the task
• Permits to be obtained to access restricted
areas.
• Ensure proper cable management to avoid
tripping over cables
• Do the needful to avoid trailing cables in the
walkways and access area

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 4 of 33
aspect of work:

4 Planning & Mobilization of Operatives/Staff • All tasks carried out by trained and Construction Supervisors
form works / material competent personnel only. Supervision / Foreman/Safety officer
Equipment always by the site supervisor and working
• Poor communication under RAMS and permit requirements.
between work parties. • Coordinate with other parties if applicable
• Vehicle movements. for work hand-over.
• Improper manual • Competent supervision mandatory.
handling. • Pre-planning of route for the activity
• Back strain. • Ensure adequacy of access and egress.
• Bodily Injuries / No • Display sign board and barricade if
3 P AR 3 R A
PPE. applicable.
• Slip, trip and falls. • Unauthorized entrance to be controlled.
• Flag man to be used if using equipment or
reversing heavy vehicle.
• Better to be used one way system.
• 360 checks shall be followed on vehicle
before moving and speed limit 20km must
be followed at site
• Trained employees to be used.
• Use correct manual handling techniques.

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 5 of 33
aspect of work:

• Ensure no scattered materials present in


walkways.
• Area to be levelled and stabled.
• Maintain good coordination and
communication between team members.
• Access routes should clear from all
potential obstacles.
• Do not place hands and fingers in trap
points.
• Ensure adequate manpower for the job.
• Competent supervision mandatory.
• Always follow safe manual lifting
practices.
• Use mechanical aids (wheel borrow, etc.)
as a first approach.
• Implement correct lifting postures and
buddy system when lifting large and
awkward items.
• All personnel should attend safety
orientation. And must obtain NEOM ids
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 6 of 33
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
before sending them to site
• Use coverall uniforms, safety glasses, steel
toed boots and rubber gloves for the task.
• Ensure all equipment, truck drivers to wear
mandatory PPE’s whenever
visiting/working the site.
• Wearing of required PPE is mandatory to
all workers.
• Arrange the materials orderly.
• Provide planks as walking platform to top
of all rebar reinforcement.
• Provide pail for small materials as
containment.
• Always implement proper housekeeping
before, during and after work.

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 7 of 33
aspect of work:

5 Crane Lifting and Rigging Operatives/Staff • All lifts will have an approved lift plan and Construction Supervisors
Activities. appropriate permits / Foreman/Safety officer
• Unauthorized lifts • All crane operators and riggers to produce
• Unauthorized valid qualifications.
personnel for crane • Crane operator to operate only crane that he
usage is qualified to operate
• Damaged or • All Cranes will undergo 3rd party
substandard crane and certification to ensure crane is in proper
equipment operating conditions before entering site
• Lack of • Lifting equipment (i.e. shackles, slings,
Communication with 3 P AR spreader bars etc.) will undergo 3rd party 3 R A
ground crew Unstable certification before using on site
load Entanglement • Cranes and lifting equipment will be
• Untrained operator checked daily by the competent person to
• Falling object ensure its proper operating conditions
• Only qualified rigger will do the rigging
job and give signal to crane operator.
• Load to be lifted approximately 1 meter off
the ground and adjustments made to
determine central gravity point, qualified
rigger to do this operation.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 8 of 33
aspect of work:

• All personnel not involved in lift to stay


outside of the barricaded area
• Use tag line to control load, do not use
hands on the load
• Tag line to place before the lift begins
• Use correct body position to control load
• Check rope for length prior to lift Rigger to
use rigger gloves while handling the tag
line The operator always follows the load
chart.
• Trained and experienced operator shall be
used for lifting
• All the lifting operations shall be carried
out under the direct supervision of lifting
appointed person and lifting supervisor
approved by NEOM
6 Manual Handling for Operatives/Staff • Ensure use of inspected tools and Construction Supervisors
shattering materials / form mechanical aids / Foreman/Safety officer
works: 3 p AR • Clear the work location and the path 3 R A
• Dusts, • Assess load, its weight and individual
• Fall of material, capability
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 9 of 33
aspect of work:

• Damaged/unsafe tool, • Use safety helmets, safety googles, dust


• Vehicle / human traffic, masks, safety shoes, safety gloves
• Extreme hot/wintry appropriate to the task.
weather, • Follow planned work process with
• Poor work posture, scheduled breaks
• Improper lifting, • Use Competent technicians to carry out
• Repetitive activity.
movements, • Use safety signs and proper barricading, if
• Pinch points, required
• Use of uninspected • Use face googles in case of dust
equipment / machine, accumulation, clean the material before
• Hand injury, moving into site or to trailer
• Slips, trips and fall of • Read any instructions posted over the
workers container/ box/ package
• Manually lift only if there is no other option
available.
• Load the heavy objects in bottom rack and
lighter load in the top racks
1 m radius of space around the FFE
• Do not stack or pile over lighting units
• Manually lift only if there is no other option
available.

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 10 of 33
aspect of work:

• Load the heavy objects in bottom rack and


lighter load in the top racks
1 m radius of space around the FFE
• Do not stack or pile over lighting units
• Ensure use of inspected tools and
mechanical aids
• Clear the work location and the path
• Assess load, its weight and individual
capability
• Use safety helmets, safety googles, dust
masks, safety shoes, safety gloves
appropriate to the task.
• Follow planned work process with
scheduled breaks
• Use physically competent technicians to
carry out activity.
• Use safety signs and proper barricading, if
required
• Use face mask in case of dust
accumulation, clean the material before
moving into store
• Read any instructions posted over the
container/ box/ package
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 11 of 33
aspect of work:

• Manually lift only if there is no other option


available.

7 Form Work and Braces Operatives/Staff • Remove unwanted materials from activity Construction Manager
Installation area. Supervisors /
• Slip and Trip hazard • Conduct good housekeeping before, during Foreman/Safety officer
• Uninspected tools and and after work.
power tools. • Provide magnet and small bucket for nail as
• Possible body injury. containment.
• Pinch in.
• Elevate electrical power tool cords and
• Ergonomics hazards.
from extension cables.
• Struck by nail.
• Arrange temporary material storage area
4 P AR 4 R A
• . All tools and power tools shall be
inspected and documented prior start of
work.
• Inspection stickers shall be provided on all
power tools that will passed safety
inspection.
• Monthly colour code will also provide to
all tools that are safe to use.
• Plugs of power cords will be inspected and
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 12 of 33
aspect of work:

should have grounding (3 prong plug).


• Power tools shall be inspected for machine
guarding.
• Hand tools with wobbly parts such as
hammer shall not be allowed to use.
• Wearing of mandatory PPE’s such as hard
hats, safety vest, gloves, safety glasses and
safety shoes will be strictly imposed.
• Use of additional PPE’s such as face
shields will be provided as necessary
• Use leather gloves.
• High level of alertness is required when
doing the job.
• Keep hands away from adjacent objects.
• Hammers shall be inspected and to be in
good condition.
• Implement buddy system in raising large
plywood’s and timbers
• Provide working tables or platforms
appropriate with the height of the worker
conducting the activity.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 13 of 33
aspect of work:

• De-nailing area will be provided on site.


• Any carpentry activities will be isolated by
barricades with safety and warning signs.
• Nails on grounds shall be immediately
removed upon seeing.
• Workers will be provided with appropriate
respiratory protection.
• Wood dust generated on working area will
be removed by ongoing housekeeping

8 Erection & Dismantling of Operatives/Staff • Rubber coated gloves to be worn to avoid Construction Supervisors
shattering materials / form hand and finger Injury. / Foreman/Safety officer
work • All tools are to be tied with tool lanyard
• Structural instability prior to work at height.
leading to collapse • Full body harness to be worn by all and
during installation or 4 L UA 100% tie off to be maintained. 4 R A
dismantling. • Make sure proper working platform is
• Pinch point / finger or provided prior to send work force.
hand injury. • Make sure equipment / form works, and all
• Fall of tools materials fitting equipment’s should not have dents
from height. or any visible damages.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 14 of 33
aspect of work:

• improper working • If any discrepancies noted report to the


platform. concern authorities.
• Damaged equipment • Prior to install the shattering materials,
• Installation without proper inspection shall be conducted from
inspection. concern authority
• Working without • Ensure that frames and shattering parts are
wearing the approved free from damage, supported properly and
• Injury due to wrong tightly connected.
tools usage or • Follow the manufacturer’s
mishandling recommendations and in accordance with
of tools. the applicable codes.
• Unauthorized entry in • Ensure proper clearance is provided with a
work area. minimum of 1-meter clearance on each
• Injury due to sharp piece of equipment.
edges. • Ensure proper access panels or doors is
provided wherever service and inspection
. will be required for proper
• operation and maintenance of the system
• Ensure anchor bolts shall be used for duct
hanging supports.

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 15 of 33
aspect of work:

• Make sure duct sealant is provided on all


joints, corners, branch connections, flanges
and all portions that may cause of possible
air leakage.
• Sealant shall be applied with forks or
chisels, not by fingers, avoid eating or
drinking while work with sealant.
• MSDS available and followed.
• Ensure proper/rigid support is provided to
avoid the load on the equipment and will be
connected with the flexible-duct connector
to avoid mechanical equipment
vibration to the duct.
• All necessary personal protective
equipment, such as coverall, safety shoes,
safety glasses, face shield safety
helmet, safety vest, full body harness and
hand gloves shall be worn by personnel
always performing work.

• Use right tools for the job.


Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 16 of 33
aspect of work:

• Ensure all grounding connections shall be


installed with proper grounding materials.
• Ensure the connectors used shall be of
same size.
• Barricading and signage to be provided to
avoid unauthorized entry.
• Ensure availability of supervisor to oversee
workers until the end of activity
• Maximum care shall be taken to avoid
contact between sharp edges
9 Work at Height Operatives/Staff • All Work at height is properly panned, Construction Supervisors
• Untrained & organized and supervised by a competent / Foreman/Safety officer
Incompetent personnel person
• Slips, trips and falls • Weather conditions are taken in account
• Falling materials • Edge protection with guard rails and toe
• Fall from height 4 L UA boards 4 R A
• Unprotected edges • Pre-inspection should be conducted for all
• Open holes work at height equipment.
• Material stored on the • Primary fall protection shall be installed
edges • All personnel working at height must wear
Full Body Harness with double lanyard.

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 17 of 33
aspect of work:

• Unsafe excess and • When working at heights, 100% tie off


egress policy is to be always enforced.
• Bad Weather • Workers to be trained in working at heights
procedure and how to use Full Body
Harness correctly
• Permit to be obtained for edge works
• Safety Lifelines to be provided to those who
working on leading edges
• STARRT Card to be done prior to any
Work at Height activities
• Ensure proper cable management to avoid
tripping over cables Do the needful to avoid
trailing cables in the walkways and access
areas
• Tools must be carried in a toolbox
• Ensure proper cable management to avoid
tripping over cables
• Follow good housekeeping procedures to
keep area free of tripping hazards
• Scaffold is not to be used for storing or
stacking material.
• Scaffold to have toe boards to prevent tools
from falling.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 18 of 33
aspect of work:

• Area to be barricaded to prevent


• unauthorized personnel. (Exclusion zone)
• Tools to be carried in a tool back.
• Tools to be tied off if necessary.
• Adequate signage informing of overhead
activities.
• All the open hole at work at heights must
be covered with exterior grade Plywood
with signages and barricades shall be
installed around it
• Material shall not be stored on the edge it
should be kept minimum 2 meter

10 Using Hand Tools for form Operatives/Staff • Provide non-conductor tools to protect from Construction Supervisors
works: electrical hazard / Foreman/Safety officer
• Improper use of tool • Only color-coded tools will be used.
(using of knife as • Use right tools for the right task
screwdriver) 3 P AR • Do not use modified tools 3 R A
• Use of • Keep your hand clear of line of fire when
modified/damage tools using knife and concentrate on task
• Fall of tools from • Secure the tools by using Tool Kit
heights • Barricade the area under wherever
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 19 of 33
aspect of work:

• Slip/trip hazards • Avoid wearing Jewelry at work applicable


• Improper footing when • Post signage’s about hazards
using/swinging tools • Proper footing while using hand tools
such as hammer • Stand in a safe direction away from impact
• Improper use of gloves area
for the task • Use of appropriate PPEs for the task
• Cutting in improper Use of hand tools in the right direction
direction
• Workers
standing/position in the
impact area
11 Use of power tools. For Operatives/Staff • The power tool shall be inspected by Construction Supervisors
installation of shattering competent person prior use. / Foreman/Safety officer
components: • Portable power tools shall not be left lying
• Hand Injury.
around the work area where they could be
• Electrocution and short
damaged.
circuit. 4 L UA 4 R A
• Portable power tools shall be equipped with
properly functioning controls that will shut
off the power when released.
• Power tools shall not be equipped with
trigger locks

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 20 of 33
aspect of work:

• Protective shields / guards supplied with


the tools (as per design) shall not be
removed.
• Before they are set down, rotating power
tools shall be switched off and held until
the rotation has completely stopped. They
shall not be stopped by grasping the
rotating assembly
• Power tools shall be disconnected from the
power source before changing bits, blades,
cutters or wheels.
• Wear gloves during work.
• All electric connections shall be secured
with GFCI or ELCB safety devices.
• Do not work on wet surface in order to
decrease the risk of electric shock
• The generator supplying power shall be
equipped with grounding’s
• Color-code shall be provided on all the
equipment after carrying out inspection by
the competent electrical person
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 21 of 33
aspect of work:

12 [Link] Scaffolding Operatives/Staff • All scaffold erection shall be carried under Construction Supervisors
• Erection and the supervision on scaffold supervisor and / Foreman/Safety officer
dismantling of scaffold scaffold inspector approved by NEOM
• (Collapse of scaffold) • Scaffold erectors to possess valid third-
• Untrained & party certificates.
Incompetent personnel • Scaffolds only to be erected by competent
• Defective tools and/or and certified scaffolds.
scaffolding material • Scaffold must be inspected by a competent
• Unauthorized, misuse scaffold inspector.
• of scaffold • All scaffold erectors to use Full Body
• Falls from heights 4 L UA Harness with two lanyards, 100% tie off 4 R A
• Falling materials policy to be always enforced.
• Do not move mobile scaffold with workers
on it
• All tools to be carried in tool bag, all
• tools to be previously inspected. hand tools
to be secured with tool lanyards.
• Avoid stacking of materials on hazards.
• Barricade area, post signage and place
watchman where scaffolding is being
erected to warn workers of ongoing task.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 22 of 33
aspect of work:

• Do not turn boards with loose material on


them.
• Do not overload scaffold with dismantled
equipment.
• Live electrical cables shouldn't tie with
scaffolds, should be separated
• STARRT Card to be done prior to
• any scaffolding activities
• Personnel to use scaffold only if it has a
GREEN TAG certifying the scaffold.
• Personnel is not to use scaffold if it has a
YELLOW or RED TAG.
• When scaffold is being modified area is to
be closed off to workers and properly
signed to prevent them from using an
unsafe, uncertified scaffold.
• Only competent person is to place
• a GREEN TAG on scaffolding
• All personnel using a scaffold must wear
Full Body Harness with double lanyard.

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 23 of 33
aspect of work:

• When working at heights 100% tie off


police is to be always enforced.
• Workers to be trained in working at heights
procedure and how to use
Full Body Harness correctly.
• Scaffold is not to be used for storing or
stacking material.
• Scaffold to have toe boards to prevent tools
from falling.
• Area to be barricaded to prevent
unauthorized personnel.
• Tools to be carried in a tool back.
• Tools to be tied off if necessary.
• Adequate signage informing of
overhead activities
13 Using Ladder Operatives/Staff • Ladders shall have non-skid surfaces on each Construction Supervisors
rung / Foreman/Safety officer
• Incorrect selection of
ladder 3 P AR • Ladders shall be capable of supporting four 3 R A
• Misuse of ladder times their intended load
• Defective, damage • Ladders shall be of the proper size and design
for the specific task at hand. There is no single
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 24 of 33
aspect of work:
Ladders ladder that is appropriate for all jobs.
• Fall of personnel • Ladders shall not be tied or fastened together to
• material & tools provide longer sections unless they are
specifically designed for such use.
• Ladders shall not be used in inclement weather
such as rain, muddy conditions without being
evaluated by supervision.
• Ladders shall not be loaded beyond the
maximum intended load for which they were
built, or beyond their manufacturer's rated
capacity.
• Ladders shall be used only for the purpose for
which they were designed
• Ladders shall be used only on stable and level
surfaces unless secured to prevent accidental
displacement.
• Ladders shall not be moved, shifted, or
extended while occupied.
• The top or top step of a stepladder shall not be
used as a step, remove excess oil, grease or mud
from boots before climbing a ladder.
• Ladders shall not be used horizontally as
runways or scaffolds.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 25 of 33
aspect of work:

• All ladders to be inspected by competent person


and records maintained
• Damaged ladders are to be sent for repair to
match the manufacturers specifications by a
competent person.
• Damaged or defective ladders are to be
reported to supervisor and tagged as damaged,
remove from site
• While ascending or descending ladder,
maintain 3-point contact at all times.
• Tools are to be carried in a tool bag, no
ascending or descending with tools in hands.
• Ladders to be properly secured, temporary
ladders to be held by a second person at the
bottom.
• Ladders shall extend at least 1.1 m above the
access level or landing platform.
14 Lack of Welfare facilities Operatives/Staff • Ensure shaded rest shelters are provided for Construction Supervisors
• Health issue to workers the workers near the rig. / Foreman/Safety officer
3 P AR • Ensure cool water is provided in the rest shelter
3 R A
• Provide isotonic solutions during summer.

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 26 of 33
aspect of work:
• If there are no work people should take rest in
the rest shelter. They should not roam around
the working platform
• Provide toilets at a reasonable distance
15 Working in the dark / Operatives/Staff • Workers shall be detailed in pair or buddy Construction Supervisors
nighttime system, not to allow working alone. / Foreman/Safety officer
• Persons get disoriented. • Close monitoring of workers discourages
Failure of body mechanism wandering and staying in the concealed areas.
• Sufficient lighting will be provided, and lighting
shall be arranged in way to reduces the creation
of shadow
• Detail men in pair, close monitoring by HSE and
3 P AR Supervisor. 3 R A
• Count the workers before leaving the site.
• Encourage the person to rest in the designated
area. Never rest / lay on open ground as
poisonous creatures are present the area
• Regular Health check shall be done by the site
nurse.

16 Illumination while working Operatives/Staff • Position light coherently to eliminate shadows. Construction Supervisors
at night / extended hours • Provide extra light to illuminate the working / Foreman/Safety officer
• Shadows due to improper 4 L UA area 4 R A
positioning of lights. • Position light in sufficient distance to avoid
• Glare of light. glare.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 27 of 33
aspect of work:
• Electric shock / fire • Avoid shining objects or cover shining objects
• Driving • Flood lights shall be provided
• Fatigue • Check cables and connectors for damage and
insulation.
• Avoid overloading by providing sufficient
junction boxes.
• Provide safety devices (ELCB & MCCB) to
protect the circuit from overloading.
• Remove all flammable materials from near to
the light point.
• Provide fire exit / fire evacuation route.
• Proper inspection of electrical tools by CP
person and colour code must be updated
• Defective tools must be removed ASAP and put
them out of services
• Proper cable management shall be done
• Restricted entry only authorized person can
make the electrical connection
• Fire extinguisher training must be provided
• Use beacon lights on all site vehicles.
• Maintain the specified site speed limits 20KM
• Do not park vehicles in dark without head
lamps and beacon lights
• Do not park vehicles with the doors wide open
and without engaging hand brake
• No foot on ground in equipment operation area
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 28 of 33
aspect of work:
• MEPI training to all the driver and operators
who engaged in the work
• Have good sleep in the day
• Consume healthy food
• Do not use any drugs before coming to
nightshift.
• If feel tired go to the site office/rest area and
take a rest. Do not go to the dark /
behind/under any vehicles to take a rest.

17 Emergency response Operatives/Staff • Ensure that all workers are aware what action Construction Supervisors
in case of an required during emergency. / Foreman/Safety officer
accident or incident. • All workers should be aware about the
• Miscommunication
ambulance point location.
• Unclear direction
• Congested area • Mask sure ambulance and emergency team are
• Too many onlookers 3 P AR readily available to tackle the emergency. 3 R A
• Unavailability of rescue • Emergency drills are conducted as per schedule
equipment at the place. to enhance the awareness and fulfil the
deficiencies for emergencies.
• All workers should know and aware about
assembly point.

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 29 of 33
aspect of work:
• All workers should be aware and familiar with the
emergency contact numbers.
• Clear the area from onlookers Only qualified and
trained personnel to assist in an emergency.
• Minimum critical information to provide in case
of emergency:
- Incident location
- Short description of incident
- State name clearly
- Badge number
-Stay online until further instruction
• Ensure that approved rescue plan on site.
• All rescue equipment stretcher, man basket shall
be at workplace.
• All rescue team should be trained.
• Emergency routes should always be clear.
Exit routes must take the worker direct to
assembly points

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 30 of 33
aspect of work:

18 Housekeeping Operatives/Staff • Housekeeping shall be conducted prior to start the Construction Supervisors
• Trip, Slips & fall activity and after finished the job. / Foreman/Safety officer
• Fire hazard • All unwanted materials shall be kept away from
• Personal injuries walkways, aisle and access.
• Daily housekeeping will be implemented
• Rubbish generated daily shall be pulled out from
3 P AR site to avoid accumulation and infestation of
3 R A
rodents.
• Fire extinguisher shall be provided at site in case of
fire accident.
• Emergency response team and ambulance shall be
available at site to tackle out all kind of emergency.
19 Weather conditions Operatives/Staff • Avoid working outside during sandstorm. Construction Supervisors
• Adverse Weather. • During sandstorm secure all falling and flying / Foreman/Safety officer
• Heat stress materials.
• Hot weather • Keep covered all drinking water and foods to secure
• Rainfall from foreign particles and avoid contamination.
3 P AR 3 R A
• Cold environment • Avoid driving during high sandstorm.
• Accident • Drive slowly with light indicator on during
• Personal injuries, sandstorm.
• Dehydration • Emergency response team and ambulance shall be
available at site to tackle out all kind of emergency.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 31 of 33
aspect of work:
• Heat stroke to worker • Use the required PPE, dust mask and hand gloves,
result in personal injuries goggles, hard hat and safety shoes.
• Floods include risk to • Avoid working on direct under sunlight during
human life /property restricted hours.
damage • Provide adequate rest shelter facility with cooling
• Illness to worker/cough/flu fan.
• Frequent job breaks or work rotation should be
applied to give enough rest to workers and prevent
heat exhaustion.
• Ensure the adequate supply and easily access of
cold drinking water at site.
• Posting of heat stress campaign materials and
signage for workers awareness should be provided
with close supervision.
• Maske sure implementation of heat stress
management system at site during the hot weather.
• Drink more water during hot weather or humid air
conditions.
• Use ORS solution if continuous sweating occurs
from the body.
• Avoid carbonated drink (e.g., Pepsi, Coke, etc.).
• Avoid taking heavy meals during hot weather.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 32 of 33
aspect of work:
• Sleep properly at night at least 6 to 8 hours.
• Assure to take breakfast before performing the
morning task.
• Use loose cotton clothing and body parts should be
covered.
• Used buddy system for lone workers.
• Don't allow to work at height or work on open area
while raining.
• Unplug and remove all the electrical appliance /
tool / equipment from work site and keep it
secured.
• Ensure that all electrical distribution board and
panels are covered and not penetrated by
rainwater. Keep covered all trenches and
excavation.
• All power cable should be double insulated and
protected from water before work commence.
• Don't work or use any electrical appliances while
cloth is wet.
• Be careful while using access and egress.
• Avoid using slippery shoes.
• Do not use wet ladder.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Construction of the Industrial Support Facilities (ISF) NEOM code:
Component or
Risk Assessment for Shattering – PROFEMAX - Wall Sheet no. 33 of 33
aspect of work:
• Use proper PPE, raincoat, helmet and safety boot
etc.
• Avoid working in open area if weather is extreme
cold.
• Shield extremely cold surface.
• Provide warm area while working in extreme cold
environment.
• Frequent job breaks and job rotation is required

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur NAVEED AFTAB 19-5-
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A 2024
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR ENG REAL QCM 19-5-
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA [Link] CM 2024
5 to 15 man-days (LTI)

Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA REAL
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible