0 ratings0% found this document useful (0 votes) 110 views169 pagesESTIasdby Max Fajardo
sdsggggggrgrgrgrrewewqewq
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
TABLE OF CONTENTS
CHAPTER - 10 PAINTING
10-1
10-2
10:3
10-4
10-5
10-6
10-7
10-8
10-9
Paint
Ingredient of Paint
Essel and Specific Properties of Good
Quality Paint
Elements of a Good Painting Job
Surface Preparation
Kinds of Paint, Uses and Area Coverage
Estimating Your Paint
Failures and Remedy
CHAPTER- 11 AUXILIARY TOPICS
14
11-2
11-3
11-4
145
116
147
18
‘Accordion Door Cover
Glass Jalousie
‘Water Tank
‘Wood Piles
Bituminous Surface Treatment
Filling Materials
Nipa Shingle Roofing
‘Anahaw Roofing
297
300
301
305
311
317
323
325
326
331
332
334
338
CHAPTER
CONCRETE
1-1 PLAIN AND REINFORCED CONCRETE
Concrete is either Plain or Reinforced. By definition, Plain
Concrete is an artificial stone as a result of mixing cement, fine
aggregates, coarse aggregates and water. The conglomeration
of these materials producing a solid mass is called plain con-
crete.
Reinforced Concrete on the other hand, is a concrete with
reinforcement properly embedded in such a manner that the
two materials act together in resisting forces.
The Different Types of Concrete Used in Construction are :
4. The Ordinary Portland cement.
2. The Rapid Hardening Portland Cement whi
when high early strength concrete is desired.
3. The Blast Furnace or Sulfate Cement used on concrete
structures designed to resist chemical attack.
4. The Low Heat Portland Cement used for massive sec-
tions designed to reduce the heat of hydration.
5. The Portland Pozzolan Cement with a low hardening
characteristic concrete.
6. The High Alumina Cement.
is preferred
The High Alumina Cement is sometimes called aluminous
‘cement or cement fundu. Its chemical composition is different
from that of Portland cement for having predominant alumina
‘oxide content of at least 32% by weight. The alumina lime is
within the limit of 0.85% to 1.3%.|
‘SIMPLIFIED CONSTRUCTION ESTIMATE
‘This type of cement has a very high rate of strength devel-
opment compared with the ordinary Portland cement. Aside
from its rapid hardening properties, it can resist chemical attack
by sulfate and weak acids including sea water. It can also with-
stand. prolonged exposure to high temperature of more than
4,000°C. Alumina cement however, is not advisable for mixing
with any other types of cement.
‘The Main Composition of Cement are:
1.6 to 65% Lime
18.0 - 25% Silica
3.0 - 8% Alumina
3.0 - 5% Iron oxide
2.0 - 5% Magnesia
1,0 - 5% Sulfurtrioxide
AGGREGATES,
‘Aggregates for concrete work are classified into two:
4. Coarse Aggregate such as crushed stone, crushed
gravel or natural gravel with particles retained on a 5
mm sieve.
2. Fine Aggregate such as crushed stone, crushed gravel,
sand or natural sand with particles passing ona 5 mm
sieve.
Size of Aggregates. - For coarse aggregate (gravel), the
‘maximum nominal size varies from 40, 20, 14 or 10 mm diame-
ter. The choice from the above sizes depends upon the dimen-
sions of the concrete member more particularly, the spacing of
the steel bars reinforcement or as specified.
Good practice demand that the maximum size of coarse ag-
gregate (gravel) should not exceed 25% of the minimum thick-
ness of the member structure nor exceed the clear distance
between the reinforcing bars and the form.
2
CONCRETE
‘The coarse aggregate should be small enough for the con-
crete mixture to flow smoothly around the reinforcement. This is.
referred to as workability of concrete.
1-2 THE PRINCIPLES OF CONCRETE MIXING
‘The purpose in mixing concrete is to select an optimum pro-
portion of cement, water and aggregates, to produce @ concrete
mixture that will meet the following requirements:
4. Workability 3. Durability
2. Strength 4. Economy
‘The proportion that will be finally adopted in concrete mixing
has to be established by actual trial and adjustment processes
to atiain the desired strength and quality of concrete required
under the following procedures:
4, The water cement ratio is first determined at the very first
hhour of mixing to meet the requirements of strength and
durability
2. The cement-aggregate ratio is then chosen and estab-
lished to satisfy the workability requirements. Workability,
‘means the ability of the fresh concrete to fill all the voids
between the stee! bars and the forms without necessarily
exerting much effort in tamping.
Laboratory tests showed that the water-cement content ratio
Is the most important consideration in mixing because it deter-
mines not only the strength and durability of the concrete but
also the workability of the mbdure.
Concrete mixtures in a paste form, is preferred than those,
‘mixtures which are flowing with water.
‘The ACI Requirements for Concrete are as follows:
1. Fresh concrete shall be workable. Meaning, that fresh con-
3‘SIMPLIFIED CONSTRUCTION ESTIMATE
crete could freely flow around the reinforcements to fill all
‘the voids inside the form.
2. That, the hardened concrete shall be strong enough to
carry the design load.
3, That, hardened concrete could withstand the conditions to
which itis expected to perform.
4, That, concrete should be economically produced.
Concrete Mixture may be classified as either:
a. Designed Mixture
'b. Prescribed Midture
Designed Mixture. Where the contractor is responsible in
establishing the mixture proportion that will achieve the required
strength and workability as specified in the plan.
Prescribed Mixture. Where the designing engineer specify
the mixture proportion. The contractor's responsibility is only to
provide a mixed concrete containing the right propor-
tions as in the plan.
1-3 THE UNIT OF MEASURE
Prior to the worldwide acceptance of Metrication, otherwise
known as System International (SI), materials for concrete
structures were estimated in terms of cubic meter although, the
‘components thereof like; cement, sand, gravel and water, are
measured in pounds, cubic foot and gallons per bag respec-
tively.
Lately however, under the SI measures, the 94 pounds per
bag cement equivalent to 42.72 kilograms was changed and
fixed at 40 kilograms per bag. The traditional wooden box used
‘to measure the sand and gravel is 12 inches wide by 12 inches
long and 12 inches high, having niet volume of 1 cubic foot.
4
CONCRETE
Today, instead of the traditionial measuring wooden box, the
‘empty plastic bag of cement is popularly used to measure the
volume of sand and gravel for convenience in handling aggre-
‘Gates during the mixing operations.
TABLE 1-1 CONVERSION FROM INCHES TO METER
Nemec] Acarae | Appesat | numer | Aciam | Apron
vice | ie ae | PR
+ | case [as [anf sae | aes
2 | vse | 60 | ze | see | So
3 | ome | oe | % | ten | Se
4 | ‘oe | oo | i | soo | oo
5 | ao | fos | 2 | too | 8
s | ss | 150 | 25 | sos
7 | ime | as | my | see | 8
& | zz | 200 | oe | Hee | Sp
9 2286 228 29 7366 725
10 | 20 | 250 | 2 | tem | Teo
| 20 | a | oo | sem | tts
12 | Sma | 30 | S| ate | toe
3 | Sooo | 0 | 3 | aoe | oe
a | 3s | 50] 3 | Gewe | SS
1 | 30 | ae | 3 | tom | 28
1s | 404 | 400 | a feo
v | aoa} ae | [came | $2
te | ‘er | 450 | Se | asso | oon
to | 4a | 7s | 3 | 0m | oe
x | S000 | so | fo | toe | too
1
‘The values presented in Table 1-1 could be useful in:
1. Finding the accurate conver
Metric a sion of length from English to
2. Determining the approximate value to be used
in our simplified methods of estimating. GettaSIMPLIFIED CONSTRUCTION ESTIMATE
For Instance :
In solving problems, the probability of committing error is
subetantaly high when severe! digitnumbers are being used.
Example:
It is easier to use .10 meter, the approximate equivalent of 4
inches than .1016 it's exact equivelent, be it by multiplication or
bby division processes.
8 = 80 by inspection and analysis
“g_ = 78.7 by long process of division
A016
B) To memorize the values given in Table 1-1 is a waste of
time end nota practical approach in estimating. A simple guide
will be adopted so that one could easily determine the equiva-
lent values from English to Metric or vise versa.
Example:
1, Toconvert Meter to Feet: Divide the length by .30
Say 6,00 meters = 20ft
30
2, To convert Feet to Meters: Multiply by .20
Say, 30 feet x .30 = 9.00 meters
3. To convert Inches to Meter, just remember the following
values of equivalent.
CONCRETE
Take note that all length in inches is divisible by one or any
combination of these five numbers. Thus, it could be easily con-
verted to meters by summing up their quotient equival
Example:
a, Whats the meter length equivalent of 7 inches 2 By sim-
ple analysis, 7 inches could be the sum of 4 and 3, there-
fore:
4 inches = 10 meter
3 inches = .075 meter
Answer = .175 meter
b. How about 21 inches ?
§ x 4inches = 20 + 1 = 21 inches
since 4" = 10m. and
1" = 025; multiply
5 x 10m. = 504.025 = 525m.
Problem Exes
Using the foregoing simple guide, convert the following num-
bers from inches to meters or vise versa.
Inches _to__Meters | “Meters _to._Inches
66 2.42
99 3.35
413 427
178 4.88
233 5.19
1-4 CONCRETE PROPORTION
Proportioning concrete mixture is done in two different ways:
by weight or by volume method. The most common and con-
venient way is by the volume method using the empty plastic
bag of cement, or by a measuring box for sand and gravel as
7SIMPLIFIED CONSTRUCTION ESTIMATE
ction 1-3. Measuring the aggregates and water |
welnt IB sometimes used n'a eonereto batching plant for
ready-mix concrete or as specified in the plan.
~
00m
rs
=
~o
=
PURE 1-4 MEASURING BOX
TABLE 12 CONGRETE PROPORTION
Moaure Cenertingay | Sand | Grval
Gass | Proporin [H0KG | Soke] cum | cum
9
| zo | os | oo | 4
iE ia | So | ro | im | te
8 [iakis| rs | ao | & | to
¢ |i: :6| 60 | so |
iioning concrete by volume method had long been
practiced in almost al ypes of concrete sonstucon. Tine has
proven it to be effective and successful. However, on construc;
tion where space for materials stock piling and mixing does n
permit, ready-mixed concrete is the most practical solution.
interest of sand
{tis interesting to note in Table 1-2 that the volume
and gravel for all lasses of mixture is constant at 50 and 1.0
cubic meter respectively. It is rue, on the assumption that
cement paste enters the void of the sand and at the same ins-
CONCRETE
tance, the composition of these two materials fil the voids of the
gravel and thereafter, form a solid mass called concrete equiva-
lent to one cubic meter.
Based on actual concreting work, one cubic meter of gravel
Plus one-half cubic meter sand mixed with cement and water
will obtain a litle bit more than one cubic meter solid concrete,
The small excess over one cubic meter will be considered as
contingency.
Comment :
{In actual concreting and masonry work, there are several
factors that might affect the accuracy of the estimate. Some of
which are enumerated as follows:
1. Inaccurate volume of delivered aggregates which is very
common. Delivery truck should be measured to check if -
the volume of aggregates being delivered is exactly as or-
dered,
2,. Dumping of aggregates on uneven ground surface and
‘grass areas reduces the net volume of aggregates.
3. Improper measuring of the aggregates during the mixing
operation. This is common practice when the work is on its
‘momentum where laborers fails to observe the right meas-
turing of aggregates being delivered to the mixer.
4, The cement and fine aggregate for grouting concrete
Joints are mostly overlooked in the estimating processes,
5. Cement waste due to reckless handling and hauling,
6. The pure cement powder used by mason in plastering op-
erations to prevent the plaster from sliding downward is,
Not considered in estimating,
7. Pilferage of materials. This could be avoided with an effec-
tive system of construction management.SIMPLIFIED CONSTRUCTION ESTIMATE
Ordering of Coarse Aggregate must be Specific as tot
a. Kind of gravel, either crushed stone or natural gravel from
the creek.
b. The minimum and maximum size of the stone must be
specified. It should be free from mixed sand because
‘sand is cheaper than gravel.
c., Natural gravel from the creek requires screening to obtain
a well-graded coarse aggregate. Take note that soreening
of aggregates means additional cost of labor and reduc
tion in the net usable volume of gravel.
1-5 CONCRETE SLAB
The discussions from cement to concrete proportions plus
the Tables as presented could be more meaningful and appre~
ciated if accompanied by illustrations of actual applications.
ILLUSTRATION 1-1
‘A proposed concrete pavement has a general dimension of
40 om. thick, 3,00 meters wide and 5.00 meters long. Determine
the quantity of cement in bags, sand and gravel in cubic meters
required using class "C* mixture.
cS
FIGURE 12 CONCRETE PAVEMENT
CONCRETE
SOLUTION
1. Determine the volume of the proposed concrete pave-
ment.
Volume = Thickness x Width x Length
V = 10 x 9.00 x 5,00
V = 1.5 cubic meters
2, Refer to Table 1-2. Using 40 kg. cement class © mix-
; Multiply the volume by the corresponding values:
6.0 = 9.0 bags
50 = .75 cu. m.
xx
3, Take note that the computation is for a 40 kg. cement.
‘Suppose there is no 40 kilograms cement and what is
lable are 50 kilograms per bag. How many bags will
be ordered using the later?
SOLUTION - 2 ( Using a 50 kg. Cement)
1. Knowing the volunte to be 1.5 cubic meters, refer again
to Table 1-2. Under 50 kg. cement, using class “C* mix.
ture; muttiply the volume by the corresponding values,
Cement: 1.5 x 5.0 = 7.5 bags
Sand: 1.5 x 50 = .75cu.m.
Gravel: 1.5 x 1.0 = 1.5cu.m.
ILLUSTRATION 1-2
A rural road 6.00 meters wide after base preparation re-
‘quires concreting of one kilometer long. Find the number of
bags cement, sand and gravel required using class “A” concrete
ifthe slab is 6 inches thick.
"‘SIMPLIFIED CONSTRUCTION ESTIMATE,
° [or
Tenet
Scop
FIGURE 13 CONCRETE ROAD
SOLUTION
1. Solve for the volume of concrete pavement, convert 6
inches to meter = .15 m. (see table 1-1)
V = Thickness x Width x Length
V.= 45 x 6.00 x 1,000 m.
V = 900 cubic meters
2. Refer to Table 1-2. Using 40 kg. cement, multiply the vo-
ume by the corresponding values:
Comat: 900 x 9.0 = 8,100 bags
Sand: 900 x 50 = [Link].m.
Gravel: 909 x 1.0 = 900cu.m.
3. Ifthere is no available 40 kg. cement, a 50 kg. cernent will
require:
‘Cement: 900 x 7.0 = 6,300 bags
Sand: 900 x .50 = [Link]. m.
Gravel: 900 x 1.0 = 900 cu. m.
Take note that the thickness was first converted from
inches to meters using the approximate values in Tabie 1-1.
12
CONCRETE
ILLUSTRATION 1-3
‘Annational highway project as shown in Figure 1-4 specify 25
‘centimeters thick concrete. Find the number of bags cement,
‘sand [Link] required using class “A* mixture.
mE ee 7s
1,000 m.
PLAN,
FIGURE 1-4 CONCRETE ROAD
SOLUTION
1. Find the volume of the concrete slab;
V'= Thickness x Width x Length
V = .25 x 7.20 x 1,000 meters
V = 1,800 cubic meters
2. Refer to Table 1-2. Using 40 kg. cement class A mixture,
‘multiply the volume by the corresponding values:
Cement: 1,800 x 9.0 = 18,200 bags
Sand: 1,800 x 50 = 900 cu. m,
Gravel: 1,800 x 1.0 = 1,[Link], m,
3. If S0kg, cement will be use, we need:
Cement: 1,800 x 7,0 » 12,600 bags
‘Sand and Gravel same as in step 2.
ILLUSTRATION 1-4
‘The ground floor of a residential house has an area of 200
‘square meters. The plan specify 4 inches thick concrete floor on
fill using class C concrete. List down the materials required,
13SIMPLIFIED CONSTRUCTION ESTIMATE
10.00m.
FIGURE 15 FLOOR PLAN
SOLUTION
1. Find the volume of the floor slab. Convert 4 inches to
meter = 10m, and then multiply:
200 x .10 = 20 cubic meters
2. Refer to Table 1-2 under 40 kg. cement along class C
mixture, multiply:
Cement: 20 x 6.0 = 120 bags
k 20 x .60 = 10 cu. m.
Gravel: 20 x 1.0 = 20cu.m.
Problem Exercise
1. Acconcrete road 15 meters wide, § kilometers long, is de-
signed with a thickness as shown in the following cross seo-
tion, Specifying class “A” concrete, determine the quantity
of 40 kg. cement, sand and gravel required. If there is no
available 40 kg. cement, how many bags at 50 kg. would be
needed instead?
e e
s
Bal iv
1500 m,
FIGURE 15 CROSS SECTION OF THE ROAD
CONCRETE
2, From the following figure, solve for cement, sand and gravel
using class B concrete if the floor is § inches thick.
FIGURE 1-7 FLOOR PLAN
1-6 ESTIMATING CONCRETE SLAB BY THE
AREA METHOD
Estimating concrete slab by the “Area Method” is much eas-
jer than the Volume Method as explained in Sec. 1-5. However,
this could: be done with the aid of Table 1-3 which readily offer
the quantity of cement, sand and gravel per square meter de-
pending upon the required thickness of the slab.
‘TABLE 1.3 QUANTITY OF CEMENT, SAND AND GRAVEL FOR SLAB.
'AND WALLS PER SQUARE METER AREA
Modure Class =
Sib
Thick [40 Kg. Cement 50 kg. Cement Sond’ | Gravel
ess T
om | a [se feo [a c [cum|cum
so | 459 | 375 | 200] 250 |. 280. | 0280
7s | 675 | ‘563 | 450] ‘505 37s | (0375
10.0 | ‘s00 | 750 | 600} 700
125 | 1125 | 938 | 750] 975
450 | 1.350 | 1.125 | ‘900 | 1.050
a7s_| 1575 | 1313 | 1950 | 1.225] 1.050
200 | 11800 | 1500 | 1-200 | 1.400] 1200 | 1.00 | -1000
225 | 2030 | 1688 | 1.350 | 1575] 1350 | 1425 | 1125
250 | 2250 | 1875 | 1500 | 1.750| 1500 | 1.250 | ‘+250
278, | 2475 | 2063 | 1.950 | 11925] 1650 | 1375 | 1380
300° | 2700 | 2250 | 1.800 | 2100| 1.800 | 1.500 | ‘+500
(0500
(0750.
e888 |°
a
subeagaes®
6
3SIMPLIFIED CONSTRUCTION ESTIMATE. CONCRETE
3. Again, comparing the result with that of illustration 1-2 the
ILLUSTRATION 1-5 answers are pracoaly the same: Thus, solving the quan
SF a tity of coment, sanci and gravel for concrete pavement
gon a tte erobtern net panel hate 2 by nei Aree ‘and walls can’be done by the Volume Method and the
‘Area Method. The choice is yours.
Solution for Illustration 1-1
ILLUSTRATION 1-6
1. Solve for the pavement area.
‘A concrete wall, 3 inches thick with general dimensions of
‘Area = Width x Length 3.00 meters high by 7.00 meters long specify class “B" mixture.
A= 3.00 x 5.0m. Find the number of 40 kg. cement, sand and gravel required
A= 15sq.m.
2. Refer to Table 1-3. Along 10 cm. slab thickness under 40
kg. cement class °C" mixture, multiply:
Cement: 15 x .600 = 9.0 bags
Sand: 15 x .050 = .75 cu. m.
Gravel: 15 x .100 = 1.5 cu. m,
3. Compare this quantity to that of illustration 1-1, the results PE ONSET Sone
are the same. SOLUTION
Solution for Mustration 1-2 1, Convert 3 inches to centimeters.= 7.5 (see Table 1-1)
1. Find the area of the concrete road pavement; 22); Fingltne Aree of the,yran
ate ‘Area = Height x Length
A pete ‘A = 3.00 x 7.00m. = 21.59. m.
‘A = 6.00 x 1,000 meters
A= 6,000 sq.m. 3, Refer to Table 1-3. Under slab thickness 7.5 cm. 40 kg.
‘cement class B mixture we obtain the number .563,
2. Refer to Table 1-3. Using class"
thick concrete slab, multiply:
Cement: 6,800 x 1.350 = 8,100 bags
sonate 18.15 Fn. 4. Likewise, under column sand and gravel of Table 1-3 we
obtain .0375 and .075 respectively.
5. Multiply the Area by each of these numbers to get the
‘quantity of cement, sand and gravel respectively.
16 m‘SIMPLIFIED CONSTRUCTION ESTIMATE CONCRETE
Cement: 21 x 663 = 11.82 say 12 bags i?
Sand: 21 x .0375 = .79cu. m. 1-7 SQUARE CONCRETE COLUMN
Gravel: 21x 075 = 1.87 cu.m. sae oun een ce oy
umn can also be done In two simple ways:
erable eases 4. By Volume Method and
1. By the Area Method, determine the quantity of cement, 2, By Linear Meter Method.
ssand and gravel of the proposed concrete parking area 6
inches thick with a general dimensions of 160 x 120 me- iLbostaateice?
ters using class "A" mixture,
‘A reinforced concrete square column is 5.00 meters long
with @ cross sectional dimensions of 16 by 16 inches. Deter-
mine the quantity of cement, sand and gravel using class A
‘concrete,
16
FIGURE 1.9 FLOOR PLAN OF PARKING AREA
16
2. By the Volume and Area Method, find the quantity of ce-
‘ment, sand and gravel of the concrete pavement 4” thick
as shown in Figure 1-10 using class “B" concrete.
FIGURE 111 SQUARE COLUMN
2.00 "
800m. SOLUTION :
at A. By Volume Method
000) Pre LS 1. Convert first all measurements from inches to meter. 16
inches = .40 meter ( See Table 1-1)
; 2. Solve for the cross sectional area of the column,
; 11.00 Area: 40 x AO = .16 sq.m.
FIGURE 1.10 CONCRETE PAVEMENT PLAN i 3. Find the volume of the column.
18 19SIMPLIFIED CONSTRUCTION ESTIMATE
V = 16 x 5.00 meters
V = .80 cum.
4, Refer to Table 1-2, using 40 kg. cement class
crete, multiply:
Cement: .80 x 9.0 = 7.2say 8 bags
Sand; .80 x .50 = 0.4 say 0.5 cu. m.
Gravel: .80 x 1.0 = 0.8 say 1.0 cu. m.
ILLUSTRATION 1-8
‘A concrete column is 7.00 meters high with a cross sec-
tional dimensions of 20 by 20 inches. Determine the quantity of
‘cement sand and gravel content of the column if there are 8
‘columns in the row using class “A* conicrete.
‘CROSS SECTION XX
FIGURE 1-12 CONCRETE COLUMN
CONCRETE
SOLUTION
1. Convert all dimensions from inches to meters. (Refer to
Table 1-1, use approximate values).
2. Solve for the volume of one square column.
V = 50 x 50 x 7.00
V = 1.75 cu. m,
3. Find the volume of the 8 columns,
Ve 175x8
V = 14 cubic meters
4. Refer to Table 1-2. Using a 40 kg. cement class “A* mix-
ture, multiply
Cement: 14 x 9.0 = 126 bags
Sand: 14 x 50 = 7.0 cu.m.
Gravel: 14 x 1.0 = [Link]. m,
1-8 ESTIMATING SQUARE CONCRETE
COLUMN BY LINEAR METER METHOD
Another way of estimating the quantity of materials for con-
crete column is by the Linear Meter Method.
Under this method, the length of the column is first deter-
mined. With the aid of Table 1-4, the materials required are
found by multiplying the length by the corresponding values of
‘cement, sand and gravel given in Table 1-4,
aSIMPLIFIED CONSTRUCTION ESTIMATE
ILLUSTRATION 1-9
Solving the problem of |ilustration 1-8 Figure 1-12 where
there are 8 columns at 7.00 mé:ars high each, we have:
SOLUTION
1. Find the total length of the 8 columns
‘8 column x 7.00 m. = 66.00 meters
2. Referto Table 1-4. Along 60x 50 cm, column, using
‘40 kg. cement class “A” concrete, multiply:
‘Cement : 58.00 x 2.250 = 126 bags
‘Sand: 56.00 x .125 = 7.0 cu.m.
Gravel: 56.00 x .260 = [Link]. m.
3. Comparing the results to that of iilustration 1-7, the an-
swers are the same.
Problem Exe
4. From the following figure, solve for thé quantity of ce-
‘ment, sand and gravel by the Volume Method using (2)
class “A” concrete; (b) Class B conerete,
CROSS SECTION FIGURE 1-13 CROSS SECTION
@.) 6 COLUMN [Link] b) 8 COLUMNS AT 16M. HIGH
CONCRETE
‘TABLE 1-4 QUANTITY OF CEMENT, SAND AND GRAVEL FOR POST
"BEAM AND GIRDER PER METER LENGTH
Size Mixture Ciags Sand | Gravet
A] By] AT 8 | cum | um
18x20 ao | z5| 210] 180] or | cao
18x25 3 | 281 | 263] 225] ‘ore | 038
45x30 | 405 | 338] 318] 270] 023 | 045
18x35 | (473 | 304 | 360] (315 | 028 | ‘053
35x40 | ‘540 | 450 | 420] 360] 030 | ‘060
20x20 | 260} 200| 280) 240} 020 | 040
20x25 | 450] 375 | 350] 300] 025 | 050
20x30 | S40} 480 | 420] 360] 030 | 060
20x35 | 630] 525 | 490] 420] 035 | 070
zox40 | 720] .00| sco} 480] 040 | 080
25x25 | sea} soo] 43a] 275] 031 | 069
25x30 | (675 | 563) ‘525| 450] 038 | 075
25x35 | 7e8} 656) 613| 525| 044 | ose
25x40 | ‘900| 750) 700] 600} 050 | 100
25x45 | 1013] ea4| 7e8| 575] (058 | 113,
25x50 | 1125] 998 | e75| 750) 053 | (125
soxso | sro} 675 | 520] 540} 048 | 000
goxas | ‘9s | 783 | 735] 620] 053 | 105
30x40 | 1080} 900] e40| 720) 060 | ‘120
20x45 | 1125] 1013] 945] ‘8t0| 08 | 138
30x80 | 1.350 | 1.425 | 1.050] 900] (078 | (150
3x35 | 1103] 10] e568 |° 795] 06: | 123
35x40 | 1260 | 1050 | 960] 840] ‘970 | 140
35x45 | 1418 | 181 | 1.103] 9451 079 | 158
5x50 | 1575 | 1313 | 1.225] 1.050] 088 | 175
38x85 | 11890 | 1575 | 1.470| 1260] 105 | 210
40x40 | 1.440 | 1200 | 1.120] 960} 080 | 160
40x45 | 11620 | 1350 | 1.260] 1080} 090 | 120
40x50 | 1.800 | 1500 | 1.400] 1.200] 100 | 200
40x55 | 1.980 | 1650 | 1.540] 1.320] ‘110 | 220
oxo | 2160] 1800 | 1.680] 1.440] 120 | 240
45x45 | 1923] 1510 | 1.418] 1215] tor | 208
45x50 | 2025 | 1688 | 1575] 1350] 113 | 226
45x55 | 2228 | 1.956 | 1.733| 1495] 124 | 248
45x60 | 2430 | 2025 | 1.890] 1620] 135 | 270
23SIMPLIFIED CONSTRUCTION ESTIMATE. CONCRETE
1-9 POST AND FOOTING
Structurally, post is always supported by slab called footing
or foundation. Estimating the quantity of materials for these
types of structures could be done by:
4, The Volume Method or
2. The Area and Linear Meter Method combined for
Post and footing.
s0xs0 | 2250] 1.875} 1.750] 1.600] 125
50x55 | 2475 | 2083 | 1.9925) 1.650 “138
50x60 | 2700] 2250} 2100) 1.800] ‘160
ssxe0 | 2970| 2475) 2310] 1.980| 165
55x70 | 3485 | 2088, 608] 2310| ‘16
55x80 | 3960 | 3200 | s080) 2640] 220
55x00 | 4455| 3713 | 3405] 2970] ‘248
85x10 | 4950] 4125 | 3850 3300] 275
60x60 | 3240 | 2700} 2520) 2160] 100
60x70 | 3780 | 3150] 2940] 2520] ‘210
60x80 | 4320) 3800 | 3360] 2880] 240
60x80 | 4860 | 4050 | 3780] 3.240] 270
60x 100 | 5.400} 4500 | 4200] 3600] “300
ILLUSTRATION 1-10
‘A concrete post 4.00 meters high with cross sectional di-
‘mensions of 40 cm. x 40 cm. is supported by a footing slab 20
‘cm. thick by 1.20 m. square. Using class "A" concrete, find the
quantity of cement, sand and gravel if there are 12 posts of the
5x60 | 2510 | 2925 | 2730] 2340] 195
6x70 | 4095 | 3413 | 3185] 2730| ‘ze
5x80 | 4680 | 3900] 3640] 3120] 260
5x90 | 5265 | 4388 | 4095] 3510| ‘203
65x 100 | 5.850! 4875 | 4550] 3200] 325
70x70 | 4410 | 3675 | 3.430) 2040] 245
7oxa0 | 5040 | 4200] 3920| 3360] 200
70x90 | 5670) 4725 | 4.410] 3780| 315
3883 BESRE BEERS BREE BSE
roxi00 | 6300 | 5260 | 4200| 4200| 350 He=A0m
7x70 | 4725 | 3958 | 675] 3150] 253] 25 120m,
75x80 | 5400 | 4500 | 4200] 3000) 300 | 720
75x90 | cars| S0s3 | 4725| 4050 | ss8| es
75x10 | 6750 8625 | 5250] 4500| ‘37s | 760
80x80 | 5760| 4900} 4480) 3240] 20] 640 ELEVATION
20x90 | 6480 | 5400 | S040| 4320| 360) 720
eox100 | 7950 | 6375 | ses0| s.100| sos | +050
FIGURE 1-14 POST AND FOOTING
s5x20 | s120| 5100} 4760] 4080| 340] 500
85x50 | cass| s7se | sass) 4s80| S05] tee
e5x100 | 7950] 6375 | 5050 8100) 425 | 0 SOLUTION
2x80 | 7290] 607s | se70| 4860| 405 ‘210 ecxe Meth
soxi00 | 8100] 6750 | 6300] s400| aso | ‘S00 fh) oan ene Mead,
95x90 | 7605] e419 | 5005] 5130) 420 | 255 1. Find the volume ofthe 12 posts
25x00. | ass0| 7125| s650| 5700) 475 | 980
100x100 | “800 | 7500 | 7.000| 6.000 | _‘s00'| 1.000 Volume = Sectional area x Height x No. of post
24 2SIMPLIFIED CONSTRUCTION ESTIMATE,
Volume = 12 posts x (.40 x .40) x 4,00 m. nt.
V_ = 7.68 cubic meters
Solve for the volume of 12 footing slab
a
V = 12(.20x1.20x1.20)
V = 3.456 cubic meters
Find the total volume. Add 1 and 2
Total Volume = 7.68 + 3.456
V = 11.136 cu. m
Refer to Table 1-2. Using 40 kg. cement class
concrete, multiply :
Cement: 11.136 x 9.0 = 100.2 bags
Sand: 11.136 x 50 = 5.56 cu. m.
Gravel: 11.136 x 1.0 = 11.136 cu. m.
B. Solution by the Linear Meter and Area Method
1
Find the total length of 12 posts
L
L
42 posts x 4.00 m. ht.
48 meters
Refer to Table 1-4. Along the 40 x 40 cm. column size
class "A" mixture; multiply.
Cement: 48 x 1.440 = 69.12 bags
Sand: 48 x .080 = [Link]. m.
Gravel: 48 x .160 = 7.68 cu. m.
Find the area of the footing slab,
Area = 12 pos. (1.2 x12)
= 17.28 sq.m.
CONCRETE
4, Refer to Table 1-3, using 40 kg. cement class “A” mix:
ture for 20 cm. thick stab; multiply:
Cement: 17.28 x 1.80 = 31.1 bags
Sand: 17.28 x 100 = 1.72cu.m
Gravel: 17.28 x .200 = 3.46 cu.m.
5. Add results of step 2 and step 4.
Cement: 69.12 + 31.1 = 100.2 bags
Sand: 3.84 + 1.72 = 5.56 cu.m.
Gravel: 7.68 + 3.45 = 11.13 cu. m,
ILLUSTRATION 1-11
From Figure 1-15, determine the number of 40 kg. cement,
‘sand and a gravel required using class “A concrete for the foot-
ing and class *C* concrete for the flooring 4” thick.
20
490m.
# floor 7
‘concrete for sab |3.00m,
Pp |90
45
0
PLAN ELEVATION
FIGURE 1-15.
SOLUTION
A. Footing Slab
4. Solve forthe volume of F
Volume = .15 x .80x.80 = ,096 cu. m.
2. Total volume of 4 pieces footing slabSIMPLIFIED CONSTRUCTION ESTIMATE,
V = 096 x 4 f001INgS ose seene 0.384
B. Pedestal
1. Solve for the volume of P
30.x.30 x90
1081 cu. m. x 4 pieces... 0.324
Total volume........0.708 ou. m.
2.. Refer to Table 1-2. Using 40 kg. cement class "A" con-
crete; multiply:
708 x 9.0 = 6.37 bags
708 x .50 = .354 cum.
Gravel: .708 x 1.0 = .708 cu. m.
C. Concrete Floor Slab
1. Solve for the volume of concrete floor slab.
Volume = .10 x 3.00 x 4.00
V= 1.2cu.m.
2. Refer to Table 1-2. Using 40 kg. cement class °C” con-
crete; mi
3. Summary of the materials B and C.
Cement: 6.37 + 7.2 = 13.57 say 14 bags
354 +06 = .95cu.m.
Gravel: 708 + 1.2 = 1.90cu. m.
Comment:
To a meticulous estimator, the area occupied by the posts,
will be subtracted from the gross area of the floor although the
result is an insignificant amount.
28
CONCRETE
1-10 RECTANGULAR COLUMN
‘The procedure in estimating rectangular column is practically
the saine as that of the square column. It-could be either by. ”
volume method or by the linear meter method as previously
explained. The choice of the method however, depends upon
the convenience and preference of the estimator.
ILLUSTRATION 1-12
A series of 8 rectangular concrete columns with typical
cross sectional dimensions of 40 x 60 cm. is supporting a beam.
‘The column has a clear height of 8.00 meters from the floor line
to the bottom line of the beam. Specifying class *A* concrete,
determine the quantity of cement sand and gravel required,
FIGURE 1-18 RECTANGULAR COLUMN,
SOLUTION (By Linear Meter Method)
1. , Find the total length of the 8 columns,
Length: 8.00 x 5.00 m. = 40 meters
20‘SIMPLIFIED CONSTRUCTION ESTIMATE
2. Refer to Table 1-4. Along the 40 x 60 om. column size
under 40 kg. cement class “A” concrete, multiply:
Cement: 40 x 2.16 = 86.4 bags
‘Sand > 40 x .120 = 4.8 cu. m.
Gravel: 40 x .240 = 9.6 cu. m.
SOLUTION (By Volume Method )
4, Find the volume of the eight columns:
* v= 40x.60 x 5.00ht. x 8
V = 9.6 cubic meters
2. Refer to Table 1-2. Using 40 kg. cement class
crete, multiply:
Cement: 9.6 x 9.0 = 86.4 bags
Sand: 9.6 x 60 = 48cu.m.
el: 9.6 x 1.0 = [Link].m.
*
Comparing the result of the two methods, the answers are
‘the same. As to which method to use is now your choice.
Plastering
Ifthe post will be plastered with class “A” mortar mixture, the
solution will be as follows:
4. Find the total surface area of the 8 columns.
Perimeter = 2 (40) +2 (.60)
P = 2.00m.
2. Solve for the surface area of the 8 columns.
‘Area = Px height x Number of posts
‘A = 2.00 x 5.00 x 8
A = 8089. m.
30
CONCRETE
3. Find the volunre of the plaster at 12 mm thick.
V = Area x thickness of the plaster
V = 80 x 012m. = .96 cu. m.
4. Refer to Table 2-1. Using 40 kg. cement class "A’ mix:
ture, multiply:
Cement: .96 x 18.0 = 17.2 bags
Fine Sand: .96 x 1.0°= .96 cu. m.
Plastering is a separate subject matter to be discussed
thoroughly in Chapter - 2.
1-11 RECTANGULAR BEAM AND GIRDER
‘ABeam is defined as a strong horizontal piece of reinforced
‘concrete for spanning and supporting weights. On the other
Fond. a beam that is carrying of supporting another beam is
Called girder. Similarly, estimating the materials for these types
Gf structures is etther by the volume or the linear meter methodSIMPLIFIED CONSTRUCTION ESTIMATE,
SLLUSTRATION 1-13
From Figure 1-17, using class “A” concrete, list down the
materials required.
SOLUTION (By Volume Method)
1. Find the volume of the beam
Volume = 5 pes. x .25x.40 x 8.00 m. span
V = 4cubic meters
2. Solve for the volume of the girder
Volume = 2 pes. x .40 x .60 x 16.00 m. span
V = 7.68 cu. m.
3, Total volume of beam and girder
Total V = 4+ 7.68
V = 11,68 cu. m.
4. Refer to Table 1-2. Using 40 kg. cement class “A” con-
crete; muitiply:
Cement: 11.68 x 9.0 = 105.12 bags
Sand: 11.68 x .50 = 5.84 cu. m.
Gravel: 11.68 x 1.0 = 11.68 cu. m
SOLUTION (By The Linear Meter Method )
1. Find the total length of the Beam
5 pes. x 800m. = 40 meters
2. Refer to Table 1-4. Along column size 25 x 40 om. under
40 kg. class A concrete, multiply:
Cement: 40 m.x.900 = 36 bags
Sand: 40m. x .050 = 2cu.m.
Gravel: 40m. x.100 = 4cu.m.
32
CONCRETE
3. Find the total length of the Girder
16m. x 2 pes. = 32 meters
4. Refer to Table 1-4 along column size 40 x 60 under
‘column 40 kg class A mixture, muttiply:
Cement: 32 x 2.160 = 69.12 bags
Sand: 32x 120 = 3.84 cu. m.
Gravel: 32x 240 = 7.68 cu. m.
5. Summarized results of 2 and 4.
Cement: 36 + 69.12 = 105.12 say 106 bags
Sand: 2+ 3.84 = 5.84 cu.m.
Gravel: 4+ 7.68 = 11.68cu.m.
1-12 CIRCULAR COLUMN
Estimating the materials for circular column is typically the
‘same as the volume method for the square and rectangular col-
umns with the aid of Table 1-2. However, Table 1-5 was also
prepared for circular column problems to avail of the linear me-
ter method of estimating
ILLUSTRATION 1-14
AA circular concrete column has a diameter of 60 cm. by 6,00
meters high. Find the concrete materials required if there are 5
columns of the same size in a row,
SOLUTION -~ 1 ( By the Volume Method )
41. Solve for the cross sectional area of the column,
A= Tr? or A = 0,7854xd? (Formula)
0.7854 x 607) = .283 sq.m.
: N 33{| SIMPLIFIED CONSTRUCTION ESTIMATE
ELEVATION SECTION AA
FIGURE 1-18 CIRCULAR COLUMN
2. Find the volume of one column.
V = 283 x 6m. ht. = 1,698 cu. m.
3. Solve for the volume of 5 columns.
Total volume: (1.698 x5) = 8.49 cu. m.
‘TABLE 1-6 QUANTITY OF CEMENT, SAND AND GRAVEL PER METER.
LENGTH OF CIRCULAR COLUMN
MIXTURE CLASS
cot | 40g. coment 50 kg, cement Sand | Gravet
Dia,
om [| A B A 8 foum|oum
| 2 | 42 | 368 | see 295 | 1025 | 050
30 530 | 495 424 | 035 | 070
lt 35 | ‘ses | 722 | 73 S77 | 048 | 096
4 | 1131 | ‘942 | 880 754 | 063 | 126
so | 1767 | 1473 | 1374 | 1178 | 0968 | 106
86 | 2198 | 1782 | 1663 | 1425 | 119 | 238
! eo | 2545 | 2121 | 1970 | 1696 | 141 | 262
i 65 | 2986 | 2498 | 2923 | 1991 | ‘168 | 332
! 70 | 3464 | 2886 | 2604 | 2300 | ‘182 | ‘e4
75 | as7e | 3313 | 3003 | 2651 | zat | 442
0 | 4524 | 3770 | aste | sore | 251 | ‘soa
85 | 107 | 4256 | s972 | 3405 | 254 | 508
90 | 5726 | 4771 | 4453 | 3at7 | 318
100 | 7.069 | 5800 | sass | 4712 | 200 | 706
34
CONCRETE
4. Refer to Table 1:2. Using 40 kg. cement class “AY con-
crete; multiply:
Cement: 8.49 x 9.0.= 76.4 bags
Sand: 8.49 x .50 = 4.24 cu. m.
Gravel: 8.49 x 1.0 = [Link]. m.
SOLUTION - 2 ( By Linear Meter Method )
1. Determine the total length ofthe § circular columns.
L = (5 x 6.00mht) = 30,00 meters
2. Refer to Table 1-5. Along the 60 cm. column diameter
under 40 kg. cement, class “A” mixture, multiply:
Cement: 30.00 x 2.545 = 76.4 bags
Sand: 30.00 x .141 = 4.23cu.m.
Gravel: 30.00 x .282 = 8.46 cu. m.
Problem Exercise
1. From the following figure, List down the concrete materials
by any method using class “A” concrete.
a
la.00m.
ae | 26 4
20m. 7
Ea o
PLAN ELEVATION
FIGURE 1-19 POST AND FOOTING‘SIMPLIFIED CONSTRUCTION ESTIMATE.
From the following figures, solve for the concrete materials
of slab, beams and girders using class “A* concrete.
(Cross Section of Beam Cross Section of Girer
CONCRETE
3. From the following figure, find the concrete materials re-
quired for the columns 9.00 meters high each using class A
concrete,
10 pos. Hexagonal Column
FIGURE 1.22
4. From the following Figure 1-23, find the cement, sand and
gravel if there are 8 columns, using class “A” mixture,
PLAN ELEVATION.
FIGURE 1-2 CROSS SECTION OF ELIPTICAL COLUMN,
5. A building design has spiral reinforced concrete column 9
meters high with a general cross sectional diameter of 45
inches. Determine the required materials by the volume
‘method and the linear meter method using class A concrete |
if there are 6 columns in the plan.
1-13 CONCRETE PIPE
Concrete pipe is much in demand for smell and medium
drainage construction. The use of concrete pipe as drainage
structure materially save cost of forms, time and labor costs as
well
37‘SIMPLIFIED CONSTRUCTION ESTIMATE,
Procedures in Estimating the Materials for Concrete Pipe.
1. Find the net volume of the concrete pipe. That is, by sub-
tracting the volume occupied by the hole from the gross volume
of the pipe.
2. Knowing the net volume of the concrete, [Link] Table 1-
2, under 40 kg. cement and class of mixture specified, multiply
by the net volume found for cement, sand and gravel or
3, Use Table 1-6 for final result
Tongue
d
1,00 Meter Pipe
Where: D = Diameter of the Pipe
d= diameter of the pipe hole
L_= Length of the pipe 1.00 m.
FIGURE 1.24 CONCRETE PIPE
ILLUSTRATION 1-15
‘A road construction requires 12 pieces of 90 cm. diameter
concrete pipes for drainage purposes. Determine the quantity of
‘cement, sand and gravel needed to manufacture said pipes
using class “A” concrete. (excluding reinforcement which will be
discussed later in chapter 3).
SOLUTION (By Volume Method )
1, Solve for the gross volume of the concrete pipe.
CONCRETE
Formula: . Volume = 0.7854D7h Formula
V = 0.7854 x 1.10? x 1.00m.
V = .950 cu. m,
90 cm, Diameter Concrete Pipe
FGURE 1.25 CONCRETE PIPE
2. Solve for the volume of the hole.
V = 0.7854 x d?h
V = (0.7854 x .907 x 1.00 length) = .636 cu. m.
3. Subtract result of step 2 from step 1 to get the net volume
‘of the conorete pipe.
Ve = 950-636 = 314
4. Total volume of the 12 pipes.
M = 314 x 12
Vi = 3.768 cubic meters
5, Refer to Table 1-2. Using 40 kg. cement class
crete; multiply:
Cement: 3.768 x 9.0 = 33.912 say 34 bags
Sand: 3.768 x .50 = 1.88 say 2.0 cu. m.
Gravel: 3.768 x 1.0 = 3.7 say 4.0cu.m.
30SIMPLIFIED CONSTRUCTION ESTIMATE
‘TABLE 1-6 QUANTITY OF CEMENT, SAND AND GRAVEL
PER CONCRETE PIPE.
Diameterin |__CEMENTINEAGS _
—Gentipeter ‘lass of eee
o | 4 a [enreecremn Ga
a8 | 52 wa | oo | oe
ead ea {95 163 ont ‘oz
els | 38 zm | om | car
alae 30s | 025 | 060
50} 40 635 530 038 ee
60 | 50 779 850 084 al
ge | 0 | 175 | 1483 | 98 | 106
go | 7 | 2200 | teas | 126 | 22
wo | oo | 258 | 215 | 14 | 2m
tio | 9 | 202 | 2955 | 157 | ste
420 | 100 3.110 2595 473 346
faa [120 | aaez | 3705 | 200 | 8
ia |io | S500 | 45e3 | 306 | e12
SOLUTION -2 (Per Pipe Using Table 1-6)
1
To say 90 centimeters concrete pipe, it refers to the hole
diameter. And for the purpose of estimating the volume
of concrete, we consider the inside diameter of the pipe
{35 presented in the second column d of Table 1-6.
Refer to Table 1-6. Under d = 90 pipe diameter, class
*A" mixture, multiply
Cement: 12 x 2.826 = 33.9 say 34 bags
Sand: 12 x 187 = 1.88 say 2.0cu.m,
Gravel: 12 x 314 = 3.77 say [Link].m.
MASONRY
-1 CONCRETE HOLLOW BLOCKS
Concrete Hollow Block is popularly known as CHB. It is
classified as load bearing and non-bearing blocks. Load bearing
blocks are those whose thickness ranges from 15 to 20 centi-
meters and are used to camry load aside from its own weight.
Non-bearing blocks on the other hand, are blocks intended
for walls, partitions, fences, dividers and the like carrying its
‘own weight whose thickness ranges from 7 to 10 centimeters,
FIGURE 2-1 CONCRETE HOLLOW BLOCK
The standard hollow blocks has three void cells and two half
cells at both ends having a total of four. These hollow cells vary
In sizes as there are different manufacturers using different
types of mold. Hence, itis recommended that concrete hollow
blocks with bigger cells. be considered in estimating for a more
realistic result.
In this study, what we want to know is the quantity of the ma-
terials needed for a certain masonry work made of concrete.
a‘SIMPLIFIED CONSTRUCTION ESTIMATE
hollow blo:! vhich generally comprises of the following items.
Concrete hollow blocks.
Cement and sand for block laying.
‘Gement, sand and gravel filer for the hollow core or cell.
Cement and fine sand for plastering
‘Cement sand and gravel for foundation or footing,
Reinforcing steel bars and
Tie wires.
NOREEN
Item 4 to 5 will be discussed in this chapter. The reinforcing
steel bars and Tie wires will be presented in Chapter 3 -Metal
Reinforcement.
Estimating the materials for masonry work using hollow
looks, could be done in either of the following methods:
ay Fundamental methods
By the Area methods
ILLUSTRATION 2-1
‘A concrete hollow block wall has a general dimension of
3.00 meters high by 4.00 meters long. Determine the number of
CHB, cement and sand required to construct the wall.
ELEVATION
ig" > CONCRETE HOLLOW BLOCKS WALL
2
MASONRY
SOLUTION - 1 (By Fundamental Method )
1. Divide the height of the fence by the height of one block.
3.00 = 15 layers
:20
2. Divide the length of the fence by the length of one block
4.00 = 10 pieces
40
3. Multiply the result of step 1 by step 2
15x10 = 150 pieces
SOLUTION -2 (By the Area Method )
Let us examine first how many pieces of ( cover
one square meter area. ee Spee He
Te
[3 Pe | 10m.
[4 fe]
pe tao i)
FIGURE 23 NUMBER OF CHB PER SQUARE METER
From the above figure it appears, that one
1 s r
sre reques 125 neces cone halon las Thora, by
iplying the entire area of the wall by 12.5, 0
number of CHB required. Thus, ie enrator
1, Area ofthe fence; 3.00 x 4.00m = 12sq.m.
2. Multiply: 12,00 sq.m. x 12.6 = 150 pieces.
a:D CONSTRUCTION ESTIMATE,
SIMPLIFIE oe
ILLUSTRATION 2-2
From the following Figure 2-4, find the number of 4” x 8° x
16" concrete hollow blocks to construct the fence,
2. If there are 12.5 blocks in one square meter then,
‘muttiply by the area.
156 x 12.5 = 1,950 pieces.
Comments
400m 1. Comparing the results obtained by the two methods, the
260m. answers are practically the same, but for convenience,
the solution by the area method is much favored for be-
ing simple and direct to the answer.
400m.
400m.
2. Take note that in the above example, we computed the
N
oe Soe ‘number of hollow blocks without posts, Suppose that
etree es oa Figure 2-4 was provided with the necessary posts as in-
dleated In Figure 2, in this case, the area covered by
: thod ost will be subtracted from the total area of the wail,
SOLUTION: By Baadamestal Hethod ) then solve for the CHB adopting the area method for
simplicity of the process.
1. Find the Perimeter of the Fence
P= 444412420420 = 60,00 meters. 20.00m. 20% 20 post |
2. Divide this perimeter by the length of one biock
26
60,00 = 150 pieces 1200 4a |
40
3. Divide the height of the wail by the height of one block. x [x
|
2.60 = 13 layers PLAN at
20 60
Section XX
4, Multiply 2 and 3: 150 x 13 = 1,950 pieces. nialine techn ienes
SOLUTION - 2 ( By the Area Method ) ILLUSTRATION 2-3
TS ay hecletesha dena be From Figure 2-5, using class B mixture find the nuniver of:
ARRON coe he Ea ME ater 8) 10x20 x 40 om. conerete hollow blocks
ae : 45‘SIMPLIFIED CONSTRUCTION ESTIMATE
b)_Gement and sand.
j ©) Concrete for the posts and footings.
SOLUTION ~1 (Finding the CHB )
} 1, Find the perimeter of the wei.
P= 20420+12+8
P = 60.00 meters
2. Find the space length occupied by the posts
‘Along 20m. (.20x6)2 = 2.40
‘Along 12m. (.20x4)2 = 1.60
j Total space occupied by posts = 4.00
3, Subtract: 60.00 m.~ 4,00 m.
= 56.00 m. net length for CHB:
5. Multiply by the height of fence to get the Net Area.
Net Area = 56.00 x 2.60 ht.
A'= 145.6 square meters
i 6. Multiply by 12.5 to get the total number of concrete hot
4 ow blocks required.
} 14566 x 12.5 = 1,820 pieces.
I 7. Comparing this result to that of illustration 2-2, with 1,950
I pieces hollow blocks, there is a material difference of 130
pieces because we subtracted the space occupied by the
concrete posts.
SOLUTION- 2 (Concrete Posts and its Footing )
1. Find the volume of one concrete footing slab.
46
‘MASONRY
Volume = Thickness x Width x Length
V = 15 x 60 x .60
V = .054 cu. m.
20m.x.20m.
fom.
260 r
a8 =
7) ey
ELEVATION PLAN
FIGURE 2-4 POST AND FOOTING
2. Find the volume of 16 footings
V'=(.084 x 16)= 964 cu. m.
3. Find the volume of 16 concrete posts
V = (.20 x .20 x 2.60 x 16) = 1.67 0u.m.
4. Total volume of concrete posts and its footing:
‘Add results of step [Link] 3: _
Vi; 864 + 1.67 = 253cu.m.
5. Refer to Table 1-2. Using class "B" concrete under co-
‘umn 40 kg. cement, multiply: i
Cement : 2.53 x 7.5 = 19.0 bags
Sand: 2.53'x .60 = [Link]. m.
Gravel: 2.53 x 1.0 = 2.53 cu. m.
* Note:
Concrete was thoroughly discussed in Chapter - 1
47SIMPLIFTED CONSTRUCTION ESTIMATE MASONRY
ILLUSTRATION 2-4 7. Find the CHB at Area C: S00 = 1250
From the following Figure, determine the number of 15 x 20 Peril
x 40 cm, CHB required to construct the building firewall 8. Height of C divided by height of one boot
190 = 950
20
{1.00
9. Multiply (7) and (8) 12.50 x 9.50 = 118.75 pieces
‘Add Total CHB for Area A, B and C.
170 + 603.75 + 118.75 = 893 pieces
Comment:
ELEVATION.
‘Take note that in the preceding example solution, fundamen-
tal methods of determining the number of blocks were used.
‘The methods had undergone a very long process of finding the
quantity by area one at a time. The process must be simplified
with the aid of Table 2-2, presented as follows:
FIGURE 27 16 CHB FIREWALL
SOLUTION ( By Direct Counting )
1. Find the CHB at AreaA: 4.00 = 10 pieces
AO
of one block
SOLUTION - 2 ( By the Area Method )
1. Find the Area of A: 3.40x4.00 = 13.60 sq. m.
2, Find the Area of B: 7.00x6.90 = 48.30 sq. m.
2. Height of wall A divided by he
3:40 = 17 pieces
20
3. Find the Area of C: 5.00% 1.90 = _9.50'sa, m.
3 a =1
Multiply: (1) and (2): 10x17 = 170 pieces meh Sel eos
4. Find the CHB at AreaB: 7,00 = 175 bs
40 4. Refero Table 2-2. Along 15 x 20 x 40 CHB under column
‘umber per square meter; multiply:
5. Average Height of Area B divided by .20 ht. of one block
71.40 x 12.50 = 893 pieces,
6.90 = 34.50
20
Reminder
Before estimating the quantity of concrete hollow blocks, be
. Multiply (4) and (6): 17.5 x 34.50 = 603.75 pieces
48 40SIMPLIFIED CONSTRUCTION ESTIMATE
‘sure to verify the plan specially the clear height of the wall
which is very Important in the process. The following questions
should be given due consideration for these might affect the
result of the estimate.
1
Does the elevation as indicated in the plan specify the
height from the first floor to the second floor line, or is it
from floor to ceiling? In either case, the depth of the
beam has to be considered in the estimate, either added
or subtracted
Have you considered the CHB to be installed from the
underground foundation to the floor line? This particular
portion of the wall is often overlook in the process of es-
timating especially when there is no detailed plan or
‘cross section detail. Don't ever commit the same mis-
take experienced by most estimators.
See to it that the concrete hollow blocks to be installed
are uniform in sizes and in thickness. Have it ordered
from one manufacturer or supplier only. Installing differ-
ent sizes of CHB means additional expenses for cement
plaster and labor. If several suppliers cannot be
avoided, have their respective blocks installed in a par-
ticular phase of work.
2-2: ESTIMATING CEMENT MORTAR
After knowing the number of blocks needed for a particular
masonry work, the next step is to find its work partner called
‘cement mortar. Cement mortar is a mixture of cement, sand
and water, It is used as bonding materials in installing masonry
blocks and other various plastering work. In estimating cement
‘mortar, one has to consider the following items.
a
b.
‘The mortar to be used in between the layer of CHB.
‘The mortar filler for the hollow core or cell of the blocks.
This filler could be pure mortar or mortar with gravel for
economy.
Fine screened sand for plastering.
MASONRY
ILLUSTRATION 2-5
_ Continuing the problem of Illustration 2-1 Figure 2-2, deter-
mine how many bags of cement and sand needed to install the
10 pieces 10 x 20 x 40 cm. CHB using class *B" mortar.
‘There are three solutions offered in finding the cement mortar
for cencrete hollow blocks installation.
4. By volume method.
2. By the Area Method.
3. Per Hundred Block method.
SOLUTION - 1 (By Volume Method )
1. Determine the volume of mortar in between the layer of
the blocks, adopting the 12 mm ( %') or .012 meters uni-
form thickness of the mortar.
Volume = Thickness x Width of CHB x Length
v
v
012 x .10 x 4.00 m.
(0048 cubic meter
2. Take note that 3.00 meters high wall divided by .20 m.
height of one block is = 15 layers. Thus, multiply
v
v
15 layers x .0048
072 cu. m.
This is the total volume of the mortar in between the 15
layers of concrete hollow blocks.
3. Aside from the cement mortar used in between block,
layers, there are 4 hollow cores or cells per block to be
filled up with mortar. Find the volume per block.
Volume = .05 x .075 x .20 x 4 cores
V = .003 cu. m.
51MASONRY
‘SIMPLIFIED CONSTRUCTION ESTIMATE Area: (3.00 x 4.00) = 42 square meters.
05m. 2. Refer to Table 2-2. Along 10 x 20 x 40 CHB under
Be Glass “B* mixture; multiply:
Cement : 12 x .522 = 6.26 bags
Sand : 12 x .0435 = .522 cu.m.
075m.
‘TABLE 22 QUANTITY OF CENENT AND SAND FOR CHB MORTAR
FIGURE 2-8 HOLLOW [Link] 48x 16 CHB PER SQUARE METER
4. Find the total volume of hollow core for the 150 CHB. Se iees
V = 150 x .003 = .45cu.m. paste Lebets oa eee te sel aioe
5. Total volume; add the results of step 2 and step 4 tox20x40 | 125 | 792 | .522 | 204 | .228 | o«ss
Total Volume: .072 + .45 = 522 cu. m. Se anit anid sea nee hee
20x20x40 | 125 |2.260 | 1.500 | 1.125 | 998 | 1250
6. Referto Table 2-1. Using class “B" mixture, multiply:
Cement: 522 x 12.0 = 6.26 bags SOLUTION - 3 ( By the Hundred Block Method )
Sand: 622 x 1.0 = 622
‘The Hundred Block Method is the third solution offered for a
‘TABLE 2-1 QUANTITY OF CEMENT AND SAND FOR MORTAR ‘more simpler approach with the aid of Table 2-3.
‘AND PLASTER IN CUBIC METER.
Class | Proportion | Cement inbage | Sana 41. Find the number of conorete hollow blocks,
eae some AOS Sec Area: 3.00x 4.00 = 12sq.m.
a [4:2 | 0 | ms | 10 42'sq. m. x 12.5 = 150 pieces CHB
B | 1:3 | 120 | 95 | to Ee
oo teal seo ros ts tg us
Oe Miaealaenad cee tadeant 2 Converttount of 100: 160 = 1.5
; 3. Refer to Table 2-3. Under class “B* mixture for a
Another way of finding the mortar for block laying is by the ;
‘Area Method with the aid of Table 2-2. 50x 40,.GH8 rumen
Cement: 1.5 x 4.176 = 6.26 bags
SOLUTION ~2 ( By the Arca Method ) Sand: 15 x 348 = .[Link].m.
1. Find the area of the wail.
62SIMPLIFIED CONSTRUCTION ESTIMATE
‘TABLE 2-3 QUANTITY OF CEMENT AND SAND PER ONE
NSCS ae
Cement in Bags 40 kg..
mines
seaetons [7s sant
10x20x40 | 6.336 | 4176 | 3.162 | 2624 | 0.248
16x 20x40 | 12.150 | 8.104 | 6.072 | 5.064 | 0675
20x20x40 | 18.072 | 12.000 | 9.000 | 7.604 | 4.000
Comment:
‘Comparing the answers of the three methods in finding the
materials for cement mortar, the results are practically the
same. The estimator now has the choice which method to use,
but before using Table 2-2 and 2-3, know first the kind of mix-
ture and the size of CHB to be used because this is where most.
errors are being committed,
ILLUSTRATION 2-6
Going back to the problem of llustration 2-2, Figure 2-4, find
the quantity of hollow blocks, cement and sand, for mortar using
the area method of estimating,
SOLUTION:
1. Find the area of the wall,
Area = Perimeter x Height
A = 60.00 m. x 2.60 m,
A = 158 square meters
2. Find the number of CHB. Refer to Table 2-2, under col
‘umn number per sq. m. multiply:
186 x 12.5 = 1,950 pieces
MASONRY
3. Find the cement and sand. Refer again to Table 2-2, us-
ing class B mortar; Multiply:
Cement: 156 x 522 = 81.43 say 82 bags
Sand: 156 x .0435 = 6.78 say 7 cu. m.
4, Summary of the materials:
1,950 pieces CHB
82 bags cement
7 cubic meters sand,
‘Take note that the above materials found does not include
the cement, sand and gravel for the footing. For this item, refer
to Chapter 1 where it was thoroughly discussed,
2-3 CEMENT MORTAR FOR PLASTERING
Aside from the cement mortar for block laying, plastering is
another item to consider. Most estimators however, make their
estimate of mortar for block laying and plastering through sim-
pple guessing and calculation, assuming the quantity of cement
{and sand without the pain of computation. The reason is simple,
they are justin a hurry and has no time to do it. And for this rea-
sons, we offer the following methods accompanied by a simpli-
fied tables of equivalent values.
Estimating the cement mortar for plastering oan be done by:
1. The Volume Method and
2. The Area Method
ILLUSTRATION 2-7
Continuing the problem of illustration 2-1, find the cement
land sand necessary to plaster two sides of the 3.00 x 4.00 me-
ters wall.