Final - TP Ridge
Final - TP Ridge
FOR
• Stretch length: 70 m.
• Description of strata.
• Project site accessibility: The site is accessible from the bottom and top of the slope.
2. SITE PHOTOGRAPHS
Figure 1: Overburden
3. PROBLEM DESCRIPTION
Design section
Based on the topographical survey of critical section, the design analysis was carried out.
Strata parameters
In-situ strata and properties: (Geotechnical Investigation report has been attached)
Table 1. Properties
Angle of
Sl.no. Strata Cohesion, c internal friction Unit Weight
(kPa) (degree)
1 Overburden / Debris 15 31 16
2 Weathered Rock 50 40 22
Considering the behavior of anchors, the anchor calculation must assume the unstable
portion of the slope lies in condition of limit equilibrium, where the safety factor is equal
to 1.05 in case of seismic condition and 1.30 in static condition
The analysis of nailed slope with Flexible fascia and Global stability for overall slope has
been carried out using slide of rock science which is a 2D slope stability program for
evaluating stability of circular or non-circular failure surfaces in soil or rock slopes.
External loading, groundwater and support can all be modeled in a variety of ways.
SLIDE analyzes the stability of slip surfaces using vertical slice limit equilibrium methods.
Individual slip surfaces can be analyzed, or search methods can be applied to locate the
critical slip surface for a given slope. Bishop simplified method (Circular slip circles
method) has been used here.
4.2.2 Design summary
The design Summary of factor of safety (FOS) achieved for both sets are shown in table
below:
Table 2: Summary of FOS achieved in SLIDE analysis
Sl. Seismic/Static Case Achieved
Slope Required FOS
No. FOS
1.05 (as per section 7.4 of WSDOT-
1.101
Seismic Case Geotechnical
1 (Safe)
Design Manual)
Slope with nails 1.3 (as per section 4.7 of IR HRB
Special report 15- Landslide correction 1.364
2 Static Case
techniques) (Safe)
5. PROPOSED SOLUTION
The objective of the proposal is to address slope stabilization and erosion problems by
bringing vegetation to the exposed dumped slope area as mentioned below:
• Before carrying out the installation of proposed solutions, it is recommended that loose scaling
of the slope be done to remove the rock blocks which can be easily dislodged from the surface.
• All loose debris (>100mm) deposited shall be removed before carrying out the installation
of the proposed systems/ solutions.
6. SOLUTION COMPONENTS
High tensile rolled cable net of minimum longitudinal tensile strength 100 KN/M and with a
minimum tensile strength of wire of the cable as 1770 N/sqmm with Zn Coating Class A or
95% Zn * 5% Al Class-B Coating as per EN 10244-2:2009.
High tensile wire-mesh having minimum tensile strength of 150 KN / m with Zn Coating
Class A or 95% Zn + 5% Al Class-B Coating as per EN 10244-2:2009.
6.3. SELF- DRILLING ANCHORS
Self-Drilling Anchors (SDA) is a commonly used system for rock mass stabilization,
especially in cut slope stabilization applications like in tunnelling, mining, and road
infrastructure industries. Surface nailing is typically used to protect the existing slopes or
excavation. These anchors are typically drilled or installed at 10 to 20 degrees with
horizontal and are primarily subjected to tensile stresses. In case of difficult installation
conditions (insitu strata comprising of soil/soil + rock boulders /collapsible strata), self-
drilling anchors are used. It consists of hollow anchor bars, sacrificial drill bits, couplers,
anchor plate, and bolt. They can also be used for cortical strengthening in inaccessible
terrain where drilling operations are difficult, andthe use of regular bars would be time-
consuming and difficult. The self-drilling anchor system is comprised of a hollow threaded
bar with an attached drill bit that performs drilling, anchoring, and grouting in a single
operation. The hollow bar allows air and water to freely pass through the bar during drilling
to remove debris and then allow grout to be injected immediately after drilling is completed.
Alternatively, grout can be injected during the drilling operation itself. Grout is pumped
through the hollow bar, which exits through the nail bottom at the drill bit and fills up the
entire drill hole length. Couplers can be used to join hollow bars and extend the bolt length
while nuts and plates are secure the anchor at the slope face.
Biotic Soil Media will act as a topsoil alternative that accelerates the development of
depleted soils/substrates with low organic matter, low nutrient levels and limited biological
activity.
ANNEXURE – 1
Report on
MITIGATION MEASURES AND SUGGESTION FOR
FOUNDATION DESIGN: RCC STRUCTURE AT RIGDE,
SHIMLA (HP)
by
Mahendra Singh
N.K. Samadhiya
M.N. Viladkar
Project Sponsored by
HPPWD Shimla, HP
June 2020
LIST OF CONTENTS
Page No.
LIST OF CONTENTS i
LIST OF FIGURES ii
LIST OF TABLES iii
1.0 PREAMBLE 1
12.0 PRECAUTIONS 24
IMPORTANT NOTE 24
ACKNOWLEDGEMENT 24
REFERENCE 25
FIGURES 26-35
i
LIST OF FIGURES
Figure Page
No.
Fig 1: Subsidence on road side 26
Fig 6 Cumulative distribution function of UCS from Point Load Strength Index 31
tests
Fig 9 Simulated triaxial test results for weathered rock using Hoek-brown 32
criterion
ii
LIST OF TABLES
Page No.
Table 4.1 Details of Surface strata 6
(Source: Rajneesh Sharma and Atul Sharma)
Table 4.2 Details from Bore Holes on the Northern slope of ridge in between 7
Laveena Restaurant and D.A.V School for Boys.
Table 4.4 Geological material details from drill holes advanced by Geological 9
Wing, Directorate of Industries (Rajneesh Sharma and Atul Sharma)
Table 7.1: Dip and dip directions of the joint planes near Shimla Ridge 15
(Source: Rajneesh Sharma and Atul Sharma)
iii
MITIGATION MEASURES AND SUGGESTION FOR FOUNDATION DESIGN:
RCC STRUCTURE AT RIGDE, SHIMLA (HP)
Mahendra Singh1 , N.K. Samadhiya1, M.N. Viladkar2
1.0 PREAMBLE
Shimla is one of the most famous tourist places in the state of Himachal Pradesh and
attracts thousands of tourists each year from India and abroad. The Ridge located at Mall road is
a favourite destination of these tourists. However, the ridge area of Shimla (H.P.) has been
experiencing settlement in recent years. The HPPWD has decided to construct a RCC framed
structure to arrest the settlements. Besides this, the Government of Himachal Pradesh has also
decided to install a statue of former Prime Minister late Shri Atal Bihari Vajpayee at Ridge Shimla.
The statue is proposed to be installed at the top terrace of this structure. It is proposed that
foundation of this structure should rest over firm strata/ rock. The superintending Engineer,
HPPWD Shimla, vide his letter No. SE-IV-Ridge Stabilisation Statue/ 2019-20/10745-48 dated
05.09.19 requested Dr. Mahendra Singh, Professor, Department of Civil Engineering, IIT Roorkee,
Roorkee for opinion/ advice. A visit to site was undertaken on 27.09.19 by a team comprising the
followings:
From IIT Roorkee:
i. Dr. Mahendra Singh, Professor, Department of Civil Engineering, IIT Roorkee,
ii. Dr. M.N. Viladkar, Professor retired, Department of Civil Engineering, IIT Roorkee.
From HPPWD Shimla
i. Shri Suresh Kapoor, SE,
ii. Shri Ajay Kumar Soni, Executive Engineer, Shimla Division No. III;
iii. Shri Puneet Guleria, State Geologist, Department of Industries; and
iv. Shri Vivek Thakur, JE, HPPWD, Section Winterfield, Shimla.
Based on site observations a proposal for further work was submitted to the HPPWD Shimla vide
letter No. IITR/CED/GTEG/MS/1170 dated 09/10/19. The HPPWD Shimla accepted the proposal
and the project was awarded vide letter No. SE-IV-R-(Shimla Smart City) Misc, Est/19-20-19140-
1
Professor, Department of Civil Engineering, IIT Roorkee, Roorkee-247667
2
Professor & Emeritus Fellow (Retd.), Department of Civil Engineering, IIT Roorkee, Roorkee-247667
1
44 dated 18-01-2020. Another visit to the site was made on March 8 and 9, 2020 during which,
observations were taken for a plate load test conducted at the site. The slope is dipping generally
by about 30 to 40 towards north. The slope material, which under saturated ground conditions
is already on the verge of failure, gets aggravated during monsoons. The large extent of the
overburden material with very low shear strength does not seem suitable for the foundation of
a RRC framed structure and hence the load of the structure is planned to be transferred to a firm
ground by means of engineered structure.
This report gives the details of the project and the recommendations for designing the RCC
framed structure.
2
iii. Topographic survey to be carried out by HPPWD Shimla. Slope profiles at FIVE different
locations spaced at regular interval to be prepared and shall be made available to IIT
Roorkee, alongwith other data, for further analysis.
iv. HPPWD Shimla to provide rainfall data of the area for the last five years to IIT Roorkee.
The Scope of IIT Roorkee included the followings:
i. Mapping of the core logs available from the site,
ii. Laboratory testing of the material received from the site.
iii. Interpretation of laboratory and field data,
iv. Assessment of the rock mass properties available at the site,
v. Stability analyses of the slopes at the site of subsidence and suggestions for mitigation
measures.
3
4.0 GEOLOGY AND GEOTECHNICAL INFORMATION FROM PREVIOUS STUDIES
4.1 Overburden and Debris
A detailed report entitled “Geotechnical Report on the Occurrence of Debris slide near Tibetan
Market located towards Northern Slope of Ridge in Shimla Town, District Shimla, Himachal
Pradesh” authored by Shri Rajneesh Sharma (geologist) and Shri Atul Sharma (Assistant
geologist), Geological Wing, Directorate of Industries, Udyog Bhawan, Bemloe, Shimla (HP) was
made available by HPPWD Shimla. The salient details collected from the report are as follows:
The water supply of Shimla Town comes from the water reservoir located at the ridge.
The storage capacity of the water tank is about 4.6 million liters of water. It has a length of 45 m
and width 32m. The tank has nine chambers and was built around year 1883. Frequent landslides
have occurred during past which often take place after heavy rains. A landslide occurred on 19th
September 2008, when a debris slide destroyed more than 20 makeshift shops at around 10:30
P.M. (Friday) due to which two persons were reported to be killed. Debris slide was triggered on
the northern slope of the Ridge in Tibetan market. It is reported that heavy rainfall in the
monsoon season of 1971 triggered off a series of failures in the Ridge area of Shimla. Central
Road Research Institute, New Delhi submitted a report on Hillside safety of Shimla area. The
causes of damages were attributed to enmass movement in the mantle of slope. The sound
bedrock was, however not involved in the failure. The northern slope of ridge falls in sinking zone
as declared by the Town and Country Planning Department of Himachal Pradesh. All the
geological experts who have studied the problems of slope and subsidence the ridge area of
Shimla have attributed the slope failure to over saturation of over burden soil and debris by the
percolating water, may be due to rains or snow or sewerage or leakage in water supply system.
Geological wing, Department of Industries also carried out detailed investigations at the northern
slope of the ridge area including surface exploration by drilling during 1971. The details are given
in Tables 4.1. The thickness of overburden from these studies are also reported in table 4.2.
The report includes several investigations that have mentioned overburden thickness for
northern slope of the ridge. Some of these, especially for northern slope of ridge are as given in
Table 4.3.
4
Four numbers of drill-holes were advanced during investigation done by Geological Wing,
Directorate of Industries (Rajneesh Sharma and Atul Sharma). The location of field investigations
lies in the survey of India Topo sheet No. 53E/4 located towards downhill side of ladies’ toilet on
Eastern side, Tourist Information Centre on the western side and extends upto foot path leading
to local Bazar. The data extracted from these borehole investigations is presented in table 4.4.
4.3 General Geology of Shimla Town: (Source: Rajneesh Sharma & Atul Sharma, Geological
Wing, Directorate of Industries)
The Shimla town is situated on the rocks of Jutogh group and Shimla Group. Stratigraphic
sequence of the rocks is given in Table 4.5.
Jutogh Formation
Jutogh formation of Shimla area is lying at higher tectonic level and is surrounded structurally by
younger Shimla, Chail and Blaini series, is a part of Klippe brought in to its present position by a
thrust sheet. The road section east of northern slope is composed of carbonaceous phyllite,
Chloritic phyllite and interbedded carbonaceous limestone ad quartzite.
Member A: Carbonaceous Phyllite extends all along the Jakhu hill at lower level and is well
exposed near Lift, Ramnagar area along the NH-22, between St. Bede’s College and the lower
slope of the Kaithu and Annadale.
Member B: Quartzite has the less thickness and it is exposed near the Victory tunnel and
Kasumpti area below Pari Mahal.
Member C: has the maximum thickness and covers the large part of the central Shimla i.e. the
western slope of the Jakhu ridge, old Rashtrapati Niwas and Tuti Kandi area.
5
Table 4.1 Details of Surface strata (Source: Rajneesh Sharma and Atul Sharma)
Sr. Bore Location Total Debris Nature of rock
No. Hole Depth thickness
No. (m) (m)
1 E-1 North of Town 45 5.50 From 0.5 to 5.50mtrs, overburden
Hall, just comprised of silty clay and carbonaceous
below the phyllite was encountered. From 0.50 to
Ridge 36.68mtrs weathered zone having Iron
staining was encountered. From 36.68 to
45.0mtrs thinly bedded and slightly
jointed rock encountered.
2 E-2 Ice skating 45 9.14 From 0.5 to 11.58mtrs brownish silty
rink clays, clay chlorite schist and phyllite
fragments were encountered. From 11.58
to 27.70 mtrs weathered chlorite schist
with highly jointed carbonaceous phyllite
was encountered. From 27.70 to 45mtrs
carbonaceous phyllite was encountered.
3 E-3 Id-Gah. 51 5.00 From 0 to 5.00 mtrs brownish yellow silty
clays mixed with phyllite and quartzite
fragments were encountered. From 5.0 to
20.11mtrs weathered zone carbonaceous
phyllite highly iron stained encountered
whereas no iron stained was observed
from 20.11 to 51mtrs.
4 E-4 North of Regal 24 4.57 From 0 to 4.57mtrs overburden including
cinema Hall clay mixed with carbonaceous phyllite
slates and quartzite fragments was
encountered whereas weathered and
jointed phyllite was encountered from
4.57 to 24.00mtrs.
5 E-5 Willows Hotel 52.50 12.49 From 0 to 12.49 mtrs overburden
including clays, weathered fragments of
chlorite schist and carbonaceous schist
was encountered. From 12.49m to
30.70m weathered portion composed of
carbonaceous phyllites with quartz veins.
The portion from 30.70m to 52.50mtrs is
composed of buff colored limestone
carbonaceous phyllite, grey quartzite and
purple slates.
6
Sr. Bore Location Total Debris Nature of rock
No. Hole Depth thickness
No. (m) (m)
6 E-6 Ruldu--- 37.50 6.40 From 0 to 6.40mtrs, overburden
comprised of clays and carbonaceous
phyllite, fragments were encountered
from 6.40 to 32.30mtrs. It was observed
that water action is quite conspicuous up
to the depth because the iron present has
been rusted. from 32.30 to 37.00mtrs
mostly carbonaceous phyllite was
encountered
7 E-7 Mouth of 24 3.00 From 0 to 3.0mtrs soil cover comprised of
Lakkar bazaar clays and weathered pieces of blackish
grey phyllite was encountered from
3.0mtrs to 24.0mtrs weathered and
jointed rock is encountered
8 E-8 North of cart 49.50 6.40 From 0 to 6.40mtrs overburden clay,
road near quartzite and phyllite fragments were
wood depot. reported from 6.40 to 20.12mtrs
weathered phyllite were encountered
from 20.12 to 49.50mtrs. No weathering
effect was observed.
9 E-9 Gobindgarh 45.00 6.40 From 0 to 6.40mtrs overburden consisting
of silty clay, phyllite, sand, slates and
quartzite fragments were encountered.
From 6.40-12.50m weathered zones
composed of phyllites was reported.
Table 4.2 Details from Bore Holes on the Northern slope of ridge in between Laveena
Restaurant and D.A.V School for Boys (Sharma & Sharma)
Drill Holes No. Total Depth. (in mtrs.) Thickness of over burden
1 24.00 4.70
2 15.60 3.00
3 12.60 3.00
4 22.50 12.80
5 12.30 3.90
7
Table 4.3 Overburden details from various investigations
(Source: Rajneesh Sharma and Atul Sharma)
Geological Report Thickness of overburden
(1) A Geological Report on the sinking of land 1.5mtrs to 2.5mtrs. based on study of three
below Crostophan Estate district Shimla (H.P) test pits.
By Sh. Gian Chand, Dec-1975
(2) A Geological Report on the proposed 3.0mtrs to 6.80mtrs. proved by drilling
shopping centre on the northern slope of (Drilling carried out in the year 1972)
Ridge district Shimla (H.P)
By. Sh. Subhash Sharma and O.P. Rana, Jan -
1981.
(3) A Geological Report on hill side safety of Boring of the slopes in the area has shown the
Shimla (H.P) local phyllitic debris varied in thickness from
By: Sh. T.K. Natrajan, R.K.Bhandari and Ajaib 0.0 to 3.0mtrs and overlies openly jointed and
Singh Jul-1977. fractured phyllites.
(4) A Geological Report on “Evaluation of a Varies from 3.0mtrs to 6,0mtrs at the site.
foundation site for a multistoried building”.
By: Sh. Prakash, G.Ranajan and G.Ramaswami
April,1980.
(5) A Geological Report of the proposed site Drill Hole Total Depth Thickness of
for the construction of administrative block of No. (In mtrs.) overburden.
the municipal corporation of Shimla on the MCS1 19.00 8.60
Northern slope of the Ridge the “Mall” MCS2 22.00 6.70
Shimla. MCS3 15.00 3.00
By: Sh. N.C Bhasin & S.C.Mahajan Dec-1994 MCS4 16.00 7.50
MCS5 16.00 5.50
MCS6 16.00 4.85
MCS7 18.00 7.00
Member D: Quartzite is very well exposed around the Prospect Hill, between Boileauganj and
Taradevi.
Member E: Phyllite and schists have its minimum thickness in this area and exposed near the top
of the Prospect Hill (Kamna Devi Temple)
Shimla Group comprising the earlier Chail Formation and Shimla Series represented by Shale,
Slate, Quartzite, local conglomerate are well exposed in Sanjauli-Dhalli, NW part of Walker
Hospital, Steling Castle and Gorcha village area.
8
Table 4.4 Geological material details from drill holes advanced by Geological Wing,
Directorate of Industries (Rajneesh Sharma and Atul Sharma)
Bore Hole No. 1; Location: Below Lades Toilet;
Depth: 15.80m; R.L of collar of Borehole: 2196.80m
Depth Nature of Material
0.0-4.25m Debris/ overburden material
4.25 - 6.60m Cores of grey coloured phyllite and bed rock started at 4.25m depth
6.60 - 8.0m No core recovered, indicating soft nature of rock.
8.00 - Core comprising of carbonaceous grey colored phyllite
15.80m
Bore Hole No.3: Location: Downhill side of Gent’s Toilet on Lakkar Bazar footpath.
Depth: 17m; RL of collar of Bore hole = 2185.65m
Depth Nature of Material
0.0 - 2.30m Debris material from 0 to 0.90m depth from 0.90 to 2.30m depth sludge was
recovered.
2.30 -6.10m Sludge material with rock pieces. Bed rock is indicated at 2.30m depth
6.10 - From 6.10 to 6.40m dry rock samples were recovered from 6.40. to 7.90m
17.00m no core was recovered. From 7.90m to 8.5m dry again dry sample of rock
was obtained.
9
The boulder beds of Blaini formations comprises of sub-angular to sub-rounded boulders,
cobbles, and pebbles of quartzite, shale, greywacke and silt stone entombed in a matrix of
argillaceous and erroneous composition. The Blaine boulder beds were regarded by Bhargava,
Gaur and Dave as glaciomarine whereas Pilgrim, West and Auden regarded them as tillites.
10
the Jang Ghar building. The exposed bed rocks are highly jointed and fractured in nature. The bed
rock comprises of grey coloured phyllite. The bed rock strikes in N30° W- S30°E to N 45°W- S45°E
and dips in S-W direction with amount of dip from 10° to 30°. The bed rock is jointed in nature
and following prominent sets of joints are observed:
Strike Dip
N50°E-S50°W 70°N40°West
N70°W S 70°E 70°N20°East
N35°E-S35° Vertical
11
Concluding Remarks from the Report (Rajneesh Sharma & Atul Sharma)
The report concludes that bed rock is encountered at depths 4.25m, 5.5m, 2.3m and 4.55m
respectively. Based on the geological information it was recommended that the structure should
be placed at 2 to 3 m in sound bed rock. The safe bearing capacity for the design of foundation
was recommended to be 18 to 20 t/m2.
12
Table 5.1b Details of material observed in Bore hole 2 (Present study)
Collar level=2151.0; Depth of borehole=20.0m
Depth Nature of Material
0.0 to 6.0m Debars/ overburden material containing rock pieces
6.0 to 9.0m Completely weathered soft rock. No rock pieces are observed. The material
is in powder form.
9.0 to 20m Highly fractured rock (phyllite) is encountered. Core recovering is about
10% at 9.0m depth. At higher depth the recovery gradually increases to
about 20% at 20m depth.
The shallow sub soil strata observed from the pits excavated adjacent to road are detailed
in Table 5.2.
Table 5.2 Overburden properties (based on debris samples collected from shallow pits)
I.S. Grain Size Analysis Liquid Plastic Natural Water
Reference Classification Gravel Sand Fines Limit Limit Content
% % % % % %
Pit 1 GC-GM 47.1 17.0 35.9 32.6 24.5 --
Pit-2 CI-MI 12 20.6 67.5 36.6 25.4 18
Pit-3 GM 59.5 17.5 23.1 41.8 32.3 --
13
Concluding remarks on depth of overburden from present investigation
The previous investigations (Sharma & Sharma) had indicated likelihood of encountering debris
thickness ranging between about 2.5 to 4.5m below the topographic ground level. The
observations from the present study, however, indicate that at the proposed location of the
structure the thickness of debris is likely to vary from 6 to 9m below topographic ground level. It
is also seen that the debris is in loose state and not stable. It is therefore proposed that the load
of the structure be transferred to deeper strata. It is also suggested that the structure be
anchored to sound rock to provide lateral stability against destabilizing forces exerted by debris
material.
14
Table 6.1 Engineering and physical properties of different strata
Sl Geological material Unit weight, Cohesion, c, Angle of internal
(kN/m3) (kPa) friction,
1 Debris 16 26 34
2 Weathered rock 22 50 40
3 Fractured rock 25 100 40
4 Bed rock 28 1000 40
15
The values of factor of safety for these conditions have been found to be 1.443, 1.148
(H=0.14, V=0.07), 0.997 and 0.794 respectively. It is seen that the FOS drops drastically if the
slope mass is saturated. The drainage conditions will therefore substantially influence the
stability of the slope. An enhancement in the shear strength parameters of the overburden and
debris will also enhance the stability.
16
f. Provide adequate and efficient drainage system in the soil mass and also around the
structure to minimise ingress of water into slope mass.
A typical section of the slope with the proposed scheme is shown in Figs. 12 (a,b). It is
aimed that during excavation/ construction minimum disturbance occurs to the existing slope
profile. A tentative sequence is suggested below. The scheme will have to be adjusted as per the
feasibility and local site conditions before execution of work.
a. Initially the top cable anchors will be installed. The cable anchors should be embedded in
hard stratum for a minimum length of 3m. The cable anchors will finally be monolithic
with RCC columns of the structure to provide resistance against lateral movement.
b. A cut of about 7.5m depth, will now be made in steps and stabilised. To do this, initially
1.2m deep cut will be made. Self-drilling anchors (SDA), 6m long, 25 mm dia, will be
installed and grouting will be done to stabilise the cut. A shotcrete facing will be placed
to temporarily restrain the exposed soil in cut face. The facing will consist of 150 mm of
shotcrete reinforced with a single layer of welded wire mesh. The same procedure will be
adopted for another remaining steps of cutting and supporting cuts of about 1.2 m each.
c. After reaching the desired depth, a trench will be constructed and micropiles will be
installed. A pile cap will now be constructed; the pile cap will also act as foundation of the
RCC wall of RCC structure. Vertical wall of the RCC structure will be constructed laterally
supported by Cable anchors. The reinforcement of the micropiles will be suitably
embedded into pile cap and the vertical RCC wall of the structure as per the requirement.
The micropiles, pile cap and vertical RCC wall will be monolithic.
d. Now a horizontal bench of about 3.5 m width will be prepared.
e. The benches will be used to support the foundation. The benches should not have loose
or filled up material. Proper ramming should be done to improve soil condition.
Additionally, grouting of the bench will be done by using vertical drill holes.
f. Another cut of about 3.3 m depth will now be made in steps. The cut will be stabilised
through grouting and nailing as discussed above.
g. A trench will be made at the toe of this cut to install micropiles and pile cap.
17
h. Another horizontal bench of about 6 m width will be made. Soil conditions should be
improved through ramming and grouting. Micropiples will now be installed. Pile caps will
also be constructed as per the drawing.
i. The third vertical cut will now be made as shown in drawing alongwith trench for pile cap
and micropiles. The cut will be stabilised through nailing and grouting using SDAs. Cement
concrete cladding will be provided in front of the stabilised cut. The SDAs will be extended
to cross the cladding by using extension bars and the plates will be used at the top of
cladding surface.
j. Slope surface downhill of the structure will be stabilised through nailing and grouting by
using SDAs.
k. Cable anchors will be embedded into RCC columns / pile caps.
18
9.2.2 Excavation from EL 2162.0 m to EL 2147.75 m
The first bench shall be of 7.65 m height and second & third benches shall be of heights 3.3 m
with vertical cuts. The vertical cuts shall be supported by 150 mm shotcrete with wire mesh and
with 25 mm dia, 6 m long grouted self-drilling anchors (SDA). The excavation in each bench shall
be carried out in steps not exceeding in depth of 1.2 m. After completion of each excavation step,
a row of SDA shall be installed with vertical spacing of 1.2 m c/c and 1.1 m c/c lateral spacing.
The SDAs shall be inclined downward at an angle of 20 with horizontal. The grout pressure in
SDA can be increased gradually up to 1-2 bars with extreme care and monitoring the slope surface
response. In any case, the grout pressure should not exceed the overburden pressure. Actual
grout pressure should be arrived at by conducting few trials at the site before the full grouting
operation is undertaken. It is suggested that in one go only 5 to 10 m long stretch along road
alignment should be excavated.
Soil-nailed excavation is usually carried out in stages. The height of the exposed slope face
is determined on the basis of its temporary stability. After installation of a row of soil nails,
subsequent excavation should progress only when the temporary stability of the excavation is
adequate. Soil-nail heads and facing should be constructed before the next stage of excavation,
unless the temporary stability of the soil-nailed excavation in the absence of soil-nail head is
adequate. The sequence and timing of installing soil nails, constructing soil- nail heads and facing,
and excavation should be monitored and controlled to fulfil these requirements.
19
bearing plate. Before proceeding with subsequent excavation lifts, the shotcrete must be cured
for at least 72 hours or it should have attained at least the specified 3-day compressive strength.
a. Shotcrete Application
For shotcrete mixtures, there are two opposing requirements: “shootability” and “pumpability”.
Shootability is the ability of a mix to stick to a surface, build up thickness, and resist sloughing.
Pumpability is the ability of a mix to flow like a viscous fluid. For shooting, a high flow resistance
and high viscosity are ideal, whereas for pumping, a low flow resistance and low viscosity are
ideal. Once it is applied, a shotcrete mix with high flow resistance and high viscosity will tend to
“stick” and remain there, as the layers of facing are formed. With the proper mix design,
shootability to a thickness of 300 mm can readily be achieved without sloughing or sag cracks
below rebar.
Any of the two types of shotcrete methods can be used: dry mix and wet mix. In the dry
mix method, the aggregate and cement are blended in the dry and fed into the shotcrete gun
while the mix water is added at the nozzle. Depending on their features, admixtures can be added
at the mix plant or with the water. The addition of water at the nozzle allows the plasticity of the
shotcrete to be adjusted at the nozzle, if required. In the wet mix method, the aggregate, cement,
water, and admixtures are mixed in a batch plant and conveyed to the nozzle by a hydraulic
pump. The plastic mix is applied at higher velocities by compressed air. Both shotcrete methods
produce a mix suitable for wall facings. Dry mix and wet mix shotcrete use a water-cement ratio
of about 0.4 and produce roughly the same mix quality, although shotcrete obtained with the
wet mix process yields a slightly greater flexural strength.
Dry mix method will require a valve at the nozzle outlet to control the amount of water
injecting into the high pressurized flow of sand/cement mix. For controlling the thickness of the
shotcrete, measuring pin shall be installed at fixed vertical and horizontal intervals to guide the
nozzle man.
20
b. Shotcrete Reinforcement
Welded wire mesh, 3 mm diameter, shall be used as reinforcement for facing. Mesh opening of
the WWM shall be 50 x 50 mm to satisfy the structural requirement (i.e., flexural and punching
shear capacities) and constructability constraints. The WWM must have a width that is consistent
with the excavation lift height (equivalent to the vertical nail spacing), plus an overlap of at least
0.2 m. Additional reinforcement (“waler bars”) shall be placed around nail heads to provide
additional flexural capacity at these locations. The waler bars consist of two vertical (one bar at
each side of the nail head) and two horizontal bars.
i) Welded wire mesh shall confirm to the requirements Specification for hard drawn steel
wire fabric of IS: 1566 (1982).
ii) The mesh shall be clean of mud, grease, oil or other foreign matter.
iii) The mesh will be placed over the previously installed hollow soil anchor and draw up tight
against the soil/rock surface by means of the nuts and bearing plates. A minimum of 10
cm lapping of the mesh shall be provided. However, at connections where it is
impracticable to maintain 10 cm laps, the laps may be extended in lieu of cutting along
regular lines.
iv) The chain link mesh as reinforcement of shotcrete can be used only when the excavated
surface is so uneven and rough that placing of welded steel wire fabric is impractical.
21
9.2.4 Installation of 32 mm dia Cable Anchors
15 m long Cable anchors of dia 32 mm with extension rod and inclined downward at angle of 20
with horizontal shall be installed at EL 2161.25 m (top of vertical structural element) and at each
pile cap levels as shown in the drawing to tie the whole support system deep into the competent
bed.
22
9.2.6 Micropiles
Battered micropiles are proposed to be installed to a specific depth shown in drawings. The
micropiles are affixed at the ground surface to a concrete cap beam. With this method, the
individual micropiles provide resisting forces through the mobilization of axial, shear, and
bending resistance. The micropiles shall be spaced @ 1.1 m c/c along the slope length. Steel pipes
of 141mm diameter 8 mm thickness confirming to P-110/ N-80 (American Petroleum institute)
will be used as micropiles. The micropiles will be perforated throughout the length by providing
perforations along length at 1m interval in staggered pattern. Grouting of the micropile shall be
done with extreme care so that no instability is caused. Trials shall be made in the field for
working out the safe and effective grout pressure. At maximum depth the grout pressure should
be maximum and then it should be telescopically reduced upto a depth of five meter to nominal
grout pressure. In any case the grout pressure should not exceed overburden pressure at any
depth. Neat cement shall be used in grouting and with water cement ratio 0.4 to 0.5 depending
on field condition. The casings shall be left in place after the micropile is installed.
23
11. MONITORING OF SLOPE MOVEMENT
Being an extremely important public place in the heart of city, the concerned authorities should
make long term plan of continuous monitoring the slope mass movement with time. Continuous
monitoring of the displacement should be carried out at regular intervals. These displacements
should be regularly analysed to help in deciding the measures, if required, in future.
12. PRECAUTIONS
It is advisable to finalize all the suggested measures taking into account the feasibility and other
constructional aspects at the site, accordingly all the above suggested measures shall be finalized.
The construction of the control measures as suggested in this report, should be done only by an
agency which has adequate expertise and experience in successful construction of similar
mitigation measures. Geology in Himalayan region is very fragile and full of surprises and
uncertainties. The agency should have in-house expertise to meet such challenges due to internet
nature of the geological materials.
IMPORTANT NOTE
The recommendations have been made on the basis of limited field investigations, laboratory
investigations and information from the available reports. Geological materials are formed under
an uncontrolled environment and scatter in strata may occur as an inherent characteristic of the
materials. If in field, any significant deviation from reported geology is observed, the matter
should be referred to the geotechnical experts for advice and review of support measures to
accommodate the change in reported geological conditions.
ACKNOWLEDGEMENT
The authors thank Shri Suresh Kapoor, SE, HPPWD Shimla for referring and sponsoring the
project. The Investigators are also thankful to Shri Ajay Kumar Soni, Executive Engineer, Shimla
Division No. III; Shri Puneet Guleria, State Geologist, Department of Industries; and Shri Vivek
Thakur, JE, HPPWD, Section Winterfield, Shimla for their kind support during the investigations.
24
The authors also acknowledge and thank the Head, Department of Civil Engineering, IIT
Roorkee, Roorkee for permitting the investigators to take this project.
REFERENCE
Rajneesh Sharma and Atul Sharma “Geotechnical Report on the Occurrence of Debris slide near
Tibetan Market located towards Northern Slope of Ridge in Shimla Town, District Shimla,
Himachal Pradesh”, Geological Wing, Directorate of Industries, Udyog Bhawan, Bemloe, Shimla
(HP).
25
Fig 1: Subsidence on road side
27
Fig. 4b Proposed RCC structure (Second floor & Terrace plan)
28
Fig. 4d. Proposed RCC structure: Ground floor (section and plan)
29
Fig. 5 Photographs of core boxes
30
1.00
0.90 Phyllite
0.80
0.70
0.60
Probability
0.50
0.40
0.30
0.20
0.10
0.00
0 25 50 75 100 125 150 175
σc (MPa)
Fig. 6 Cumulative distribution function of UCS from Point Load Strength Index tests
qup
10
Settlement, mm
15
Depth of pit = 1.5m
Size of plate = 0.3m x 0.3m
qup = 5 t/m2
20
25
31
Dynamic cone penetration resistance, Ncd
0 10 20 30 40 50 60
0
DCPT-1
3
Depth, m
6
Intact rock
m = 10
s ci = 32 MPa 5
Rock mass:
GSI = 25
mb = 0.574
s = 0.00024 4
a = 0.544
c_mass = 0.218 MPa
sig1, MPa
phi_mass = 40.31 3
y = 4.4664x + 0.9435
0
0 0.5 1 1.5 2
sig3, MPa
Fig. 9 Simulated triaxial test results for weathered rock using Hoek-brown criterion
32
Fig. 10. Stereographic projection of joint planes
33
Fig. 12a: Proposed mitigation scheme
34
Fig. 12b: Details of foundation and support scheme
35
ANNEXURE – 2
DESIGN REPORT
Safety Factor
0.000
0.250
0.12
0.500 1.117
0.750
120
1.000
0.08
1.250
1.500
1.750
2.000
2.250
2.500
110
2.750
3.000
3.250
3.500
3.750
4.000
4.250
100
4.500
4.750
5.000
5.250
5.500
5.750
6.000+
90
80
1.500
8.000
70
100 110 120 130 140 150 160 170 180 190
Project
Slope protection at Ridge,Shimla
Analysis Description
Project Summary
General Settings
Analysis Options
Bishop simplified
Number of slices: 25
Tolerance: 0.005
Maximum number of iterations: 50
Project
Slope protection at Ridge,Shimla
Analysis Description
Groundwater Analysis
Random Numbers
Surface Options
Loading
Project
Slope protection at Ridge,Shimla
Analysis Description
Support Properties
SDA - 32 MM
Support Type: Soil Nail
Force Application: Passive
Out-of-Plane Spacing: 1.5 m
Tensile Capacity: 230 kN
Plate Capacity: 5 kN
Default Bond Strength: 0 kN/m
and Material Dependent
Project
Slope protection at Ridge,Shimla
Analysis Description
Project
Slope protection at Ridge,Shimla
Analysis Description
Slice Data
Interslice Data
List Of Coordinates
External Boundary
X Y
87.458 99.514
87.458 85.408
87.458 10.0918
181.907 10.0918
181.907 46.5084
181.907 56.2197
156.556 72.6786
155.312 74.3313
154.153 75.8713
153.751 75.942
150.511 75.942
140.586 84.241
132.591 91.575
Material Boundary
X Y
87.458 85.408
Project
Slope protection at Ridge,Shimla
Analysis Description
Project
Slope protection at Ridge,Shimla
Analysis Description
1.250
1.500
1.750
2.000
2.250
2.500
2.750
110
3.000
3.250
3.500
3.750
4.000
4.250
4.500
100
4.750
5.000
5.250
5.500
5.750
6.000+
90
80
1.500
8.000
70
100 110 120 130 140 150 160 170 180 190
Project
Slope protection at Ridge,Shimla
Analysis Description
Project Summary
General Settings
Analysis Options
Bishop simplified
Number of slices: 25
Tolerance: 0.005
Maximum number of iterations: 50
Project
Slope protection at Ridge,Shimla
Analysis Description
Groundwater Analysis
Random Numbers
Surface Options
Material Properties
Project
Slope protection at Ridge,Shimla
Analysis Description
Support Properties
SDA - 32 MM
Support Type: Soil Nail
Force Application: Passive
Out-of-Plane Spacing: 1.5 m
Tensile Capacity: 230 kN
Plate Capacity: 5 kN
Default Bond Strength: 0 kN/m
and Material Dependent
Global Minimums
Slice Data
Project
Slope protection at Ridge,Shimla
Analysis Description
Interslice Data
Project
Slope protection at Ridge,Shimla
Analysis Description
External Boundary
X Y
87.458 99.514
87.458 85.408
87.458 10.0918
181.907 10.0918
181.907 46.5084
181.907 56.2197
156.556 72.6786
155.312 74.3313
154.153 75.8713
153.751 75.942
150.511 75.942
140.586 84.241
132.591 91.575
Material Boundary
X Y
87.458 85.408
133.721 77.802
158.634 59.049
181.907 46.5084
Project
Slope protection at Ridge,Shimla
Analysis Description
1.500
1.750
2.000
2.250
2.500
2.750
3.000
3.250
3.500
120
3.750
4.000
4.250
4.500
4.750
5.000
5.250
5.500
5.750
100
6.000+
80
1.500
14.000
Project Summary
General Settings
Analysis Options
Bishop simplified
Number of slices: 25
Tolerance: 0.005
Maximum number of iterations: 50
Project
Slope protection at Ridge,Shimla
Analysis Description
Groundwater Analysis
Random Numbers
Surface Options
Loading
Project
Slope protection at Ridge,Shimla
Analysis Description
Support Properties
SDA - 32 MM
Support Type: Soil Nail
Force Application: Passive
Out-of-Plane Spacing: 1.5 m
Tensile Capacity: 230 kN
Plate Capacity: 5 kN
Default Bond Strength: 0 kN/m
and Material Dependent
Project
Slope protection at Ridge,Shimla
Analysis Description
Project
Slope protection at Ridge,Shimla
Analysis Description
Slice Data
Interslice Data
List Of Coordinates
External Boundary
X Y
36.4769 107.872
36.4769 95.738
36.4769 10.0918
235.884 10.0918
235.884 33.1993
235.884 47.485
181.907 56.2197
156.556 72.6786
155.312 74.3313
154.153 75.8713
153.751 75.942
150.511 75.942
134.758 88.947
133.466 90.2154
132.592 91.0731
127.301 96.048
119.734 96.908
Project
Slope protection at Ridge,Shimla
Analysis Description
Project
Slope protection at Ridge,Shimla
Analysis Description
1.000
1.250
1.500
1.750
2.000
2.250
2.500
2.750
3.000
3.250
120
3.500
3.750
4.000
4.250
4.500
4.750
5.000
5.250
5.500
5.750
100
6.000+
80
1.500
14.000
Project Summary
General Settings
Analysis Options
Bishop simplified
Number of slices: 25
Tolerance: 0.005
Maximum number of iterations: 50
Project
Slope protection at Ridge,Shimla
Analysis Description
Groundwater Analysis
Random Numbers
Surface Options
Material Properties
Project
Slope protection at Ridge,Shimla
Analysis Description
Support Properties
SDA - 32 MM
Support Type: Soil Nail
Force Application: Passive
Out-of-Plane Spacing: 1.5 m
Tensile Capacity: 230 kN
Plate Capacity: 5 kN
Default Bond Strength: 0 kN/m
and Material Dependent
Global Minimums
Slice Data
Project
Slope protection at Ridge,Shimla
Analysis Description
Interslice Data
Project
Slope protection at Ridge,Shimla
Analysis Description
External Boundary
X Y
36.4769 107.872
36.4769 95.738
36.4769 10.0918
235.884 10.0918
235.884 33.1993
235.884 47.485
181.907 56.2197
156.556 72.6786
155.312 74.3313
154.153 75.8713
153.751 75.942
150.511 75.942
134.758 88.947
133.466 90.2154
132.592 91.0731
127.301 96.048
119.734 96.908
Material Boundary
X Y
36.4769 95.738
132.333 76.58
157.118 56.7104
Project
Slope protection at Ridge,Shimla
Analysis Description
Project
Slope protection at Ridge,Shimla
Analysis Description
0.12
0.500
0.750
1.000
0.08
1.250
1.500
1.750
160
2.000
2.250
2.500
2.750
3.000
3.250
3.500
140
3.750
4.000
4.250
4.500
4.750
5.000
120
5.250
5.500
5.750
6.000+
100
1.500
80
19.000
60
80 100 120 140 160 180 200 220 240 260 280
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
Project Summary
General Settings
Analysis Options
Bishop simplified
Number of slices: 25
Tolerance: 0.005
Maximum number of iterations: 50
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
Groundwater Analysis
Random Numbers
Surface Options
Loading
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
Support Properties
SDA - 32 MM
Support Type: Soil Nail
Force Application: Passive
Out-of-Plane Spacing: 1.5 m
Tensile Capacity: 230 kN
Plate Capacity: 5 kN
Default Bond Strength: 0 kN/m
and Material Dependent
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
Interslice Data
List Of Coordinates
External Boundary
X Y
178.387 81.1082
174.655 81.052
171.44 83.767
167.756 87.026
164.583 90.347
152.147 102.149
145.73 108.239
138.8 111.271
126.025 111.271
115.848 111.271
20.5201 124.546
20.5201 103.278
20.5201 7.71147
241.396 7.71147
241.396 35.756
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
Material Boundary
X Y
20.5201 103.278
139.4 94.2981
211.513 40.411
231.723 35.756
241.396 35.756
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
0.000
0.250
0.500 1.364
0.750
1.000
1.250
1.500
1.750
140
2.000
2.250
2.500
2.750
3.000
3.250
3.500
3.750
120
4.000
4.250
4.500
4.750
5.000
5.250
5.500
5.750
100
6.000+
1.500
80
19.000
60
Project Summary
General Settings
Analysis Options
Bishop simplified
Number of slices: 25
Tolerance: 0.005
Maximum number of iterations: 50
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
Groundwater Analysis
Random Numbers
Surface Options
Material Properties
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
Support Properties
SDA - 32 MM
Support Type: Soil Nail
Force Application: Passive
Out-of-Plane Spacing: 1.5 m
Tensile Capacity: 230 kN
Plate Capacity: 5 kN
Default Bond Strength: 0 kN/m
and Material Dependent
Global Minimums
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
Interslice Data
List Of Coordinates
External Boundary
X Y
178.387 81.1082
174.655 81.052
171.44 83.767
167.756 87.026
164.583 90.347
152.147 102.149
145.73 108.239
138.8 111.271
126.025 111.271
115.848 111.271
20.5201 124.546
20.5201 103.278
20.5201 7.71147
241.396 7.71147
241.396 35.756
241.396 56.1082
211.903 56.1082
Material Boundary
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
Project
Slope Stabilization at Ridge,Shimla
Analysis Description
DRAWINGS
Existing
R.C.C Wall
El:2145.25m
Existing
Pile foundation
Surface nails-(SDA)
Top Anchor
Length 2m , 32mm
dia,Spacing 2mc/c
8m
5% Al Class-B Coating as per EN 10244-2:2009 for
treatment of slopes.
El:2130.979m
40°
Tibetan Market Road
El:2145.25m
Surface nails-(SDA)
Top Anchor
Length 2m , 32mm
dia,Spacing 2mc/c
U-pins 500mm
13m
Length 8mm dia
@1m c/c spacing
HECP (High Performance Flexible
Growth Medium+Biotic Soil
Media+Soil Amendments + coir mat
El:2125.627m
38°
Tibetan Market Road
Surface nails-(SDA)
Top Anchor
Length 2m , 32mm
dia,Spacing 2mc/c
21m
ETA certified high tensile wire-mesh
having minimum tensile strength of 150
KN / m with Zn Coating Class A or 95%
Zn + 5% Al Class-B Coating as per EN
10244-2:2009 for treatment of slopes.
Surface nails-(SDA)
Length 19m , 32mm
dia,Spacing 1.5mc/c in
both direction
El:2118.196m
40°
Tibetan Market Road
Proposed
R.C.C Wall