Installation Guide - Mist Eliminators
Installation Guide - Mist Eliminators
Page 1
Thermal and Mechanical Separation Technology
Technical ability, flexibility and customer commitment are the key elements in the growth of
Clark Solutions.
Page 2
Contents
1. MaxiMesh® Mist Eliminators....................................................................4
1.1 Introduction...............................................................................................................................4
1.2 Equipment Description..............................................................................................................5
1.3 Receiving, Storage and Mist Eliminator Inspection...................................................................5
1.4 Existing Vessel Inspection.........................................................................................................6
1.5 Requirements to a New Vessel Support Structure....................................................................6
1.6 Internals Fixing Options.............................................................................................................7
1.6.1 Compensation Rings.....................................................................................................................7
1.6.2 Double Rings.................................................................................................................................7
1.6.3 Fixing Cage...................................................................................................................................7
1.6.4 Wire Fixing....................................................................................................................................7
1.6.5 L-Bolt Fixing..................................................................................................................................7
1.6.6 J-Type Clamp Fixing.....................................................................................................................7
1.7 Installation.................................................................................................................................9
1.7.1 Vertical Vessel with Single Ring of Support..................................................................................9
1.7.2 Vertical Vessels with Two Supporting Rings...............................................................................10
1.7.3 Horizontal Vessel with Horizontal MaxiMesh® Mist Eliminator....................................................11
1.7.4 Horizontal Vessel with Vertical MaxiMesh® Mist Eliminator........................................................12
1.8 Final Inspection........................................................................................................................12
1.9 Cleaning and Maintenance......................................................................................................13
1.10 Elimination of Operational Failures..........................................................................................14
Page 4
1.2 Equipment Description
Receiving / Storage
Inspection
Localization – Directly adjacent to the installation designs, according to the shipping documents;
site. 3 – Check the labels that indicate TOPSIDE as the
Degrading – At the time of installation. requirement of orientation;
1 – Put all the sections with the labels upside; 4 – In the inspection, remember that the MAXIMESH®
2 – Check if there is no transport damage and if the mist eliminator was manufactured slightly oversized
pieces count is the same as in Clark Solutions to avoid gaps when the unit is installed.
Page 5
1.4 Existing Vessel Inspection
Page 6
1.6 Internals Fixing Options
The mist eliminator installation does not require numbered labels, tied in part itself, as provided
any special tools or accessories. Will be required drawing. The assembly sequence is described
just a 3/8” wrench. The MAXIMESH® sections are below:
Page 7
1 - Note that there is on the upper side of the fixing
hook (side of this label) an indicator arrow, as shown
in Image 1.
4 - Mount sections of the right and left of the center 6 - In this position, the curved portion of the hook
of the vessel, leaving the central section to be “L” had been fitted below the support ring as shown
mounted last. in image 3.
5 - Turn back the hook “L”, aligning the arrow with 7 - Tighten the lock nut hook “L”
the tear of curling iron.
Image 2 Image 3
upper side of the MAXIMESH® lower side of the MAXIMESH®
Page 8
1.7 Installation
Installation Tip
Necessary Tools
Page 9
Notes:
This type of installation must be equipped with With removable sections of the ring and removed
removable sections on the ring to allow the from the beam, place the end sections of
removal or installation of the individual sections of MAXIMESH® in place with the end of the medium
MAXIMESH®. within the I-beam and between the outer end rings.
If a center beam for longer spans is used, it should The removable sections of the ring and the beam
also be removable section. are MAXIMESH® side of the inspection port.
Page 10
Install sections starting from the outer wall and add
sections toward the center.
The final sections of MAXIMESH® must be installed
according to the instructions on the preceding pages.
Note that must be used a few temporary fixing means
(such as C clamps on the ring) for exerting pressure
on each installed section until the latter section is in
place. After the removable support sections may be
bolted in place.
CAUTION: Never step or walk on the MAXIMESH®
mist eliminator because it was not designed to support
this charge.
Note that you should be a snap-on or compression fit.
Expect resistance because the final section of the grid
fields in the corners of the meshes installed. To make
installation easier and to avoid distortion of the mesh,
use a sheet of metal, cardboard or other thin, flat
material between the surfaces of the meshes (such
as a shoehorn) to reduce interference and resistance.
Remove the foil used to assist the installation after the
last section is placed.
Page 11
1.7.4 Horizontal Vessel with Vertical MaxiMesh® Mist Eliminator
Page 12
1.9 Cleaning and Maintenance
One possible cause of premature operational
problems in the MAXIMESH® is the accumulation of
foreign matter in the mesh. If your file contains fluids
(or solids) that contribute to this problem, routine
cleaning cycles can extend the life of MAXIMESH®
and help maintain its good performance.
CUIDADO: Nunca pise ou caminhe sobre o M.E.
MAXIMESH® pois ele não foi projetado para
suportar esta carga.
In the case of clogged areas or fouling resistant, the unit, marking the location of each section and
removal of the sectors exhibits a better alternative. the direction (up or down) of each section.
Depending on the nature of the fouling, water jet or The simplest method to clean an installed mesh
water with chemical solutions may eliminate most of sector is through the use of a hose and manual
the extraneous material. water or steam nozzle. Care should be taken to
Certain types of fouling, coking for example, do use reasonable levels of pressure and liquid vapor
not respond to any conventional cleaning method. that do not damage the mesh. Detergents and
In such cases, the M.E. MAXIMESH® must be chemical solvents can be added, provided they are
replaced. compatible with the metallurgy of the meshes.
There should be especial care to reinstall the An alternative cleaning method is to boil in a filled
sectors with the same orientation as there were pot. This technique can be very effective, but
before the recession. Put labels before removing obviously does not work in many vessels.
Page 13
1.10 Elimination of Operational Failures
After your MAXIMESH ® mist eliminator has can be given in the following ways:
been installed and is operating, its monitoring
Pressure Drop:
Eficiency
Page 14
2. CS Vane Separator Mist Eliminator
2.1 Introduction
The purpose of this manual is to assist a satisfactory safety during the course of installation services.
installation of the CS-Vane Separator mist eliminator Dimensional information of the equipment, as well
within the shelter vessel. as layout and distance between sections, type of
It is very important the correct handling of the sections setting, are in Clark Solutions design submitted for
that make up the equipment to ensure complete approval.
Page 15
2.4 Inspection and Pre-Assembly
Page 16
You should be hoisting module already with the
housing cover removed, installing the same, taking
care to verify the installation of the same side (the
modules are identified by metallic sticker) as sense
of gas flow.
It should also be noted the number of modules for
the shelter of vessel in question.
Depending on the final height of the under vessel
may be provided for mounting two modules one
upon the other (they will be referred to as “Module
High” and “Low Modulus”).
Remove the lifting eyes after assembly of the
upper module, so there is no interference with the
mounting of the vessel under the cover.
Place the housing cover, not forgetting to put the
gasket (PTFE tape Board 7mm x 20mm) all around,
thus preventing a possible gas leak.
Page 17
2.6.3 Expander Beam Fixing
2.8 Recomendations
Page 18
3. CS FiberBed® Mist Eliminator
3.1 Introduction
The equipment can be damaged by contact with It is necessary to check if there was any damage
sharp objects or inadequate discharge of the truck, during transport and take note for claims against
such as the withdrawal of the transport box by the the shipping company. Check also if all the
lid that can be opened. equipment is present.
3.3 Storage
Page 19
3.4 Installation
3.4.1 General
1 - Check the design details of the equipment and the 4 - Avoid using sharp objects that may puncture the fiber;
tower or the vessel side to see where the element is to
be installed; 5 - The installation must be made mandatory with the
gasket installed between the mirror and the flange
2 - The elements should be lifted by the holes on the end element;
cover and then inside the flange;
6 - After mounting the element on the mirror not forgetting
3 - Before installing remove the plastic protective film that the gasket, install all screws or fasteners to ensure proper
involves the entire fiber element; grip and the necessary seal as shown in the torque chart.
3.4.2 Joints
Below are the main types of joints used in the
sealing of Fiberbed elements will be presented:
NOTE:
Other materials or thickness can be provided by
preliminary analysis
a. – Cut the cord tape length specified in Table 1; placed as shown in Figure 2, that is, crossing the
b. – Select the length of the cord based on the ends to prevent leaks by the board;
diameter of the element and building materials;
7 - In all the facilities, but mainly in spare elements,
NOTE: the surface on which the joints will be installed
should be thoroughly cleaned to ensure perfect
1- flange element with the same body diameter is bonding and sealing;
called flangeless;
8 - Care must be taken to avoid damage to the
2- flange whose diameter exceeds the body member tapes, so do not leave the element contacting the
on both sides is called flanged type flange; joint until the screws are aligned.
Page 20
Table 1 – Board cuts especification
Metal 24 Flanged 83
Metal 15 Flanged 55
a. Full Face type joints are supplied already pierced, b. The joint must be placed directly on the mirror
as the internal dimensions, external and hurricanes with matching hurricanes and the surface must be
of the elements mounting flange; completely clean for a perfect seating and sealing.
Page 21
Joint Element Element Screw Screw Torque
Type Type Style Type Lenght
(ft-lb) N-m
1/4” Rope Pastic
Flanged 1/2-13UNC 1.1/2” 30 40,67
Tape (FRP)
1/4” Rope
Metal Flanged 1/2-13UNC 1” 45 61,01
Tape
Glass Fiber
25% Metal Flanged 1/2-13UNC 1” 60 81,35
Tube
Full Face Metal Flanged 1/2-13UNC Thickness 60 81,35
+ 5/8”
NOTES:
1 - Tighten the screws gradually and interchangeably; it is less likely that the bolts are tightened evenly as
2 - It is recommended to use an impact wrench as specified.
3.5 Recomendations
1 – When Fiberbed® is installed in the mirror, or 2 – When Fiberbeds® are installed hanging from
your installation is up, it is important to realize the the mirror the sealing cups should be filled before
locking between the elements according to the departure thus avoiding preferential paths as
picture below; pictured below
Review Historical
Review Date Description Elaborate Reviewed Approved
•Social reason
alteration
03 18/11/2015 •Equipment name IAS ADR CAA
alteration
•General Review
Page 22
Page 23
Brazil Office
281 Av. Moema
Moema / SP 04077-020
Brazil Plant 1
69 R. Galeão - Vila Morellato
Barueri / SP 06408-050
Brazil Plant 2
91 Dn. Joaninha - Moinho Velho
Embu das Artes / SP 06807-690
USA
411 SE Mizner BLVD #72
Boca Raton FL 33432-6001
Website: [Link]
Email: contato@[Link]
Tel.: 55 11 3472-3333
Page 24
The final inspection involves checking for uniform compression in all joints and ensuring sections are evenly seated in brackets. All temporary installation tools and materials should be removed, and sections should be verified for secure attachment with appropriate fasteners .
Safety precautions include ensuring easy access to the installation site, following confined space requirements, and avoiding walking on the MAXIMESH® mist eliminator since it cannot support weight . Installation should be done carefully to avoid damage from welding spatter and proper alignment is necessary to prevent installation errors .
Inspection and alignment are critical to ensure that each section is properly compressed and securely fitted, preventing potential gas leaks and ensuring the overall efficiency of the mist eliminator . Proper alignment ensures even distribution of pressure and supports durability .
Before installation, inspect the MAXIMESH® mist eliminator for transport damage, verify the count of sections against shipping documents, and ensure labels are correctly oriented. Sections should be placed with labels upwards and compared with supplied designs .
For installing MAXIMESH® in confined spaces, measure and mark support rings, and use tools like a measuring tape and T ruler to ensure alignment. Consider additional specific tools for different accommodations that may be required during installation .
Removable sections in vertical vessels allow for easier installation and access, especially when space is limited for placing the final sections. These removable sections can be bolted in place for stability after installation .
The CS Vane-Separator Mist Eliminator should be kept in a dry, clean, and covered environment if installation does not occur soon after receipt . For long-term storage, the box should be placed in a dry location, such as a storage area or warehouse, to prevent damage .
MAXIMESH® mist eliminators are designed to accommodate vessel eccentricities by being slightly oversized, ensuring a tight fit within the vessel to avoid gaps that might allow gas passage . This design accounts for the expected tolerances and eccentricities in the vessel shape .
In horizontal vessels, the MAXIMESH® is typically rectangular and may be chamfered to fit contours. Sections are installed starting from the ends, ensuring parallel alignment and using temporary supports if necessary. The design allows for either snap-on or compression fits to ease installation and removal .
If resistance is encountered, metal sheets or other thin materials should be used to reduce friction and interference between the meshes. Bending or shifting adjacent sections can also aid the process . Once sections are in place, the temporary materials should be removed carefully to avoid mesh damage .