Switching Transients
Switching Transients
DIgSILENT PowerFactory *
ing analysed the network model should include: • Stray inductances and capacitances
~
Power Plant SG Generator
C Bank
2
GT-1 GT-2
0 9
PP1 Load NE
PP2 Central North-East
Inactive
Out of Calculation
De-energised
East-1
CE-2.1
Grid TR_C1 30 km
Load E-2
TR_C2 CE-2.2
30 km
0
East-2
WC-1.1 WC-1.2 WC-1.3
100 km 100 km 100 km
Wind Farm
WFT-1
WC-2.1 WC-2.2 WC-2.3 WT
8
100 km 100 km 100 km CE-3
12 km 8
West 1 West 2
WF WFT-2
IS.R0.2
CCE-1-1
IS.R0.1 CB.R0
IS4.3
CNC-1_comp
CNE-2 IS7.3
IS.R5.3 100 km
CNC1
CCE-1-2
IS.R1.3
IS6.3
CCE2-2
IS.R4.3 IS3.3
TR_C1
TR_C1-HV
IS3.2 CB3 IS3.1 CE-2.2
TR_C1-MV
CBS1 30 km
CBS2
CWC1_comp
TR_C2-MV
30 km
TR_C2-HV
IS.L2.1 CB.L2 IS.L2.2 IS2.3
WC-1.3
100 km
CCE2-1
CWC1
IS5.3
IS.L3.3
CWC2
IS1.3
IS0.2
IS.L0.2
CWC-2_comp
CCE-3
CB0 IS0.1
IS.L0.1 CB.L0
C1_1 C1_2
C4_1.1 C4_1.2
Overhead Lines
Overhead lines can be modelled based on their ge- Figure 3: 400 kV double circuit overhead line structure
ometry and material characteristics of the conductors
and earth return path in PowerFactory.
The Y-values which are entered in PowerFactory cor-
The geometry is entered in PowerFactory using the respond to the average height of the conductor and
X-Y coordinates of the phase conductors and ground ground wire along the line. The average height in-
wires as shown in Figure 3. The graph shows the ge- cludes the sag and is calculated as follows:
ometry of the 400 kV and 110 kV double circuit over-
head line being used in the network model (Figure 1).
The cables are layed directly in ground in flat formation tion of the wind farm with the 110 kV terminal of the
with a distance of 0.7 m apart. Two cable systems con- sub-transmission system.
nect the substation North with the Power Plant (see
Figure 1). They are laid in parallel. The layout of Saturation Model
the complete cable system is shown in Figure 6. The
earth resistivity is assumed to be 100 Ωm. For simulating non-linear, electromagnetic transients
such as the transformer energisation, the core satu-
ration needs to be included in the model of the trans-
former.
2.2 Transformers
Transformer Types
2.3 Generator
NPP-1 NPP-2 NNPS2_comp
IS2.2 IS4.2
IS1.1 IS3.1
2.4 Loads
CB1 CB3
2.5 Substations
NC
WN
The network model comprises 5 substations:
2.5.3 Reactive Power Compensation The magnetic flux Ψ, representing the time-integral of
the voltage, lags in steady state the sinusoidal wave-
form of the voltage by 90∘ . Being still in the linear
For reactive power compensation a shunt reactor is in- part of the saturation characteristic, the current is si-
stalled in substation Central. The rated reactive power nusoidal as well. Thus, the current is proportional to
of the shunt reactor is 50 Mvar per step. The reactor the voltage.
is switchable and has 4 steps. Thus, the shunt reactor
can consume a maximum of 200 Mvar. When a completely demagnetised transformer is en-
ergised the flux Ψ in the iron core is zero at the instant
A capacitor bank is installed at the substation North- of switching. The instantaneous voltage in Figure 10
East with a rated reactive power of 50 Mvar per step. is zero at this instance. Due to the 90∘ phase shift
It is also switchable and has 10 steps. between the flux Ψ and the voltage, the flux ought to
be at its peak in steady state operation. However, due
to the initial condition (Ψ equals zero) the flux starts at supply voltage 𝑢𝑆 .
zero. As a result the curve of the flux Ψ is shifted by
Ψ𝑚 upwards in the first cycle of the transient. Thus, At the receiving end of the line, the voltage 𝑢𝑅 is still
the flux starts at zero and then reaches a maximum of zero since the surge needs a certain time to travel
2Ψ𝑚 in the first cycle as indicated in Figure 10 [1]. from the sending to the receiving end of the line. The
surge propagates with the speed 𝑣 along the line and
Taking into a account a residual flux of Ψ𝑅 in the iron arrives at the sending end of the line with a delay equal
core, the curve is shifted upwards even further as in- with the propagation time 𝜏 .
dicated in Figure 10 and reaches a maximum peak
values of Ψ𝑅 + 2Ψ𝑚 . The magnetization curve is now The propagation speed 𝑣 is a function of the line in-
′ ′′
operating in the saturated region and the relationship ductance 𝐿 and capacitance 𝐶𝐿 . For a lossless line
between the flux Ψ𝑚 and the current 𝑖 are no longer the propagation speed 𝑣 is calculated by the following
governed by a linear relationship. This causes high equation [1]:
and distorted inrush currents as shown in the graph.
1
𝑣=√
ψ ψ, B 𝐿 · 𝐶′
′
ψR + 2 ψm
2 ∙ ψm
The propagation time constant 𝜏 is dependent on the
ψR propagation speed v and the line length
H, i
𝑙 √︀
𝜏= = 𝑙 · 𝐿′ · 𝐶 ′
u 𝑣
i
Figure 11 shows the voltage surge during the line en-
ergisation of an ideal single phase conductor for three
time steps of the transient:
3.2 Travelling Waves Transient voltage and current surges are thus a func-
tion of time and location along the line. Distributed pa-
rameter line models are therefore required to analyse
When investigating transient and high-frequency such phenomena. Depending on the transient being
steady-state phenomena, it is necessary to account investigated, line models with constant or frequency
for the distributed-parameter nature of conductors dependent parameters are used in simulation models.
such as overhead lines, cables and in the case of high
frequency transients, even of busbars. The constant distributed parameter model in Power-
Factory is based on Bergeron’s method, which calcu-
Typically, for low frequency steady-state analysis, lines lates the voltages and currents at one end of the line
and cables are modelled using the well-known lumped based on the voltage and current at the other end de-
parameter equivalent circuit, thus neglecting the dis- layed in time. For further information refer to the tech-
tributed nature without loosing too much accuracy in nical reference of the line models [4].
the results. In reality, a current in a conductor having
even a very short length, needs a certain time to travel With the exception of lossless and distortion-less
from its sending end to the remote end [1]. lines, the characteristic impedance 𝑍𝐶 and the propa-
gation constant 𝛾 are frequency dependent. To handle
When an overhead line or cable is energised from frequency-dependent parameters for overhead lines,
the grid as shown in Figure 11, a voltage and current PowerFactory uses the approach proposed by J.Marti
surge are injected into the line. Before the breaker is [4]. For cable systems the Universal Line Model is
closed, the voltage at both ends of the line is zero. available and offers a high accuracy and a phase-
Upon breaker closing at the sending end of the line, domain formulation [5].
the voltage changes instantaneously from zero to the
𝑢𝑆 𝑢𝑅 𝑢2 2 · 𝑍2
=
𝑢1 𝑍1 + 𝑍2
𝑍 + 𝑍1
𝑢𝑆 𝑢𝑅 𝑢𝑟 = 2
𝑍1 + 𝑍2
𝑖1 2 · 𝑍1
=
𝑖2 𝑍1 + 𝑍2
𝑢𝑆 𝑢𝑅
𝑍 − 𝑍2
𝑖𝑟 = 1
𝑍1 + 𝑍2
Figure 11: Voltage surge line energisation Typical surge impedances for common power system
components are:
During the transient, the surge is travelling back and • Overhead lines: 200 Ω to 500 Ω
forward until damping and attenuation will eventually • Cable systems: 40 Ω to 70 Ω
result in a steady state condition. At each electri-
cal boundary the surge is reflected and refracted as • Transformers: 1 kΩ to 10 kΩ
indicated in Figure 11. Electrical boundaries arise
when the surge impedance of the network compo-
nents change, e.g. at an overhead line - cable tran- 3.3 Transient Recovery Voltage (TRV)
sition or at the open end of a line.
Transient recovery voltages (TRV) arise both at fault
interruption and load switching. In both cases a circuit
𝑍1 𝑍2 breaker is switching off. The circuit breaker opening
procedure is explained in Figure 13. The switching
𝑖1 𝑖2 command is usually initiated automatically by a relay
that detects a fault in the system or a switching com-
𝑢1 mand from the control center to trigger a change in the
𝑢2 operation scenario of the network.
𝑍2 > 𝑍1 : 𝑢𝑟
The tripping command activates the operating mech-
𝑢𝑟 anism and through its kinematic chain separates the
𝑢2
𝑢1 contacts in the circuit-breaker. After a certain opening
time, the circuit-breaker arcing contacts will open in all
three poles.
𝑖1 Breaker state
𝑖1 𝑖2
𝑖𝑟
arcing time
The reflected and refracted voltage and current surge Total break time
interruption must wait for the zero crossing of the cur- side is defined by 𝐿𝐿 and 𝐶𝐿 and is a single frequency
rent. Depending on the type of circuit-breaker, the de- oscillation in case of linear inductive load.
vice may not be ready to interrupt at the first occurring
current zero after contact separation.
1 1
𝑓𝑅 = · √︀
For SF6 circuit breakers, it takes a certain minimum 2𝜋 𝐿𝐿 · 𝐶𝐿
arcing time before the electric arc extinguishes in the
circuit breaker because sufficient cooling pressure of The Transient Recovery Voltage (TRV) is the voltage
the extinction medium must be available and sufficient across the open circuit-breaker contacts which arises
contact distance must be reached. For vacuum circuit immediately after current interruption. It is the differ-
breakers sufficient contact distance has to be reached ence between the voltage-to-earth at the source side
in order to extinguish the electric arc [2]. 𝑢𝑆 and load side 𝑢𝐿 :
𝐿𝑆
𝑢TRV = 𝑢𝑆 − 𝑢𝐿
Immediately after current interruption a transient volt- Figure 15 shows that the TRV starts from zero at
age will oscillate on the load side and source side. current zero, makes an excursion to the momentary
Figure 14 shows the equivalent circuit of the load and power-frequency voltage, overshoots in a damped
source side after the switching action. oscillatory manner and continues to oscillate until a
steady-state condition is reached. The frequency of
The source side voltage is composed of two compo- the load side oscillation is 𝑓𝐿 = 3558.8 Hz and of
nents, the power frequency voltage (e.g. 50 Hz) and the source side 𝑓𝑆 = 73.9 Hz. Important parame-
the transient voltage oscillating between 𝐿𝑆 and 𝐶𝑆 . ters in a TRV study are the maximum transient recov-
The frequency of the transient part of the voltage is ery voltage 𝑈𝐶 and the rate of rise of recovery volt-
calculated by the following formula: age (RRRV). Both parameters are required for circuit
breaker design studies.
1 1
𝑓𝑆 = · √︀ Current chopping may need be considered as well in
2𝜋 𝐿𝑆 · 𝐶𝑆
the TRV study for some types of circuit breakers or
switching transients.
The oscillation frequency of the voltage on the load
200,00
100,00
0,00
-100,00
-200,00
-300,00
0,00 2,00 4,00 6,00 8,00 [ms] 10,00
Source: Phase Voltage SP in kV
200,00
100,00
0,00
-100,00
-200,00
-300,00
0,00 2,00 4,00 6,00 8,00 [ms] 10,00
Load: Phase Voltage SP in kV
200,00 40,00
100,00 30,00
0,00 20,00
-100,00 10,00
-200,00 0,00
-300,00 -10,00
0,00 2,00 4,00 6,00 8,00 [ms] 10,00
Circuit Breaker: Voltage Difference in kV Circuit Breaker: Phase Current/Terminal i in A
Source: Power Frequency Voltage
Figure 15: Source side, load side and transient recovery voltage (TRV)
6,00
4.1 Steady State Load Flow 5,00
Analysis 4,00
3,00
ances resulting from imperfect line transposition of -240, -210, -180, -150, -120, -90,0 -60,0 -30,0 30,0 60,0 90,0 120, 150, 180, [kV]
the multi-phase network and unsymmetrical loads and -1,00
-6,00
4.2 Transformer Energisation phase C results in a phase current of 2.97 p.u. in the
saturation curve corresponding to transformer WF-1.
This study case investigates the energisation of the
A Fast Fourier Transform (FFT) is used to investigate
wind farm transformer WF-1. Before energisation, the
the inrush currents in order to quantify their harmonic
complete wind farm is disconnected. The 110 kV HV
content. The FFT is carried out with a 20 ms win-
cable which connects the wind farm to the point of
dow and 64 samples, resulting in a sampling rate of
common coupling (PCC) at substation Central is al-
3200 Hz. Figure 18 shows the FFT of the inrush cur-
ready energised and in steady state. The wind farm
rents in the same plot. As can be seen, phase C con-
transformer WF-1 is energised by closing the circuit
tains a significant DC-component. This is because the
breaker CB4. The residual flux in the transformer core
flux in phase C starts at zero when the transformer is
is assumed to be zero at the time when the trans-
energised, thus resulting in a fluctuating flux between
former is energised (𝜓𝐴 (𝑡0 ) = 𝜓𝐵 (𝑡0 ) = 𝜓𝐶 (𝑡0 ) = 0).
0 p.u. and 2 p.u. (fluctuating around 1 p.u.).
The EMT simulation is initialised at 𝑡 = −100 ms and
The energisation of the wind farm transformer causes
the integration step size is set to 𝑡 = 100 𝜇s . The cir-
a voltage drop at the grid connection point (Central
cuit breaker CB4 is closed at 𝑡 = 0 s. The simulation
substation). The RMS voltage during the energisation
results are documented in Figure 17 and Figure 18.
process is shown in Figure 18. Ahead of energisation
Following the switch event the flux in all three phases
the RMS voltage in all three phases is approximately
rises proportional to the source voltage at the HV side
1.015 p.u. The minimum RMS voltage during the en-
of the transformer with a 90∘ phase shift. The peak
ergisation occurs in phase C and is 0.99 p.u. which
flux arises in phase C and is -1.68 p.u. which corre-
corresponds to a voltage dip of approximately 2.5%.
sponds to a flux of 339.6 Vs.
Usually grid code requirements limit the maximum al-
During the energisation, the fluxes in all three phases lowable RMS voltage dip to 2.0%. Thus, countermea-
exceed 1 p.u. and drive the transformer into satura- sures such as point on wave switching (𝑃 𝑜𝑊 ) would
tion. The current-flux relationship is no longer linear have to be considered for the specific case.
and results in high inrush currents which contain har-
Energising both transformers instantaneously at
monic distortion as described in section 3.1. The non-
𝑡 = 0 s results in a minimum voltage of 0.97 p.u. This
linear flux-current relationship can also be plotted in
will most likely not be acceptable with regard to the
PowerFactory and is shown in Figure 17. The peak
grid code. Taking residual flux into consideration will
inrush current on the HV side of the transformer arises
increase the inrush currents and consequently the
in phase C and is 780 A. This is approximately 3 times
RMS voltage dip.
the rated current of 262.4 A. Thus, a flux of 1.68 p.u. in
2 3 3
0 1 1
-1 0 0
-2 -1 -1
4 800 3,00
[p.u.] [A] [p.u.]
2 400
2,00
0 0
1,00
-2 -400
0,00
-4 -800
-1,00
-6 -1200
0 10 20 30 40 [ms] 50 0 10 20 30 40 [ms] 50
WFT-1: Magnetising Current, Phase a WFT-1: Phase Current A/HV-Side -2,00
WFT-1: Magnetising Current, Phase b WFT-1: Phase Current B/HV-Side -6 -4 -2 0 2 [p.u.] 4
WFT-1: Magnetising Current, Phase c WFT-1: Phase Current C/HV-Side
Figure 17: Transformer HV side voltage, magnetic flux in the core, magnetizing current
1,03
[sec.V]
1,02
0,99
0,98
0,0 100,0 200,0 300,0 400,0 [ms] 500,0
800,0
[A]
400,0
-800,0
-1200,0
0,0 100,0 200,0 300,0 400,0 [ms] 500,0
500,0
[A]
400,0
WFT-1: Phase A
300,0
WFT-1: Phase B
WFT-1: Phase C
200,0
100,0
0,0
0,000 50,00 100,0 150,0 200,0 [Hz]
Figure 18: RMS voltage dip at PCC, Inrush currents and their harmonic distortion
300
-300
-600
-900
0 4 8 12 16 [ms] 20
L2: Phase Voltage A in kV
T1.6: Phase Voltage A in kV
500
250
-250
-750
0 4 8 12 16 [ms] 20
L2: Phase Voltage B in kV
T1.6: Phase Voltage B in kV
500
250
-250
-750
0 4 8 12 16 [ms] 20
L2: Phase Voltage C in kV
T1.6: Phase Voltage C in kV
Figure 21: Transient phase-to-ground voltages at the sending and receiving end during the energisation of
OHL WC-1
1200
[A]
800
-400
-800
0 300 600 900 1200 [us] 1500
1200
[A]
800
-400
-800
0 300 600 900 1200 [us] 1500
300
[A]
0
-900
-1200
0 300 600 900 1200 [us] 1500
Figure 22: Transient phase currents during the energisation of OHL WC-1
Figure 21 shows the transient voltage at the sending the switch event) is varied randomly by ± 10 ms. Fur-
and receiving end of overhead line WC-1 during the thermore, the scatter time corresponding to the me-
energisation process. The voltage surges are injected chanical delay of the closing time of each individual
at the sending end of the overhead line and then du- phase of the breaker is varied randomly by 0...1 ms in
plicated and reflected at the receiving end (substation each simulation. Figure 25 shows the maximum over-
West). Then the surges travel back to substation Cen- voltages for the 𝑛 = 100 EMT simulations executed
tral. Due to attenuation, the magnitude of the wave automatically by the statistical tool in PowerFactory.
decreases and the waveform is distorted, as it prop-
agates along the line. The current and voltage wave Figure 25 documents the maximum line-to-earth over-
shapes become dissimilar, though they were the same voltages at substation West resulting from each sim-
initially. The following maximum overvoltages arise ulation executed during statistical analysis. The plot
during the energisation of overhead line WC-1: documents the overvoltages resulting from the energi-
sation of overhead line WC-1 from substation Central
• Phase A: 516 kV for all three phases.
• Phase B: 400 kV As demonstrated, the overvoltages significantly de-
pend on the breaker closing time and also the oper-
• Phase C: 420 kV
ation scenario, such as e.g. energisation from sub-
Figure 22 shows the current surge along the line. In station West or Central. For economic reasons the
phase A a current surge of approximately 1080 A is in- insulation design for self-restoring insulation is usually
jected into the line, in phase B the amplitude is 845 A not based on the maximum prospective overvoltage
and in phase C 267 A. The propagation time of the of all investigated cases. Instead the design is based
first line segment is approximately 234 µs. Thus the on a probabilistic approach to withstand only a certain
percentage, e.g. 98%, of the prospective overvoltages
injected current surge arrives at the first point of trans-
position only after 234 µs which can be observed in which are calculated in a statistical analysis.
Figure 22. The surge arrives at SS West (open end
of overhead line WC-1) approximately 712 µs after the According to the insulation coordination standard IEC
circuit breaker is closed. 60071-2 first the maximum overvoltages are deter-
mined using EMT simulations. The maximum over-
The overvoltages resulting from line energisation voltages are documented in Figure 25 and are based
highly depend on the magnitude of the injected surge on the statistical analysis. As a next step, the rep-
at the sending end of the line. The magnitude of the resentative overvoltage 𝑈𝑟𝑝 is derived from the max-
injected surge depends mainly upon the voltage in- imum overvoltages. Secondly, the coordination with-
stantaneous value (point on the waveform) at which stand voltage 𝑈𝑐𝑤 is calculated from the representa-
the circuit-breaker contacts close electrically. Since tive overvoltage using the coordination factor 𝐾𝑐 , as
the point on the waveform of the voltage depends on follows:
the circuit breaker closing instant, statistical studies
should usually be performed. As the circuit breaker
closing time is of random nature in reality, all potential 𝑈𝑐𝑤 = 𝑈𝑟𝑝 · 𝐾𝑐
breaker closing times and thus overvoltages should be
evaluated. The coordination factor 𝐾𝑐 makes allowance for lim-
itations in the modelling, shape and duration of an
The randomness of the circuit breaker closing time overvoltage. For the deterministic approach (non-self
is modelled in PowerFactory by means of statistical restoring insulation) in the insulation coordination 𝐾𝑐
analysis. The statistical analysis tool in PowerFactory is usually 1.0 . For a probabilistic approach it is based
runs a number of n simulations. In each simulation on the statistical analysis.
the breaker closing time is varied randomly within a
defined range. Additionally, breaker pole scattering For that purpose, the risk of failure 𝑅(𝑈 ) is calcu-
can be included in the statistical analysis in order to lated based both on the probability distribution of the
account for deviations in the closing time between the overvoltage 𝑓 (𝑈 ) and the probability of the insulation
three phases. strength 𝑃 (𝑈 ) and is illustrated in Figure 23.
overvoltages and the failure probability of the dielec- The mean 𝜇 of the distribution function and the stan-
tric strength of the insulation. According to the figure, dard deviation 𝜎 are determined using the statistical
a voltage of 1.5 p.u. is most likely. For that voltage tool in PowerFactory. The normal distribution function
the failure of the insulation is very small. Thus, the is shown in Figure 24 and shows the probability versus
risk of failure R(U) is also relatively small. For higher standard deviation 𝜎 in general.
voltages, e.g. 2 p.u., the probability for overvoltages is
smaller. However, the probability of insulation failure is The insulation for self-restoring insulation, such as
much higher. Thus, the overall risk of failure is higher. overhead lines, is usually designed for the 98%
For very high overvoltages the risk of insulation failure percent value of the prospective voltage stresses.
is significant. However, the probability of such high The statistical tool in PowerFactory determines the
overvoltages is almost zero and thus the risk of failure prospective overvoltage 𝑈 for a defined probability
is also nearly zero. 𝑓 (𝑈 ) (e.g. 98%). The analysis is based on the 𝑛 num-
ber of EMT simulations executed during the statistical
analysis. In this example (𝑛 = 100 EMT simulations)
1
the statistical results in Table 1 are obtained for en-
f(U) ergisation of overhead line WC-1 from the substation
0,8
P(U) Central.
Probability in p.u.
0,6 R(U)
Table 1: Statistical overvoltages for different bands
0,4
around the mean 𝜇
0,2
𝑎𝑟𝑒𝑎 𝑃 (𝑈 ) 𝜇 𝑢𝑚𝑎𝑥
0 (𝜇 − 𝜎, 𝜇 + 𝜎) 65.9% 471 kV 492 kV
-3 -2 -1 0 1 2 3 4
Stress, e.g. voltage in p.u. (𝜇 − 2𝜎, 𝜇 + 2𝜎) 95.5% 471 kV 548 kV
(𝜇 − 3𝜎, 𝜇 + 3𝜎) 99.73% 470 kV 593 kV
Figure 23: Risk of failure 𝑅(𝑈 )
0,4
Probability overvoltages in p.u.
𝑈𝑟𝑤 = 𝑈𝑐𝑤 · 𝐾𝑠 · 𝐾𝑎
0,3
600
overvoltages in kV
500
400
300
200
Phase A Phase B Phase C
100
0
0 20 40 60 80 100
number of simulation n
100
Phase A Phase B Phase C
80
probability in %
60
40
20
0
350 400 450 500 550 600
voltage in kV
4.4 TRV Analysis of Shunt Reactor The network impedance at the shunt reactor is calcu-
Switching off lated using the Frequency Sweep Calculation Tool in
PowerFactory. The inductance is 68.51 mH at substa-
tion Central in case the shunt reactor is out of service.
For reactive power compensation a shunt reactor is
Based on the network capacitances and inductances
installed at substation Central as shown in Figure 2.
the approximate oscillation frequency can be calcu-
The shunt reactor is a three-phase five-leg core type
lated as described in section 3.3. The load side oscil-
with a rated reactive power of 200 Mvar. The reac-
lation frequency is approximately 1.58 kHz:
tor is switchable and has 4 steps. Thus, it is able
to consume 0 Mvar, 50 Mvar, 100 Mvar, 150 Mvar and
200 Mvar. The reactor is connected directly to the 1 1
𝑓𝑅 = · √︀ = 1.58 kHz
400 kV busbar via a 400 kV circuit breaker. 2𝜋 𝐿𝑅 · 𝐶 𝑅
600
[kV]
400
200
-200
-400
0 4 8 12 16 [ms] 20
T1: Phase Voltage A
T1: Phase Voltage B
T1: Phase Voltage C
200
[A]
100
-100
-200
-300
0 4 8 12 16 [ms] 20
CB phase A: Phase Current/Terminal i
CB phase B: Phase Current/Terminal i
CB phase C: Phase Current/Terminal i
Figure 28: Load side oscillation voltagesand phase currents in the high voltage circuit breaker
1000
500
-500
-1000
-1500
0,0 2,5 5,0 7,5 10,0 [ms] 12,5
CB phase A: Voltage Difference in kV
TRV Limit Phase A T10: TRV_limit_neg
TRV Limit Phase A T10: TRV_limit_pos
1000
500
-500
-1000
-1500
0,0 2,5 5,0 7,5 10,0 [ms] 12,5
CB phase B: Voltage Difference in kV
TRV Limit Phase B T10: TRV_limit_neg
TRV Limit Phase B T10: TRV_limit_pos
1000
500
-500
-1000
-1500
0,0 2,5 5,0 7,5 10,0 [ms] 12,5
CB phase C: Voltage Difference in kV
TRV Limit Phase C T10: TRV_limit_neg
TRV Limit Phase C T10: TRV_limit_pos
Figure 29: Transient recovery voltage (TRV) and dielectric strength of circuit breaker
0,00
91,4
0,0
CBS1
CBS2
CWC1_comp
In this section the transient recovery voltage across
the breaker poles of the circuit breaker CB.L2 in sub- IS.L2.3
CB.L2
station Central is analysed, following a terminal fault
IS.L2.1 IS.L2.2
on the line side of the circuit breaker. For the purpose WC-1.3
of this analysis the CB.L2 is modelled by detailed cir-
cuit breaker model. The breakers include a model of
CWC1
IS.L3.2 CB.L3
the dielectric strength during the transient according
to IEC 62271-100. IS.L3.3
CWC2
The detailed breaker model is stored in the Variation
TRV Analysis Terminal Fault which is activated with WC-2.3 IS.L1.1 CB.L1 IS.L1.2
0,00
91,4
0,00
91,4
0,0
0,0
𝑓𝜏 =
4·𝑙 C4_1.1 C4_1.2
The current in each circuit breaker is interrupted at the Curve 𝑢1 /kV 𝑡1 /𝜇s 𝑈𝐶 /kV 𝑡2 /𝜇s
following current zero of each individual phase. The
line is re-connected after clearing of the fault. How- T100 334 167 624 668
ever, the re-closure action of the line is not simulated T60 334 11 669 666
in this study case since the investigation focuses on
T30 - - 687 137
the TRV capability of the HV circuit breaker during the
Terminal fault.
The breaker capability curve is modelled according to Figure 31 shows the short circuit current flowing from
the limits defined in IEC62271-100 for a voltage level substation Central to the fault location at the beginning
of 420 kV. The relevant parameters for the envelope of overhead line (OHL) WC-1.3. Initially the current
curve are listed in Table 2 and define a 4-parameter through the circuit breaker is in steady state. At time
envelope. The envelope curve defines the maximum 𝑡 = 0 s the fault is initiated with zero fault impedance
transient voltages which are allowed after the fault in- (𝑅𝑓 𝑎𝑢𝑙𝑡 = 0 Ω and 𝑋𝑓 𝑎𝑢𝑙𝑡 = 0 Ω).
terruption across the breaker poles and represents the
dielectric strength of the breaker. The steady state load current changes into a signif-
icantly higher short circuit current in an oscillatory
manner as shown in Figure 31. After a few ms the
short circuit current is nearly in steady state. At time
𝑡 = 50 s a switch event triggers the CBs to open. The The maximum peak voltages 𝑢𝑐 and rate of rise of re-
short circuit current is then interrupted at the following covery voltage 𝑅𝑅𝑅𝑉 during the transient for the dif-
current zero (zero-crossing) in each phase. ferent phases are as follows :
[kA]
20
10
-10
-20
0 20 40 60 80 [ms] 100
IS.L2.3: Phase Current A/Terminal i
IS.L2.3: Phase Current B/Terminal i
IS.L2.3: Phase Current C/Terminal i
[kV]
300
-300
-600
-900
0 20 40 60 80 [ms] 100
C4_1.1: Phase Voltage A
C4_1.1: Phase Voltage B
C4_1.1: Phase Voltage C
Figure 31: Short circuit current through the CB.L2 during the transient and voltage at substation Central
1000
500
-500
-1000
-1500
50 54 58 62 66 [ms] 70
CB phase A(1): Voltage Difference in kV
TRV Limit Phase A: TRV_limit_neg
TRV Limit Phase A: TRV_limit_pos
1200
800
400
-400
-800
50 54 58 62 66 [ms] 70
CB phase B(1): Voltage Difference in kV
TRV Limit Phase B: TRV_limit_neg
TRV Limit Phase B: TRV_limit_pos
1000
500
-500
-1000
-1500
50 54 58 62 66 [ms] 70
CB phase C(1): Voltage Difference in kV
TRV Limit Phase C: TRV_limit_neg
TRV Limit Phase C: TRV_limit_pos
Figure 32: Transient recovery voltage (TRV) and dielectric strength of circuit breaker