0% found this document useful (0 votes)
123 views2 pages

Sufiyan Power Plant Construction Schedule

Uploaded by

SAMAR QASIM
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
123 views2 pages

Sufiyan Power Plant Construction Schedule

Uploaded by

SAMAR QASIM
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

SUFIYAN TEMPORARY POWER PLANT CONSTRUCTION Classic Schedule Layout 15-Dec-16 10:41

Activity ID Activity Name Start Finish Activity % Budgeted


November
Total 2016 December 2016 January 2017 February 2017
Complete Cost 14 21 28 05 12 19 26 02 09 16 23 30 06
18-Nov-16PLANT
A 23-Jan-17 23-Jan-17, SUFTPP-1 SUFIYAN T
SUFTPP-1 SUFIYAN TEMPORARY POWER CONSTRUCTION $10,372.00
SUFTPP-1.5 GENERALS 18-Nov-16 A 22-Nov-16 A $1,224.80 22-Nov-16 A, SUFTPP-1.5 GENERALS

A1440 Award of Contract 18-Nov-16 A 100% $0.00 Award of Contract, 18-Nov-16 A


A1450 Resource Mobilization 18-Nov-16 A 22-Nov-16 A 100% $1,224.80 Resource Mobilization

SUFTPP-1.1 CIVIL WORKS 19-Nov-16 A 05-Dec-16 A $4,080.00 05-Dec-16 A, SUFTPP-1.1 CIVIL WORKS

SUFTPP-1.1.1 Power Plant Pad Works 19-Nov-16 A 30-Nov-16 A $1,440.80 30-Nov-16 A, SUFTPP-1.1.1 Power Plant Pad Works
A1000
Surveying of pad location 19-Nov-16 A 22-Nov-16 A 100% $52.80 Surveying of pad location
A1010
Selected Material Shifting 22-Nov-16 A 24-Nov-16 A 100% $0.00 Selected Material Shifting
A1020
Grading of the Selected Material 23-Nov-16 A 24-Nov-16 A 100% $776.00 Grading of the Selected Material
A1030
Compaction of Selected Material 23-Nov-16 A 30-Nov-16 A 100% $612.00 Compaction of Selected Material
SUFTPP-1.1.2 Foundations Works 25-Nov-16 A 05-Dec-16 A $1,684.80 05-Dec-16 A, SUFTPP-1.1.2 Foundations Works
A1040
Surveying and Marking of Foundations 25-Nov-16 A 05-Dec-16 A 100% $52.80 Surveying and Marking of Foundations
A1050
Selected Material Placement at Foundations Marks
29-Nov-16 A 29-Nov-16 A 100% $612.00 Selected Material Placement at Foundations Marks
A1060
Leveling of Selected Material 25-Nov-16 A 29-Nov-16 A 100% $408.00 Leveling of Selected Material
A1070
Compaction of Selected Material 29-Nov-16 A 01-Dec-16 A 100% $612.00 Compaction of Selected Material
SUFTPP-1.1.3 Fence Works 29-Nov-16 A 05-Dec-16 A $954.40 05-Dec-16 A, SUFTPP-1.1.3 Fence Works
A1080
Surveying and Marking of Fence 29-Nov-16 A 01-Dec-16 A 100% $26.40 Surveying and Marking of Fence
A1090
Excavation of Pols 29-Nov-16 A 01-Dec-16 A 100% $612.00 Excavation of Pols
A1100
Erection of Fence Pols 01-Dec-16 A 02-Dec-16 A 100% $40.80 Erection of Fence Pols
A1110
Concret of Fence Pols 01-Dec-16 A 02-Dec-16 A 100% $24.00 Concret of Fence Pols
A1120
Installation of Fence Mesh 02-Dec-16 A 05-Dec-16 A 100% $228.00 Installation of Fence Mesh
A1130
Installation of Gate 03-Dec-16 A 05-Dec-16 A 100% $23.20 Installation of Gate

SUFTPP-1.2 MECHANICAL WORKS 01-Dec-16 A 14-Dec-16 A $2,819.20 14-Dec-16 A, SUFTPP-1.2 MECHANICAL WORKS

SUFTPP-1.2.1 Installation of Generator Skids 01-Dec-16 A 05-Dec-16 A $735.20 05-Dec-16 A, SUFTPP-1.2.1 Installation of Generator Skids
A1140
Loading of Generators from PE Warehouse 01-Dec-16 A 01-Dec-16 A 100% $417.60 Loading of Generators from PE Warehouse
A1150
Shifting of Generators at Site 01-Dec-16 A 01-Dec-16 A 100% $0.00 Shifting of Generators at Site
A1160
Offloading of Generators at Site 01-Dec-16 A 01-Dec-16 A 100% $209.60 Offloading of Generators at Site
A1200
Installation of Interconnection Fuel Piping 02-Dec-16 A 05-Dec-16 A 100% $108.00 Installation of Interconnection Fuel Piping
SUFTPP-1.2.2 Installation of Fuel Tank 05-Dec-16 A 07-Dec-16 A $628.80 07-Dec-16 A, SUFTPP-1.2.2 Installation of Fuel Tank
A1170
Installation of Piling Support for Fuel Tank 05-Dec-16 A 05-Dec-16 A 100% $208.00 Installation of Piling Support for Fuel Tank
A1180
Installation of Piling Cap and Support Beam 05-Dec-16 A 05-Dec-16 A 100% $98.40 Installation of Piling Cap and Support Beam

Actual Level of Effort Remaining Work Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work Prepared By: Aqeel Imran © Oracle Corporation
SUFIYAN TEMPORARY POWER PLANT CONSTRUCTION Classic Schedule Layout 15-Dec-16 10:41
Activity ID Activity Name Start Finish Activity % Budgeted
November
Total 2016 December 2016 January 2017 February 2017
Complete Cost 14 21 28 05 12 19 26 02 09 16 23 30 06
A1190
Loading of Fuel Tank from PE Warehouse 05-Dec-16 A 06-Dec-16 A 100% $0.00 Loading of Fuel Tank from PE Warehouse
A1210
Installation of Fuel Tank at Site 06-Dec-16 A 06-Dec-16 A 100% $189.60 Installation of Fuel Tank at Site
A1220
Welding of Fuel Tank with Supports 06-Dec-16 A 06-Dec-16 A 100% $66.40 Welding of Fuel Tank with Supports
A1230
Installation of Connecting Piping with Generators
07-Dec-16 A 07-Dec-16 A 100% $66.40 Installation of Connecting Piping with Generators
SUFTPP-1.2.3 Installation of Transformer Skid07-Dec-16 A 07-Dec-16 A $607.20 07-Dec-16 A, SUFTPP-1.2.3 Installation of Transformer Skid
A1240
Loading of Transformer Skid from PE Warehouse
07-Dec-16 A 07-Dec-16 A 100% $417.60 Loading of Transformer Skid from PE Warehouse
A1250
Shifting of Transformer Skid 07-Dec-16 A 07-Dec-16 A 100% $0.00 Shifting of Transformer Skid
A1260
Offloading of Transformer Skid at Site 07-Dec-16 A 07-Dec-16 A 100% $189.60 Offloading of Transformer Skid at Site
SUFTPP-1.2.4 Miscelleneous Installations 08-Dec-16 A 14-Dec-16 A $848.00 14-Dec-16 A, SUFTPP-1.2.4 Miscelleneous Installations
A1270
Shifting & Installation of Store Container 08-Dec-16 A 08-Dec-16 A 100% $169.60 Shifting & Installation of Store Container
A1280
Shifting & Installation of Office Container 09-Dec-16 A 09-Dec-16 A 100% $169.60 Shifting & Installation of Office Container
A1290
Shifting & Installation of Switchgear Container 12-Dec-16 A 12-Dec-16 A 100% $169.60 Shifting & Installation of Switchgear Container
A1300
Shifting & Installation of AC/DC Distribution Container
13-Dec-16 A 13-Dec-16 A 100% $169.60 Shifting & Installation of AC/DC Distribution Container
A1310
Shifting & Installation of Battery Room Container
14-Dec-16 A 14-Dec-16 A 100% $169.60 Shifting & Installation of Battery Room Container

SUFTPP-1.3 ELECTRICAL WORKS 14-Dec-16 A 20-Jan-17 $2,115.20 20-Jan-17, SUFTPP-1.3 ELECTRICA

SUFTPP-1.3.1 Installation of Electrical Items 14-Dec-16 A 06-Jan-17 $996.00 06-Jan-17, SUFTPP-1.3.1 Installation of Electrical
A1320
Installation of MV Switchgear 14-Dec-16 A 15-Dec-16 A 100% $168.00 Installation of MV Switchgear
A1330
Installation of LV Switchgear 15-Dec-16 A 15-Dec-16 A 100% $168.00 Installation of LV Switchgear
A1340
Installation of Earthing System 15-Dec-16 A 21-Dec-16 70% $352.00 Installation of Earthing System
A1350
Installation of AC/DC Auxiliary Supply Distribution
15-Dec-16 A 06-Jan-17 50% $308.00 Installation of AC/DC Auxiliary Supply Distribution
SUFTPP-1.3.2 Cable Layings 03-Jan-17 17-Jan-17 $947.20 17-Jan-17, SUFTPP-1.3.2 Cable Laying
A1360
LV cable Laying 03-Jan-17 09-Jan-17 0% $240.00 LV cable Laying
A1370
MV Cable Laying 06-Jan-17 12-Jan-17 0% $240.00 MV Cable Laying
A1380
Connections to OHTL 09-Jan-17 13-Jan-17 0% $400.00 Connections to OHTL
A1390
Cable testings 16-Jan-17 17-Jan-17 0% $67.20 Cable testings
SUFTPP-1.3.3 Synchronizations 18-Jan-17 20-Jan-17 $172.00 20-Jan-17, SUFTPP-1.3.3 Synchroni
A1400
Synchronization of Three Generators 18-Jan-17 20-Jan-17 0% $103.20 Synchronization of Three Generators
A1410
Load Sharing Tests 19-Jan-17 20-Jan-17 0% $68.80 Load Sharing Tests

SUFTPP-1.4 Commessioning & 20-Jan-17


Handingover 23-Jan-17 $132.80 23-Jan-17, SUFTPP-1.4 Commes

A1420 Precommissioning of Power Plan 20-Jan-17 20-Jan-17 0% $66.40 Precommissioning of Power Plan
A1430 Commissioning of Power Plant 23-Jan-17 23-Jan-17 0% $66.40 Commissioning of Power Plant

Actual Level of Effort Remaining Work Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work Prepared By: Aqeel Imran © Oracle Corporation