0% found this document useful (0 votes)
10 views3 pages

Handout 4 - CH4

Uploaded by

musfat016
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views3 pages

Handout 4 - CH4

Uploaded by

musfat016
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

ACCT 130 – Principles of Managerial Accounting

Fall 2023, Section 5 & 6


Handout 4 – Chapter 4 &4A Process Costing

Equivalent units-Weighted Average method


Smith Company reported the following activity in the Assembly Department for the month of
June:

Example 1: Calculate Equivalent units of production - Weighted Average Method.


Materials Conversion Total
Units Completed and transferred out of Department
in June
Work in Process, June 30

Equivalent units of Production in the department


during June

Example 2: Compute and apply costs

Use the formula above to compute the cost per equivalent unit of production.

1
Data:
Beginning work in process: 300 units
Materials: 40% complete $ 6,119
Conversion: 20% complete $ 3,920
Production started during June 6,000 units
Production completed during June 5,400 units
Costs added to production in June
Materials cost $ 118,621
Conversion cost $ 81,130
Ending work in process 900 units
Materials: 60% complete
Conversion: 30% complete

Use the cost per equivalent unit for materials and conversion and assign costs to units in the table
below.

Example 3: Assign Costs to Units


Cost of Ending WIP and Units Transferred Out Materials Conversion Total
Ending WIP inventory:
Equivalents units
Cost per Equivalents units
Cost of Ending WIP inventory
Units completed and transferred out:
Units transferred
Cost per equivalent unit
Cost of units transferred out

Equivalent units-FIFO method

Refer to the data provided for Smith Company above concerning the Assembly Department for
the month of June.

Example 4: Calculate equivalent units of production-FIFO method.


Materials Conversion Total
To complete beginning Work in Process:
Materials
Conversion
Units started and completed during June
Ending Work in Process
Materials
Conversion
Equivalent units of Production

2
Reconcile equivalent units of production with Weighted Average method.

Materials Conversion Total


Equivalent units-weighted average method
Less equivalent units in beginning inventory

Equivalent units- FIFO method

Example 5:
Revisit the data for Smith Company’s Assembly Department for the month of June provided
above. Use the cost per equivalent unit for materials and conversion and assign costs to units in
the table below.

The formula for computing the cost per equivalent unit under FIFO method is:

Materials Conversion Total


Cost of Units Transferred Out:
Cost in beginning WIP inventory
Cost to complete beginning WIP
Equivalent units to complete
Cost per equivalent unit
Cost to complete beginning WIP
Cost of units started and completed:
Units started and completed
Cost per equivalent unit
Cost of units started and completed
Cost of Units Transferred Out

You might also like