Construction Labour Rate Date:10/07/2024
SUB : Rate Quotation for Masonry , Plastering and Tiles work.
[Link] DESCRIPTION OF ITEM UNIT RATE
Single brick masonry work. Sft. 35
1
Note : Extra charge for all masonry work at each floor Sft. 10%
Double brick masonry work. Sft. 45
2
Note : Extra charge for all masonry work at each floor Sft. 10%
3 Fixing of door and window frames Nos. 1000
4 Fixing of grill, gate and railing Nos. 900
Single coat plaster with sponge finish Sft. 45
5
Note : Extra charge for each floor for every plaster item. Sft. 10%
External coat plaster with sponge finish Sft. 55
6
Note : Extra charge for each floor for every plaster item. Sft. 10%
7 Groove and drip mould Rmt. 120
8 Balusters fixing Rmt. 350
9 Roof Level Water proofing Sqm. 450
Filling in concrete and masonry joint
10 i] Internal Rmt. 60
ii] External Rmt. 80
Italian marble floor fitting with polish Sft. 100
11
Note : Extra charge for each floor. Sft. 10%
Italian marble wall and cladding fitting with polish Sft. 160
12
Note : Extra charge for each floor. Sft. 10%
Granite floor fitting with polish Sft. 55
13
Note : Extra charge for each floor. Sft. 10%
Granite wall and cladding fitting with polish Sft. 75
14
Note : Extra charge for each floor. Sft. 10%
Marble floor fitting with polish Sft. 65
15
Note : Extra charge for each floor. Sft. 10%
Marble wall and cladding fitting with polish Sft. 85
16
Note : Extra charge for each floor. Sft. 10%
8 x 4 floor tiles fitting Sft. 40
17
Note : Extra charge for each floor. Sft. 10%
8 x 4 wall tiles fitting Sft. 45
18
Note : Extra charge for each floor. Sft. 10%
6 x 4 floor tiles fitting Sft. 35
19
Note : Extra charge for each floor. Sft. 10%
6 x 4 wall tiles fitting Sft. 40
20
Note : Extra charge for each floor. Sft. 10%
4 x 2 or 2 x 2 floor tiles fitting Sft. 35
21
Note : Extra charge for each floor. Sft. 10%
4 x 2 or 2 x 2 wall tiles fitting Sft. 40
22
Note : Extra charge for each floor. Sft. 10%