Model For CC Drain
Model For CC Drain
RWS&S Dept
DETAILED ESTIMATE
Grant : MGNREGS
GP :
Year : 2024-25
Specification report to accompany the original estimate for the
Providing Open Side Drains (Lead Drain) With Cover Slabs from Wellness center to Highschool beside Oora cheruvu H/O CHN
Agraharam Gram Panchayat.
The work was proposed vide procgs R.C.No : 10 , Dt:_23-08-2024__of The Secretary chairman,VWSC CHN
Agraharam,Anakapalli under SBM(G)& MGNREGS funds.
Unskilled labour charges for Earth work excavation and depositing on bank with initial lead of 10mt and initial
1 lift of 2.0 mts in loamy and clayey soils like black cotton soils, red earth and chowdu soils (Ordinary soils) as
per RSSR Item 6b
Rmt
Provision for Supply and filling of sand in trenches, sides of foundations with intial lead in layers not exceeding 15cm thick,
2 comnsolidated each deposited layer by watering and ramming as per drawing and technical specification Excluding GST and
all operational charges etc complete finished item of work. Sand Bed
Vibrated Cement Concrete Nominal Mix (1:3:6) 40 mm down graded HBG Metal including cost of all materials and labour
3 charges etc,,complete -1 cum with Machine mixing for CC Bed including conveyance, seigonarage of materials of sand
&metal and excluding cost of steel and its fabrication charges etc . CC Drain Bed
Vibrated Cement Concrete Nominal mix (1:2:4) using 20mm HBG graded metal including cost of all materials and labour
4 charges etc,,complete -1 cum with Machine mixing for side walls of drains including conveyance, seigonarage of materials of
sand & metal including Centering charges.
Providing concrete for RCC (1:2:4) in open foundations using 20&12 mm nominal size Graded hard stone aggregate,
mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings
5
and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH but excluding VAT and
seigniorage charges for RCC DRAIN COVER SLABS
Providing high yield strength deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of 8mm to 40mm diameters,
cutting, bending, to required sizes and shapes placing in position with cover blocks of approved size and binding wire of
6
20SWG, forming grills for reinforcement work as per approved designs and drawings including cost and conveyance of bars
etc Complted
Cutting open C.C.road surface/Constructions like brick walls/RR foundations with saw cutter including stacking of excavated
7
materials for pipe line trench work as directed by the departmental officers..
a) Bailing out water from the pipe line trenches with oil engine driven pump sets, including hire charges, fuel charges and
8
wages for Driver and Helper.
9 Engaging Unskilled Labour for Light bush clearance(Net Area)- (RSSR)
10 Provision for Name board
11 Provision for Seignorage charges
12 Provision for GST
13 Provision for QC Charges @ 0.5%
14 Provision for Unforeseen items
Assistant Engineer,
RWS&S Anakapalli
Material calculations
S.No Item Qty unit factor 40mm 20mm 12mm Sand for Cement Steel (in RCC Mason Other material Unskilled labour charges
metal metal metal in Kgs MT) PIPES components(Skilled/
semiskilled etc
Filling Plastering Concrete Weight Rate Rate Amount Rate Amount
1157.50 1800.50 1460.10 1362.20 1718.40 1718.40 4220.00 59000.00 2276.55 500
Earth work
1 300.00 Cum
excavartion 211 63300.00
2 Stone dust
Unskilled labour 75.00 Cum 0.31 211 4905.75
3 Selected earth
Unskilled labour 75.00 Cum 0.31 211 4905.75
4 PCC 1:4:8)
Cement 1.00 Cum 162 162
sand for concrete 1.00 Cum 0.48 0.48
40mm metal 1.00 Cum 0.90 0.9
12mm metal 1.00 Cum
Mason 1.00 Cum 0.1 0.1
Other material
component 1.00 Cum 664 664 0.00
unskilled labour 1.00 Cum 1.39 211 293.29
5 PCC 1:3:6)
Cement 66.00 Cum 216 14256
sand for concrete 66.00 Cum 0.48 31.68
20mm metal 66.00 Cum 0.54 35.64
12mm metal 66.00 Cum 0.36 23.76
Other material
component 66.00 Cum 146 9636 0.00
unskilled labour 66.00 Cum 1.39 211 19357.14
6 RCC (1:2:4)
Cement 7.50 Cum 324 2430
sand for concrete 7.50 Cum 0.48 3.6
20mm metal 7.50 Cum 0.54 4.05
12mm metal 7.50 Cum 0.36 2.7
Other material
component 7.50 Cum 689.27 5169.525 0.00
unskilled labour 7.50 Cum 1.39 211 2199.68
Supply and cost of
7 steel 1.93 MT 1.05 2.02 0
unskilled labour 1.93 10 211 4061.75
other component 1.93 6610 12724.25
8 Plastering
Cement 110.83 sqm 0 0.00
sand for concrete 110.83 sqm 0 0.00
Unskilled labour 110.83 sqm 0.99 211 2315.08
Other component 110.83 sqm 0.00 0
Unforseen for cc
9 road cutting 14.00 cum 4902.80 68639.2
Unforseen for
bailing out of
10 water 200.00 hour 192.00 38400
Un skilled labour
for dumping of
11 excavated earth 0.00 cum 211 0.00
Unskilled labour
for jungle
12 clearance 1.00 no 211 211.00
Unforseen for
13 75.00 cum 1
stone dust 438.01 32850.75
14 RCC NP3 pipes
NP3 pipes 500.00 Rmt 1087.00
other component 500.00 Rmt 550.65 275325
Total Quantities In 0.90 39.69 26.46 0.00 0.00 35.76 1087.00 14192.73 ### 2110.00 101549.43
Cum
Total Quantities In 16848.00 2.02
Kgs
a= 1
0.6 0.6
h= 0.6
0.95
0.1 1 0.1
a 0.05
PCC (1:3:6) 0.15
sand filling 0.15
1.50
slope= 0.608276253029822
1.5
2 0.2 0.6 0.24
Rate of Centering charges for 1 Cum Concrete (for side walls only)
4900
DETAILED ESTIMATE
Name of the Work: Pr
ovi
di
ng
Outlet 1 ,Bit1 part 500.00 Rmt 16.00 Lakhs
S. Descri Nos. Measuremen Qty. Rate per Amoun
No ption L t in Mts.
B D/H t
. 1 Unskilled labour
of charges for Earth work excavation and depositing
on bank with item
initial lead of 10mt and initial lift of 2.0 mts in loamy
and clayey soils like black cotton soils, red earth and chowdu soils
(Ordinary soils) as per RSSR Item 6b
MA 40%
Qty. Description of Work Rate Per Amount
II Sand filling
Unit = cum
Taking output = 1 cum
1 a) Cost of sand for filling 1362.20 Cum 1362.20
1 Filling charges as per RSSR 25.59 Cum 25.59
Total 1387.79
Rate per cum 1387.79
8 Providing high yield strength deformed (HYSD) steel bars (Fe 415 grade as per
IS 1786-1985) of 8mm to
Materal
1.05 K High Yield Strengh Deformed Bars HYSD) 1 M.T
59000.00 61950.00
6.00 gK Binding wire 64.00 kg 384.00
gs 62334.00
(b) Labour for cutting, bending, shifting to site, tying and placing in position
20230.00
82564.00
Over head charges @14% 0.000% 54418.00 0.00
0.00
Total per 1 MT 82564.00
14.00 49028
44.70 62615.76
111644
216
324.00
Leads statement
Providing Open Side Drains (Lead Drain) With Cover Slabs from Wellness center to Highschool
beside Oora cheruvu H/O CHN Agraharam Gram Panchayat. SSR 2019-20
Ghat Total 'lead Conveyance-
Name of the Lead Lead
Sl.No Description of material (1.5 (km)i.e Initial cost Excluding Total
Quarry (Plain) ( ghat)
times) (4+6) Col 13.615%
1 40mm size HBG metal Mamidipalem 5.90 5.90 1033.00 124.50 1157.50
2 20mm size HBG metal Mamidipalem 5.90 5.90 1676.00 124.50 1800.50
11 12mm size HBG metal Mamidipalem 9.00 5.90 1350.00 110.10 1460.10
12 10mm size HBG metal Mamidipalem 9.00 5.90 1145.00 110.10 1255.10
8
Qty. Description of Work Rate Per Amount
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum hour 0.40 525.50 210.20
capacity fitted with water measuring device
and preferably also with load cell. Sl. No. 18
Vibrator needle Vibrator hour 0.40 203.50 81.40
Water tanker 6 kl capacity hour 0.13 655.20 85.18
4,523.89
(d) Formwork @ 10% on cost of material, 10.00% 452.39
labour and machinery (a+b+c)
10 Providing concrete for RCC (1:2:4) in open foundations using 20&12 mm nominal size Graded
hard stone aggregate, mechanically mixed, placed in foundation and compacted by vibration
including curing for 14 days complete as per drawings and technical specifications Clause 802, 803,
1202 & 1203 MORD and 1500, 1700 & 2100 MORTH but excluding VAT and seigniorage charges for
RCC DRAIN COVER SLABS
Note : Water for concrete : A provision for cost of water may be added at
1.2 kl / 1 cum (including curing purpose) keeping the site conditions
PART 3 BUILDING WORKS PAGE 138 LAYING AND JOINTING 494 1 MT 494.40
1637.65 818.825
Name of the Work
Material calculations - 16.00 Lakhs
S. Item Qty unit factor 40mm metal in 20mm metal 12mm Sand in cum Cement in Kgs Steel (in MT) RCC PIPES in Stone dust Mason Water Other material Unskilled Total Amount
No cum cum metal cum Rmt cum components(Ski labour charges
lled/ semiskilled
etc
Filling Plastering Concrete
40% 40%
1157.50 1800.50 1460.10 1362.20 1718.40 1718.40 4220.00 59000.00 2276.55 576.10 700 80 588
Earth work
1 300.00 Cum 1
excavartion 300
63300 63300.00
2 Sand filling
Sand 75.00 Cum 1.00 75
Unskilled labour 75.00 Cum 25.59 1919.25
0 0 0 102165.000 0 0 0 0 0 0 1919.3 104084.25
3 PCC 1:3:6)
Cement 75.00 Cum 0.216 16.20
sand for concrete 75.00 Cum 0.45 33.75
40mm metal 75.00 Cum 0.90 67.5
Mason 75.00 Cum 0.10 7.5 5250
Water 75.00 Cum 1.20 90 7200
Other material
component 75.00 Cum 930.30 69772.2
unskilled labour 75.00 Cum 1.39 104.25
78131.25 57996 68364 82222.2 61299 348012.45
4 VCC 1:2:4)
Cement 66.00 Cum 0.324 21.38
sand for concrete 66.00 Cum 0.45 29.70
20mm metal 66.00 Cum 0.90 59.4
12mm metal 66.00 Cum 0.36 0
Water 66.00 Cum 1.20 79.2 6336
Mason 66.00 Cum 0.10 6.6 4620
Other material
component 66.00 Cum 4,029.25 265930.5726
unskilled labour 66.00 Cum 1.39 91.74
106949.7 0 51036.48 90240.48 276886.5726 53943.12 579056.35
5 RCC (1:2:4)
Cement 7.50 Cum 0.324 2.43
sand for concrete 7.50 Cum 0.45 3.38
20mm metal 7.50 Cum 0.9 6.75
12mm metal 7.50 Cum 0.36 0
Water 7.50 Cum 1.2 9 720
Mason 7.50 Cum 0.10 0.75 525
Other material
component 7.50 Cum 930.30 6977.22
unskilled labour 7.50 Cum 1.39 10.43
12153.375 0 5799.6 10254.6 8222.22 6129.9 42559.70
Supply and cost of
6 steel
Steel 1.93 MT 1.05 2.02
Binding wire 1.93 40% 6.00 635.25
unskilled labour 1.93 10.00 19.25
other component 1.93 10.00 16843.75
119253.75 17479 11319 148051.75
Unforseen for cc
7 road cutting 14.00 cum 1 33936
Other component 14.00 cum 0.40 13574.4
47510.4 47510.40
S. Item Qty unit factor 40mm metal in 20mm metal 12mm Sand in cum Cement in Kgs Steel (in MT) RCC PIPES in Stone dust Mason Water Other material Unskilled Total Amount
No cum cum metal cum Rmt cum components(Ski labour charges
lled/ semiskilled
etc
Filling Plastering Concrete
40% 40%
1157.50 1800.50 1460.10 1362.20 1718.40 1718.40 4220.00 59000.00 2276.55 576.10 700 80 588
Unforseen for
8 bailing out of water 200.00 hour 38400.00
38400.00 38400.00
Un skilled labour
for dumping of
9 excavated earth 0.00 cum 0.00
0.00 0.00
sluice valve
With 10%
Extra for
Conveyance-
PN1
6310.00 Bailing out water (oil engine) 53
8337.00 Diesel generating set 30 KVA 1032
10986.00 Truck 10 t 923.7
13634.00
21973.00
30173.00
51039.00
153400.00
165100.00
203400.00
211500.00
276300.00
141 141
7 Painter Cl - II 640
Specials GI Pipe 32 mm B Clss 398 398.00
7 GI Pipe 50 mm B Clss 484 484.00
8 GI Pipe 40 mm B Clss 444 444.00
9 GI Pipe 25 mm B Clss 286 286.00
33 65 mm GI B Class 837 837.00
33 20 mm GI B Class 198 220.00
10 12 mm NP bib tap 248 281.77
11 20 mm GI Pipe 220 249.95
12 20 mm GI Union 51 57.94
13 25 mm GI union 77 87.48
13 32 mm GI union 95 107.93
14 40 mm GI Union 114 129.52
15 50 mm GI Union 142 161.33
16 Saddle piece 0.00
17 GM 40 NRV hor check 2069 2350.69 25.1
18 GM 40 GATE VALVE 2389 2714.26
19 3 core 2.5 mm coper cable 98 111.34
20 6 Sqm WPSC service wire 28 31.81 6000
21 Fuse 32A 100 113.62
22 Single Phase Panel Board 5445 6186.34 upto 1.5HP
23 Cost of 150 mm Bore cover 150
24 2 HP Pump submesible single phase 29403 ### 250mm
25 6-32 A TPN / FP/ MCB 1200 1363.38
180mm UPVC casing pipe #VALUE! 6kg/cm^2
26 25 mm GI Service pipe set including be 150
27 Cost of Shellock bottles 10.00
28 Cost of Cable joint kit 325.00
29 Cost of Teflon tapes 35.00
30 Cost of Insulation tapes 10.00 950
all weathered
acking (per 0.024
146.45
1087.19
1093.16
above 2H 6816.90
1275 1448.59