Ongoing Construction
1 Erection of continuous Dust or wind breaking Photographs attached
Tin/Metal sheet of more than 20 feet height herewith.
around the periphery of entire construction
project site is provided? If yes then provide an
option to upload site
photographs
2 Tarpaulin/Green cloth/Jute sheet to be Noted.
mandatorily used to cover the floor where any
construction activity is in progress and
two floors below
Storage of Construction and Demolition Materials
1 Loose soil, Sand, Construction materials, and Noted.
debris of any kind and quality should be stored
in the demarcated/dedicated area, property
barricaded and
fully covered/enclosed/protected with tarpaulin.
2 Complete ban on dumping of construction Noted.
material and debris on public Roads,
Footpaths, pavements, and open area
3 Appropriate dust extraction system with Noted.
appropriate Air pollution control technology to be
provided, if required.
Construction work of super Structure
1 Chutes, Skips, and transfer points used for Noted.
dropping/transfer of material shall be enclosed
and should be properly operated and maintained
to avoid emission and
spillage
2 Water sprinkling and water fogging should be Noted.
carried out during construction and super
structure construction activity,
material handling operations, loading as well as
unloading material.
3 Grinding, Cutting, drilling, sawing and trimming Noted.
should be carried out in enclosed area and water
sprinkling and water fogging to be used
4 Mixing and manual batching of concrete at the Noted.
site should be avoided. However, in unavoidable
circumstances, it should be done in an
enclosed/confined area
5 Mixing of material for plaster should be Noted.
undertaken in an enclosed/confined area
Transportation ( vehicle carrying materials and construction debris and other
vehicles )
1 Inside the project premises, vehicle movement Noted.
should be slow and should be carried out only on
fixed route. The fixed route should be paved or
hard top and regularly sprinkled with water.
2 All vehicle should be thoroughly cleaned Noted.
after unloading of material.
3 All the vehicles carrying material should be fully Noted.
covered and protected so as to ensure dust from
construction material or debris does not become
air-borne during
transportation.
4 All vehicles carrying material should mandatorily Noted.
obtain pollution under control certificate (PUC)
and shall produce it as and when asked.
5 All vehicles carrying material should be loaded in Noted.
proper manner to avoid spillage
and overloading.
6 After loading and unloading of material, two-level Noted.
tyre washing facility shall be provided at all exit
points. The waste water generated shall be
collected and treated/ reused in construction
process before
disposal.
7 C and D waste generated within the Noted.
premises/site of the work shall be transported to
the designated unloading site strictly as per the
BMC- approved C and D waste management plan
Others
1 Certificate from site supervisor regarding Noted.
Building regarding building construction activity
2 Only after mild water sprinkling- Brushing. Noted.
Brooming, and sweeping should be undertaken
on daily basis. Daily cleaning to be carried out
at the Entry and Exit of the gate and nearby
roads for removal of dust. If possible vacuum
sweeping be carried out at dust laden
areas/routes
3 Other unpaved surfaces and areas with loose Noted.
soil should be adequately water sprinkled
4 Use of green walls, screens, other Noted.
vegetation barriers, and any other
innovative dust-minimizing technologies.
5 DG set (If installed) to be compliant with Noted.
CPCB/MPCB standards, If possible, a temporary
power supply connection is to be
obtained.
6 Mandatorily use of personal protective Noted.
Equipment (PPE)- Mask, Goggles etc
7 All project attracting environmental clearance Noted.
shall carry out third-party Ambient air
monitoring every fortnightly from NABL/MOEF &
CC laboratory
8 Complete Ban on the use of new/Discarded wood Noted.
and/or wood products by construction workers,
Security guards, etc. As a cooking fuel or bonfires
to prevent
open burning.
9 Discarded woods &/or wood products from Noted.
construction and demolition activity to be
disposed of in a scientific manner to avoid
the open burning.