5 Sem Bcom - Costing Methods
5 Sem Bcom - Costing Methods
INTRODUCTION:
The methods or types of costing refer to the methods used in the ascertainment of costs of
products and services. Several methods have been designed to suit the needs of different
industries. The methods of costing to be used in a particular concern depends upon the type
and nature of manufacturing activity. Basically , there are two methods of costing
1. Job costing
2. Process costing
All other methods are variants of either job costing or process costing .the various
methods of costing are as follows.
1. JOB COSTING :Job Costing is that form of specific order costing which applies
where the work is undertaken as an identifiable unit such as:
Manufacture of products to customer’s specific requirements.
Fabrication of certain materials where raw materials are supplied by the customers.
Repairs are done within a factory or at customer’s premises
Internal capital expenditure jobs etc.
2. CONTRACT COSTING:
The nature of the construction work is dependent on the specification given by the contractee
(contractee is the person for whom the construction work is undertaken). The contractee may
be an individual or a partnership firm or a joint stock company. A small contractor takes up
the construction of residential houses. A big contractor will have the capacity to take up big
projects. The construction may involve period ranging from few days to few years.
2
4. Finished product of one process is the raw material for the next process until
completion.
5. It is not possible to trace the identity of any particular lot of input materials.
4. BATCH COSTING: Batch costing is a form of specific order costing. Job costing refers
to costing of jobs that are executed against specific orders whereas in batch costing items are
manufactured for stock. A finished product may require different components for assembly
and maybe manufactured in economical batch lots. When orders are received from different
customers, there are common products among orders, then production orders may be issued
for batches, consisting of a predetermined quantity of each type of product. Batch costing
method is adopted in such cases to calculate the cost of each such batch. Cost per unit is
ascertained by dividing the total cost of a batch by number of items produced in that batch.
5. OPERATING COSTING: This costing method is used to ascertain the cost of rendering
a unit of service. Operating costing is used by undertakings which do not manufacture but
render service. The following are the examples of undertakings using operating costing
method of ascertainment of cost.
Operating costing is similar to unit costing method. Cost of rendering a unit of service
can be ascertained by the preparation of a Cost Sheet.
3
UNIT -2 JOB AND BATCH COSTING
(A)JOB COSTING
Job Costing is that form of specific order costing which applieswhere the work is
undertaken as an identifiable unit such as:
Manufacture of products to customer’s specific requirements.
Fabrication of certain materials where raw materials are supplied by the customers.
Repairs are done within a factory or at customer’s premises
Internal capital expenditure jobs etc.
Under this method, cost are collected and accumulated for each job, workorderor project
separately. Each job can be separately identified and hence it becomes essential to analyse
the cost according to each job.
The industries, where this method of costing is applied, must possess these features ie:
4
DISADVANTAGES OF ORDER COSTING
RECEIVING AN ENQUIRY:
The customer will usually enquire about the price, quality to be maintained, the duration
with in which the order is to be executed and other specification of the job before placing
an order
RECEIVING OF ORDER:
If the customer is satisfied with the quotation price and other term of execution, he
will then place the order.
PRODUCTION ORDER:
If the job is accepted, a production order is made by the planning department. It is in
the form of consultations issued to the foreman to proceed with the manufacture of
product. It is prepared with sufficient copies so that copy of the same may be
given to all the departmental managers or for man who are required to take any part in
the production.
RECORDING OF COST:
The cost are collected and recorded for each job under separate production order
number. Generally, job cost sheet is maintained for each job. This is a document to
record direct material, direct wades and overheads applicable to respective jobs.
5
COMPLETION OF JOB:
On completion of a job, a completion report is sent to costing department. The
expenditure under each element of cost is totalled and the total job cost is ascertained.
The actual cost is compared with the estimated cost so as to reveal efficiency in
operation.
PROBLEMS
Q -1 Following particulars relate to job no 323
Materials used – Rs500
Direct Wages – x – 10 hrs. @Rs2.5perhour
Y – 8 hrs. @Rs3per hour
z- 5 hrs. @Rs4perhour
Variable Overheads:
X-7000 labour hours – Rs7000
Y – 3000 labour hours – Rs6000
Z- 1000 labour hours – Rs4000
Fixed overheads estimated at Rs30000 for 7500 normal working hours.
You are required to calculate the cost of job no 323 and calculate the price to give the
profit of 33 1/3%of selling price.
6
WORKING NOTE:
Variable Overheads
FIXED OVERHEAD
C+P=S
66.666+ 33.33=100
707
[707x100/66.6666]=1060.5- Sales
Batch costing is a form of specific order costing. Job costing refers to costing of jobs that are
executed against specific orders whereas in batch costing items are manufactured for stock. A
finished product may require different components for assembly and maybe manufactured in
economical batch lots. When orders are received from different customers, there are common
products among orders, then production orders may be issued for batches, consisting of a
predetermined quantity of each type of product. Batch costing method is adopted in such
cases to calculate the cost of each such batch. Cost per unit is ascertained by dividing the total
cost of a batch by number of items produced in that batch.
In order to do that a batch cost sheet. The preparation of batch cost sheet is similar to that of
job cost sheet.
Department
Factory overheads are absorbed in labour hours basis and the rate are Rs7per hour for
department A-and Rs4per hour for department B. the firm uses a cost plus system for setting
price and expects a 25% gross profit. Administratine overheads are absorbed at 10% of
selling price. Assuming that 1000 units were produced in batch A-120
7
Calculate the selling price per unit.
8
UNIT -3 PROCESS COSTING, JOINT AND BY- PRODUCTS
1. Costs obtained at the end of the accounting period are only of historical value and
are not very useful for effective control.
3. Where different products arise in the same process and common costs are prorated
to various cost units. Such individual products costs may be taken as only
approximation and hence not reliable but may be taken as the best.
5. The computation of average cost is more difficult in those cases where more than
one type of product is manufactured and a division of the cost elements are
necessary
9
Process Loss-
In many processes, some loss is inevitable. It is essential that accurate records are maintained
to enable control of the items to be affected. The cost department must be kept well
informedthrough the medium of scrap tickets, material credit notes and loss reports etc. It
should be pointed to the supervisors or foreman that any loss as scrap should be measured
and recorded, otherwise production costs will increase. The loss may arise on account of –
It is the loss which is unavoidable on account of inherent nature of production process. Such
loss can be estimated in advance on the basis of past experience or data. The normal loss is
recorded only in items of quantity and the cost per unit of usable production is increased
accordingly.
Any loss caused by unexpected or abnormal conditions such as plant break down, sub-
standard materials, accident etc. or loss in excess of the margin anticipated for normal
process loss should be regarded as abnormal process loss. The units of abnormal loss are
calculated as under –
Loss on account of abnormal wastage is borne by production, but by profit & loss a/c. if
abnormal wastage realizes some value, the realizable value is deducted from the cost of
abnormal wastage and only the difference is charged to costing P&L A/c.
Abnormal gain-
Normal wastage is only an estimated one. The actual wastage may be more than
the normal wastage or it can be less also, where the actual wastage is more than the
expected normal wastage, it is called abnormal wastage. On the other hand, if the actual
wastage is less than expected it is called abnormal gain.
JOINT PRODUCTS
When two or more products of equal importance and value are produced
simultaneously in a process, such products are called join products. For example, where
crude petroleum is the main product, fuel oil, kerosene, are join products.
10
1. which are produced in the same process with the same material.
2. which are separated in the course of the same process.
3. which are comparatively of the same importance and value.
4. which require further processing to finish them into useful and valuable products.
1. Join products are like twins emerging from the same process. Co-products do not
emerge from the same material and process.
2. Join products are produced simultaneously in automobile industry motor cars,
jeeps, trucks, scooters etc. are co-products. It depends on the choice of the
manufacturer whether to produce more of cars or more of jeeps.
BY-PRODUCTS
By-products are defined as the “products recovered from materials discovered in a main
process or from the production of some major product, where material value is to be
considered at the time of severance from the main product.”
In case of dairy industry, butter and cheese are the main products. Butter milk is the
by-product.
At the end of the accounting period work-in-progress or unfinished units may arise. The
valuation of such work-in-progress is complicated. This is because as on the data of valuation
the product may have reached different stages of completion as regards to different elements
of cost. For example- 1000 units introduced into a process are complete
Solution-
11
Overhead= 1000 units * 100% = 1000units
2000units
1. Find out the percent of work needed to complete unfinished units(express this in
units).
2. Add the no. of units completed during the period.
3. Add percentage of work done on closing stock.
Problems:1
4500 units were issued at a cost of rs 31500. An amount of rs 18000 and 13500 were
spent on labour and overhead respectively. At the end of the month 3000 units were
completed and transffered to the next process.
The closing work in progress accrued for 1500 units which recorded the following
expenses:
100% on material
60% on labour
Find out the cost of units completed and the cost of closing wip and the total cost of
equipment production
12
Statement showing equivalent production
Closing
WIP 1500 1500 100% 900 60% 600 40%
15.36
Closing W.I.P
62979
13
Problem 2 :
A – 14250
B – 13650
PROCESS A a/c
14
Cost per unit = 25575-112.5/14550 =1.75
PROCESS B A/C
Input -14250
Expected - 13395
Actual – 13650
15
Process C A/ C
Input -13650
Expected - 12285
Actual – 12012
16
ABNORMAL GAIN A/C
17
UNIT -4 CONTRACT COSTING
The nature of the construction work is dependent on the specification given by the contractee
(contractee is the person for whom the construction work is undertaken). The contractee may
be an individual or a partnership firm or a joint stockcompany. A small contractor takes up
the construction of residential houses. A big contractor will have the capacity to take up big
projects. The construction may involve period ranging from few days to few years.
xxxx xxxx
18
The contract A/c is prepared in order to ascertain the cost incurred on the contract and the
profit made. If the contract is complete, whole of the profit is transferred to P/L A/c. On the
other hand, if the contract is incomplete, only a portion of the profit is transferred to P/L A/c.
The remaining profit is kept as a reserve to meet contingencies.
25% but less than 50% Estimated profit * 1/3 * Cash received/ Work
certified
50% but less than 90% Estimated profit * 2/3 * cash received/work
certified
Above 90% but less than 100% Estimated profit * work certified/contract
price
PROBLEMS
1. XY company ltd contractors began their business on 1.1.93. During the year the
company was engaged on only one contract. The contract was Rs.500000 of the plant
and materials charged to the contract, the plant worth Rs.5000 & materials worth
Rs.4000 were lost in an accident. On 31st December plant which cost Rs.5000 each
returned to stores. The cost of work done but uncertified was Rs.2000 and the
materials costing Rs.4000 were in hand on site. Charge 10% depreciation on the plant
& complete the contract A/c and Balance sheet from the trial balance on 31.12.93 –
19
Particulars Debit Credit
Charge to contract –
Materials 90000
Plant 25000
Wages 140000
Expenses 70000
330,000 330,000
Contract A/C
20
To materials 90000 P/L A/c –
To plant 25000 By material lost 4000
To wages 140000 By plant lost 5000
To expenses 7000 By plant returned to shares 5000
283,000 283,000
21,000 21,000
Working note –
= 21000 * 2 * 200000
3 250000
= 11,200
21
BALANCE SHEET
Liabilities Amount Assets Amount
Plant 25000
(-)plant lost (-) 5000
20000
(-)dep 10% (-) 2000 18000
1,32,200 1,32,200
This costing method is used to ascertain the cost of rendering a unit of service. Operating
costing is used by undertakings which do not manufacture but render service. The following
are the examples of undertakings using operating costing method of ascertainment of cost.
Operating costing is similar to unit costing method. Cost of rendering a unit of service
can be ascertained by the preparation of a Cost Sheet.
22
Build-Up-Cost
The cost of operating is enumerated for a period say monthly, quarterly etc. They are
related to the service rendered during that period.
The build-up of cost depends upon whether only the service is rendered or whether
the service is first produced and then rendered. For example; in case of electric supply
company, electricity is first generated and then distributed.
(B)Maintenance charges –
xxx xx
1.Garage staff salaries xxx xx
2.Garage expenses xxx xx
3.Repairs & renewals xxx xx
4.Overhauling expenses xxx xx
5.Cleaning expenses
Subtotal(B) xxx xx
(C)Operating charges –
xxx xx
1.Petrol/Diesel xxx xx
2.Oil & Grease xxx xx
3.Salary of Drivers, Conductor, Cleaners xxx xx
4.Depreciation of tires, battery
xxx xx
23
Subtotal(D)
PROBLEMS
The truck carries goods to and from the city covering a distance of 50kms each
way on onward trip. Freight is available to the extent of full capacity and on return
20% of capacity.
The truck runs on an average 25days a month, work out operating cost per ton
km.
Solution –
Calculation of Ton-km :-
24
1750 0.23
Subtotal(A)
- -
(B) Maintenance charges –
(C) Operating charges – 750
1.Diesel – 15 per trip(15 * 2 * 25) 500
2.Drivers wages 250
3.Cleaners wages
1500 0.20
3250 0.43
Subtotal (B)
25
26
27
28
29
30
31
32
33
34
35
36