Api 520521 Day3 TBS
Api 520521 Day3 TBS
MODULE 4
Relief Rate Quantification: Fire Contingency
INTRODUCTION Prepared by: Ezaideen Ahmad 5
Lesson Objectives
• After completing this lesson, you will be able to:
• Identify fire contingency relief loads and specific equipment that requires protection in a fire
• Perform an overpressure analysis based on fire contingency
• Determine wetted areas within vessels
• Find the heat of vaporization for single- and multi-component fluids during a fire overpressure relief
scenario
• Calculate the required relief rate of horizontal and vertical wetted vessels and dry vessels for a fire design
contingency
Prepared by: Ezaideen Ahmad 6
MODULE 4
Fire Contingency: Equipment To Be Protected From Fire
EQUIPMENT TO BE PROTECTED FROM FIRE Prepared by: Ezaideen Ahmad 7
MODULE 4
Fire Contingency: Vessels Containing Liquids
VESSELS CONTAINING LIQUIDS Prepared by: Ezaideen Ahmad 10
Q L V
W
L
• Where:
• W = Vapor Release Rate, Lb/Hr
• Q = Heat Absorbed, BTU/Hr
• λ = Heat Absorbed per Pound of Liquid Vaporized, BTU/lb
VESSELS CONTAINING LIQUIDS Prepared by: Ezaideen Ahmad 11
• Where:
• Q = Heat Absorbed, BTU/Hr
• F = Environmental Factor, Dimensionless
• A = Vessel Wetted Surface Area, ft2
• Good Drainage – Paved Areas; Typically Process Units
• Poor Drainage – Unpaved Areas; Typically Tank Farms
VESSELS CONTAINING LIQUIDS Prepared by: Ezaideen Ahmad 12
MODULE 4
Fire Contingency: Effect of Insulation on Fire Loads
EFFECT OF INSULATION ON FIRE LOADS Prepared by: Ezaideen Ahmad 16
• Insulation Conductivity:
o
• Gunite and Concrete: K = 8 Btu-in/Hr Ft2 F
EFFECT OF INSULATION ON FIRE LOADS Prepared by: Ezaideen Ahmad 17
• Note that insulation used to reduce fire relief loads does not
necessarily qualify as fireproofing.
EFFECT OF INSULATION ON FIRE LOADS Prepared by: Ezaideen Ahmad 18
• Insulation of vessels solely for the purpose of reducing fire relief loads (e.g.,
where heat conservation or personnel protection is not required) is seldom
economical and requires a careful assessment of the risks associated with
potential corrosion under the insulation, especially for vessels operating
under 250oF
EFFECT OF INSULATION ON FIRE LOADS Prepared by: Ezaideen Ahmad 19
Material Conductance F
Mineral Wool (1” min.) 1 0.075
Gunite (1.5”) 5.3 0.40
Bare 1
EFFECT OF INSULATION ON FIRE LOADS Prepared by: Ezaideen Ahmad 20
k (1660 T )
F
21,000t
• Where:
• F = Environmental Factor (0.075 minimum)
• k = Thermal Conductivity, BTU-in/hr-ft2oF
• T = Relieving Temperature, oF
• t = Insulation Thickness, Inches
MODULE 4
Fire Contingency: Determining Wetted Areas For Fire
DETERMINING WETTED AREAS FOR FIRE Prepared by: Ezaideen Ahmad 22
Horizontal Vessels
• Wetted Surface for Horizontal Vessels:
1. Determine the Expanded Liquid Level (XLL) at the onset of relief
2. For a horizontal drum with an XLL that is below the drum centerline, the wetted
area includes all of the vessel surface up to the XLL regardless of the elevation
3. For a horizontal drum with an XLL that is above the drum centerline, the wetted
area includes the vessel surface up to centerline regardless of elevation plus any
additional vessel surface between the centerline and the lesser of XLL or 25 feet
above grade level
DETERMINING WETTED AREAS FOR FIRE Prepared by: Ezaideen Ahmad 23
W ET T ED AR EA
W ET T ED AR EA
25 FEET
WETTED AREA
DETERMINING WETTED AREAS FOR FIRE Prepared by: Ezaideen Ahmad 25
Vertical Vessels
• For a vertical drum, consider the vessel surface up to the Expanded Liquid Level
(XLL) within 25 feet of grade including the vessel bottom head if applicable
• If the entire vessel is more than 25 feet above the grade, then consider only the
vessel bottom head if applicable
• Fractionating towers are considered the same as vertical drums, except that the
liquid inventory of the trays or packing is added to the HLL before calculating
the XLL
• In all cases, the Expanded Liquid Level (XLL) should be used in determining the
extent of the wetted surface
DETERMINING WETTED AREAS FOR FIRE Prepared by: Ezaideen Ahmad 26
HLL
ADD EQUIVALENT
" DUMPED" LIQUID
T O HLL
HLL
W ET T ED AREA
HLL
HLL
W ET T ED AREA
25 FEET
W ET T ED AREA
WETTED AREA
DETERMINING WETTED AREAS FOR FIRE Prepared by: Ezaideen Ahmad 29
Spheres
• For a storage sphere, consider the greater of:
• The total exposed surface of the sphere within 25 feet of grade
• The total exposed surface of the sphere below the horizontal center line
• Storage spheres are always assumed to be 100% full of liquid at the onset of
the fire and the entire surface of the sphere is assumed to be wetted.
However, only the surface calculated above is considered as being exposed
to radiation from the fire.
DETERMINING WETTED AREAS FOR FIRE Prepared by: Ezaideen Ahmad 30
Spheres (Continued)
TOTAL EXPOSED TOTAL EXPOSED
SURFACE BELOW
SURFACE WITHIN OR HORIZONTAL
25 FEET OF GRADE CENTERLINE
HLL
CENTERLINE
HLL
WETTED AREA
25 FEET
WETTED AREA
WETTED AREA
(up to arrows)
DETERMINING WETTED AREAS FOR FIRE Prepared by: Ezaideen Ahmad 31
Spheres (Continued)
• If the top of the sphere is within 25 feet of grade, the entire surface
of the sphere is normally considered as exposed wetted area
regardless of the location of high-liquid level (HLL). An exception
may be made in the case of spheres in which the location of the HLL
is significantly lower than the top of the sphere.
Prepared by: Ezaideen Ahmad 32
MODULE 4
Fire Contingency: Determining Heat for Vaporization
DETERMINING HEAT OF VAPORIZATION Prepared by: Ezaideen Ahmad 33
• The peak relief load will always occur at the start of the fire, when the
wetted surface, A, and consequently, the heat input, Q, are both at a
maximum
• The latent heat, vaporization temperature, and physical properties of the
liquid and vapor phases in equilibrium remain constant as the vaporization
proceeds
DETERMINING HEAT OF VAPORIZATION Prepared by: Ezaideen Ahmad 34
Multi-Component Systems
• Vaporization of the liquid in the vessel proceeds as a batch distillation
• Not all the heat absorbed by the system goes into vapor generation.
Some of it is sensible heat that goes into increasing the system
equilibrium temperature as the vaporization proceeds.
• The peak relief load may or may not coincide with the start of the fire
DETERMINING HEAT OF VAPORIZATION Prepared by: Ezaideen Ahmad 37
MODULE 4
Fire Contingency: Dry Vessels
DRY VESSELS Prepared by: Ezaideen Ahmad 40
General Considerations
• For dry vessels, or for vessels that contain supercritical fluids (or fluids that
become supercritical as a result of the fire), overpressure protection by a
pressure relief valve, by itself, is not effective in the prevention of vessel
rupture since, eventually, the exposed vessel will fail due to overheating
• A pressure relief valve, on the other hand, merely prevents the pressure
from rising significantly above the MAWP of the equipment, but does not
relieve the internal pressure
DRY VESSELS Prepared by: Ezaideen Ahmad 42
2. Vertical Vessels
• The exposed surface within 25 ft (7.5 m) of grade is used. If the entire vessel is
more than 25 ft (7.5 m) above grade, then only the surface of the bottom head
need be included. For vessels supported on skirts that do not require fireproofing
of their inside surface, the surface of the bottom head need not be included in the
exposed surface area regardless of elevation.
DRY VESSELS Prepared by: Ezaideen Ahmad 49
• The dry vessel relief rate equation is based on ideal gas behavior and may
not be accurate for fluids that deviate significantly from ideality, such as
supercritical fluids
MODULE 4
Fire Contingency: Determining Fire Load Example Calculation
Prepared by: Ezaideen Ahmad
DETERMINING FIRE LOAD EXAMPLE CALCULATION 52
• The required relief load for each source should be calculated first and
then combined with the individual relief loads from other sources
Prepared by: Ezaideen Ahmad
DETERMINING FIRE LOAD EXAMPLE CALCULATION 53
General Assumptions
1. Assume that at relieving conditions the system is far removed from the
critical point such that (L - V) / L 1.0. This assumption is conservative
because this density factor should always be less than 1.
3. Both process vessels are located in a paved process area with good
drainage
Prepared by: Ezaideen Ahmad
DETERMINING FIRE LOAD EXAMPLE CALCULATION 54
• When finished, check your answers with the results in the next lesson
Prepared by: Ezaideen Ahmad 58
MODULE 4
Fire Contingency: FRACTIONATOR RESULTS
FRACTIONATOR RESULTS Prepared by: Ezaideen Ahmad 59
• The “dumped” liquid level is 11.44 feet from the bottom tangent line.
However, only 10 feet are within 25 feet of grade, since the bottom tangent
line is 15 feet above grade. Thus the wetted area is the sum of the area of
the bottom head plus the cylindrical area of the shell up to 10 feet above
the bottom tangent line.
FRACTIONATOR RESULTS Prepared by: Ezaideen Ahmad 61
• Relief Rate:
Q L V
W
L
FRACTIONATOR RESULTS Prepared by: Ezaideen Ahmad 63
MODULE 4
Fire Contingency: FRACTIONATOR RESULTS
OVERHEAD DRUM RESULTS
OVERHEAD DRUM RESULTS Prepared by: Ezaideen Ahmad 66
• The wetted area within 25 feet of grade is half the area of the cylindrical shell
plus half the area of the vessel heads
• Shell area: (5.50 ft)(15 ft)(0.50) = 130 ft2
• Head area: (2)(32.8 ft2)(0.50) = 32.8 ft2
• Total Wetted Area: 130 ft2 + 32.8 ft2 = 162.8 ft2
OVERHEAD DRUM RESULTS Prepared by: Ezaideen Ahmad 67
• Relief Rate:
Q L V
W
L
OVERHEAD DRUM RESULTS Prepared by: Ezaideen Ahmad 69
• The same considerations regarding the use of the density correction factor
discussed under “Fractionators Relief Load” apply to the Overhead Drum Relief
Load
Prepared by: Ezaideen Ahmad 70
MODULE 4
Fire Contingency: FRACTIONATOR RESULTS
COMBINED RELIEF RATE
COMBINED RELIEF RATE Prepared by: Ezaideen Ahmad 71
Mixture Temperature:
Solve For the Temperature Using a Heat Balance
Q = Wdrum Cpdrum (T-227) = Wfrac Cpfrac (622-T)
Q = (11,937 lb / hr) (0.43 Btu / lb°F) (T-227) =
(2177 lb / hr) (0.58 Btu / lb°F) (622-T)
T = 305°F
COMBINED RELIEF RATE Prepared by: Ezaideen Ahmad 72
MODULE 4
Fire Contingency: Summary
SUMMARY Prepared by: Ezaideen Ahmad 74
Lesson Objectives
• After completing this lesson, you will understand how to evaluate the
control valve failure contingency as a basis for determining the need for
protection against overpressure
• In particular, you will be able to identify:
• The cases to be considered when assessing the requirement for protection from
overpressure
• The assumptions to be made regarding the flow through control valve bypasses
• The downstream pressure to be considered in determining the flow rate through a
failed control valve
• The effects of the pump curve on the required relief flow rate when the potential
overpressure source is a centrifugal pump
• Additional issues that should be examined when assessing flow through a control
valve that could affect the sizing of relief devices
Prepared by: Ezaideen Ahmad 76
MODULE 4
Control Valve Failure Contingency
GENERAL PRINCIPLES Prepared by: Ezaideen Ahmad 77
Basics (1/2)
• Control valves are specified to fail open (FO), fail closed (FC) or fail
stationary (FH) upon loss of the actuating medium (usually instrument air)
• Often referred to as the “Fail Safe” position
• The designer is responsible for selecting the failure position based upon which
position is most safe
• Fail Stationary is also commonly referred to as Fail Hold
GENERAL PRINCIPLES Prepared by: Ezaideen Ahmad 78
Basics (2/2)
• Control valves that fail stationary will eventually “drift” to the fully open
(FH-O) or fully closed (FH-C) position
• Drift position needs to be specified
• Any individual control valve may go to the fully open or fully closed position
at any time regardless of its specified failure position
• As a result of controller actions, instrument malfunctions or mechanical damage
• Contingency analysis must take this into consideration
GENERAL PRINCIPLES Prepared by: Ezaideen Ahmad 79
Review Question #1
Click on the correct answer
Which is not a control valve failure contingency that needs to be considered?
X Incorrect!
Fail openFail of open of a control
a control valvevalve
which which lets
lets down high-pressure
down high-pressure vapor vapor to a
low-pressure system. Fail open of a control valve which lets down fluid from high
to a low-pressure
pressure to low is a key system
contingency of concern.
X Incorrect! Fail close of a control valve in a vessel outlet stream. This
Fail closemust
contingency of abecontrol
evaluatedvalve
sincein a vessel
it can outlet stream
lead to overpressure or liquid overfill of the
downstream vessel.
Correct! Fail close of a control valve adding heat to a system. If the addition of
Fail
energyclose
to the of a control
system valve
is stopped as a adding heat valve
result of control to a failure,
system the system is
generally in a safer state. Fail open of this control valve would be a concern.
X Incorrect!
Fail openFail of open of a letdown
a letdown valvevalve normally
normally passing liquid,
passing liquid,followed
followed by loss
by
of liquid level. Vapor blow-through is a contingency of concern since it will pressure
loss
up theof liquid level
downstream equipment.
Prepared by: Ezaideen Ahmad 83
MODULE 4
Control Valve Failure Contingency: Gas Blowby
BLOW-THROUGH CONTINGENCIES Prepared by: Ezaideen Ahmad 84
Blow-through Contingencies
• For contingencies involving control valves failing in the full open position that are
equipped with bypasses, the possibility that the bypass valve may be partially or fully
open must be considered in determining the relief requirements
TO ATMOSPHERE OR FLARE
BYPASS VALVE
BLOW-THROUGH CONTINGENCIES Prepared by: Ezaideen Ahmad 85
Additional Considerations
• If flow through the wide open control valve is mixed phase, then this should
be considered when determining the maximum flow through the control
valve
• As a conservative simplification, the flow rate through the partially open
bypass valve may be assumed to be equal to 50% of the flow rate through
the fully open control valve
• Instead of 50% of the flow rate through the control valve in its normal operating
position
• When taking credit for partial relief through normal process channels, any
control valve in the process relief path that does not close in response to
the incident must be assumed to remain in the position corresponding to its
operating capacity at the time of the incident
• Consider both design capacity and nominal turndown operations
BLOW-THROUGH CONTINGENCIES Prepared by: Ezaideen Ahmad 92
Review Question #2
Click on the correct answer
Which of the following is a remote contingency?
X Incorrect!CCVfails
failswide
wideopen
open with
with bypass
bypasspartly
partlyopen.
openFailure of a
V
control valve with its bypass partially open is a “Design” contingency.
Correct! CCV fails wide open with bypass fully open. Failure of a control
V fails wide open with bypass fully open
valve with its bypass fully open is a remote contingency.
MODULE 4
Control Valve Failure Contingency:
Control Valves in a Pressurization Path
Prepared by: Ezaideen Ahmad
CONTROL VALVES IN A PRESSURIZATION PATH 96
Review Question #3
Click on the appropriate answer
Which of the following statements about control valves in pressurization paths is
false?
MODULE 4
Control Valve Failure Contingency:
Control Valves in a Relief Path
CONTROL VALVES IN A RELIEF PATH Prepared by: Ezaideen Ahmad 99
Review Question #4
Click on the correct answer
Which of the following valve setups is not allowed in a relief path?
X Incorrect! ValveValve
with minimum flow cutout.
with minimum flow Control
cutoutvalves with cutouts are
allowed when specific conditions (e.g., hole is sized to pass design relieving rate)
are met.
X Incorrect! Two way Twoparallel
way parallel
butterflybutterfly valvesbutterfly valves are allowed
valves. Parallel
when specific conditions (e.g., valve stems are mechanically linked and single
actuator manipulates both valves) are met.
X Incorrect! ThreeThree way valves
way valves. 3-way valves are allowed when specific conditions
(e.g., there is an adequate relief path regardless of valve position) are met.
MODULE 4
Control Valve Failure Contingency:
Calculations
Prepared by: Ezaideen Ahmad
CONTROL VALVE CONTINGENCY CALCULATIONS 104
Basics
• In design calculations the flowrate is known and the selection of control
valve size involves determining the valve flow coefficient, CV
• In blow-through calculations, the CV is known and it is the flow rate that is
calculated (through the valve and any bypass)
• The equations for determining the required CV for a given flow rate or the
flow rate for a given CV are presented in DP-XII-F
• PDR’s Pegasys EMoValve is a useful software tool for performing these calculations
• To use these equations, it is necessary to know the pressures upstream and
downstream of the control valve so that the pressure drop across the
control valve and the resulting flow rate can be calculated
Prepared by: Ezaideen Ahmad
CONTROL VALVE CONTINGENCY CALCULATIONS 105
Upstream Pressure
• Upstream pressure is defined as the maximum normal pressure
• i.e., the maximum pressure that can be expected upstream of the control valve within
the range of normal operations
• The maximum normal pressure does not equal the maximum pressure that
could be reached upstream of the control valve as a result of abnormal
conditions
• For example, a pressure relief event upstream of the control valve
• When the source of pressure is a centrifugal pump or compressor, the
maximum upstream pressure depends on the head/capacity curve
• An iterative solution may be required to determine the maximum pressure upstream
of the control valve
Prepared by: Ezaideen Ahmad
CONTROL VALVE CONTINGENCY CALCULATIONS 106
Control Valve ΔP
• Generally, the control valve ΔP used to calculate either the required
CV for a given flow rate or the flow rate for a given CV will be the
difference between the upstream and downstream pressures
• For control valves in vapor service, the control valve ΔP to be used in
the sizing/capacity equations cannot exceed the critical ΔP
• Critical ΔP is defined as the pressure drop across the valve which results in
sonic (choked) flow at the control valve orifice
• The same ΔP limitations apply to control valves in flashing liquid service or in
cavitating service
• Refer to DP-XII-F for additional information on control valve ΔP limits for
vapor, flashing liquid or cavitating service
Prepared by: Ezaideen Ahmad
CONTROL VALVE CONTINGENCY CALCULATIONS 109
Review Question #5
Click on the correct answer
Which of the following is not required when calculating control valve blowthrough
capacity?
MODULE 4
Control Valve Failure Contingency:
Single Phase Blowby
EXAMPLE #1: SINGLE-PHASE BLOW-THROUGHPrepared by: Ezaideen
– PROBLEM Ahmad
STATEMENT 113
Problem Statement
• A flushing oil supply system operating at two different pressure levels is fed
from a single pump
• See the simplified flow diagram on the next slide
• The low-pressure section of the system is fed from the pump discharge via a
pressure control valve
• Control valve is specified fail open
• Determine the required relief rate for the pressure relief valve protecting
the low-pressure system for the contingency of failure of the pressure
control valve in the full open position
• Be sure to consider both the design contingency and the remote contingency cases
EXAMPLE #1: SINGLE-PHASE BLOW-THROUGHPrepared by: Ezaideen
– PROBLEM Ahmad
STATEMENT 114
SET @ 230
PR PSIG
LOW PRESSURE
FLUSHING OIL
60 GPM NORMAL
SET @ 100 20 GPM MIN.
PSIG 100 PSIG MIN.
PC
150
300
FO
P-1--
HIGH PRESSURE
FLUSHING OIL
40 GPM NORMAL
10 GPM MIN.
500 PSIG MIN.
FLUSHING OIL PUMP
100 GPM
P = 450 PSI
S.G. = 0.750
EXAMPLE #1: SINGLE-PHASE BLOW-THROUGHPrepared by: Ezaideen
– PROBLEM Ahmad
STATEMENT 115
600
500
DIFFERENTIAL PRESSURE, PSI
400
300
200
100
0
0 20 40 60 80 100 120 140 160 180 200
CAPACITY, GPM
EXAMPLE #1: SINGLE-PHASE BLOW-THROUGHPrepared by: Ezaideen
– PROBLEM Ahmad
STATEMENT 117
MODULE 4
Control Valve Failure Contingency:
Single Phase Blowby Calculation
EXAMPLE #1: SINGLE-PHASE BLOW-THROUGHPrepared by: EzaideenSOLUTION
– CALCULATION Ahmad 120
q Gf 60 0.75
CV = = = 2.6
N1 (p1 - p2 ) 1.0 (500 - 100)
7. HP Flushing Oil Flow Rate during relief = 10 GPM (corresponding to maximum pump
discharge Calculation pressure)
8. Calculated pump flow rate during relief
HP Flushing Oil Flow Rate = 10 GPM
Control Valve + Bypass Flow Rate = 192 GPM
Total = 10 + 192 = 202 GPM
EXAMPLE #1: SINGLE-PHASE BLOW-THROUGH – CALCULATION SOLUTION
Control Valve
Pump Flow Pump Pump Control Valve plus Bypass HP Flushing Calculated
Rate Suction Discharge Downstream Control Valve Flow Rate Oil Flow Rate Pump Flow
GPM Pump ΔP, psi Pressure psig Pressure psig Pressure psig ΔP psi GPM GPM Rate GPM
0 564 75 639 345 294 198 10 208
10 560 75 635 345 290 197 10 207
20 554 75 629 345 284 194 10 204
30 546 75 621 345 276 192 10 202
40 537 75 612 345 267 189 10 199
50 526 75 601 345 256 185 10 195
60 514 75 589 345 244 180 10 190
70 500 75 575 345 230 175 10 185
80 485 75 560 345 215 169 10 179
90 468 75 543 345 198 163 10 173
100 450 75 525 345 180 155 10 165
110 430 75 505 345 160 146 10 156
120 409 75 484 345 139 136 10 146
130 386 75 461 345 116 124 10 134
140 361 75 436 345 91 110 10 120
150 335 75 410 345 65 93 10 103
160 308 75 383 345 38 71 10 81
170 279 75 354 345 9 35 10 45
EXAMPLE #1: SINGLE-PHASE BLOW-THROUGH – CALCULATION SOLUTION
MODULE 4
Control Valve Failure Contingency:
Two Phase Blowby
Prepared by:STATEMENT
EXAMPLE #2: TWO-PHASE BLOW-THROUGH – PROBLEM Ezaideen Ahmad 133
Problem Statement
• A low pressure drum receives feed from a high pressure separator
• See flow diagram on next slide
• The low pressure drum is fed via a level control valve
• Control valve is fail closed
• Determine the required relief rate for the pressure relief valve protecting
the low-pressure system for the contingency of failure of the level control
valve in the full open position
• Be sure to consider both the design contingency and the remote contingency cases
Prepared by:STATEMENT
EXAMPLE #2: TWO-PHASE BLOW-THROUGH – PROBLEM Ezaideen Ahmad 134
LC
FC
Control Valve
DP = 665 psi
Flow = 2,200 gpm
S.G. = 0.637
Prepared by:STATEMENT
EXAMPLE #2: TWO-PHASE BLOW-THROUGH – PROBLEM Ezaideen Ahmad 135
MODULE 4
Control Valve Failure Contingency:
Two Phase Blowby Calculation
Prepared by: Ezaideen
EXAMPLE #2: TWO-PHASE BLOW-THROUGH – CALCULATION Ahmad
SOLUTION 137
q Gf 2200 0.637
CV 99.5
N1 FL ( p1 - FF pv ) 1.0 0.90 (785 0.51 785)
CV Cv 1.2 119.4
EXAMPLE #2: TWO-PHASE BLOW-THROUGH – CALCULATION SOLUTION
q Gf 1508 0.667
CV 48.8
N1 ( p1 - p 2 ) 1.0 (770 132)
EXAMPLE #2: TWO-PHASE BLOW-THROUGH – CALCULATION SOLUTION
Step 6.5 – Calculate the percentage of the total flow that can actually
pass through the valve and bypass
Cv(design ) 100 209.7 100
% Flow 58.6%
Cv(comb) 357.7
4. Flow rate through the control valve plus bypass during relief
• Use the same procedure as was followed for the design contingency
EXAMPLE #2: TWO-PHASE BLOW-THROUGH – CALCULATION SOLUTION
q Gf 1630 0.662
CV 54.6
N1 ( p1 - p 2 ) 1.0 (770 180)
EXAMPLE #2: TWO-PHASE BLOW-THROUGH – CALCULATION SOLUTION
w T1 318,527 1009.67
CV 289.5
4) Calculate the CV N8 p1Y Mx 19.3 784.7 0.664 21.20 0.57
Prepared by: Ezaideen
EXAMPLE #2: TWO-PHASE BLOW-THROUGH – CALCULATION Ahmad
SOLUTION 151
CV (liquid) = 54.6
CV (vapor) = 289.5
Cv(comb) Cvl Cvv 54.6 289.5 344.1
Step 4.5 – Calculate the percentage of the total flow that can actually pass through the
control valve and bypass
MODULE 4
Control Valve Failure Contingency:
Summary
SUMMARY Prepared by: Ezaideen Ahmad 154
Module Objectives
• After completing this module, you will be able to:
• List the advantages and disadvantages of each type of Pressure Relief Device
(PRD)
• Explain the different types of backpressure and its impact on the operation of
the different types of PRDs
• Explain the reasoning behind the specification of a proposed PRD
Prepared by: Ezaideen Ahmad 157
MODULE 5
DEFINITIONS
DEFINITIONS Prepared by: Ezaideen Ahmad 158
“Valves”
The terms relief valve, safety valve, safety relief valve and pressure
relief valve are often used interchangeably
• Relief Valve
• An automatic pressure-relieving device actuated by the static pressure upstream of the
valve which opens in proportion to the increase in pressure over the opening pressure
• Used primarily for liquids
• Safety Valve
• An automatic spring-loaded pressure-relieving device actuated by the static pressure
upstream of the valve characterized by a rapid full opening or “pop” action
• Used primarily for gases / vapors
DEFINITIONS Prepared by: Ezaideen Ahmad 159
“Valves” (Continued)
• Safety Relief Valve
• A safety valve or a relief valve
Back Pressures
• Back Pressure
• The pressure on the discharge side of a PRV. Total back pressure is the sum
of superimposed plus built-up back pressure.
• Superimposed Back Pressure
• The pressure at the outlet of the PRV while the valve is in the closed position
• Superimposed back pressure results from other sources of pressure in the
discharge system. It is treated as a static pressure and it may be constant or
variable.
• Superimposed back pressure affects the opening pressure and must be
considered in setting the differential spring pressure for non-balanced valves
DEFINITIONS Prepared by: Ezaideen Ahmad 163
Blowdown
• Once a PRV opens and the condition that caused it to open is corrected, the inlet
pressure will decay. However, the PRV will not reseat until the inlet pressure drops below
the PRV opening (set) pressure.
• The difference between the set pressure and the reseating pressure is known as
blowdown and is expressed as a percentage of the set pressure
• Blowdown is typically in the range of 4% to 8% of set pressure, but may be as high as 22%
of set pressure for certain valves in liquid or vapor / liquid service or as low as 2% of set
pressure for certain pilot-operated valves
• The blowdown may be adjustable within certain limits by various means depending on
the valve manufacturer
DEFINITIONS Prepared by: Ezaideen Ahmad 166
Chattering
The rapidly alternating opening and closing of a PRV. Chattering
may occur in both liquid and vapor service PRVs.
• Chattering may result in misalignment and leakage when the valve returns to its normal
closed position. If chattering continues, it may result in mechanical failure of valve
internals or associated pipe fittings. In addition, the vibration may loosen bolts and result
in flange leaks around the PRV.
DEFINITIONS Prepared by: Ezaideen Ahmad 167
Capacity
• Design Capacity
• The capacity (flowrate) of the limiting contingency, used to determine the minimum
required area of a PRD
• Rated Capacity
• The capacity a PRD can pass when fully open at accumulated pressure, regardless of
design capacity specification
• The rated capacity of a PRD must equal or exceed its design capacity
• The rated capacity equals the design capacity multiplied by the ratio of installed relief
area to required relief area
DEFINITIONS Prepared by: Ezaideen Ahmad 168
Question (1/1)
Click on the correct answer
Superimposed backpressure equals:
X Review section
The frictional on Definitions
pressure for more
drop resulting from information
other sources
that relieve simultaneously
X Review section
The pressure on on
the Definitions for of
discharge side more information
the PRV when it
is open
Superimposed Back Pressure is the pressure at the outlet of the PRV while the
The pressure
valve is on
in the closed the discharge
position. Superimposed side
backof the PRV
pressure resultswhen
from it
other sources of pressure in the discharge system. It is treated as a static
is closed
pressure and it may be constant or variable.
X Review section
The increase on Definitions
in pressure for more information
on the discharge side of the
PRV resulting from flow through the open PRV
Prepared by: Ezaideen Ahmad 169
MODULE 5
ASME SECTION VIII
CODE REQUIREMENTS
ASME SECTION VIII CODE REQUIREMENTS Prepared by: Ezaideen Ahmad 170
Capacity Certification
• Pressure Relief Valve Capacity Certification (UG-131)
• Capacity certification tests are conducted at an overpressure of 10% of set pressure or
3 psi, whichever is greater
• When a single relief valve is provided for contingencies other than fire, that valve must
be set at a pressure not exceeding the MAWP. If the valve is set at the MAWP, the
maximum overpressure must be 10% of MAWP, which is exactly the same as the
accumulation allowed by the American Society of Mechanical Engineers (ASME) Code.
ASME SECTION VIII CODE REQUIREMENTS Prepared by: Ezaideen Ahmad 171
Accumulation
• Maximum Allowable Accumulation (UG-125)
• Single Relief Valve – Contingencies Other Than Fire
• Maximum Allowable Accumulation = 10% or 3 psi, whichever is greater
• Fire
• Maximum Allowable Accumulation = 21%
• Steam Boilers
• Maximum Allowable Accumulation = 6%
• The above apply in the USA and many countries. However, there are some countries where
these will be different. Local regulations need to be consulted.
ASME SECTION VIII CODE REQUIREMENTS Prepared by: Ezaideen Ahmad 172
Non-Fire Contingencies
• When multiple relief valves are provided for contingencies other than
fire, at least one PRV must be set at a pressure not exceeding the
MAWP but the other(s) may be set as high as 105% of MAWP
• However, a valve set at 105% of MAWP may not achieve its certified (rated)
relieving capacity until its inlet pressure is at least 110% of its set pressure
(10% overpressure)
• Thus, to ensure that such valves achieve their certified relieving capacity, the
Code allows the vessel pressure to increase to 105% x 110% = 116% of
MAWP, resulting in an allowable accumulation of 16%
• Under these conditions, relief valves set at the MAWP will operate at a
capacity in excess of their certified relieving capacity at 10% overpressure
since they will operate at 16% overpressure at relieving conditions
ASME SECTION VIII CODE REQUIREMENTS Prepared by: Ezaideen Ahmad 173
Fire Contingencies
• When supplemental PRVs are provided for protection against overpressure
due to external fire (or when fire is the only contingency), the Code allows
such valves to be set as high as 110% of MAWP
• A valve set at 110% of MAWP may not achieve its certified (rated) relieving capacity
until its inlet pressure is at least 110% of its set pressure (10% overpressure)
• Thus, to ensure that such PRVs achieve their certified relieving capacity, the Code
allows the vessel pressure to increase to 110% x 110% = 121% of MAWP, resulting in
an allowable accumulation of 21%
• In many cases, the same PRVs provide protection against both fire and non-
fire contingencies
• In such cases, none of the PRVs may be set higher than 105% of MAWP and at least
one must be set at or below MAWP
• However, the permissible accumulation during a fire relief scenario is still 21%
ASME SECTION VIII CODE REQUIREMENTS Prepared by: Ezaideen Ahmad 175
Question (1/1)
Click on the correct answer
Maximum allowable accumulation for multiple relief valves during a non-fire
contingency is:
X Review
6% or 3 ASME SectionVIII
psi, whichever for more information
is greater
X Review
10% or 4ASME SectionVIII
psi, whichever for more information
is greater
X Review
21% ASME SectionVIII for more information
Prepared by: Ezaideen Ahmad 176
MODULE 5
CONVENTIONAL PRVs
CONVENTIONAL PRVs Prepared by: Ezaideen Ahmad 177
• When the internal pressure of the protected equipment equals or exceeds the
set pressure of the spring, the valve opens
• For PRVs that discharge non-hazardous fluids (such as steam) directly to the
atmosphere, the spring may be exposed to the atmosphere
• For valves that discharge hazardous fluids or that discharge to closed systems, the
spring is enclosed by a bonnet vented through an internal passage to the valve outlet
• Because of this, any pressure on the valve outlet is added to the spring pressure that tends to
keep the valve closed
• This so-called “back pressure” effect must be considered when determining the
required spring pressure and the valve operational characteristics
CONVENTIONAL PRVs Prepared by: Ezaideen Ahmad 178
Cross-Sectional View
EXTERNAL
BONNET VENT VENT PLUGGED
CONVENTIONAL PRVs Prepared by: Ezaideen Ahmad 179
Closed
Spring
Bonnet
Body 2 psi
Blowdown
Ring
(100 psi)
CONVENTIONAL PRVs Prepared by: Ezaideen Ahmad 180
Open
Spring
Bonnet
Body 2 psi
Blowdown
Ring (100 psi)
CONVENTIONAL PRVs Prepared by: Ezaideen Ahmad 181
Operational Characteristics
• Significant leakage between the valve seat and disc (“simmer”) typically begins
to occur as operating pressure rises to about 90 to 95% of set pressure
• Simmer is due to the progressively decreasing net closing force acting on the disc (spring
pressure minus internal pressure) as the operating pressure approaches the set pressure
• Depending upon valve maintenance, seating type, and condition, simmer-free operation
may be possible at up to 98% of set pressure
• When vessel pressure falls below set pressure, the disc tends to close under
the action of the spring
CONVENTIONAL PRVs Prepared by: Ezaideen Ahmad 183
• The difference between the set pressure and the full reseating
pressure, expressed as a percent of set pressure, is known as
“blowdown”
• Typically, blowdown is in the range of 4% to 8% of the set pressure
• Certain valves in liquid or vapor / liquid service may have blowdowns as high
as 22% of set pressure
• The blowdown may be adjusted within certain limits by various means
recommended by the valve manufacturer
CONVENTIONAL PRVs Prepared by: Ezaideen Ahmad 184
Vapor Service
• PRVs for vapor service are designed for “pop” action, moving to the full
open position at only a slight overpressure and remaining fully open as the
inlet pressure builds up to the permissible maximum
• The “pop” action characteristic is achieved by a secondary annular orifice formed
outside the disc-to-nozzle seat. This causes additional disc area to be exposed to the
operating pressure as soon as a slight lift occurs, accelerating the opening movement.
• The kinetic energy of the flowing vapor, by action between the valve disc holder and
the blowdown ring, adds to the opening force and causes the valve to “pop" open
• This kinetic energy also continues to act against the spring force as the fluid
pressure returns to the PRV set point
• This explains why the PRV reseats at a pressure below the set pressure
CONVENTIONAL PRVs Prepared by: Ezaideen Ahmad 185
• As pressure drops below the set pressure, PRV remains fully open until
blowdown pressure is reached
• Usually around 92 - 93% of set pressure
• May be as low as 80% of set pressure
• Flow through the valve is usually sonic and directly proportional to upstream
absolute pressure
• Not affected by back pressure as long as valve is 100% open
• Excessive back pressure may result in partial closing of the valve
• If back pressure exceeds “critical flow” pressure, flow will be subsonic
CONVENTIONAL PRVs Prepared by: Ezaideen Ahmad 186
Liquid Service
• Liquid relief valves, since 1985, are required by the ASME to have capacity
certification and achieve full lift at no more than 10% overpressure
• Non-certified valves achieve full lift at 25% overpressure
• When capacity certified relief valves are used in services where some contingencies
involve the flow of vapor or a vapor / liquid mixture through the PRV nozzle, the reseating
pressure may be as low as 78 – 80% of the set pressure (20 – 22% blowdown)
• The long blowdown may not be acceptable in some installations since it would require
dropping the system pressure significantly below operating pressure to achieve reclosure
of the PRV
CONVENTIONAL PRVs Prepared by: Ezaideen Ahmad 188
• For these reasons, conventional PRVs and discharge systems must be designed
such that built-up back pressure (for non-fire contingencies) at the PRV rated
capacity does not exceed the overpressure at relieving conditions
• Usually 10% of set pressure for single valve installations
• For valves in which differential spring pressure is significantly less than set pressure
(constant SIBP >>0), a detailed system evaluation is required to determine maximum
allowable variable SIBP
• Or the use of a balanced valve (bellows or pilot-operated) should be considered
CONVENTIONAL PRVs Prepared by: Ezaideen Ahmad 192
Question (1/1)
Click on the correct answer
Capacity-certified PRVs:
X Review
Achievesection
full lifton
at Conventional PRVs for more information
10% overpressure
X Review
Achievesection
full lifton
at Conventional PRVs for more information
25% accumulation
Liquid relief valves since 1985 are required by the ASME to have
Achieve full rated relief capacity at lower overpressure
capacity certification and achieve full lift at no more than 10%
than non-certified
overpressure. PRVs
Non-certified valves achieve full lift at 25% overpressure.
X Review sectionby
Are required onASME
Conventional
Code forPRVs for more information
vessels
completely filled with liquid
Prepared by: Ezaideen Ahmad 194
MODULE 5
BALANCED BELLOWS PRVs
BALANCED BELLOWS PRVs Prepared by: Ezaideen Ahmad 195
VENT OPEN
BELLOWS
BALANCED BELLOWS PRVs Prepared by: Ezaideen Ahmad 197
Operational Characteristics
• Differential spring pressure is the same as nominal set pressure
Applications
• Use When:
• Excessive fluctuation in SIBPs
• Large SIBP fluctuations on a conventional PRV may result in either premature or delayed
opening of the valve, potentially resulting in operational upsets or equipment overpressure
• BUBP exceeds limits for conventional valves
• Fouling or corrosive services
• Bellows shields the spring from process fluid
• However – Bellows “folds” could corrode in highly corrosive service or foul in extremely
viscous service, such as asphalt, limiting the lift of the valve
• Valve should be heated and insulated
BALANCED BELLOWS PRVs Prepared by: Ezaideen Ahmad 200
Limitations
• The bellows is inherently a point of mechanical weakness which introduces
some degree of additional risk in case the bellows should fail and release
process fluids through the vent
Bonnet Venting
• To achieve the required balancing of the valve disc, the interior of the bellows must be
vented through the bonnet chamber to the atmosphere. A 3/8 to 3/4 inch (10 to 20 mm)
diameter vent hole is provided in the bonnet for this purpose. Any bellows failure or
leakage will permit process fluid from the discharge side of the valve to be released
through the vent to the atmosphere.
• Shipping plugs must be removed from the bonnet vent holes before a new valve is
commissioned
Question (1/1)
Click on the correct answer
In general, when should a Balanced Bellows PRV not be used?
X Review section
Excessive on Balanced
fluctuation Bellows PRVs for more information
in SIBP
X Review section on
BUBP exceeds Balanced
the limit forBellows PRVs for
conventional PRVmore information
X Review
Foulingsection on Balanced
or corrosive Bellows PRVs for more information
services
• In general,
Cold- a Balanced Bellows
or auto-refrigerating PRV should not be used in Cold or
services
auto-refrigerating services
Potential for ice formation around the spring, bellows and other internal
components could interfere with the opening and/or reseating of the valve
If a balanced bellows valve must be used in such service, a steam-
jacketed or equivalent heat-traced design should be considered
Prepared by: Ezaideen Ahmad 205
MODULE 5
PILOT OPERATED PRVs
PILOT OPERATED PRVs Prepared by: Ezaideen Ahmad 206
Fundamentals
• Assembly consists of a main valve combined with a self-actuated,
auxiliary PRV called a “pilot valve”
Operational Characteristics
• Under normal operating conditions, the vessel pressure acts on the main
valve seat at the bottom of a free-floating differential area piston or flexible
diaphragm and is also applied to the top of the piston (or diaphragm) and
under the pilot valve disc
• Since the top area of the piston (or diaphragm) is larger than the nozzle area at the
lower end of the piston (or diaphragm), there is a net force holding the piston down
on the nozzle
• Under static conditions, this net sealing force increases as the vessel
pressure increases and the pilot valve approaches the set point
• When the set pressure of the pilot valve is reached, it opens and
depressurizes the volume above the piston (or diaphragm) causing the main
valve to open
PILOT OPERATED PRVs Prepared by: Ezaideen Ahmad 208
Valve Types
Once pilot valve reaches set pressure and relieves:
• Flowing Type
• Allows continued venting of the process fluid through the pilot valve until the
blowdown pressure is reached and the valve recloses
• Not recommended because they are more prone to plugging
• Non-Flowing Type
• Most common and usually preferred design
• Once the top cavity of the piston (or diaphragm) is depressured, continued
venting of the process fluid is prevented
PILOT OPERATED PRVs Prepared by: Ezaideen Ahmad 209
• “Pop”- action
• The pressure on top of the piston (or diaphragm) is vented fully when the pilot valve
opens causing the main valve to open fully
• Preferred for vapor services to achieve the required relieving rate quickly
• Modulating action
• The pilot valve vents the top of the piston only as much as required to satisfy the relief
demand and the main valve may not reach full lift
• Preferred for liquid services to minimize the potential for chattering
PILOT OPERATED PRVs Prepared by: Ezaideen Ahmad 210
• All valves in the sensing line must be car-sealed open (CSO) and shall
be of a design that minimizes the risk of accidental closure
• Avoid use of quarter-turn valves unless their handles are removed
PILOT OPERATED PRVs Prepared by: Ezaideen Ahmad 212
• Once the set pressure is reached, the valve opens fully if a “pop”- action pilot is
used
• Because the pilot operated valve is slower acting, it may be less prone to
chattering in cyclic service
• A modulating pilot valve may also be considered where chattering is a potential problem
PILOT OPERATED PRVs Prepared by: Ezaideen Ahmad 213
Advantages
• PRV is inherently balanced when pilot exhausts to atmosphere
• Opening pressure not affected by SIBP
• High BUBP does not result in chattering
• Vapor relief capacity unaffected by back pressure as long as flow is critical
Limitations
• Not recommended for dirty or fouling services
• If the pilot valve or pilot connections become fouled, the valve will not open
• Where fouling is a function of entrained solids, this limitation may be countered by the use
of a non-flowing pilot valve and a pilot line filter or a barrier fluid such as glycol
• With a non-flowing pilot valve, there is no flow in the pilot system when the valve opens and;
therefore, solids entrainment is reduced
• Blowback with a suitable fluid can also be used to reduce solids entrainment in the sensing
line
• Maximum inlet temperature limited to 450oF (232oC) by the “O" ring piston
seals
• Newer designs available for a maximum inlet temperature of about 1000F (538C) in a
limited number of valve sizes and for a limited range of set pressures. Check with vendors.
• “O" ring piston seals must also be compatible with the process fluid
PILOT OPERATED PRVs Prepared by: Ezaideen Ahmad 216
Limitations (Continued)
• Vapor condensation and liquid accumulation above the piston (or diaphragm) may cause
the valve to malfunction unless special designs are used
• If the back pressure exceeds the process pressure under any circumstance (e.g., during
start-up or shutdown) the main valve will open and material will flow from the discharge
backwards through the valve and into the process vessel
• To prevent this, a backflow preventer should be specified for all pilot operated PRVs that discharge to
closed systems
• For start-up a pilot pressurizing fluid may be required to provide pressure on the top side
of the piston
• This is because during initial pressurization the pilot line pressure drop may not allow pressure to
accumulate on the top before the pressure under the piston is present, causing premature opening
PILOT OPERATED PRVs Prepared by: Ezaideen Ahmad 217
Question (1/1)
Click on three correct answer
Which three of the following statements are true?
RUPTURE DISKS
RUPTURE DISKS Prepared by: Ezaideen Ahmad 220
Rupture Disks
• A Rupture Disk (RD) is a thin diaphragm designed to rupture at a designated
pressure differential
• It is used as a weak point element for the protection of vessels and piping systems against
excessive pressure
• To be “fail-safe,” the RD must not fragment and its design should limit the burst
pressure when damaged or installed upside-down to less than what is allowed
by the “Remote Contingency Rule,” typically “HTF” times the Design Pressure
• Acceptable types
• Pre-scored (cross-score) reverse buckling RD for gas service
• Pre-scored (semi-circular score) reverse buckling RD installed in holder with capture bar for
gas or liquid service
• Pre-scored tension-loaded RD for gas or liquid service
RUPTURE DISKS Prepared by: Ezaideen Ahmad 221
Pre-Scored Tension-Loaded
RUPTURE DISKS Prepared by: Ezaideen Ahmad 223
Advantages / Disadvantages
• The advantages of RDs over PRVs are:
• No simmering or leaking prior to bursting
• More reliable for responding to explosions
• Less expensive to provide corrosion resistance
• Can be installed to minimize tendency to foul or plug
• Can provide both depressuring and overpressure protection
Applications
• Reduce fugitive emissions from PRVs
• Requires derating of the relief capacity of the PRVs
• In the event of a fire, rapidly depressure dry vessels, vessels in super-critical service or vessels
with higher Boiling Liquid Expanding Vapor Explosion (BLEVE) potential due to layout
congestion
• Minimizes potential for catastrophic failure
RUPTURE DISKS Prepared by: Ezaideen Ahmad 225
Sizing
• RDs should be sized to pass the same required relieving rate as a PRV
• Three methods for sizing RDs:
1. Coefficient of Discharge method
2. Resistance Coefficient method
3. Combination Capacity method
RUPTURE DISKS Prepared by: Ezaideen Ahmad 226
Sizing (Continued)
1. Coefficient of Discharge (Kd) method
• Uses the manufacturer’s provided Minimum Net Flow Area (MNFA) as the effective
relief area for the RD installation including vessel nozzle, inlet piping, burst RD and
outlet piping
• Relief capacity calculated using restriction orifice equation with a discharge coefficient,
Kd = 0.62
• Applies only when the following conditions are met:
• RD discharges directly to atmosphere
• RD installed within 8 pipe diameters from protected vessel nozzle
• Discharge piping length not greater than 5 pipe diameters
• Nominal diameter of inlet and outlet piping equal to or greater than nominal pipe size of the
RD
RUPTURE DISKS Prepared by: Ezaideen Ahmad 227
Sizing (Continued)
2. Resistance Coefficient (Kr) method
• Recommended by ASME Code when other methods do not apply
• RD is treated as a piping component within the entire relief system
• Resistance coefficient, Kr of the RD is determined by the manufacturer during the
certification process
• Calculated relieving capacity of the system is multiplied by a derating factor of 0.9 to
allow for uncertainties inherent in this method
• Two resistance coefficients are typically determined by the manufacturer: Krl for liquid
and Krv for gas / vapor
RUPTURE DISKS Prepared by: Ezaideen Ahmad 228
Sizing (Continued)
2. Resistance Coefficient (Kr) method (Continued)
• Resistance coefficient based on the media directly in contact with the RD prior to
bursting should be used
• In liquid service, the pressure drop is larger than predicted by the KrL since the RD is not
likely to open fully
• To account for partial opening in liquid service, the pressure drop exerted by the RD
should be based on either assuming that the RD pressure drop is equivalent to the
pressure drop through a restriction orifice with area equal to one-half the nominal RD
flow area or by multiplying the manufacturer’s KrL recommendation by a factor of 4
RUPTURE DISKS Prepared by: Ezaideen Ahmad 229
Sizing (Continued)
3. Combination Capacity method
• Applicable only when the RD is used upstream of a PRV
• PRV is sized using normal sizing procedures
• Capacity of the PRV and RD combination is de-rated by multiplying by the
combination capacity factor, KC
• Published KC values from manufacturers are usually in the range of 0.95 to 0.98
• Published values apply to specific RD / PRV combinations and are registered with the
National Board of Boiler and Pressure Vessel Inspectors
• When no published values are available, ASME Code requires using KC = 0.90
RUPTURE DISKS Prepared by: Ezaideen Ahmad 230
Installation
• RDs must comply with the installation requirements for PRVs
• The installation must have isolation valves unless the equipment can be placed off-line without
requiring a unit shutdown
• RDs need not comply with the inlet piping pressure drop limitations since these limitations are
required only to prevent chattering of PRVs (chattering cannot occur in a RD)
• However, if significant, the inlet line pressure drop must be taken into account in establishing the
system Design Pressure
• In addition, the discharge piping must limit the accumulated pressure in the system being
protected to 110% of the Design Pressure (or 121% in the case of fire contingency)
• When a RD is installed for a heat exchanger tube failure, install the RD directly on the shell or
channel to minimize the peak transient overpressure before the RD bursts
RUPTURE DISKS Prepared by: Ezaideen Ahmad 231
Installation (Continued)
• When a RD is installed upstream or downstream of a PRV, the installation
must provide means for detecting any pressure buildup between the RD
and the PRV
Question (1/1)
Click on two correct answers
Which two of the following types of RDs are acceptable for use?
X Conventional tension-loaded
Pre-scored tension-loaded
Prepared by: Ezaideen Ahmad 233
MODULE 5
RUPTURE / BUCKLING
PIN PRVs
RUPTURE / BUCKLING PIN PRVs Prepared by: Ezaideen Ahmad 234
Balanced / Unbalanced
• Design can be balanced or unbalanced
• Unbalanced
• Piston is connected to the pin by a shaft having a smaller diameter than the piston
• The opening pressure will be affected by back pressure
• Balanced
• Piston diameter is constant all the way to the pin
• The opening pressure will not be affected by back pressure
RUPTURE / BUCKLING PIN PRVs Prepared by: Ezaideen Ahmad 236
Sizing
• Sizing is similar to that of a RD
• When installed as a stand-alone PRD and there is essentially no inlet or
outlet piping, it is sized as an orifice with a discharge coefficient of 0.62
• When placed in series with a PRV, the PRV rated capacity should be
multiplied by the published derating factor for the tested Rupture Pin Valve
/ Pressure Relief Valve (RPV / PRV) combination
• If no published derating factor is available, use 0.90
Prepared by: Ezaideen Ahmad 239
MODULE 5
OTHER PRDs
OTHER PRDs Prepared by: Ezaideen Ahmad 240
Explosion Hatch
• A hinged metal cover fitted over an opening on top of the vessel and sealed
by its own weight
• Typically used to protect a vessel which operates at essentially atmospheric
pressure but may be subjected to an internal explosion (e.g., an asphalt
oxidizer)
• Relief area should be at least 80% the protected vessel cross-sectional area
• For vessels which normally operate at a slight positive pressure, a tight seal
is achieved by the use of hold-down brackets with shear pins, rather than by
increasing the weight of the hatch which would increase inertia and prevent
quick opening
OTHER PRDs Prepared by: Ezaideen Ahmad 241
Liquid Seal
• Consists of a simple U-tube containing a suitable liquid (normally water) with
the seal depth and diameter sized to pass the maximum relieving flow at the
required Design Pressure
• Used for relieving overpressure on equipment operating at pressures slightly
above atmospheric
• Example: Fluid Catalytic Cracking Unit (FCCU) Regenerator Overhead upstream of CO boiler
• Key design considerations
• Continuous water makeup and overflow on the seal loop
• Winterizing to prevent freezing of the seal
• Safe disposal of the effluent seal water
• Acceptability of discharging process fluids to atmosphere
• Potential for liquid hydrocarbon discharges
• Flashback protection (snuffing steam)
OTHER PRDs Prepared by: Ezaideen Ahmad 242
MODULE 5
EXAMPLE PROBLEM
EXAMPLE PROBLEM Prepared by: Ezaideen Ahmad 244
Problem Statement
• A pressure vessel has a MAWP of 100 psig. It is protected against overpressure
(other than due to fire) by two PRVs (A and B) designed to operate in parallel.
The set pressures of the valves are staggered, with the “A” valve being set at
the lower pressure. The HTF for the vessel is 1.3. Answer the following
questions:
1. What is the maximum allowable set pressure for the “A” valve?
2. What is the maximum allowable set pressure for the “B” valve?
3. What is the maximum allowable accumulated pressure?
4. What is the overpressure (as percent of set pressure) for the “A” valve at the maximum
allowable accumulated pressure?
5. What is the overpressure (as percent of set pressure) for the “B” valve at the maximum
allowable accumulated pressure?
6. What is the maximum permissible accumulated pressure for a remote contingency?
EXAMPLE PROBLEM Prepared by: Ezaideen Ahmad 245
Problem Solution
1. 100 psig
• At least one valve must be set at a pressure not exceeding the MAWP
2. 105 psig
• Additional valves may be set at up to 105% of MAWP
3. 116 psig
• Maximum permissible accumulation for non-fire contingencies is 16%
of the MAWP when multiple valves in parallel are provided
EXAMPLE PROBLEM Prepared by: Ezaideen Ahmad 246
MODULE 5
SUMMARY
SUMMARY Prepared by: Ezaideen Ahmad 248
• Explain the different types of backpressure and its impact on the operation of
the different types of PRDs